C. Lanzisera v. Northslope III Owners Association, Inc. ( 2019 )


Menu:
  •                  IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Carl Lanzisera,                          :
    Appellant         :
    :
    v.                :
    :
    Northslope III Owners                    :   No. 728 C.D. 2018
    Association, Inc.                        :   Submitted: March 14, 2019
    BEFORE:        HONORABLE ROBERT SIMPSON, Judge
    HONORABLE ANNE E. COVEY, Judge (P.)
    HONORABLE ELLEN CEISLER, Judge
    OPINION NOT REPORTED
    MEMORANDUM OPINION BY
    JUDGE COVEY                                  FILED: April 2, 2019
    Carl Lanzisera (Lanzisera) appeals from the Monroe County Common
    Pleas Court’s (trial court) November 21, 2017 order: (1) setting aside the Northslope
    III Owners Association, Inc. (Association) board of directors’ (Board) action
    reducing the number of directors on the Board from nine to seven; (2) denying
    Lanzisera’s request to be reinstated to the Board; (3) finding that the Board’s August
    2016 decision to proceed to contract to replace the siding on buildings 37-41 violated
    Section 5303(b) of the Uniform Planned Community Act’s (UPCA)1 (Section
    5303(b)) notice requirements; and (4) voiding the Board’s decision to encumber the
    Association’s reserve account as collateral for a loan. Lanzisera presents three issues
    for this Court’s review: (1) whether the trial court erred or abused its discretion by
    failing to determine that the Board breached its fiduciary duty to the Association
    when it found that the Board violated Sections 5303(b) and 5302(a)(17) of the UPCA
    (Section 5302(a)(17)); (2) whether the trial court erred or abused its discretion by
    1
    68 Pa.C.S. § 5303(b).
    failing to determine that the Board breached its fiduciary duty to the Association
    when the Board voted to proceed to contract to replace the siding on buildings 37-41;
    and (3) whether the trial court erred or abused its discretion by determining the issue
    of Lanzisera’s request to be reinstated to the Board was moot.
    Facts
    Northslope III is a planned residential community located in Smithfield
    and Middle Smithfield Townships, comprised of 198 residential townhouse units
    contained in 39 wood-framed 2 and 3-story buildings. Lanzisera was appointed to the
    Board during the June 2015 annual meeting of the Association’s members. The
    Board voted to reduce the number of directors from nine to seven members at the
    February 2015 Board meeting, before Lanzisera became a Board member. The
    Board’s decision to reduce its complement was due to difficulty in obtaining quorums
    and because Board members’ resignations often required the Board to work with
    fewer than nine directors.
    Before 1993, 14 of the Northslope III buildings were constructed with
    exterior cedar clapboard siding. The remaining 25 buildings were built after 1999.
    These buildings have wooden T-111, wooden board and batten or vinyl exterior
    siding. In 2014, the Board replaced the cedar siding on buildings 37-41 with vinyl
    siding that was applied over the cedar siding. However, notwithstanding that no
    waterproof barrier was installed in the original buildings under the cedar clapboard,
    no new waterproof barrier was installed under the vinyl siding during the 2014 work
    on buildings 37-41.       Further, the contractor did not finish the vinyl siding on
    buildings 40 and 41, and the vinyl siding that was installed on the other buildings was
    not installed properly.
    The Falcon Group (Falcon), an engineering, architectural and energy-
    consulting firm, performed a Reserve Fund Analysis (RFA) for the Board in March
    2
    2015. It also inspected buildings 37-41 for siding defects (Inspection), leading to a
    report dated June 2015. The Board discussed Falcon’s March 2015 RFA and the
    June 2015 Inspection at the June 27, 2015 annual Association’s members’ meeting.
    In particular, it was noted that Falcon found deficiencies in the siding installation,
    lack of weatherproofing under the siding and deteriorating cedar exterior siding
    which was left in place under the newly-installed vinyl siding. Falcon concluded that
    the buildings needed to have the existing siding completely removed, some support
    beams replaced, plywood installed, weatherproofing applied to the plywood and new
    exterior siding installed.
    The Board held a meeting on July 25, 2015, wherein, the Board voted to
    obtain bids to fix and complete the inadequate siding work done on buildings 37-41.
