Bonarrigo Enterprises, Inc. v. Highridge Water Authority ( 2018 )


Menu:
  •            IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Bonarrigo Enterprises, Inc.,          :
    Appellant           :
    :
    v.                        : No. 928 C.D. 2017
    : Argued: February 6, 2018
    Highridge Water Authority             :
    BEFORE:     HONORABLE P. KEVIN BROBSON, Judge
    HONORABLE PATRICIA A. McCULLOUGH, Judge
    HONORABLE DAN PELLEGRINI, Senior Judge
    OPINION NOT REPORTED
    MEMORANDUM OPINION BY
    SENIOR JUDGE PELLEGRINI                        FILED: February 27, 2018
    Bonarrigo Enterprises, Inc. (BEI) appeals from the order of the Court of
    Common Pleas of Indiana County (trial court) denying its motion for post-trial relief
    from an order entered on April 10, 2017 (2017 Order), because the trial court found
    that despite representations to the contrary, Highridge Water Authority (Authority)
    elected not to provide water service to BEI pursuant to a previous order issued by the
    trial court on August 26, 2015.
    I.
    In 2004, Russell J. Bonarrigo, II (Bonarrigo) purchased 3.71 acres
    located at 64 Rocky Road, Burrell Township, Pennsylvania (Property) on which he
    wanted to operate a recreational vehicle park. He installed an eight-inch service line
    as well as sewage and electric on the Property. Although the Lower Indiana County
    Municipal Authority originally provided water service to the Property, in 2008,
    Bonarrigo granted an easement to the Authority for that service line after which the
    Authority took over the system.
    By deed dated April 23, 2012, Bonarrigo transferred the Property to BEI,
    which is the Property’s current owner. BEI submitted an application and payment to
    the Authority for establishing water service to the Property, and in late 2012, the
    Authority made one tap-in connection on the Property and initiated water service.
    BEI then began operating a recreational vehicle (RV) campground for up to 18
    campers, depending on the season. After the water passes through the Authority’s
    meter, BEI then transports water to each RV through individual hoses connecting to
    the service line.
    While the Property’s service line was above ground when the Authority
    began providing water service, sometime before the winter of 2012-13, BEI buried
    the Property’s water, sewage and electric lines.
    Roughly one-year-and-half years later, in the summer of 2014, the
    Authority terminated BEI’s water service.          Before it would reinstate service, it
    demanded that each of the 18 RV pads have an individual tap-in connection because
    servicing those vehicles through a single tap-in connection violated its Rules and
    Regulations. Then, on February 2, 2015, the Authority filed for a municipal lien
    against the Property for $10,363 alleging that BEI defaulted on payment of tap-in fees
    and other costs.
    2
    The Authority then filed an action requesting that the trial court require
    BEI to connect all RVs on its Property to the public water system immediately and to
    cease use of the Property for such purpose until that occurred. In response, BEI filed
    a complaint seeking declaratory judgment that the Authority violated its own
    regulations by imposing multiple tap-in fees on the Property and an order directing
    the Authority to provide water service to the Property through the existing tap, and to
    strike the municipal liens.
    Following a hearing, testimony and various filings by both parties, the
    trial court entered an order on August 26, 2015 (2015 Order), holding that the
    Authority was not permitted to charge an individual tap-in fee for each recreational
    vehicle pad and found the $10,363 municipal lien was null and void. The trial court
    also held:
    [The Authority] has the following two options: [the
    Authority] can require [BEI] to connect to the Highridge
    Water System . . . keeping in mind that a tapping fee cannot
    be charged for each recreational vehicle. Or, Highridge can
    decide not to provide water service to the recreational
    vehicles on the [Property], keeping in mind that Highridge
    cannot prevent Bonarrigo from providing another water
    source for the recreational vehicles on the [Property].
    (Trial Court Order dated August 26, 2015.) Neither party appealed that order.
    II.
    Following the 2015 Order, BEI made a written request for the Authority
    to advise as to the steps to restore water service to the Property. In response, the
    3
    Authority provided BEI with an Application of Service.           BEI submitted that
    application, circling the option to “turn on” service – as opposed to the other option
    of “new tap.” (Reproduced Record (R.R.) at 387a.)
    In response, the Authority sent a letter dated May 5, 2016, providing:
    Enclosed are the conditions for receiving water now
    that we have received your application for service.
    1. Authority rules and regulations require:
    a) That the entire layout throughout the site be
    inspected prior to being backfilled;
    b) Each unit served shall have its own curb stop and
    check valve;
    c) Blowoffs must be installed at the ends of the
    “private water system” being built;
    2. The maximum number of units (15) may not be
    exceeded unless written permission is provided by the
    Authority.
    3. The minimum monthly water bill for fifteen units is
    $239.80 and includes 22,000 gallons. Water usage in
    excess of this amount shall be billed at $8.40 per thousand
