The Delaware Riverkeeper Network and M. van Rossum, The Delaware Riverkeeper v. DEP ( 2018 )


Menu:
  •             IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    The Delaware Riverkeeper                     :
    Network and Maya van Rossum,                 :
    The Delaware Riverkeeper,                    :
    Petitioners                 :
    :
    v.                                    : No. 1571 C.D. 2017
    : ARGUED: June 4, 2018
    Department of Environmental                  :
    Protection,                                  :
    Respondent                  :
    BEFORE:        HONORABLE ROBERT SIMPSON, Judge
    HONORABLE ELLEN CEISLER, Judge
    HONORABLE BONNIE BRIGANCE LEADBETTER, Senior Judge
    OPINION NOT REPORTED
    MEMORANDUM OPINION
    BY JUDGE CEISLER                                             FILED: August 1, 2018
    Petitioners, The Delaware Riverkeeper Network and Maya van Rossum, The
    Delaware Riverkeeper (Riverkeeper, collectively), petition for review of the
    Pennsylvania Environmental Hearing Board’s (EHB) October 24, 2017 Order
    denying Riverkeeper’s Petition for Leave to File Appeal Nunc Pro Tunc (Nunc Pro
    Tunc Petition).1 Through this Nunc Pro Tunc Petition, Riverkeeper requested
    1
    The Delaware Riverkeeper Network is a non-profit organization
    established in 1988 to protect and restore the Delaware River, its
    associated watershed, tributaries and habitats. The . . . Network is a
    membership organization headquartered in Bristol, Pennsylvania,
    with more than 16,000 members. . . . Maya van Rossum is the
    Delaware Riverkeeper, a full-time, privately funded ombudsman
    who is responsible for the protection of the waterways in the
    Delaware River Watershed.
    Nunc Pro Tunc Petition at 1.
    permission to file what otherwise would have been an untimely challenge to
    Respondent Commonwealth of Pennsylvania, Department of Environmental
    Protection’s (DEP) February 7, 2017 approval of Intervenor PennEast Pipeline
    Company, LLC’s (PPC) Water Quality Certification application. This application
    pertained to PPC’s PennEast Pipeline Project (PennEast Project), a natural gas
    pipeline that is slated to traverse portions of Bucks, Carbon, Luzerne, and
    Northampton Counties. Riverkeeper’s Brief at 2-3; Reproduced Record (R.R.) at
    18a. After careful review, we affirm the EHB.
    I.
    To place this matter in the proper context, we must first examine the interplay
    between state and federal environmental regulatory schemes governing such
    pipelines. By virtue of the Natural Gas Act of 1938 (NGA),2 “Congress [has]
    occupied the field of matters relating to wholesale sales and transportation of natural
    gas in interstate commerce,” thereby almost completely preempting state laws and
    regulations in this area. Schneidewind v. ANR Pipeline Co., 
    485 U.S. 293
    , 305
    (1988). Consequently, “the Federal Energy Regulatory Commission (‘FERC’) is the
    ‘lead agency’ for evaluating interstate [natural gas] pipeline projects. 15 U.S.C. §
    717n(b).” Del. Riverkeeper Network v. Sec’y of Pa. Dep’t of Envtl. Prot. (Orion),
    
    870 F.3d 171
    , 174 (3d Cir. 2017). The NGA’s preemptive powers are not absolute,
    however, as the statute includes explicit preemption carve-outs declaring that
    [e]xcept as specifically provided in [the NGA], nothing in
    [the NGA] affects the rights of States under-- (1) the
    Coastal Zone Management Act of 1972 (16 U.S.C. 1451
    et seq.); (2) the Clean Air Act (42 U.S.C. 7401 et seq.); or
    (3) the Federal Water Pollution Control Act [(Clean Water
    Act)] (33 U.S.C. 1251 et seq.).
    2
    
    15 U.S.C. §§ 717
    -717z.
    2
    15 U.S.C. § 717b; see Del. Riverkeeper Network v. Sec’y Pa. Dep’t of Envtl. Prot.
    (Leidy Line), 
    833 F.3d 360
    , 372 (3d Cir. 2016) (“In other words, the only state action
    over interstate natural gas pipeline facilities that [can] be taken pursuant to federal
    law is state action taken under [these] statutes.”). This exception thus preserves a
    limited regulatory role for state environmental agencies with regard to such
    pipelines, including a permit process necessitated by the Clean Water Act and known
    as a “Water Quality Certification.”
    Section 401 of the Clean Water Act requires
    [a]ny applicant for a Federal license or permit to conduct
    any activity including, but not limited to, the construction
    or operation of facilities, which may result in any
    discharge into the navigable waters, [to] provide the
    licensing or permitting agency a [Water Quality
    C]ertification from the State in which the discharge
    originates or will originate, or, if appropriate, from the
    interstate water pollution control agency having
    jurisdiction over the navigable waters at the point where
    the discharge originates or will originate, that any such
    discharge will comply with the applicable provisions of
    sections 1311, 1312, 1313, 1316, and 1317 of [the Clean
    Water Act, which address effluent discharge and water
    quality levels].