    Lanzisera attended the Board meeting. The Board decided under new business that
    the Board would need to know by the following Monday which siding the Board will
    be selecting for scope of work/specs from Falcon. The Board chose Celect as the
    siding material for buildings 37-41 shortly after the July 25, 2015 meeting. Bids were
    solicited and reviewed. After the bids were received, the Board considered them too
    expensive. Falcon was directed to reduce the scope of the project. At the time this
    lawsuit was filed, on February 3, 2016, the Board had not decided whether to contract
    for the re-siding of buildings 37-41.
    The Board voted to proceed with the project in August 2016 at a closed
    Board meeting. The Board did not give notice of its decision to re-side buildings 37-
    41 and its cost to the Association members. At the time the re-siding project started,
    the capital reserve fund contained $700,000. The total re-siding cost was $592,000.
    The Association entered into a loan agreement with Branch Banking and Trust
    Company (BBT) on November 8, 2016, in which it agreed to borrow $350,000 to pay
    for a portion of the siding project of buildings 37-41. The Board deposited $400,000
    of the reserve account with BBT as collateral for the loan as of May 31, 2017. In the
    3
    event of default, the loan documents authorized BBT to seize the reserve fund. By
    May 31, 2017, the Board had spent $235,000 of the reserve fund on the re-siding
    project. The Board had not drawn any funds from the BBT loan as of May 31, 2017.
    The Association operated at deficits of $65,468 in 2014, $52,997 in 2015
    and $89,606 in 2016, totaling $208,071. The Falcon RFA showed that in March 2015
    the cedar siding on buildings 69-72 needed to be replaced immediately with vinyl
    siding and the cedar siding on buildings 45-47 needed to be replaced with vinyl
    siding within one year. Buildings 37-41 were not scheduled for new vinyl siding for
    34 years in that study. However, the Falcon Inspection had not yet occurred at that
    time. Lanzisera expressed concerns about the siding project at the January 16, 2016
    Board meeting. A discussion followed with a full explanation of the siding project
    timeline. A motion was then made and passed to remove Lanzisera from the Board.
    Procedural background
    On February 3, 2016, Lanzisera filed a Petition for Review of Contested
    Corporate Action (Petition) in the trial court. On February 16, 2016, the Association
    filed preliminary objections to the Petition (Preliminary Objections). Lanzisera filed
    an answer thereto and New Matter on March 1, 2016. The Association filed an
    answer to the New Matter on March 14, 2016. On April 8, 2016, the trial court
    sustained the preliminary objection to Lanzisera’s claim that he was wrongfully
    removed as a director on the grounds of lack of specificity as required by
    Pennsylvania Rule of Civil Procedure No. 1028(a)(3), and overruled the remaining
    objections. On April 28, 2016, Lanzisera filed an Amended Petition for Review of
    Contested Corporate Action (Amended Petition). The trial court scheduled a hearing
    for September 28, 2016. After many continuances, hearings were held on July 7, and
    May 31, 2017. On November 21, 2017, the trial court ordered:
    4
    1. The Board’s action in reducing the number of directors of
    the corporation from nine to seven is set aside.
    2. [] Lanzisera’s request to be reinstated to the Board is
    denied.
    3. The Board’s decision in August, 2016 to proceed to
    contract to replace the siding on [b]uildings 37-41 without
    notice to the [Association’s] members pursuant to [Section
    5303(b)] violated the notice requirements of that statute.
    4. The Board’s decision to encumber the [Association’s]
    reserve account as collateral for the BBT loan violated
    [Section 5302(a)(17)] and was void.
    Trial Ct. Op. at 21-22.
    Lanzisera filed post-trial motions on November 30, 2017.2                          On
    December 20, 2017, Lanzisera appealed to the Pennsylvania Superior Court. On
    December 26, 2017, the trial court issued an order directing Lanzisera to file a
    Pennsylvania Rule of Appellate Procedure 1925(b) statement of matters complained
    of on appeal (Rule 1925(b) Statement). Lanzisera filed his Rule 1925(b) Statement
    on December 28, 2017. On January 3, 2018, the trial court filed its Statement
    pursuant to Pennsylvania Rule of Appellate Procedure 1925(a) (1925(a) Statement)
    determining it would rely upon its November 21, 2017 opinion. By February 14,
    2018 order, the Superior Court transferred the appeal to this Court.