    gallons.
    There is also the issue of your past due bill. Because
    a mandatory connection notice exists for Burrell Township,
    and you had not made the necessary arrangements to legally
    connect, a monthly bill was assessed which now totals
    $603.76. This must also be satisfied prior to water service
    being rendered.
    (R.R. at 306a) (emphasis added).
    4
    Because BEI refused to dig up all of the Property’s service lines so that
    they could be visually inspected, the Authority denied water service to the Property.
    Notwithstanding, the Authority continued to impose monthly “water” and service
    charges totaling $2,633.04. (R.R. at 305a.)
    III.
    In August 2016, BEI filed a three-count complaint for declaratory
    judgment.    Count I contends that the Authority’s demand to inspect the entire
    premises is not permitted by its Rules and Regulations and is unlawful and unduly
    burdensome. Count II contends that the Authority’s ongoing billing practices were
    improper because no service was being provided to the Property. Count III sought an
    order compelling the Authority to provide water to the Property on the basis that it
    was not applying its Rules and Regulations uniformly.
    In its Answer, the Authority denied any non-uniform and/or unlawful
    application of its Rules and Regulations and as it relates to Count II, “denied that the
    Authority refused to provide water service, as the Authority merely requires [BEI] to
    abide by its Rules and Regulations in order to obtain water, which [BEI] has failed
    and refused to do.” (R.R. at 60a.) In its prayer for relief, the Authority requested the
    trial court to “permit the Authority to inspect the waterlines on [the Property],
    including the individual service lines, permit the Authority to charge for water
    services provided to [BEI,] and to deny the request to mandate the Authority to
    supply water to the [Property] until [BEI] comes into compliance with the Rules and
    Regulations of the Authority . . . .” (R.R. at 62a.)
    5
    IV.
    A.
    At the February 13, 2017 bench trial, BEI presented the testimonies of
    Bonarrigo and Mark Olechovski (Olechovski), a BEI employee for the last 26 years,
    to describe the Property’s service line as well as how and why it was buried. The
    testimony can be summarized as follows. In 2007, Olechovski installed an eight-inch
    service line with a backflow preventer on the meter set.1 While the service line was
    originally above ground, after the Authority began providing service to the Property
    in 2012, the waterline as well as other utility lines to service each RV pad were
    buried below the frost line. Water is now provided to each RV through use of a hose
    that connects to the service line. Until July 2014, the Authority continued providing
    service to the Property even after the service line was buried.
    Regarding its claim that the Authority was enforcing its Rules and
    Regulations in a non-uniform manner, BEI presented the testimony of Bernard David
    Myers (Myers), the owner of a five-acre trailer park in Westmoreland County. He
    testified that his property contains 12 trailer pads that receive water service through
    one Authority tap-in connection. Although the Authority had to relocate that tap-in
    connection, it has never required any further inspection of the buried service line on
    that property. He testified, though, that the single connection was installed prior to
    his acquisition of the property.
    1
    Although there was no testimony as to the actual length of the Property’s waterline, BEI
    submitted into evidence a Water & Sanitary Sewer Plan (Plan) for the proposed development of
    approximately 16 multi-bedroom apartment buildings that would surround the Property and use its
    waterline. (See R.R. at 313a.) While the Plan does not include the exact length of the waterline, we
    note that if read to scale, that it would be somewhere between 450 to 500 feet in length.
    6
    Also regarding the disparate treatment issue, BEI presented the
    testimony of Gary Clawson (Clawson), a general contractor who has done work on
    approximately 30 properties serviced by the Authority. He testified that one of those
    properties was a 300-acre property in Westmoreland County (Dolan Property), on
    which there was a residence and three outbuildings. In 2015, he dug and built a
    9,000-foot connection to the main residence and requested the Authority to come and
    inspect it before he buried the line. He testified that the Authority did not come to
    inspect until the next day, when approximately a quarter of the 9,000-foot line was
    already buried. While the Authority originally told him that he would need to dig up
    the line, to date, the Authority has never required those buried lines be excavated or
    inspected.
    In response, George Edward Sulkosky, Jr. (Sulkosky), the Executive
    Director of the Authority since its foundation, testified. Regarding the continuous
    billing of the Property, Sulkosky testified that the Property’s water and service
    charges are based on a minimum of 11 RV units. He further explained that if BEI
    desired to discontinue those charges, it could request that the meter be pulled.
    Regarding the alleged non-uniform application of the Authority’s Rules
    and Regulations, Sulkosky explained that the Authority provided service to the Dolan
    Property without first inspecting the entire service line because those owners signed a