    
    33 U.S.C. § 1341
    (a)(1).
    A Water Quality Certification confirms that a given
    facility will comply with federal discharge limitations and
    state water quality standards. . . . [T]he Water Quality
    Certification is by default a state permit, and the issuance
    and review of a Water Quality Certification is typically left
    to the states.
    Leidy Line, 833 F.3d at 368-69. Once an applicant files a Water Quality Certification
    application, the Clean Water Act gives the relevant state agency (here, the DEP) one
    year from the filing date of the application to return a decision; a failure to do so
    results in waiver of the certification requirement. 
    33 U.S.C. § 1341
    (a)(1); Leidy Line,
    3
    833 F.3d at 369. If an individual or entity disagrees with the DEP’s decision the
    NGA affords the individual or entity the right to petition the United States Court of
    Appeals for the Third Circuit (Third Circuit) for review. See 15 U.S.C. § 717r(d)(1);
    Leidy Line, 833 F.3d at 372 (“[A] state action taken pursuant to the Clean Water Act
    . . . is subject to review exclusively in the Courts of Appeals.”).
    Significantly, the question of when exactly that right attaches has not been
    completely settled, at least in the context of Pennsylvania’s environmental
    regulatory scheme. This is due to the existence of the EHB, which is “an independent
    quasi-judicial agency” that has the “power and duty to hold hearings and issue
    adjudications . . . on orders, permits, licenses or decisions of the [DEP].” Sections
    3(a) and 4(a) of the Environmental Hearing Board Act, Act of July 13, 1988, P.L.
    530, 35 P.S. §§ 7513(a), 7514(a); Orion, 870 F.3d at 177-78.
    When an appeal is taken from DEP to the EHB, the EHB
    is required to conduct a hearing de novo. The EHB is not
    an appellate body with a limited scope of review
    attempting to determine if DEP’s action can be supported
    by the evidence received at DEP’s fact finding hearing.
    Rather, the EHB’s duty is to determine if DEP’s action can
    be sustained or supported by the evidence taken by the
    EHB.
    Leatherwood, Inc. v. Dep’t of Envtl. Prot., 
    819 A.2d 604
    , 611 (Pa. Cmwlth. 2003)
    (internal citations omitted).
    The Third Circuit has yet to decide whether it may exercise jurisdiction over
    a DEP Water Quality Certification-related petition for review where an EHB appeal
    addressing the same matter is still pending; however, it has concluded that a party’s
    failure to file a timely appeal with the EHB renders the DEP’s action final and, thus,
    ripe for review by the Third Circuit. See Orion, 870 F.3d at 177-78.
    4
    In Orion, Riverkeeper had petitioned for review of the DEP’s approval of a
    Water Quality Certification application from Tennessee Gas Pipeline Company
    (Tennessee) for a 12.9-mile-long natural gas pipeline running through Pike and
    Wayne Counties, but did not also challenge that approval via a timely appeal to the
    EHB. Id. at 173-78. Riverkeeper argued, in part, that the NGA prevented the Third
    Circuit from exercising jurisdiction over the petition, because the underlying DEP
    decision was not reviewable until the state-level administrative process had been
    completed, which would not occur until the EHB had issued its own assessment.
    Thus, Riverkeeper sought to have the matter transferred to EHB on this basis. Id. at
    175. The Orion court sidestepped the question of whether the NGA required
    administrative finality, noting that there were other pending cases on the Third
    Circuit’s docket in which that question could be “better resolved.” Id. at 176-78.3
    Still, the Third Circuit found that it had jurisdiction over the Orion petition,
    explaining that Riverkeeper’s failure to appeal the DEP’s decision to the EHB
    rendered that decision final and, thus, reviewable by the Third Circuit. Id. at 177-78.
    II.
    With all of this in mind, we now turn to the current matter. On February 9,
    2016, PPC filed a Water Quality Certification application with the DEP for the
    PennEast Project, which the DEP approved on February 7, 2017. 47 Pa. B. 1218-
    1220 (2017); R.R. at 5a, 18a-19a, 25a-27a. DEP published notice of this approval in
    the Pennsylvania Bulletin on February 25, 2017, and included the following
    instruction:
    Any person aggrieved by this action may file a petition for
    review pursuant to Section 19(d) of the [NGA], 15
    3
    The parties’ briefs do not address whether the Third Circuit has since answered this
    question.
    5
    U.S.C.A. § 717r(d), with the Office of the Clerk, United
    States Court of Appeals for the Third Circuit, 21400 U.S.
    Courthouse, 601 Market Street, Philadelphia, PA 19106-
    1790 within 30 days of publication of this notice, or within
    30 days of receipt of written notice of this action,
    whichever occurs first.
