Hubley Twp. v. R. Wetzel Hegins Twp. v. Hubley Twp. and PA DEP ( 2018 )


Menu:
  •           IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Hubley Township,                    :
    Petitioner       :
    :
    v.                             : No. 899 C.D. 2017
    : SUBMITTED: April 12, 2018
    Roger Wetzel, William Wolfgang,     :
    Randy Shadle, Kenneth W. Richter,   :
    Kenneth Graham, Harry Mausser,      :
    and Hegins Township,                :
    Respondents       :
    Hegins Township,                    :
    Petitioner       :
    :
    v.                       : No. 969 C.D. 2017
    :
    Hubley Township and                 :
    Commonwealth of Pennsylvania        :
    Department of Environmental         :
    Protection,                         :
    Respondents        :
    BEFORE:    HONORABLE RENÉE COHN JUBELIRER, Judge
    HONORABLE ELLEN CEISLER, Judge
    HONORABLE DAN PELLEGRINI, Senior Judge
    OPINION NOT REPORTED
    MEMORANDUM OPINION
    BY JUDGE CEISLER                                 FILED: May 22, 2018
    In these consolidated appeals, Hubley Township (Hubley) petitions for review
    of the June 7, 2017 Adjudication of the Pennsylvania Environmental Hearing Board
    (Board), which (1) sustained the appeal of Roger Wetzel, William Wolfgang, Randy
    Shadle, Kenneth W. Richter, Kenneth Graham, and Harry Mausser (together,
    Landowners) and (2) vacated the Pennsylvania Department of Environmental
    Protection’s (DEP) April 17, 2015 approval of the Joint Act 537 Sewage Facilities Plan
    Update (Joint Plan) submitted by Hubley and Hegins Township (Hegins) pursuant to
    the Pennsylvania Sewage Facilities Act (Act).1 Hegins has also filed a Cross-Petition
    for Review, seeking reversal of the Board’s Adjudication only to the extent that it
    denied Hegins’ request to remand this matter to DEP for further public comment on
    the Joint Plan. For the reasons that follow, we reverse the Board’s Adjudication and
    deny Hegins’ request for a remand.
    Background
    Hubley and Hegins (together, the Townships) are neighboring municipalities
    located in Schuylkill County, Pennsylvania. Bd. Finding of Fact (F.F.) No. 3. On
    October 3, 2013, the Townships and the Hegins-Hubley Water Authority executed an
    intermunicipal agreement, authorizing the Authority to develop, finance, construct, and
    operate a sewage collection and treatment system serving both Townships. Bd.
    Adjudication at 13. Under the intermunicipal agreement, the Hegins-Hubley Water
    Authority would ultimately take control of implementing the Townships’ Joint Plan.
    Bd. F.F. No. 71.
    1
    Act of Jan. 24, 1966, P.L. (1965) 1535, as amended, 35 §§ P.S. 750.1-750.20a. The purpose
    of the Act is “to ensure public health, safety and welfare of the citizens by providing for a technically
    competent, integrated and coordinated system of sanitary sewage disposal.” Section 3 of the Act, 35
    P.S. § 750.3. Section 5 of the Act requires every municipality to adopt an official plan, commonly
    known as an “Act 537” plan, subject to DEP’s approval. 35 P.S. § 750.5. Municipalities are required
    to update their Act 537 plans to account for new development and other changes that impact sewage
    capacity. 
    Id. The Act
    permits two municipalities to submit a joint Act 537 plan or any revisions thereto.
    Section 5(c) of the Act, 35 P.S. § 750.5(c). It also sets forth a policy favoring intermunicipal
    cooperation in implementing and administering Act 537 plans. Section 3(2) and (3) of the Act, 35
    P.S. § 750.3(2), (3). However, the Act does not require the submission of a joint Act 537 plan, even
    where two municipalities share a sewage treatment facility.
    2
    On August 4, 2014, the Townships submitted their Joint Plan to DEP. Bd. F.F.
    No. 4. The Joint Plan was the first comprehensive revision to the Townships’ Act 537
    plans since 1967. Bd. F.F. No. 63. In the Joint Plan, the Townships proposed the
    construction of a 600,000-gallon-per-day wastewater treatment plant in Hubley. Bd.