    supplemental application and/or agreement stating that they would be responsible for
    any detrimental effects to the Authority’s water system if there is a leak, which was
    then recorded with the deed. He also explained that the Authority did not require an
    7
    inspection of Myers’ buried service line because, unlike BEI’s service line, it was
    constructed and buried well before the Authority serviced that property.
    Michael Caugherty (Caugherty), the Vice Chairman of the Authority,
    testified that Section 5.04 of the Authority’s Rules and Regulations2 provide that the
    Authority must be notified prior to backfilling any trench in which a service line is
    placed so that it can be inspected. While BEI requested that the Authority’s Board of
    Directors (Board) waive or modify that regulation, the Board voted six to one that it
    wanted the service line uncovered for inspection.3 Caugherty explained that if BEI
    2
    Section 5.04 of both the 1991 and 2015 Highridge Water Authority Rules and Regulations,
    provides:
    When the installation of the Customer Facilities is completed, the
    Authority shall be notified, prior to any backfilling of the trench, in
    order that the installation be inspected and improved in the open
    trench. No water service will be supplied through an installation
    which has not been inspected and approved in the open trench. This
    requirement of approval is applicable to all new installations and to
    repairs made to any existing installation.
    (R.R. at 327a, 362a.)
    3
    As pertinent, the minutes for the Board’s decision provides:
    [BEI] asked the Board to reconsider its demand that the pipelines be
    inspected [in] their entirety suggesting that maybe uncovering several
    spots within the park system could suffice.
    [The Authority’s] request for curb stops and backflow preventers for
    each unit will be honored as will its requirement that blow-off valves
    be installed at each end of the park’s water system.
    [BEI] asked if [the Authority’s] minimum monthly fee for eleven
    units be amended to five in exchange for his promise to keep the park
    open throughout the year.
    (Footnote continued on next page…)
    8
    complied with the Authority’s Rules and Regulations, it would supply water to the
    Property.
    The Authority also presented the testimony of Calvin Gindlesperger
    (Gindlesperger), who is the Authority’s Operations Manager.                   He testified that
    Section 5.04 of the Authority’s Rules and Regulations is a typical regulation that is
    necessary to make sure that the service lines are the correct depth and the correct
    connections are used if there is coupling, and to ensure the quality of water as well as
    water pressure. While he was not involved with BEI’s application for water for the
    Property, he did inspect the Property on one occasion. During that inspection, he
    observed hoses connecting the RVs to the Authority’s water source, which is not an
    uncommon practice. While Gindlesperger discussed certain risks of contamination,
    on cross-examination, it was clarified:
    [Counsel:] Mr. Gindlesperger, just a couple things because
    I’m a little confused. You were talking about the potential
    for contamination from the [BEI] line to the [Authority]
    system. I think that’s what you said.
    [Gindlesperger:] Contamination into his own service line
    on his property.
    [Counsel:] Right. So contamination into [BEI’s] property.
    No contamination into the [Authority] system because you
    have a blackflow preventer on the meter; right?
    (continued…)
    Mr. Sulkosky promised to give the requests consideration.
    (R.R. at 308a.)
    9
    [Gindlesperger:] Correct.
    [Counsel:] So nothing that’s in [BEI’s] system can get back
    into [Authority’s system]; correct?
    [Gindlesperger:] Correct.
    (R.R. at 207a-08a.) He also confirmed that he has never had a problem with a service
    line done by Olechovski on other properties. (R.R. at 209a.)
    Finally, the Authority presented the testimony of Edward F. Schmitt
    (Schmitt), Vice President of Gibson-Thomson Engineering Company, Inc., who has
    been the Authority’s consulting engineer since its inception and was involved with
    the drafting of its 1991 and 2015 Rules and Regulations. Schmitt testified that he had
    the opportunity to visit the Property on one occasion and observed that the RVs were
    connected to the service line via garden hoses.       While admitting the backflow
    preventer prevents cross contamination of the Authority system, he testified that it
    was important to have backflow preventers connected to each RV to prevent cross
    contamination with other connections on the Property. He recommended the full
    excavation of the Property’s service line to inspect its depth, material and integrity
    because such factors can increase the risk of leakage, which can affect water pressure
    levels and service throughout the area. Regarding the Authority still sending BEI a
    bill despite discontinuing service, Schmitt explained that this was common practice
    and that if BEI desired the service charge to cease, then it could simply request the
    Authority to disconnect the tap-in connection.
    10
    B.
    On April 10, 2017, the trial court issued an order finding that the
    Authority, “through its actions, has demonstrated its settled decision not to provide
    water service to the recreational vehicles on the [Property]. This is permissible under