    47 Pa. B. 1220 (2017); R.R. at 27a. In response, Riverkeeper petitioned the Third
    Circuit on February 28, 2017 for review of the DEP’s approval of PPC’s Water
    Quality Certification application, but, as in Orion, did not elect to appeal this
    approval to the EHB at that time. PPC’s Brief at 5. To date, the Third Circuit has not
    rendered a decision on Riverkeeper’s petition. Id.
    On September 19, 2017, more than 6 months after the administrative appeal
    window had closed, Riverkeeper filed its Nunc Pro Tunc Petition with the EHB.
    Therein, Riverkeeper mentioned the Orion decision, without explaining that
    decision’s relevance, and argued that it should be allowed to appeal the DEP’s
    decision nunc pro tunc to the EHB, claiming “good cause” for granting such relief
    existed for two reasons. First, it was misled about its appeal options by the DEP’s
    February 25, 2017 notice, which, in contrast to notices issued in other, similar
    matters, explicitly stated that the proper way to challenge the DEP’s decision
    regarding PPC’s Water Quality Certification application was by petitioning the
    Third Circuit, rather than through an appeal to the EHB. Memorandum of Law in
    Support of Nunc Pro Tunc Petition at 1-4. Second, in petitioning the Third Circuit
    for review, Riverkeeper claimed it was acting “with cognizance of the [United States
    District Court for the Middle District of Pennsylvania’s] decision in Tennessee Gas
    Pipeline Co. v. Delaware Riverkeeper Network [(Northeast Upgrade Project)], 921
    
    6 F. Supp. 2d 381
     (M.D. Pa. 2013).” Id. at 6.4 Riverkeeper analogized the putatively
    deficient DEP notice to those at issue in California University of Pennsylvania v.
    Zoning Hearing Board, 
    107 A.3d 241
     (Pa. Cmwlth. 2014),5 and Department of
    Transportation, Bureau of Traffic Safety v. Moore, 
    554 A.2d 130
     (Pa. Cmwlth.
    1988).6 In these cases, our Court held that the appellants were permitted to file
    4
    In Northeast Upgrade Project, the District Court found that Section 19(d)(1) of the NGA,
    15 U.S.C. § 717r(d)(1), barred the EHB from reviewing DEP decisions regarding pipeline-related
    permit applications made pursuant or closely related to requirements set forth by the Clean Water
    Act, and opined that, under the NGA, that role was reserved exclusively for the Third Circuit. 921
    F. Supp. 2d at 387-96. On that basis, the District Court issued a preliminary injunction barring the
    EHB from reviewing challenges filed by a number of private environmental protection
    organizations (including Riverkeeper) regarding several permits the DEP had approved for the
    Northeast Upgrade natural gas pipeline project. Id. This decision did not enjoin the EHB from
    entertaining such challenges in other matters and, according to PPC, the District Court dismissed
    the Northeast Upgrade Project case on April 23, 2013. PPC’s Brief at 15-16.
    5
    In California University of Pennsylvania v. Zoning Hearing Board, we vacated the trial
    court’s dismissal of a statutory appeal filed by California University. We held that there had been
    a breakdown in the judicial process, because the Zoning Hearing Board (ZHB) had erroneously
    informed the University, via the ZHB’s cover letter attached to the copy of the decision that was
    mailed to the University, that the appeal window was open for thirty days after the University’s
    receipt of the decision, rather than from the date of the decision’s mailing. Accordingly, we
    remanded the matter to the trial court, with instructions to hold an evidentiary hearing to determine
    when exactly the University had received the decision and whether, based upon that date and the
    ZHB’s incorrect instructions, the University should be allowed to file a nunc pro tunc appeal. 
    107 A.3d at 242-46
    .
    6
    In Department of Transportation, Bureau of Traffic Safety v. Moore:
    [Moore] received a citation on April 20, 1983 for an invalid registration sticker and
    was fined $44.00. Effective November 15, 1983, his [vehicle] operating privilege
    was suspended for failure to respond to that citation. He contend[ed] that he never
    received notice of this suspension and did not learn of it until he was cited on March
    3, 1986 for failure to stop at a red light. At that time, he was also cited for driving
    while his operating privilege was suspended, in violation of Section 1543 of the
    Vehicle Code, as amended, 75 Pa.C.S. § 1543.
    554 A.2d at 131.
    7
    appeals nunc pro tunc because they had received erroneous information from the
    relevant governmental entities, which prevented the appellants from appropriately
    exercising their appellate rights. Memorandum of Law in Support of Nunc Pro Tunc
    Petition at 5-6. In addition, Riverkeeper argued that neither the DEP nor PPC would
    be prejudiced by a nunc pro tunc appeal because, even if the appeal had been timely
    filed, the EHB would likely have stayed it until the Third Circuit entered a “ruling
    on its jurisdiction [over] these [kinds of] matters.” Id. at 7.