    F.F. No. 4. They also proposed the installation of public sewers in various sections of
    both Townships where there had been on-lot septic malfunctions and direct discharges
    of raw sewage into Commonwealth waters. Bd. Adjudication at 12.
    On September 8, 2014, DEP issued preliminary comments to the Townships
    about the Joint Plan. Bd. F.F. No. 5. On September 23, 2014, DEP received a response
    from the Townships. Bd. F.F. No. 6. On March 20, 2015, DEP sent a comment letter
    to the Townships, outlining 13 technical issues with the Joint Plan. Bd. F.F. Nos. 7-8.
    On April 6, 2015, the Townships responded to DEP’s comments via letter and provided
    supplementary materials in support of the Joint Plan. Bd. F.F. No. 9. No public
    hearings were held on the Joint Plan following the Townships’ April 6, 2015 letter.
    Bd. F.F. Nos. 10, 70. Both Townships passed resolutions approving the Joint Plan
    before obtaining DEP’s approval. Bd. F.F. Nos. 15, 60.2
    On April 17, 2015, DEP issued a written decision approving the Joint Plan. Bd.
    F.F. No. 12. Landowners, who own properties within the proposed planning area,
    appealed DEP’s approval of the Plan. Bd. F.F. No. 13. In their Notice of Appeal,
    Landowners raised various objections, primarily asserting that the costs of the Joint
    Plan were unreasonable and unjustifiable. Both Townships initially joined DEP in
    defense of the Joint Plan. Bd. Adjudication at 14, 37. During the pendency of the
    2
    On April 13, 2015, the Hegins Township Board of Supervisors passed a resolution approving
    the Joint Plan. Bd. F.F. No. 66. Kenneth W. Richter, a Landowner in this appeal, attended the April
    13, 2015 meeting and voiced his objection to the Joint Plan. 
    Id. Richter also
    sits on the Board of the
    Hegins-Hubley Water Authority. Bd. F.F. No. 64.
    3
    appeal, however, Hegins changed positions and decided to join Landowners’ challenge
    to the economic unfeasibility of the Joint Plan. 
    Id. at 37.
           The Board held a two-day evidentiary hearing on April 19 and April 20, 2016.
    At the hearing, Hegins’ counsel stated:
    It’s become clear that the Plan as written is to benefit certain individuals
    within Hubley Township, all done at the detriment of residents of Hegins
    Township. The record evidence will show that coincidentally, as the Plan
    stands now, the sewage treatment facility center is planned to go on the
    property of one of the members of the Board of Supervisors of Hubley
    Township.
    N.T., 4/19/16, at 7-8.3 Hegins’ position at the hearing was that the Joint “Plan as written
    severely underestimates the true cost of the project.” 
    Id. at 8.
    Landowners’ expert,
    Entech Engineering, Inc. (Entech), projected the cost to be $38 million, whereas
    Hubley’s expert, Alfred Benesch and Company (Benesch), projected the cost to be $26
    million.4 Hegins maintained that DEP “only relied on Benesch’s estimates which
    3
    The only express reference at the hearing to Hegins’ change of position (from supporting the
    Joint Plan to opposing it) was the following statement by the presiding administrative law judge:
    When we had our call last week, we had talked about the order of presentation.
    [Landowners] have the burden so we’re going to proceed first with [Landowners’]
    case. Because of the unusual posture of Hegins Township who had initially supported
    the Plan and now is opposed to the Plan, I think we agreed that you would go second
    followed by [DEP] and then Hubley Township. So we’ll proceed that way.
    N.T., 4/19/16, at 11.
    4
    Entech prepared its report in February 2016. See N.T., 4/19/16, Ex. A-12. In its report,
    Entech stated that it was requested to do so “by the Hegins Township Board of Supervisors at their
    January 4, 2016 meeting.” 
    Id., Ex. A-12,
    at 1. Hegins and Landowners also presented the expert
    report and testimony of engineer Frederick Ebert, who opined that DEP “failed to require Hegins and
    Hubley Townships to properly prepare the 537 Plan” in accordance with the regulations and that the
    Joint Plan “did not meet the requirements of a complete alternative evaluation and accurate
    construction cost estimates . . . to provide the public with a complete understanding of all the
    wastewater alternatives.” 
    Id., Ex. A-10,
    at 1. Ebert prepared his expert report in December 2015.