    the Court’s prior decision.” (R.R. at 460a.) Based on that finding, the trial court
    dismissed Count I – regarding the Authority’s right to demand full excavation – and
    Count III – where BEI sought an order compelling the Authority to provide water to
    the Property. It did, however, find in favor of BEI for Count II, determining that the
    Authority’s ongoing billing practices were improper because no service was being
    provided to the Property.
    After BEI filed a notice of appeal and a 1925(b) Concise Statement, the
    trial court issued an opinion stating that:
    Following this Court’s [2015 Order] . . . [BEI] failed to
    request that [Authority] cho[o]se one of the options set forth
    by the Court, i.e., Bonarrigo failed to request that the Board
    of Directors take a vote to decide whether it would, or
    would not provide water service to [BEI]. [BEI] merely
    submitted [an] application for service, and the Board of
    Directors responded with a list of conditions that must be
    met by [BEI]. The Court finds that such a conditional
    response from [Authority] is not a decision to provide
    service. Additionally, the Court notes that some of the
    conditions imposed were arguably connected to rules
    promulgated after, and as a result of, the Court’s prior
    Opinion. [The Authority’s] failure to make an affirmative
    decision in regard to the options clearly presented by this
    Court in the prior decision leads the Court to conclude [it]
    has effectively chosen to decline to provide water service to
    [BEI].
    11
    Finally, at oral argument on Plaintiff’s Motion for Post-
    Trial Relief, the Court asked counsel for [Authority] if [it]
    was willing to commit to provide water service to [BEI]
    upon the terms and conditions that the Court might set if the
    Court granted the Motion for Post -Trial Relief, and decided
    the present issues on the merits; counsel could not make
    that commitment on behalf of the Board of Directors.
    Because of the aforementioned findings and factual
    realities, Bonarrigo is essentially asking this Court, and the
    Commonwealth Court, to issue an advisory opinion. [The
    Authority] has chosen to not provide water service to [BEI]
    (or in the light most favorable to [BEI], not made a decision
    in regard to the Court’s [2015 Order] . . . therefore, [BEI’s]
    request for Declaratory Judgment on the applicability of the
    new rules (i.e.[,] the inspection requirement) and
    discriminatory treatment by [the Authority] is premature
    and entirely academic. A decision on those substantive
    issues will, in fact, not resolve this dispute for [BEI]. No
    matter what this Court or the Commonwealth Court’s
    decision on these matters are, [the Authority] has the option
    of simply not providing water service to [BEI] pursuant to
    this Court's [2015 Order].
    (R.R. at 520a-522a.)
    V.
    On appeal, BEI contends that the trial court erred when determining that
    the Authority decided not to provide water service to the Property as allowed by its
    2015 Order. Instead, it states that the Authority had decided to provide water but
    only if a list of conditions were satisfied. It contends that those conditions were
    unreasonable and were enforced in a discriminatory manner.
    12
    We agree with BEI that the Authority decided to provide service to the
    Property. All evidence and testimony unequivocally demonstrates that the Authority
    chose to service the Property under the condition that BEI comply with its Rules and
    Regulations.
    Because the Authority chose to provide service under the condition that
    (1) the buried waterline be uncovered to permit inspection, (2) each RV must have its
    own curb stop and check valve, and (3) blowoffs must be installed at the ends of the
    “private water system” being built (R.R. at 306a), the question remains whether those
    conditions are reasonable and whether it was disparately applying its rules and
    regulations to the Property.      Having reversed the trial court’s finding that the
    Authority chose not to provide service to the Property, we remand the matter to the
    trial court to determine if, based on the evidence presented, the conditions that the
    Authority imposed are reasonable and whether it is disparately applying its Rules and
    Regulations.
    Accordingly, we reverse the trial court’s finding that the Authority chose
    not to provide service to the Property and remand the matter to the trial court to
    determine if, based on the evidence presented, the conditions that the Authority
    imposed are reasonable and whether it is disparately applying its Rules and
    Regulations.
    ________________________________
    DAN PELLEGRINI, Senior Judge
    13
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Bonarrigo Enterprises, Inc.,             :
    Appellant              :
    :
    v.                           : No. 928 C.D. 2017
    :
    Highridge Water Authority                :
    ORDER
    AND NOW, this 27th day of February, 2018, it is hereby ordered that the
    order of the Court of Common Pleas of Indiana County (trial court) in the above-
    captioned matter is reversed, and the matter is remanded to the trial court for further
    proceedings consistent with this opinion.
    Jurisdiction relinquished.
    ________________________________
    DAN PELLEGRINI, Senior Judge
    

Document Info

Docket Number: 928 C.D. 2017

Judges: Pellegrini, Senior Judge

Filed Date: 2/27/2018

Precedential Status: Precedential

Modified Date: 2/27/2018