    Judgment was entered on April 12, 2018. Lanzisera appealed to this
    Court on May 1, 2018.3 On May 2, 2018, the trial court entered another order
    2
    The trial court did not rule on the post-trial motions within 120 days, thus they were denied
    by operation of law. See Pa.R.C.P. No. 227.4(1)(b).
    3
    This Court’s review of the trial court’s decision is limited to
    determining whether the trial court committed an error of law or
    abused its discretion and whether its findings of fact are supported by
    the evidence. The interpretation of [a statute] is a question of law,
    subject to de novo, plenary review.
    5
    directing Lanzisera to file a Rule 1925(b) Statement.        Lanzisera filed his Rule
    1925(b) Statement on May 18, 2018. The trial court filed another 1925(a) Statement
    on June 7, 2018, stating it would rely upon its November 21, 2017 opinion.
    Discussion
    Lanzisera first argues that the trial court erred or abused its discretion by
    failing to determine that the Board breached its fiduciary duty to the Association
    when it found that the Board violated Sections 5303(b) and 5302(a)(17). Lanzisera
    relies upon New Hope Academy Charter School v. School District of City of York, 
    89 A.3d 731
    (Pa. Cmwlth. 2014) (New Hope) to support his position. The Association
    rejoins that if the legislature intended for a UPCA violation to amount to an automatic
    finding of a breach of fiduciary duty, such a per se finding would have been provided
    for within the statute. In addition, the Association contends that the relief Lanzisera
    seeks has to be relief afforded under the Pennsylvania Nonprofit Corporation Law of
    1988 (NPCL),4 upon which Lanzisera filed his Amended Petition.
    Initially, Section 5303(b) provides in relevant part:
    The executive board shall deliver to all unit owners . . .
    notice of any capital expenditure approved by the
    executive board promptly after such approval. . . . [T]he
    unit owners, by majority or any larger vote specified in the
    declaration, may reject any . . . capital expenditure
    approved by the executive board within 30 days after
    approval.
    68 Pa.C.S. § 5303(b) (emphasis added). Section 5302(a)(17) states, in pertinent part,
    that an association may “[a]ssign its right to future income, including the right to
    receive common expense assessments[, but r]eserve funds held for future major
    A Pocono Country Place Prop. Owners Ass’n, Inc. v. Kowalski, 
    186 A.3d 537
    , 541 n.1 (Pa.
    Cmwlth. 2018) (citation omitted).
    4
    15 Pa.C.S. §§ 5101–6160.
    6
    repairs and replacements of the common elements may not be assigned or
    pledged.” 68 Pa.C.S. § 5302(a)(17) (emphasis added).
    The relevant facts in New Hope are as follows:
    New Hope’s founder, Isiah Anderson, own[ed] three
    companies that d[id] substantial business with New Hope:
    Three Cord, Inc. (Three Cord), Three Cord Youth Services,
    LLC (TCYS), and I. Anderson Real Estate. Three Cord
    [was] a for-profit company solely owned by Anderson that
    was incorporated by him in February 2007. Three Cord
    manage[d] New Hope under written management
    agreements that require[d] New Hope to pay Three Cord
    15% of its gross revenues and entitle[d] Three Cord to 50%
    of any unrestricted net income after expenses. TCYS
    operate[d] Challenge Academy, an Alternative Education
    for Disruptive Youth (AEDY) program in which New Hope
    place[d] disruptive students. Anderson Real Estate own[ed]
    the school building that New Hope use[ed] and lease[ed] it
    to New Hope.
    Anderson [was] not a member of New Hope’s board of
    trustees and [was] not a salaried employee of New Hope.
    New Hope’s charter, however, provided that [] Anderson
    [would] administer the school during the first few years of
    startup [sic]. New Hope listed Anderson as its principal
    officer and managing director in its 2008 and 2009 tax
    filings and listed Anderson as its Managing Officer on its
    letterhead as late as November 2010, and Anderson in 2011
    and 2012 filed statements of financial interests stating that
    he was the Managing Officer of New Hope in 2010 and
    2011.