    4
    severely underestimated true costs of the Plan.” 
    Id. Hubley’s position,
    in contrast, was
    that both Townships had “agreed both through municipal action, ordinances, . . . and
    through an intermunicipal agreement to hire Benesch . . . to prepare an Act 537 Plan,
    to investigate what was needed to put that Plan together, and to come up with a Plan
    that could be submitted to DEP; and that’s what they did.” 
    Id. at 10.
           Following the hearing and additional briefing by the parties, the Board
    concluded that the Joint Plan satisfied all regulatory requirements and that the Joint
    Plan, as approved by DEP, was feasible and able to be implemented. Bd. Adjudication
    at 28.5 The Board found, however, that Hegins was not committed to implementation
    of the Joint Plan. Bd. Conclusion of Law (C.L.) No. 12. Although the Board
    determined that DEP acted reasonably at the time it approved the Joint Plan, the Board
    found that circumstances had changed because Hegins had since demonstrated that it
    lacked the necessary commitment to implement the Joint Plan. Bd. C.L. No. 10; Bd.
    Adjudication at 40-41. The Board noted that an Act 537 plan cannot be upheld if the
    municipality lacks the commitment to implement it. Bd. Adjudication at 37 (citing
    Wilson v. DEP, 2010 EHB 827 (2010)). The Board explained:
    Hegins Township worked with Hubley Township to prepare and
    submit the Joint Act 537 Plan . . . [and] to respond to review comments
    from [DEP] and during the public notice procedures to respond to public
    comments. After [Landowners] filed their appeal challenging [DEP’s]
    decision[,] the two Townships retained a single counsel to represent
    the[m] . . . in the appeal. During the initial stages of litigation, the two
    Townships presented a joint effort to defend their Joint Act 537 Plan. But
    then in late 2015 or early 2016, something appears to have altered Hegins
    Township’s position.
    5
    See 25 Pa. Code § 71.32(d)(4) (“In approving or disapproving an official plan or official plan
    revision, [DEP] will consider . . . [w]hether the official plan or official plan revision is able to be
    implemented.”); 
    Id. § 71.31(f)
    (“The municipality shall adopt the official plan by resolution, with
    specific reference to the alternatives of choice and a commitment to implement the plan within the
    time limits established in an implementation schedule.”).
    5
    ....
    Since it switched sides in this appeal to support [Landowners] and
    to stop defending its Joint Act 537 Plan, Hegins Township has actively
    supported [Landowners] in their challenge. Hegins Township often took
    the lead at the Hearing in presenting witnesses and conducting direct and
    cross examination. Hegins Township prepared the main Post-Hearing
    Brief that [Landowners] simply incorporated by reference as their brief.
    Hegins Township’s actions since January 2016 when it switched
    sides to support [Landowners] in their challenge to the Joint Act 537 Plan
    is a strong indication that Hegins Township no longer has the commitment
    to implement its Joint Act 537 Plan under Sections 71.32(d)(4) and
    71.31(f) [of the Pennsylvania Code]. 25 Pa. Code §§ 71.31(f) and
    71.32(d)(4).
    ....
    . . . The circumstances have changed since [DEP] approved the
    Plan, and the Board is authorized and required to consider these changed
    circumstances since [DEP] took its action under appeal. Through its
    words and actions, Hegins Township has demonstrated that it no longer
    has the required municipal commitment to implement the Joint Act 537
    Plan.
    
    Id. at 37-38,
    40-41 (footnote omitted).6 Therefore, the Board sustained Landowners’
    appeal and vacated DEP’s approval of the Joint Plan. Both Hubley and Hegins now
    petition for review of that decision.
    6
    Two of the five Board members dissented, finding that the majority improperly vacated
    DEP’s approval of the Joint Plan on a ground “not raised by any of the parties.” Bd. Adjudication at
    50 (emphasis in original). First, the dissent emphasized that “[n]o party, including [Landowners],
    who bear the burden of proving that [DEP] erred, has presented any argument or evidence to support
    the Majority’s conclusion that Hegins is not committed to implementing the plan update.” 
    Id. Second, the
    dissent believed that the majority improperly relied on Wilson v. DEP, 2010 EHB 827
    (2010), to justify its sua sponte action. 
    Id. at 51.