    PPC responded to Riverkeeper’s request on October 3, 2017, opining that
    nunc pro tunc relief was not warranted under the circumstances. According to PPC,
    [a]lthough not cited in its [Nunc Pro Tunc Petition],
    Riverkeeper has made clear in multiple filings in various
    court proceedings that its argument that appeal to the EHB
    is proper is based upon the United States Court of Appeals
    for the
    First Circuit’s decision in Berkshire Environmental Action
    Team, Inc. v. Tennessee Gas Pipeline Company, LLC, 
    851 F.3d 105
     (1st Cir. 2017).[7] The Berkshire decision was
    Subsequently, Moore appeared before a magisterial district judge, who told him that his
    operating privileges would be restored if he paid the citation fines, and did not discover that the
    judge had led him astray until the appeal window pertaining to the March 3, 1986 citations had
    closed, when the Department of Transportation notified him that it was suspending his operating
    privileges for six months. 
    Id.
     On appeal, “[w]e agree[d] with the trial court that incorrect
    information given to the appellee by the district justice [was] sufficient reason to permit [Moore
    to appeal the March 3, 1986 citations] nunc pro tunc.” Id. at 132.
    7
    In Berkshire, the First Circuit dismissed a petition for review regarding the Massachusetts
    Department of Environmental Protection’s (MassDEP) approval of a pipeline-related Water
    Quality Certification application for lack of jurisdiction. 851 F.3d at 113. The Berkshire court
    reviewed Massachusetts’ administrative process pertaining to such applications, noting that an
    entity or individual may appeal a MassDEP decision regarding such an application, which will
    then result in a de novo hearing in which MassDEP must again review the application. Id. at 111-
    13. Because the Berkshire petitioners had filed a timely administrative appeal of MassDEP’s
    application approval, and that appeal was still pending, the First Circuit concluded that there was
    no final agency determination, which thereby deprived it of subject matter jurisdiction. Id.
    8
    issued on March 15, 2017. At that time, 12 days remained
    in the 30 day period for appeal of the [DEP’s approval of
    PPC’s Water Quality Certification application] to the
    EHB. See 
    25 Pa. Code § 1021.52
    (a)(2)(i). Riverkeeper
    was well aware of Berkshire as soon as [that] decision was
    issued, as evidenced by the fact that Riverkeeper and its
    counsel have been citing to and making arguments based
    [up]on it ever since. Yet, Riverkeeper did not appeal . . .
    to the EHB before the deadline and [instead] waited an
    additional six months after Berkshire before seeking leave
    to file an appeal nunc pro tunc.
    PPC’s Memorandum of Law in Opposition to Nunc Pro Tunc Petition at 2.
    PPC further highlighted a number of filings by Riverkeeper in other litigation,
    including:
     A March 21, 2017 response by Riverkeeper to a Third Circuit order issued in
    Orion, in which Riverkeeper briefly discussed Berkshire in a footnote;
     Riverkeeper’s letter brief submitted to the Third Circuit in Delaware
    Riverkeeper Network, v. Department of Environmental Protection (Atlantic
    Sunrise), Case No. 16-2211, on April 18, 2017, in which Riverkeeper again
    referenced Berkshire and argued that a DEP Water Quality Certification
    decision was not final until either the EHB administrative process has finished
    or a party failed to file a timely appeal with the EHB;
     Riverkeeper’s July 11, 2017 principal brief in Atlantic Sunrise, in which
    Riverkeeper presented the same arguments as in its earlier submissions;
    In Orion, “Riverkeeper argue[d] that [the Third Circuit] should follow Berkshire’s holding
    and read a finality requirement into [section 19(d)(1) of the NGA, 15 U.S.C. §717r(d)(1)]. . . [and]
    further argue[d] that PA DEP’s order [approving Tennessee’s Water Quality Certification
    application for the Orion natural gas pipeline project was] not final because Pennsylvania’s
    administrative scheme is analogous to Massachusetts’s.” 870 F.3d at 176.
    9
     Riverkeeper’s April 21, 2017 principal brief in Orion, in which it again cited
    Berkshire and argued that the matter was not ripe for Third Circuit review
    until the EHB had weighed in; and
     Riverkeeper’s May 18, 2017 reply brief in support of its request for a stay of
    proceedings regarding the Third Circuit’s review of the DEP’s PennEast
    Project decision.8
    See PPC’s Memorandum of Law in Opposition to Nunc Pro Tunc Petition at 5-8,
    Exs. A-E.