    New Hope’s board of trustees agreed to the management
    agreements, leases and contract with TCYS without
    discussion or consideration of their terms.
    
    Id. at 734-35
    (record citations and quotation marks omitted). The Charter School
    Appeal Board determined that New Hope violated Section 1103 of the Public Official
    7
    and Employee Ethics Act (Ethics Act),5 and the NPCL in it contracts with its founder
    Anderson’s businesses. New Hope appealed, inter alia, that determination.
    This Court held that New Hope’s “trustees failed to fulfill their duties to
    exercise reasonable skill and diligence in approving the[] contracts[]” because New
    Hope’s board of trustees did not discuss or consider the terms of the
    management agreements, leases, and contract with Anderson’s businesses before
    approving them. 
    Id. at 741.
    Lanzisera asserts that the Board’s Section 5303(b)
    notice requirement violation is analogous to New Hope’s trustees’ failure to discuss
    the terms of the management agreements, leases, and contract with Anderson’s
    businesses before approving them.
    However, the New Hope Court based its holding on Section 1103(f) of
    the Ethics Act, which mandates:
    No public official or public employee . . . or any business in
    which the person . . . is associated shall enter into any
    contract valued at $500 or more with the governmental
    body with which the public official or public employee is
    associated or any subcontract valued at $500 or more with
    any person who has been awarded a contract with the
    governmental body with which the public official or public
    employee is associated, unless the contract has been
    awarded through an open and public process, including
    prior public notice and subsequent public disclosure of
    all proposals considered and contracts awarded. In such
    a case, the public official or public employee shall not have
    any supervisory or overall responsibility for the
    implementation or administration of the contract. Any
    contract or subcontract made in violation of this
    subsection shall be voidable by a court of competent
    jurisdiction if the suit is commenced within 90 days of
    the making of the contract or subcontract.
    65 Pa.C.S. § 1103(f) (emphasis added). Under the circumstances, there is no doubt
    that the trustees in New Hope violated the express terms of the Ethics Act and the
    5
    65 Pa.C.S. § 1103.
    8
    consequences stated therein applied.            Accordingly, the Court held there was a
    fiduciary duty breach.
    In contrast to the above facts and applicable law, the UPCA does not set
    forth a remedy much less mandate a conclusion that a violation is a per se fiduciary
    duty breach. This Court recognizes that Section 5412 of the UPCA provides that “[i]f
    a declarant or any other person subject to this subpart violates any provision of this
    subpart or any provisions of the declaration or bylaws, any person or class of persons
    adversely affected by the violation has a claim for appropriate relief.” 68 Pa.C.S. §
    5412. Here, while Lanzisera specifically requested relief under Section 5793 of the
    NPCL,6 in this Commonwealth, Section 5303 of the UPCA governs the standard by
    which courts review an association’s actions. Burgoyne v. Pinecrest Cmty. Ass’n,
    
    924 A.2d 675
    , 683 (Pa. Super. 2007). Section 5303 of the UPCA provides, in
    relevant part:
    Executive board members and officers
    (a)     Powers and fiduciary status.--Except as provided in
    the declaration, in the bylaws, in subsection (b) or in
    other provisions of this subpart, the executive board
    may act in all instances on behalf of the association. In
    the performance of their duties, the officers and
    members of the executive board shall stand in a
    fiduciary relation to the association and shall perform
    their duties, including duties as members of any
    committee of the board upon which they may serve, in
    good faith; in a manner they reasonably believe to be in
    the best interests of the association; and with care,
    including reasonable inquiry, skill and diligence as a
    person of ordinary prudence would use under similar
    circumstances.
    6
    Section 5793 of the NPCL states: “Upon application of any person aggrieved by any
    corporate action, the court may hear and determine the validity of the corporate action.” 15 Pa.C.S.
    § 5793.
    9
    68 Pa.C.S. § 5303. Therefore, the issue before the trial court herein was whether the
    Board acted in good faith. Burgoyne.
    Relative to the Section 5303(b) notice provision, the trial court declared:
    [T]he Board decided to proceed with the $592,000[.00]
    exterior siding contract, using or pledging almost its entire
    capital reserve account for the re-siding of [u]nits 37-41 at a
    [B]oard meeting closed to the members in August, 2016.