    The dissent distinguished Wilson as follows:
    First, the appellants in Wilson did in fact argue that the plan needed to be vacated due
    to a lack of commitment. No party in the case now before us even cited Wilson.
    Second, [DEP’s] action in Wilson was not supported by the facts when it was taken
    because it was undisputed that the Township, even at that time, had decided not to
    implement the plan. Subsequent events confirmed the lack of commitment, but that
    6
    Parties’ Arguments on Appeal
    Hubley asserts that this Court should reverse the Board’s decision for the
    following reasons. First, the Board erred in finding that Hegins was not committed to
    implementing the Joint Plan based solely on Hegins’ alignment with Landowners’
    position during the appeal. There is no evidence of record to support the Board’s
    finding. Hegins did not repeal its resolution supporting the Joint Plan, nor had it taken
    any steps to withdraw from or rescind its intermunicipal agreement with Hubley and
    the Hegins-Hubley Water Authority. The Board erroneously presumed that Hegins
    would no longer take affirmative steps to implement the Joint Plan or negotiate with
    Hubley to modify the Joint Plan if the Board were to deny Landowners’ appeal.
    Second, DEP correctly determined that the Joint Plan complied with its regulations,
    and DEP’s interpretation is entitled to deference absent a showing of a manifest abuse
    of discretion. Third, the Board’s sole basis for sustaining Landowners’ appeal—
    Hegins’ purported lack of commitment—was not raised or addressed by any of the
    parties. Finally, the Board’s decision directly conflicts with the Act’s policy to protect
    public health, safety, and welfare.
    DEP, an intervenor in this appeal, argues that the Board’s sua sponte finding that
    Hegins lacked the commitment necessary to implement the Joint Plan is unsupported
    by substantial evidence. All of Hegins’ official municipal actions, as found by the
    Board, demonstrated its commitment to implementing the Joint Plan. The Board also
    lack of commitment could be traced back to the time of [DEP’s] decision, which is
    what we review. That is not the case here. Third and most importantly, the Township
    in Wilson, contemporaneously with the Board proceeding, was in fact following proper
    procedures to further revise its plan in accordance with the Act. Indeed, the Township
    had already entered into a consent order and agreement [(COA)] with [DEP], and it
    was actively revising its plan in accordance with the law and that COA. Again, that is
    not the case here.
    
    Id. Thus, the
    dissent would have upheld DEP’s “lawful and reasonable decision.” 
    Id. at 52.
                                                     7
    erred in taking judicial notice of Hegins’ alleged lack of commitment without giving
    the parties an opportunity to be heard on the matter.
    In contrast, Hegins contends that the Board properly took judicial notice that
    Hegins lacked the requisite intent to implement the Joint Plan. Hegins’ persistent
    opposition to the Joint Plan during the course of the appeal was substantial evidence of
    its lack of commitment. Hegins further contends that if this Court reverses the Board’s
    decision, we must remand to DEP for additional public comment due to significant
    changes made to the Joint Plan during the review period.
    Landowners likewise assert that the Board correctly sustained their appeal based
    on Hegins’ lack of commitment. Hegins clearly demonstrated on the face of the record
    that it no longer had the necessary commitment to implement the Joint Plan by actively
    opposing it throughout the appeals process.
    Analysis
    Our review of the Board’s Adjudication is “limited to determining whether
    constitutional rights have been violated, an error of law has been committed, or whether
    necessary findings of fact are supported by substantial evidence.” Oley Twp. v. Pa.
    Dep’t of Envtl. Prot., 
    710 A.2d 1228
    , 1230 (Pa. Cmwlth. 1998). Substantial evidence
    is “relevant evidence upon which a reasonable mind could base a conclusion.”
    Kiskadden v. Pa. Dep’t of Envtl. Prot., 
    149 A.3d 380
    , 387 (Pa. Cmwlth. 2016). We
    “must review the adjudication of the Board rather than the administrative action which
    was reviewed by the Board.” United Refining Co. v. Dep’t of Envtl. Prot., 
    163 A.3d 1125
    , 1136 (Pa. Cmwlth. 2017) (quoting another source).
    1. Hubley’s Petition for Review
    Hubley asserts that the Board erred in vacating DEP’s approval of the Joint Plan
    based solely on the Board’s sua sponte finding that Hegins lacked the necessary
    8
    commitment, where the Board concluded, based on the substantial record evidence,
    that the Joint Plan complied with all applicable regulations. We agree.