    In addition, PPC argued that the amount of time that passed between
    publication of both Berkshire and Orion and Riverkeeper’s filing of its Nunc Pro
    Tunc Petition showed that Riverkeeper were not reasonably diligent in seeking
    relief. Id. at 11. Finally, PPC claimed that allowing Riverkeeper to appeal to the EHB
    nunc pro tunc would unfairly prejudice both the DEP and PPC because it would
    further delay progress on the PennEast Project, as both entities had relied on
    Riverkeeper’s decision to only petition the Third Circuit for review. Id. at 11-12.
    According to PPC, the parties had fully briefed the Third Circuit petition and the
    matter was ripe for review, but “[n]ow, Riverkeeper seeks to change the rules of the
    game in the ninth inning, as Riverkeeper suddenly realized that [their] failure to file
    an appeal here [with the EHB] could be dispositive on the issue of whether the Third
    Circuit exercises jurisdiction over the [Water Quality Certification approval].” Id. at
    12. In essence, PPC asserted that prejudice would result from allowing a nunc pro
    8
    Therein, Riverkeeper mentioned the EHB’s ruling, in a separate matter, that DEP’s
    approval of a pipeline-related Water Quality Certification application did not constitute a final
    agency action under the circumstances, argued that “[t]he parallels between the Massachusetts and
    Pennsylvania regulatory regimes are too similar to ignore,” and reiterated its belief that the Third
    Circuit did not have jurisdiction to entertain a petition for review until the EHB has reviewed the
    DEP’s approval of an application and issued its own ruling. PPC’s Memorandum of Law in
    Opposition to Nunc Pro Tunc Petition, Ex. D.
    10
    tunc appeal, as it would create another regulatory hurdle to the completion of the
    PennEast Project. Id. at 11-12.
    On October 6, 2017, Riverkeeper responded to PPC’s filing by sending a letter
    to the administrative law judge assigned to the matter, arguing that PPC failed to
    paint a complete and accurate picture of the jurisdictional arguments Riverkeeper
    had made to the Third Circuit in the aforementioned cases. Riverkeeper Letter,
    10/6/17, at 1. Riverkeeper attached copies of two briefs they had filed with the Third
    Circuit regarding their PennEast Project-related petition for review, to ensure that
    the EHB had a “more complete record.” See id. at 1, Exs. A-B.
    The DEP filed a response to the Nunc Pro Tunc Petition on October 18, 2017.
    The DEP disagreed with Riverkeeper’s contention that the February 25, 2017 notice
    in the Pennsylvania Bulletin “directed” aggrieved parties to petition the Third Circuit
    for review, as the notice only said that such parties “may file” a petition. DEP’s
    Memorandum of Law in Opposition to Nunc Pro Tunc Petition at 5-6. In addition,
    DEP maintained that Riverkeeper failed to show that this notice was “contrary to
    law[,]” noted the jurisdictional import of the Leidy Line, Northeast Upgrade Project,
    and Orion decisions, distinguished this matter from the California University and
    Moore decisions, and claimed that the notice was “factually accurate and consistent
    with the law.” Id. at 7-8. Finally, the DEP asserted that Riverkeeper’s request for
    relief was untimely, because Riverkeeper did not seek leave to file a nunc pro tunc
    appeal until nearly three months after they had argued to the Third Circuit that that
    Court could not exercise jurisdiction over their challenge to the PennEast Project
    until the EHB had weighed in, and more than seven months after the DEP’s approval
    of PPC’s Water Quality Certification application. Id. at 8-9.
    11
    On October 24, 2017, the EHB denied Riverkeeper’s Nunc Pro Tunc Petition.
    The EHB noted that our case law allows for nunc pro tunc appeals where “a would-
    be appellant reasonably relies to its detriment upon incorrect information from a
    governmental authority regarding the need or manner to appeal[,]” and
    acknowledged that the language of the February 25, 2017 DEP notice “was
    misleading or, at best, incomplete.” EHB Opinion, 10/24/17, at 3. Nonetheless, the
    EHB held that Riverkeeper was not entitled to nunc pro tunc relief. EHB Opinion,
    10/24/17, at 1-4. The EHB had
    difficulty accepting the Riverkeeper’s representation that
    [they] actually relied on the [Pennsylvania] Bulletin notice
    because extremely able counsel for the Riverkeeper has
    filed simultaneous appeals with this Board and the Third
    Circuit in at least one other pipeline case, Lancaster
    Against Pipelines, et al. v. DEP, EHB Docket No. 2016-
    075-L.
    Id. at 3. In addition, even assuming such reliance, the EHB
    question[ed] whether that reliance was reasonable given
    the uncertainty in the law about the appropriate forum for
    an appeal of a [Section] 401 [of the Clean Water Act]
    certification, an uncertainty about which the Riverkeeper
    was fully aware given [their] filings in the Third Circuit
    matter. The Riverkeeper [have] actually argued for months
    in the Third Circuit case that jurisdiction lies with this
    Board, yet [they] did not until this late date take the
    relatively simple step of filing an EHB appeal to preserve
    [their] rights. The Riverkeeper could very easily have filed
    simultaneous appeals before the Third Circuit and this
    Board. There was certainly no downside to doing so, given
    the minimal expense and effort associated with filing an
    EHB appeal.