    The evidence reveals no notice of this decision, as a budget
    item or as a capital expenditure, to the members. This lack
    of notice violated this provision of the UPCA, which is a
    retroactive provision under [Section 5102(b.1) of the
    UPCA,] 68 Pa.C.S.[] § 5102(b.1), and which calls for full
    disclosure to members of such a decision.
    Trial Ct. Op. at 15 (emphasis added; internal record citations omitted). Because the
    trial court ruled that the Section 5303(b) notice provision was violated, there was no
    need for the trial court to specifically opine that the Board violated its fiduciary duty
    to the Association. Accordingly, the trial court did not err or abuse its discretion by
    not finding that the notice violation was a breach of the Board’s fiduciary duty to the
    Association.
    With respect to the Section 5302(a)(17) violation, the trial court
    concluded:
    The Board was not permitted by the UPCA to agree to
    provide this collateral for the loan and this action will be
    declared void. At the time of the last hearing, the Board
    had not drawn any money down on the loan and was
    attempting to renegotiate its collateral for the loan with
    BBT.
    Trial Ct. Op. at 16 (emphasis added). Because the trial court voided the action, and
    therefore it had no legal effect, there was no need for the trial court to specifically
    opine that the Board violated its fiduciary duty to the Association. Accordingly, this
    Court does not discern any error or abuse of discretion by the trial court for not
    expressly doing so.
    10
    Lanzisera next argues that the trial court erred or abused its discretion by
    failing to determine that the Board breached its fiduciary duty to the Association
    when the Board voted to proceed to contract to replace the siding on buildings 37-41.
    Specifically, Lanzisera contends that because the Board failed to consider the
    financial ramifications of same, and what was in the Association’s best interest, it
    breached its duties of loyalty and care to the Association’s members.                The
    Association rejoins that the decision to proceed with the re-siding was a judgment
    call, which the Board had the authority to make. In addition, the Association asserts
    that courts are not permitted to substitute their judgment for that of a corporation’s
    directors and will not interfere with a corporation’s internal management unless the
    acts complained of constitute fraud, bad faith or gross mismanagement, or are
    unlawful or ultra vires.
    At the outset, the Northslope III Declaration of Protective Covenants,
    Restrictions and Easements (Declaration) provides that the Association has an
    obligation to maintain the exterior structure of units in the community. Specifically,
    Article VII(A) of the Declaration provides in relevant part:
    COVENANTS   FOR              OWNERS          ASSOCIATION
    ASSESSMENTS
    AND RIGHTS RELATING TO COLLECTIONS
    Common Expenses. The [] Association is authorized to
    contract for any goods and services as it deems necessary,
    and to pay expenses and other liabilities, out of the
    [c]ommon [f]und or reserves, if applicable, which costs for
    goods and services shall, without limiting the generality of
    the foregoing, include the following:
    ....
    (7) The cost of maintenance, repair and replacement of the
    [u]nit [e]xteriors and improvements in [c]ommon [a]reas as
    the . . . Association may deem necessary and proper, as well
    as any applicable materials, supplies, labor and services[.]
    11
    Reproduced Record (R.R.) at 296-297. The Declaration defines “[u]nit [e]xterior” as:
    The portions of a [u]nit needed to keep the [u]nit
    weathertight and attractive, including, the roof and roof
    structure; exterior walls; exterior painting, staining or
    siding; exterior windows; exterior doors, including any
    screen or storm doors; exterior ramps, steps, porches, decks,
    patios, terraces or balconies; parapets and copings; and fire
    escapes.
    R.R. at 281. Article VIII(A) of the Declaration mandates:
    Obligations of the Association. The [] Association shall be
    responsible for the management and control of the
    [c]ommon [a]reas and shall keep the same in good, clean,
    attractive and sanitary condition, order and repair. The []
    Association shall also be responsible for the oversight,
    administration and enforcement of certain obligations of the
    [o]wners relating to the [u]nit [e]xteriors and shall keep
    them in good condition. The [] Association shall be
    responsible for repairs and replacement of the roof, decks
    and steps; exterior painting; replacement of all exterior
    windows; repair and replacement of exterior doors and
    screen or storm doors.
    R.R. at 301.