    On appeal to the Board, the party challenging DEP’s action has the burden of
    proving that DEP acted arbitrarily or abused its discretion. Pa. Trout v. Dep’t of Envtl.
    Prot., 
    863 A.2d 93
    , 105 (Pa. Cmwlth. 2004). The Board is required to conduct a
    hearing de novo. 
    Id. “The Board’s
    de novo review allows it to admit and consider
    evidence that was not before [DEP] when it made its initial decision, including
    evidence developed since the filing of the appeal.” United 
    Refining, 163 A.3d at 1136
    .
    The Board must “determine[] the reasonableness and legality of [DEP’s] actions based
    upon the record developed before the Board.” 
    Id. After a
    two-day, de novo hearing, the Board concluded that DEP’s approval of
    the Joint Plan was neither arbitrary nor an abuse of discretion. Bd. C.L. No. 4. In fact,
    the Board determined that the Joint Plan complied with all applicable DEP regulations
    and was both economically feasible and able to be implemented. Bd. C.L. Nos. 5, 9;
    Bd. Adjudication at 28. Based on the evidence presented at the hearing, the Board
    concluded as follows:
    4. At the time [DEP] approved the Plan, [Landowners] ha[d] not met their
    burden of demonstrating that [DEP] abused its discretion in approving the
    Joint Act 537 Plan. See Browning-Ferris Industries, Inc. v. DEP et al.,
    
    819 A.2d 148
    , 153 (Pa. Cmwlth. 2003) citing Pequea Township v. Herr,
    
    716 A.2d 678
    (Pa. Cmwlth. 1998).
    5. At the time [DEP] approved the Plan, [DEP] acted reasonably when it
    determined that the Joint Act 537 Plan satisfied all applicable laws and
    regulations and approved the joint plan update revision on April 17, 2015.
    35 P.S. § 750.1 et seq., 25 Pa. Code Chapters 71-73.
    6. [DEP] properly determined that Hegins Township and Hubley
    Township satisfied all applicable public notice and comment requirements
    9
    in preparing its joint plan update revision. 25 Pa. Code §§ 71.31(c),
    71.32(d)(2).
    7. [DEP] properly determined that Hegins Township and Hubley
    Township reasonably identified, evaluated, and selected sewage disposal
    alternatives. 25 Pa. Code §§ 71.21(a)(6), 71.61(c).
    8. [DEP] properly determined that the Joint Act 537 Plan is “technically,
    environmentally, and administratively acceptable” for the current and
    planned sewage disposal needs. 25 Pa. Code § 71.21(a)(6).
    9. At the time [DEP] approved the Plan, [DEP] reasonably determined that
    Hegins and Hubley Townships were able and committed to implement
    their joint plan update revision when it was approved. 25 Pa. Code §§
    71.32(d)(4), 71.31(f).
    Bd. C.L. Nos. 4-9.
    With regard to the economic feasibility of the Joint Plan, the Board specifically
    credited the testimony of Hubley’s expert over that of Landowners’ experts,7
    concluding that Landowners “had not met their burden to establish that the Joint Act
    537 Plan is not able to be implemented based on inaccurate cost estimates and
    economic feasibility.” Bd. Adjudication at 30. The Board stated:
    While [Landowners] and Hegins Township have identified a number of
    legitimate concerns regarding the implementation of the Plan . . . , the
    Board finds that [DEP] and Hubley Township have addressed these
    concerns to the extent necessary to support [DEP’s] decision to approve
    the [Joint] Plan under the applicable regulatory requirements. [DEP] has
    the authority and discretion to evaluate whether a plan revision is “able to
    be implemented” on a case-by-case basis. [Landowners] and Hegins
    Township have not met their burden of proof to establish that [DEP] acted
    in a way that was unreasonable, contrary to law, not supported by the facts,
    or that was inconsistent with [DEP’s] obligations under the Pennsylvania
    7
    The Board discredited Landowners’ expert, Frederick Ebert, based on its concerns about his
    potential bias because Ebert owns property in Hegins, his parents live in Hegins, and “there are
    questions as to whether he reviewed all of the materials in the Plan files.” Bd. Adjudication at 30-31.
