Highway Materials, Inc. v. DOT ( 2019 )


Menu:
  •          IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Highway Materials, Inc.,           :
    :
    Petitioner :
    :
    v.               : No. 1267 C.D. 2018
    : Submitted: January 25, 2019
    Commonwealth of Pennsylvania,      :
    Department of Transportation,      :
    :
    Respondent :
    BEFORE:     HONORABLE RENÉE COHN JUBELIRER, Judge
    HONORABLE ROBERT SIMPSON, Judge
    HONORABLE MICHAEL H. WOJCIK, Judge
    OPINION NOT REPORTED
    MEMORANDUM OPINION
    BY JUDGE WOJCIK                                     FILED: August 22, 2019
    Highway Materials, Inc. (HMI) petitions for review of a determination
    of the Commonwealth of Pennsylvania, Department of Transportation (Department)
    that HMI’s bid protest was untimely. HMI argues that the Department erred in
    denying its bid protest as untimely when HMI filed its protest within seven days of
    when it knew or should have known that it was an aggrieved bidder. Further, HMI
    maintains that it was the lowest responsive and responsible bidder and complied with
    all statutory and regulatory requirements for a timely submission of a Public Works
    Verification Form (Form). Alternatively, HMI argues that the Department abused its
    discretion by failing to exercise its discretion to waive an immaterial post-bid
    irregularity. Upon review, we affirm.
    Background
    On May 19, 2018, the Department solicited bids for its Electronic
    Construction Management System Project No. 111063 High Friction Surface Project
    (Project) at various state routes throughout Engineering District 6-0.               The
    Department opened the bids on June 21, 2018. Section 107.31(c) of the Contract
    Specifications for the Project, as set forth in the Department’s Publication 408
    (2016),1 required the apparent low bidder for the Project to submit a Form within
    seven days after the bid opening, which meant that the Form was due on June 28,
    2018. HMI was the apparent low bidder on the Project. However, on July 3, 2018,
    the Department rejected HMI’s bid for failure to timely submit the Form in
    accordance with Section 107.31(c) of the Contract Specifications.
    On July 9, 2018, HMI filed a protest regarding the rejection of its bid
    based on its failure to comply with Section 107.31 of the Contract Specifications.
    Reproduced Record (R.R.) at 30a. HMI argued Section 107.31 of the Contract
    Specifications is unenforceable because the imposition of a seven-day deadline to
    submit the Form alters the mandates of the Public Works Employment Verification
    Act (Act)2 and attendant regulations, 4 Pa. Code §§66.1-66.9. HMI asserted that it
    submitted the Form in full compliance with the Act and the regulations on July 5,
    2018, prior to the award of the contract. Alternatively, HMI argued that any failure
    to submit the Form in accordance with Section 107.31 of the Contract Specifications
    should be considered a non-material bid defect, which the Department may waive.
    1
    Publication      408     is   available  on    the   Department’s   portal  at:
    http://www.dot.state.pa.us/public/PubsForms/Publications/Pub_408/408_2016/408_2016_IE/408
    _2016_IE.pdf (last visited July 29, 2019).
    2
    Act of July 5, 2012, P.L. 1086, 43 P.S. §§167.1-167.11.
    2
    The Department’s contracting officer initially reviewed the protest and
    recommended that the Secretary of the Department or his designee disregard the bid
    protest as untimely filed or deny the bid protest in its entirety on the basis that HMI
    did not comply with the Contract Specifications.
    The Executive Deputy Secretary of the Department (Deputy Secretary)
    then reviewed the protest and the contracting officer’s recommendation and agreed
    that HMI’s protest was untimely. Deputy Secretary reasoned that HMI knew or
    should have known of the facts giving rise to its protest when the Department
    published the Contract Specifications on May 19, 2018, or, at the very latest, by June
    21, 2018, when the Department sent HMI an email requesting that it submit the Form
    within seven days of the bid opening. However, HMI did not file a bid protest with
    the Department until July 9, 2018, well beyond the seven-day period within which
    to file protests. See Section 1711.1(b) of the Commonwealth Procurement Code
    (Procurement Code), 62 Pa. C.S. §1711.1(b) (providing “the protest shall be filed
    with the head of the purchasing agency within seven days after the aggrieved bidder
    or offeror or prospective contractor knew or should have known of the facts giving
    rise to the protest”). Thus, Deputy Secretary determined the bid protest was untimely
    and that HMI waived the right to file a protest.