    [T]he wisdom or advisability of the [Board’s decision to re-
    side buildings 37-41] is not an issue for a court to
    determine. In McDonald v. Lake Hauto Club, . . . 
    428 A.2d 785
    ([Pa. Cmwlth.] 1981), [this Court] stated:
    [I]t is [a] well[-]established legal principle that
    courts should not substitute their judgment for that
    of the directors of a corporation and will not
    interfere with the internal management of the
    corporation unless the acts complained of constitute
    fraud, bad faith or gross mismanagement or are
    unlawful or ultra vires.
    
    Id. at .
    . . 786 (citations omitted).
    Mulrine v. Pocono Highland Cmty. Ass’n, Inc., 
    616 A.2d 188
    , 190 (Pa. Cmwlth.
    1992).
    12
    Here, Lansizera specifically contends that the Board voted to proceed
    with the re-siding of buildings 37-41 solely because three of the Board’s members
    lived in those buildings, not because it was in the Association’s best interests.7
    However, the record belies this contention.
    Board member Doreen Dimonte (Dimonte) testified that she owns
    several units in Northslope III, but she resides in building 45. See R.R. at 225. When
    asked why the Board was looking into re-siding buildings 37-41, she explained:
    First, the company that was hired to install the vinyl siding
    never finished the project. They basically -- essentially, it
    was a combination of them walking off the job, not
    finishing, and demanding more money, and the Association,
    members of the Board, deciding that we would go no
    further with them.[8]
    Two buildings were left unfinished, buildings 40 and 41.
    They had nothing protecting them, very poor gutter system,
    and only partially sided throughout the winter of -- I believe
    it was ‘14 to ‘15. Or ‘15 to ‘16. I’m losing track of time. I
    think it was ‘14 to ‘15. So it was partly that. It was
    unfinished.
    We needed to get something done to complete these
    buildings. And then people were complaining about water
    seepage into their homes. . . .
    R.R. at 228-229. Dimonte related that the Board was unable to find a contractor who
    could repair the existing siding after the 2013 installation. See R.R. at 229. Dimonte
    7
    Lanzisera also asserts that the Association’s precarious financial position at the time the
    decision was made also evidences the Board’s fiduciary duty breach to the Association. However,
    the Association’s poor financial state does not change the fact that the Declaration mandates the
    Board to keep the common areas including the unit exteriors in “good, . . . order and repair.” R.R.
    at 301. Nor does it require a finding that any decisions made by the Board are a per se fiduciary
    duty breach.
    8
    The Board voted to bring an action against the original contractors. See R.R. at 233.
    13
    continued:
    Q. Did there come a point in time when the Board decided
    to engage in a study to determine what needed to be done to
    remedy the issues regarding [buildings] 37 through 41?
    A. Yes.
    Q. And is that the Falcon [Inspection]?
    A. That was the Falcon [Inspection]. Falcon . . . had done a
    [RFA] for us.[9] We were pleased with their work. We
    needed to find out – because we were getting different
    opinions from different [c]ontractors, that we decided it
    would be much better for the Association to have an
    independent company, engineering company, look at
    what we were facing and give us an objective opinion,
    not an opinion that would result in work provided to that
    person providing the opinion.
    R.R. at 229 (emphasis added). Falcon visited Northslope III on June 5, 2015, and
    conducted a visual and invasive survey of the existing siding systems on buildings 37,
    38, 39, 40 and 41. See R.R. at 432 (Falcon Inspection). Falcon concluded:
    The installation of the vinyl siding is problematic and has
    been installed over the original failing cedar and wood trim,
    which is not recommended. The original cedar siding was
    never properly installed over a weather resistive barrier or
    proper flashings. The installation of the vinyl siding over
    the old cedar siding will only hide these deficiencies and
    make future repairs more costly. When vinyl siding is
    fastened to the exterior of a building, it should be nailed to
    the framing members to insure a secure, permanent
    attachment that resists withdrawal. We also observed that
    the fasteners are nailed tight, which does not allow for the
    siding to move freely when it expands or contracts with
    changes in the air temperatures. This condition may cause
    the siding to bow or warp.
    9
    Dimonte expounded: “The Falcon [RFA] was simply to look at all the components of the
    various buildings in the Association and to come up with a plan basically for maintenance and
    going into the future.” R.R. at 230.