    10
    Constitution, when it decided that the Joint Act 537 Plan is “able to be
    implemented.”
    
    Id. at 33.
           Despite these conclusions, however, the Board ultimately determined that
    “changed circumstances” demonstrated Hegins’ lack of commitment to the Joint Plan.
    Bd. C.L. Nos. 10, 12. This conclusion was based solely on events that took place after
    Landowners had filed their appeal. In doing so, the Board reasoned that it is permitted
    to take judicial notice of facts contained in filings on its own docket. Bd. Adjudication
    at 43; see 25 Pa. Code § 1021.125(a)(3) (stating that “[t]he Board may take official
    notice of . . . [r]ecord facts reflected in the [Board’s] official docket”). However, the
    Board repeatedly indicated that it did not know why Hegins had changed its position,
    and Hegins introduced no evidence to explain its change of position at the hearing. See
    Bd. Adjudication at 37 n.17 (“The Board does not know what, if anything, happened
    to trigger Hegins Township[’s] abrupt change in position.”); 
    id. at 37
    (noting that in
    early 2016, “something appears to have altered Hegins Township’s position”).8 Absent
    any evidence on that specific issue, the Board merely speculated about Hegins’ future
    intentions, which is beyond the scope of the Board’s review powers. See United
    
    Refining, 163 A.3d at 1136
    .
    Moreover, the record shows that Hegins formally passed a resolution adopting
    the Joint Plan and denoting its commitment to implementing the Joint Plan. See 25
    Pa. Code § 71.31(f) (requiring municipality to “adopt the official plan by resolution,
    with specific reference to the alternatives of choice and a commitment to implement
    8
    It appears that Hegins neither addressed nor explained its reason for abruptly changing
    positions until the present appeal. In its brief filed with this Court, Hegins states that in January 2016,
    a new Hegins Township Board of Supervisors took office, after which Hegins notified Hubley, DEP,
    and the Board that it would align with Landowners and oppose DEP’s approval of the Joint Plan.
    Hegins Br. at 6-7. According to Hegins, the “Board of Supervisors expanded from three to five
    members and due to the deficiencies in the Joint Plan, especially its economic unfeasibility, Hegins
    Township decided to support [Landowners’] appeal.” 
    Id. at 13
    n.2.
    11
    the plan within the time limits established in an implementation schedule.”). Hegins
    also entered into an intermunicipal agreement with Hubley, authorizing the Hegins-
    Hubley Water Authority to implement, build, and operate the Townships’ chosen
    sewage treatment alternative. All of Hegins’ official municipal actions, which were
    made part of the record, support the Board’s conclusion that “[DEP] reasonably
    determined that Hegins and Hubley Townships were able and committed to implement
    their joint plan update revision when it was approved.” Bd. C.L. No. 9.
    Critically, Hegins took no official action, consistent with the Act’s requirements,
    to modify or rescind its adopted resolution or the Townships’ intermunicipal
    agreement. Bd. F.F. No. 62. Rather, Hegins unilaterally decided, mid-appeal, that it
    no longer wished to support the Joint Plan, apparently due to a change in township
    leadership. See Hegins Br. at 6-7. However, a municipality cannot “undo” an official
    resolution simply by declaring to the Board and this Court that it has “changed its
    mind” without going through the proper procedural channels. See Section 5(a) of the
    Act, 35 P.S. § 750.5(a) (stating that any revisions to an Act 537 plan “shall conform to
    the requirements of subsection (d) of this section and the rules and regulations of
    [DEP]”).
    We agree with Hubley and DEP that the Board’s ruling undermines the Act’s
    procedures and contradicts the Act’s express policy of protecting “public health, safety
    and welfare of the citizens by providing for a technically competent, integrated and
    coordinated system of sanitary sewage disposal.” Section 3 of the Act, 35 P.S. § 750.3.
    We will not permit Hegins to escape its public commitment, and its agreed-upon
    obligation, to work with Hubley and the Hegins-Hubley Water Authority to implement
    a viable sewage treatment plan without following “the proper and transparent
    procedures outlined in the Sewage Facilities Act.” Bd. Adjudication at 51.