    Moreover, even if the bid protest could be considered timely filed, the
    Deputy Secretary determined that HMI’s protest lacked merit because HMI did not
    “strictly comply with the requirements and criteria in the solicitation,” which
    required the Form to be submitted within seven days of the bid opening.
    Department’s Determination, 9/4/18, at 5. Having failed to comply with the bid
    specifications, HMI’s bid was not responsive. Accordingly, the Deputy Secretary
    3
    denied HMI’s protest. From this decision, HMI filed a timely petition for review in
    this Court.3, 4
    Issues
    HMI argues that the Department erred by denying its bid protest as
    untimely. HMI filed its protest within seven days of when it knew it was an aggrieved
    bidder when the Department rejected its bid. Further, HMI contends the Department
    erred by denying its bid protest where HMI was the lowest responsive and responsible
    bidder and complied with all statutory and regulatory requirements for a timely
    submission of a Form. Alternatively, HMI asserts that the Department abused its
    discretion by refusing to waive an immaterial post-bid irregularity in the public’s best
    interest.
    3
    HMI also filed an amended application for stay and expedited review. By order dated
    October 25, 2018, this Court denied the amended application insofar as it requested a stay, but
    granted the request for expedited review.
    4
    As this Court has explained:
    The Procurement Code sets forth the scope and standard of review
    in an appeal from a determination denying a bid protest. Section
    1711.1(i) provides, “The court shall hear the appeal, without a jury,
    on the record of determination certified by the purchasing agency.
    The court shall affirm the determination of the purchasing agency
    unless it finds from the record that the determination is arbitrary and
    capricious, an abuse of discretion or is contrary to law.” 62 Pa. C.S.
    § 1711.1(i).
    MSG Group, Inc. v. Department of Public Welfare, 
    902 A.2d 613
    , 616 n.9 (Pa. Cmwlth. 2006).
    4
    Discussion
    First, HMI maintains that the Department erred by rejecting its bid
    protest as untimely. According to HMI, it had no basis to know of its grounds for
    protest until July 3, 2018, when the Department rejected its bid. HMI maintains that
    the July 3, 2018 notice of rejection was the first notice HMI had that its bid was
    being rejected for failure to comply with the “Public Works Employment
    Verification Requirements.”
    A bidder or prospective bidder “that is aggrieved in connection with the
    solicitation or award of a contract, . . . may protest to the head of the purchasing
    agency in writing.” Section 1711.1(a) of the Procurement Code, 62 Pa. C.S.
    §1711.1(a). Such protests must be filed within “seven days” after the aggrieved
    bidder or prospective bidder “knew or should have known of the facts giving rise to
    the protest.” 62 Pa. C.S. §1711.1(b). “Untimely filed protests shall be disregarded
    by the purchasing agency.” 
    Id. HMI claims
    it was not aggrieved until the Department rejected its bid
    on July 3, 2018 and it did not know, and could not have known, of the facts giving
    rise to its protest until that time. However, this Court squarely rejected this same
    argument in Cummins v. Department of Transportation, 
    877 A.2d 550
    , 553
    (Pa. Cmwlth. 2005). We opined:
    On appeal, Cummins contends that his protest was timely
    because it was filed within seven days of when he learned
    that his bid had been rejected. This argument is without
    merit. Cummins’ protest was based upon the assertion that
    two project items were assigned the wrong classification
    codes, and had the item been properly classified, Cummins
    would have met the prequalification requirements. Thus,
    the salient facts giving rise to his protest were the codes
    assigned to the two work items and the codes for which
    Cummins has been prequalified, and the relevant inquiry
    5
    is when Cummins knew or should have known these facts.
    As noted above, the description of each work item and its
    corresponding code was included in the proposal for bids
    published in early September 2004, and Cummins does not
    claim that he was unaware of the classifications in which
    he is 
    prequalified. 877 A.2d at 553
    . Similarly, in Collinson, Inc. v. Department of Transportation, 
    959 A.2d 480
    , 484 (Pa. Cmwlth. 2008), we held that the seven-day period for a contractor
    to file a bid protest challenging the prequalification classification codes as detailed
    in the bid specifications began when the project was advertised, not when
    contractor’s bid was rejected for failing to have the proper codes.