    Id. Finally, the EHB found that Riverkeeper had “quite clearly failed to act with due
    diligence to preserve [their] rights” by waiting until 205 days after the DEP’s
    application approval, and until 20 days after Orion was published, to file its Nunc
    12
    Pro Tunc Petition, noting that Riverkeeper failed to explain these delays or why the
    Orion decision suddenly prompted them to seek such relief. Id. at 4. This Petition
    for Review followed.
    III.
    Our review of an EHB decision is limited to determining whether the EHB
    committed errors of law or constitutional violations and whether its decision is
    supported by substantial evidence. Eureka Stone Quarry, Inc. v. Dep’t of Envtl.
    Prot., 
    957 A.2d 337
    , 344 (Pa. Cmwlth. 2008).
    Substantial evidence is defined as “such relevant evidence
    as a reasonable mind might accept as adequate to support
    a conclusion.” Department of Environmental Resources v.
    Borough of Carlisle, 16 Pa. Cmwlth. 341, 
    330 A.2d 293
    ,
    298 (1974). An administrative agency has broad discretion
    in the performance of its administrative duties and
    functions and . . . an agency’s exercise of its discretion
    [cannot be invalidated] absent proof of fraud, bad faith, or
    blatant abuse of [that] discretion. Herzog v. Department of
    Environmental Resources, 166 Pa. Cmwlth. 114, 
    645 A.2d 1381
     (1994). In addition . . . the resolution of conflicts in
    testimony, the credibility of witnesses, and the weight
    given the evidence are within the province of the Board.
    Pawk v. Department of Environmental Resources, 39 Pa.
    Cmwlth. 457, 
    395 A.2d 692
     (1978).
    
    Id.
    The EHB may permit a party to file an appeal nunc pro tunc “for good cause
    shown.” 
    25 Pa. Code § 1021
    .53a. A nunc pro tunc appeal will be allowed only in
    situations where “(1) the appellant’s notice of appeal was filed late as a result of non-
    negligent circumstances, either as they relate to the appellant or the appellant’s
    counsel; (2) the appellant filed the notice of appeal shortly after the expiration date
    [of the appeal window]; and (3) the appellee was not prejudiced by the delay.” Criss
    v. Wise, 
    781 A.2d 1156
    , 1159 (Pa. 2001); see also Falcon Oil Co. v. Dep’t of Envtl.
    13
    Res., 
    609 A.2d 876
    , 878 (Pa. Cmwlth. 1992) (“A nunc pro tunc appeal of an
    administrative action will be allowed only where there is a showing of fraud,
    breakdown in the administrative process or unique and compelling factual
    circumstances establishing a non-negligent failure to file a timely appeal.”). “The
    exception for allowance of an appeal nunc pro tunc in non-negligent circumstances
    is meant to apply only in unique and compelling cases in which the appellant has
    clearly established that she attempted to file an appeal, but unforeseeable and
    unavoidable events precluded her from actually doing so.” Criss, 781 A.2d at 1160.
    IV.
    Riverkeeper put forth a single question for our consideration:
    Whether a would-be appellant [i.e. Riverkeeper] that was
    directed by [the DEP] to challenge a DEP approval for a
    natural gas pipeline with the United States Court of
    Appeals for the Third Circuit, and which was previously
    enjoined by the United States District Court for the Middle
    District of Pennsylvania [in Northeast Upgrade Project]
    from pursuing an appeal of a DEP approval for a natural
    gas pipeline before the . . . [EHB], has shown good cause
    to file an appeal nunc pro tunc with the EHB.
    Riverkeeper’s Brief at 2. In its brief, Riverkeeper rehash the central argument they
    made to the EHB - that they should have been allowed to appeal nunc pro tunc
    because the February 25, 2017 DEP notice’s misleading language, combined with
    the injunctive effect of Northeast Upgrade Project, constituted “a breakdown in the
    administrative process and/or unique and compelling factual circumstances
    establish[ing] a non-negligent failure by [Riverkeeper] to [file a timely appeal with
    the EHB].” Id. at 12.9
    9
    Curiously, and despite the express language of Northeast Upgrade Project, Riverkeeper
    claim in their brief that the District Court’s ruling enjoined Riverkeeper from moving forward with
    their EHB appeal in that matter. Riverkeeper’s Brief at 8; see Northeast Upgrade Project, 
    921 F. 14
    In addition, Riverkeeper note that the EHB properly found the February 25,
    2017 DEP notice to be “misleading or incomplete,” but dispute the rest of the EHB’s
    conclusions for several reasons. Id. at 13-14. First, in at least one other matter
    involving DEP approval of a Water Quality Certification application, the parties
    challenging the DEP’s decision had never been “the subject of an injunction issued
    by [a] Federal District Court” impacting their ability to have an appeal heard by the
    EHB. Id. at 14. Second,
    contrary to the EHB’s contention, there certainly was a
    “downside” for [Riverkeeper] to file an appeal with the
    EHB. Given that [Riverkeeper] had already been subject
    to an [injunctive] order from the Federal District Court [in
    Northeast Upgrade Project], [Riverkeeper were]
    reasonably concerned that an appeal to the EHB could
    result in a claim that [their] appeal would be challenged as
    frivolous. In fact, opposing counsel in another natural gas
    pipeline matter threatened [Riverkeeper] with just such an
    action if [they] filed an appeal with the EHB. . . . [U]ntil
    the Third Circuit ruled in Orion that the failure to appeal
    to the EHB could result in prejudice, [Riverkeeper] had no
    basis for acting contrary to the ruling of the Federal
    District Court [in Northeast Upgrade Project].