    12
    For these reasons, we conclude that the Board erred in vacating DEP’s approval
    of the Joint Plan based solely on its sua sponte finding that Hegins lacked the requisite
    commitment.         The Board’s decision is particularly disconcerting in light of the
    substantial, credible evidence of record to support DEP’s approval of the Joint Plan, as
    the Board itself found. See Bd. C.L. Nos. 4-9; see also Bd. Adjudication at 50
    (recognizing that the Joint Plan “would have gone a long way toward solving [both]
    Townships’ sewage problems”). Therefore, we reverse the Board’s Adjudication.
    2. Hegins’ Cross-Petition for Review
    In its Cross-Petition for Review, Hegins asks this Court to remand this matter to
    DEP for additional public comment on the most recent revisions to the Joint Plan.9
    Hegins contends that additional public comment is both necessary and required because
    DEP approved the Joint Plan, without additional public comment, only 11 days after
    receiving “significant” changes to the Joint Plan in April 2015. We disagree.
    DEP’s March 20, 2015 letter outlined several “significant concerns” that the
    Townships needed to address. Bd. F.F. No. 83. After reviewing the Townships’ April
    6, 2015 response, DEP determined that the Townships’ changes to the Joint Plan did
    not alter either the nature or scope of the Joint Plan. Id.; see N.T., 4/20/16, at 247-48.10
    9
    Hegins states that its Cross-Petition “is conditional and limited in that it seeks reversal of the
    [Board’s Adjudication] only to the extent [the Board] denied Hegins’ alternative request to remand
    this matter back to the DEP and instruct the DEP to require [the Townships] to open the Joint Plan to
    public comment in light of significant revisions and supplementations made to it on April 6, 2015.”
    Hegins’ Br. at 2. Hegins “only seeks such reversal if this Court reverses [the Board’s] decision.” 
    Id. Because we
    are reversing the Board’s Adjudication, we must address Hegins’ request for a remand.
    10
    DEP representative Darryl Fritz explained some of the changes as follows:
    I went down to the . . . April 6th response from Benesch [Engineering] and looked at
    the issues and the contents to see if there was any change in the nature, scope of the
    project. Did it include more area? Did it delete area? Which it did not. The service
    13
    Specifically, DEP concluded that the revisions in the Townships’ letter, while
    considerable in number, were not so significant in substance as to require additional
    public comment. 
    Id. at 253.
           Based on its review of the record, the Board agreed with DEP that the
    Townships’ April 6, 2015 letter did not change the nature or scope of the Joint Plan
    and their “responses and related clarifications and changes were not themselves
    significant.” Bd. Adjudication at 22-23; see Bd. F.F. No. 83 (“The fact that [DEP’s]
    concerns were viewed by [DEP] as significant does not necessarily make the
    Township[s’] responses to those concerns and the related changes to the Plan
    significant.”). Because we conclude that the Board did not abuse its discretion in this
    regard, we deny Hegins’ request for a remand to DEP.
    Conclusion
    Accordingly, we reverse the Board’s Adjudication and deny Hegins’ request for
    a remand.
    __________________________________
    ELLEN CEISLER, Judge
    area mapping that they provided was consistent with what the plan had provided for
    before.
    There were some cost changes due to the addition of -- the parcel acquisition costs. [I]
    [t]ook a look at how that affected the user rates. And the user rates, I believe, were
    affected somewhere in the range of 22 to 24 cents a month. That user rate was still
    within the range that was in the original public notice.
    N.T., 4/20/16, at 248.
    14
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Hubley Township,                     :
    Petitioner        :
    :
    v.                             : No. 899 C.D. 2017
    :
    Roger Wetzel, William Wolfgang,      :
    Randy Shadle, Kenneth W. Richter,    :
    Kenneth Graham, Harry Mausser,       :
    and Hegins Township,                 :
    Respondents        :
    Hegins Township,                     :
    Petitioner        :
    :
    v.                       : No. 969 C.D. 2017
    :
    Hubley Township and                  :
    Commonwealth of Pennsylvania         :
    Department of Environmental          :
    Protection,                          :
    Respondents         :
    ORDER
    AND NOW, this 22nd day of May, 2018, the Adjudication of the Pennsylvania
    Environmental Hearing Board, dated June 7, 2017, is hereby reversed, and Hegins
    Township’s request for a remand to the Pennsylvania Department of Environmental
    Protection is hereby denied.
    __________________________________
    ELLEN CEISLER, Judge