    14
    The lack of water resistive barrier under both the original
    cedar siding and the new vinyl siding is also problematic.
    This observed deficiency can lead to moisture infiltration
    behind the siding, which can then migrate to the wall
    sheathing and framing, which may lead to reported water
    leaks to the interior of a unit.
    In addition, the siding itself has been poorly installed and
    deviates from industry standards. Siding should have a
    clearing of two (2’’) inches where it meets a roof. Lack of
    proper clearance will lend distortion caused by the heat
    transferred from the asphalt shingles, and also to premature
    deterioration of wood components due to excessive
    moisture. Flashing around windows, doors and at dissimilar
    materials should be properly installed prior to installing the
    siding. Removal and replacement of rotted wood should
    have been performed prior to the installation of new vinyl
    siding; this is a primary reason why it is not recommended
    that vinyl siding is installed over cedar siding as it hides any
    wood deterioration or rotting.
    All these deficiencies appeared to be consistent
    throughout these five (5) buildings. These conditions are
    of concern because they can all lead to water infiltration,
    and there is a possibility that the vinyl siding will start to
    become unfastened over time due to improper fastening
    methods.
    R.R. at 444 (emphasis added). Falcon recommended
    that the Association plan to remove and replace the vinyl
    siding.     Based on our inspections, we would also
    recommend that the cedar siding should be removed in
    order to install plywood sheathing and provide proper
    flashing and a water resistive barrier between the framing
    and sheathing, and the exterior cladding [sic]. Existing
    wood rot and related damage should be addressed during
    the siding replacement.
    R.R. at 444.
    Further, Board President John J. Roman (Roman) testified that he owns a
    unit in building 38. See R.R. at 67-68. When asked if the Board decided to proceed
    with re-siding buildings 37-41 in good faith, Roman responded:
    15
    I think the Board approached this in a logical, systematic
    fashion in order to address a serious problem that was
    confronting this Board and the Association. They took it on
    the logical step-by-step manner, which took over a year, to
    arrive at this decision, which occurred in August of 2016.
    That is when the vote was actually taken to proceed.
    R.R. at 257. Thus, the record evidences that the reason the Board chose buildings 37-
    41 for the re-siding was that all five buildings had improper siding installation and
    buildings 40 and 41 had incomplete siding installation. The Board could not find a
    contractor who believed the buildings could be repaired without being re-sided.
    Based on the record evidence, the trial court concluded:
    [T]he Board’s actions were based upon recommendations
    from experts on how best to solve the siding issues on these
    buildings. The fact that other experts disagree[10] does not
    mean that the Board members acted improperly. There was
    no evidence of fraud, self-dealing or misuse of corporate
    funds. The Board’s decision to re-side the buildings was a
    judgment call that the directors had the authority to make.
    Trial Ct. Op. at 20.        This Court discerns no error in the trial court’s analysis.
    Accordingly, the trial court did not err or abuse its discretion by failing to determine
    that the Board breached its fiduciary duty to the Association when the Board voted to
    proceed to contract to replace the siding on buildings 37-41.
    Lastly, Lanzisera argues that the trial court erred or abused its discretion
    by resolving that the issue of Lanzisera’s request to be reinstated to the Board was
    moot. Specifically, Lanzisera contends that the trial court determined the issue was
    moot based on this Court’s decision in Lutz v. Tanglwood Lakes Community Ass’n,
    Inc., 
    866 A.2d 471
    (Pa. Cmwlth. 2005), which in fact, ruled that the issue fell within
    an exception to the mootness doctrine.
    10
    Lanzisera presented an expert who testified that he believed the siding on buildings 40 and
    41 could be repaired. See R.R. at 156-161.
    16
    The Association rejoins that the Lutz Court did not hold that any time a
    director is removed for cause and the term has expired, the court must review whether
    the director’s removal was proper. Rather, the Association maintains, the Lutz Court
    ruled that whether a board can remove a director for cause was a matter of great
    public importance that was capable of repetition and likely to evade review.