    Id. at 15. Third, Riverkeeper claim that they acted with reasonable diligence by filing
    the Nunc Pro Tunc Petition 20 days after the Third Circuit issued the Orion decision.
    Riverkeeper argues that there is no firm guidance or fixed standard regarding how
    much time a party has to file a Nunc Pro Tunc Petition, other than by implication
    through the 30-day appeal window in the EHB’s regulations, and that “[r]equiring
    [Riverkeeper] to guess as to what shorter time frame will or will not preclude [their
    Supp. 2d at 382 (“Tennessee Gas Pipeline Company LLC (‘TGPC’) filed an Amended Complaint
    . . . and Amended Motion for Emergency Preliminary Injunction . . . on January 8, 2013 seeking,
    inter alia, a declaratory judgment that the [NGA] preempted [the EHB] from reviewing permits
    that the [DEP] had issued to TGPC as required by the Federal Energy Regulatory Commission’s
    (‘FERC’) Order dated May 29, 2012. . . . [T]he Court will grant TGPC’s Motion for Preliminary
    Injunction.”).
    15
    request for relief] would be arbitrary, capricious and a violation of their due process
    rights.” Id. at 16. Finally, Riverkeeper assert that neither the DEP nor PPC would
    be prejudiced by allowing a nunc pro tunc appeal, because the EHB would likely
    have stayed any appeal “pending the Third Circuit Court[’s] ruling on its jurisdiction
    in this matter.” Id. at 17.
    Unsurprisingly, PPC opposes Riverkeeper’s Petition for Review. PPC points
    out that Northeast Upgrade Project was an entirely separate matter involving a
    completely different pipeline project, as well as a completely separate pipeline
    company, and that the preliminary injunction issued in that action enjoined the EHB,
    not Riverkeeper, and thus had no injunctive effect upon either the EHB or
    Riverkeeper in this case. PPC’s Brief at 14-16. In addition, PPC argues that the
    EHB’s factual findings were supported by substantial evidence. Id. at 16-22. Finally,
    PPC again claims that both it and the DEP would be prejudiced by a nunc pro tunc
    appeal to the EHB because it would result in additional delays to the PennEast
    Project. Id. at 23-24.
    The DEP’s arguments on appeal are substantially similar to those advanced
    by PPC, with two significant additions. First, the DEP reiterates that the phrase “may
    file” in the February 25, 2017 DEP notice was not a directive to seek relief
    exclusively in the Third Circuit. DEP’s Brief at 10-11. Second, the DEP discusses
    more fully the import of Orion. According to the DEP,
    Riverkeeper’s characterization of the Third Circuit’s
    ruling in Orion is wrong[,] in that the Riverkeeper can
    point to no language in the decision where the [Third
    Circuit] “ruled that a party could prosecute a challenge of
    the DEP action related to a natural gas pipeline before the
    EHB.” [Riverkeeper’s Brief at 7]. Orion did recognize that
    “finality remains unresolved in this circuit”; however,
    Orion concluded that “finality and how such a requirement
    would interact with Pennsylvania’s administrative scheme
    16
    are issues better resolved in [other] cases” [then] pending
    before the [Third Circuit]. Orion, 870 F.3d at 177-178. As
    recognized by the EHB . . . Riverkeeper [have] not shown
    how the Orion decision . . . justifies [Riverkeeper’s]
    failure to file a timely appeal [with the EHB].
    Id. at 14.