    As in Cummins and Collinson, HMI’s protest was premised on its
    objections to the bid requirements. Specifically, HMI claimed that the Contract
    Specifications’ seven-day requirement to submit the Form was unenforceable
    because it altered the mandates of the Act and regulations. See R.R. at 5a-6a. The
    salient facts giving rise to HMI’s protest were available to HMI at the time the
    solicitation for bids was published on May 19, 2018. Section 107.31 of the Contract
    Specifications clearly provided that the Form must be submitted within seven days
    of the bid opening. Moreover, on June 21, 2018, the date of the bid opening, the
    Department sent HMI an email stating that HMI had “been selected as the apparent
    low bidder for the Project” and reminding HMI that “[a] [Form] submission is
    required by 3:00 PM within [seven] days after the bid opening, or your bid will be
    rejected.” R.R. at 17a (emphasis added).
    HMI was on notice of the bid requirements as of May 19, 2018, or at
    the latest, June 21, 2018. However, HMI did not file its protest with the Department
    until July 9, 2018, which is more than seven days from the date HMI knew or should
    have known of the salient facts forming the basis for its protest. Thus, HMI’s protest
    6
    is untimely.       See Collinson; Cummins; see also CenturyLink Public
    Communications, Inc. v. Department of Corrections, 
    109 A.3d 820
    , 829 (Pa.
    Cmwlth. 2015) (offeror did not timely protest a threshold bid requirement at the time
    that it submitted its proposal thereby waiving any claim of error in this regard). The
    Department did not err in rejecting the protest as untimely.
    Even if we were to conclude that HMI’s protest was timely filed on the
    basis that HMI filed its protest within seven days of the Department’s rejection of
    its bid, HMI would still not prevail on the merits because: (1) Section 107.31 of the
    Contract Specifications did not impermissibly alter the mandates of the Act or the
    regulations; and (2) having failed to comply with Section 107.31, HMI’s bid was not
    responsive.
    First, Section 107.31(a) and (b) of the Contract Specifications requires
    contractors, in accordance with the Act, to use the federal government’s E-Verify
    system to ensure that all employees performing work on the Project are authorized
    to work in the United States and to use the Form to verify the employment eligibility
    of employees. Section 107.31(a) and (b) of the Contract Specifications. Subsection
    (c) then directs the contractor to email or fax the Form “by 3:00 P.M. prevailing local
    time within 7 calendar days after the bid opening.” Section 107.31(c) of the Contract
    Specifications. “When the seventh (7th) calendar day after the bid opening falls on
    a day that the Department offices are closed, submit the Form by 3:00 P.M.
    prevailing local time on the next business day.” 
    Id. Section 107.31(c)
    clearly warns
    “[f]ailure or refusal to provide the Form will be considered a refusal to comply with
    bidding requirements, will result in the rejection of the bid, and may subject the
    contractor to the enforcement activities, sanctions and civil penalties specified in the
    Act.” 
    Id. 7 Contrary
    to HMI’s assertions, Section 107.31 of the Contract
    Specifications does not alter the mandates of either the Act or the regulations. The
    Act and regulations provide that “[a]s a precondition of being awarded a contract for
    a public work . . . a public works contractor shall provide the public body with a
    verification form.” Section 4 of the Act, 43 P.S. §167.4(a); accord 4 Pa. Code
    §66.5(a). These provisions establish the submission of the Form as a precondition
    of the award of the contract, but they do not establish a time for the submission of
    the Form. Section 107.31 does not alter or otherwise violate the Act or regulations,
    but merely prescribes the time within which the Form must be filed as part of the
    Contract Specifications.
    Second, Section 512(g) of the Procurement Code requires public
    bidding contracts to be awarded to the lowest responsive and responsible bidder.
    62 Pa. C.S. §512(g). A “responsive bid . . . conforms in all material respects to the
    requirements and criteria in the invitation for bids.” Section 103 of the Procurement
    Code, 62 Pa. C.S. §103. A “responsible bidder” is “[a] bidder that has submitted a
    responsive bid and that possesses the capability to fully perform the contract
    requirements in all respects and the integrity and reliability to assure good faith
    performance.” 