    In Lutz, petitioner argued that the trial court erred in finding that the
    issue of whether he was properly removed by the board was moot because
    petitioner’s term on the board of directors had expired. The Lutz Court explained:
    It is well settled that a court will dismiss an action as moot
    unless an actual case or controversy exists at all stages of
    the judicial or administrative process. Exceptions have
    been made to this principle when conduct complained of is
    capable of repetition yet likely to evade judicial review,
    when the case involves issues of great public importance or
    when one party will suffer a detriment in the absence of a
    court decision. We agree with [the petitioner] that the first
    two exceptions are applicable here.
    First and foremost, this case presents issues of great
    importance to the governance of Pennsylvania nonprofit
    corporations: Under what circumstances may a board of
    directors remove one of its members for proper cause?
    Must the bylaws of the organization specify what
    constitutes ‘proper cause?’ Such fundamental issues of
    nonprofit corporate governance are likely to reoccur.
    Second, given the typically short term of a directorship, in
    this case three years, a director removed at mid-term or
    later, or a director elected to less than a three-year term,
    would likely see his term expire before final resolution of
    any legal challenge to his removal. Because the issue raised
    by [the petitioner] is one of great public importance, which
    is capable of repetition yet likely to evade judicial review,
    we shall determine the propriety of his removal by the
    [b]oard.
    17
    
    Lutz, 866 A.2d at 473-74
    (citations and footnote omitted). The Court concluded: “As
    a matter of law, we hold that Section 5726(b) of the [NPCL],11 15 Pa.C.S. § 5726(b),
    permits a board of directors to remove a director for proper cause irrespective of
    whether the organization’s bylaws specify what constitutes ‘proper cause.’” 
    Lutz, 866 A.2d at 475
    .
    “It is well settled that a court will dismiss an action as moot unless an
    actual case or controversy exists at all stages of the judicial or administrative
    process.” 
    Id. at 473.
    Because Lanzisera does not dispute that his term expired, the
    remedy of reinstatement is no longer available, thus, there is no meaningful relief to
    be ordered. Consequently, the issue of his removal is moot. Further, since the Lutz
    Court resolved the issue of whether a board of directors can remove a director under
    the NPCL irrespective of whether the organization’s bylaws specify what constitutes
    proper cause, that issue is no longer “capable of repetition yet likely to evade judicial
    review[.]” 
    Id. at 474.
                  Moreover, Lanzisera did not argue that his particular removal fell within
    an exception to the mootness doctrine.12 Therefore, this Court cannot conclude that
    the issue of whether the Board removed Lanzisera for proper cause is “one of great
    11
    Section 5726(b) of the NPCL provides:
    Unless otherwise provided in a bylaw adopted by the members, the
    board of directors may declare vacant the office of a director who
    has been judicially declared of unsound mind or who has been
    convicted of an offense punishable by imprisonment for a term of
    more than one year, or for any other proper cause which the
    bylaws may specify, or if, within 60 days, or other time as the bylaws
    may specify, after notice of selection, a director does not accept the
    office either in writing or by attending a meeting of the board of
    directors and fulfill the other requirements of qualification as the
    bylaws may specify.
    15 Pa.C.S. § 5726 (emphasis added).
    12
    The only argument relating to mootness that Lanzisera presented herein was since the Lutz
    Court determined that the issue therein fell within an exception to the mootness doctrine, the trial
    court should have ruled the same in this case. See Lanzisera Br. at 28.
    18
    public importance, which is capable of repetition yet likely to evade judicial
    review[.]” 
    Id. at 474.
    Accordingly, the trial court properly ruled that the issue of
    Lanzisera’s removal was moot.
    For all of the above reasons, the trial court’s order is affirmed.
    ___________________________
    ANNE E. COVEY, Judge
    19
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Carl Lanzisera,                        :
    Appellant            :
    :
    v.                   :
    :
    Northslope III Owners                  :   No. 728 C.D. 2018
    Association, Inc.                      :
    ORDER
    AND NOW, this 2nd day of April, 2019, the Monroe County Common
    Pleas Court’s November 21, 2017 order is affirmed.
    ___________________________
    ANNE E. COVEY, Judge
    

Document Info

Docket Number: 728 C.D. 2018

Judges: Covey, J.

Filed Date: 4/2/2019

Precedential Status: Precedential

Modified Date: 4/2/2019