    In their reply brief, Riverkeeper clarify the perceived impact of the Northeast
    Upgrade Project preliminary injunction, stating that “[o]bviously, [Riverkeeper
    were] not free to ignore the precedent of a federal court decision to which [they were]
    a party.” Riverkeeper’s Reply Brief at 4. Riverkeeper also opines that the fact that
    the EHB was enjoined in that action, rather than Riverkeeper, “is a distinction
    without a difference. The EHB appeal was instituted by [Riverkeeper]. [Riverkeeper
    were] sued as . . . defendant[s] in the federal district court. The result of the
    Tennessee Gas Pipeline prohibited [Riverkeeper] from pursuing [their] claims
    before the EHB.” Id. Riverkeeper further expands on the preliminary injunction
    issue in a footnote, stating
    [the] DEP and [PPC] also erroneously argue that
    [Riverkeeper claim they are] presently subject to a federal
    court injunction. [PPC] goes so far as to claim that
    [Riverkeeper’s] argument “makes it appear” as though the
    Middle District decision was an order in a proceeding
    involving the [PPC] Water Quality Certification. [PPC]
    Brief [at] 14. Neither of these arguments [is] accurate. As
    [Riverkeeper] clearly stated, the injunction had been
    issued by the federal court in a prior action - i.e. the
    [Northeast Upgrade Project] matter. The point of
    [Riverkeeper’s] argument is not that [they are] presently
    subject to the injunction but that [they] reasonably relied
    on the ruling of the federal district court and DEP’s clear
    instructions to file [their] appeal only in the Third Circuit
    Court of Appeals, until the Third Circuit issued its Orion
    decision.
    Id. at 4 n.2.
    17
    V.
    After careful review,10 we conclude that the EHB did not err or abuse its
    discretion in denying Riverkeeper’s Nunc Pro Tunc Petition. Riverkeeper were
    never enjoined, in this case or any other, from appealing DEP’s approval of a Water
    Quality Certification application to the EHB. Thus, Riverkeeper’s argument that
    they acted “with cognizance” of the Northeast Upgrade Project decision,
    Riverkeeper’s Brief at 12, which imposed a subsequently dissolved preliminary
    injunction against the EHB regarding an entirely separate pipeline matter, is
    unpersuasive. In addition, the Third Circuit has not, thus far, ruled that it has
    exclusive authority to entertain such challenges or that the NGA preempts the EHB
    from playing a role in the review process. Therefore, Riverkeeper were not precluded
    from filing an EHB appeal within the standard 30-day appeal window following the
    DEP’s approval of PPC’s application.
    Moreover, as the EHB noted in its opinion, Riverkeeper possess considerable
    knowledge and experience regarding challenges to DEP approvals of such
    applications, by virtue of Riverkeeper’s conduct and involvement in other, similar
    matters, thereby diminishing the likelihood that Riverkeeper were actually misled
    by the allegedly incomplete information in the DEP’s February 25, 2017 notice.
    Thus, this case is distinguishable from both California University and Moore, due to
    the uncontroverted evidence in those cases that the parties seeking nunc pro tunc
    10
    We note that Riverkeeper has waived one of its proffered claims by failing to raise it
    before the EHB—namely, that it was entitled to nunc pro tunc relief because it was justifiably
    concerned that an EHB appeal would be deemed frivolous and result in the imposition of sanctions.
    See Pa. R.A.P. 1551(a); Arnold v. Workers’ Comp. Appeal Bd. (Lacour Painting, Inc.), 
    110 A.3d 1063
    , 1071 (Pa. Cmwlth. 2015) (citations omitted) (“Our courts permit a litigant to make new
    arguments on appeal in support of a preserved issue . . . but do not permit a party to advance an
    entirely new and different theory of relief for the first time on appeal.”); Wert v. Dep’t of Transp.,
    
    821 A.2d 182
    , 186 (Pa. Cmwlth. 2003).
    18
    relief had received inaccurate guidance from governmental entities regarding their
    appellate rights and had relied on that information to their detriment. Finally,
    Riverkeeper never explained to the EHB precisely why, nearly seven months after
    the DEP’s approval of PPC’s application, Orion suddenly prompted it to decide that
    a nunc pro tunc administrative appeal was the correct course of action.
    Therefore, we agree with the EHB that Riverkeeper had no legal justification
    for failing to file a timely appeal with the EHB. We conclude that the EHB did not
    abuse its discretion in finding that Riverkeeper had shown neither that they relied on
    the misleading February 25, 2017 DEP notice nor that they acted diligently to
    preserve their appellate rights. Consequently, because Riverkeeper failed to establish
    “good cause” to permit the filing of an appeal nunc pro tunc with the EHB, we affirm
    the EHB’s October 24, 2017 Order.
    __________________________________
    ELLEN CEISLER, Judge
    Judge Fizzano Cannon did not participate in the decision of this case.
    19
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    The Delaware Riverkeeper           :
    Network and Maya van Rossum,       :
    The Delaware Riverkeeper,          :
    Petitioners       :
    :
    v.                            : No. 1571 C.D. 2017
    :
    Department of Environmental        :
    Protection,                        :
    Respondent        :
    ORDER
    AND NOW, this 1st day of August, 2018, the Order of the Pennsylvania
    Environmental Hearing Board, dated October 24, 2017, is hereby AFFIRMED.
    __________________________________
    ELLEN CEISLER, Judge