    Id. “In making
    a determination as to the lowest responsible bidder, each
    bid must be carefully examined to ascertain its responsiveness to the requirements
    of the [invitation for bid].” Cardiac Science, Inc. v. Department of General Services,
    
    808 A.2d 1029
    , 1033 (Pa. Cmwlth. 2002).          “[T]he statutory requirements for
    competitive bidding, and the ordinances enacted thereunder, do not exist solely to
    secure work or supplies at the lowest possible price, but also have the “‘purpose of
    inviting competition, to guard against favoritism, improvidence, extravagance, fraud
    8
    and corruption in the awarding of municipal contracts . . . and are enacted . . . not
    for the benefits or enrichment of bidders . . . .’” Conduit and Foundation Corp. v.
    City of Philadelphia, 
    401 A.2d 376
    , 379 (Pa. Cmwlth. 1979) (quoting Yohe v. Lower
    Burrell, 
    208 A.2d 847
    , 850 (Pa. 1965)).           Consequently, “[v]ariances from
    instructions and specifications in public works bidding are to be discouraged and, at
    a minimum, implicate the government’s discretionary authority to reject a non-
    compliant bid.” Cardiac 
    Science, 808 A.2d at 1033
    (internal quotation and citation
    omitted).
    Notwithstanding, a bid defect may be waived in limited circumstances.
    Gaeta v. Ridley School District, 
    788 A.2d 363
    , 367 (Pa. 2002). In Gaeta, the
    Supreme Court fashioned a two-part test for determining whether a bid defect could
    be waived. 
    Id. Specifically, a
    bid irregularity may only be clarified or disregarded as a
    waivable defect if the effect of a waiver of that term: (1)
    would not deprive the bid solicitor of an adequate
    assurance that the contract would be performed according
    to its specified requirements and (2) would not advantage
    the bidder over the other bidders.
    Cardiac 
    Science, 808 A.2d at 1034
    (citing 
    Gaeta, 788 A.2d at 367-68
    ). While a
    government entity may waive a bid defect, it may not do so if the defect involves the
    waiver of a mandatory requirement that the bid documents treat as nonwaivable. 
    Id. at 1033.
    “Where specifications set forth in a bidding document are mandatory, they
    must be strictly followed for the bid to be valid, and a violation of those mandatory
    bidding instructions constitutes a legally disqualifying error for which a public agent
    may reject a bid.” Glasgow, Inc. v. Pennsylvania Department of Transportation,
    
    851 A.2d 1014
    , 1017 (Pa. Cmwlth. 2004). Courts will not review the action of
    governmental bodies or administrative tribunals involving acts of discretion in the
    9
    absence of bad faith, fraud, capricious action, or abuse of power. Cardiac 
    Science, 808 A.2d at 1033
    .
    Here, although HMI provided the Form, it did not do so within the time
    constraints specified by the bid instructions. By failing to comply with all the bid
    requirements, HMI’s bid was not responsive. As for HMI’s argument that the
    Department may waive this bid defect, the Department may only waive non-
    mandatory requirements. 
    Glasgow, 851 A.2d at 1017
    ; Cardiac 
    Science, 808 A.2d at 1034
    . The Contract Specifications make it clear that the failure to provide the
    Form “will be considered a refusal to comply with bidding requirements, will result
    in the rejection of the bid, and may subject the contractor to the enforcement
    activities, sanctions and civil penalties specified in the Act.” Section 107.31(c) of
    the Contract Specifications. When read within the context, the seven-day deadline
    in which to submit the Form is mandatory and non-waivable. The Department does
    not have authority to waive material defects. See 
    Glasgow, 851 A.2d at 1017
    ;
    Cardiac 
    Science, 808 A.2d at 1034
    . Alternatively, even if the defect was non-
    material, the Department was under no obligation to waive it. See Cardiac 
    Science, 808 A.2d at 1033
    . The Department did not abuse its discretion by refusing to
    exercise it. See 
    id. Accordingly, we
    affirm.
    MICHAEL H. WOJCIK, Judge
    Judge Fizzano Cannon did not participate in the decision of this case.
    10
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Highway Materials, Inc.,           :
    :
    HMI        :
    :
    v.               : No. 1267 C.D. 2018
    :
    Commonwealth of Pennsylvania,      :
    Department of Transportation,      :
    :
    Respondent :
    ORDER
    AND NOW, this 22nd day of August, 2019, the order of the
    Commonwealth of Pennsylvania, Department of Transportation, dated September 4,
    2018, is AFFIRMED.
    __________________________________
    MICHAEL H. WOJCIK, Judge