United Refining Company v. DEP , 163 A.3d 1125 ( 2017 )


Menu:
  •            IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    United Refining Company,                :
    Petitioner        :
    :
    v.                          :   No. 1321 C.D. 2016
    :   Argued: April 4, 2017
    Department of Environmental             :
    Protection,                             :
    Respondent       :
    BEFORE: HONORABLE P. KEVIN BROBSON, Judge
    HONORABLE PATRICIA A. McCULLOUGH, Judge
    HONORABLE MICHAEL H. WOJCIK, Judge
    OPINION BY JUDGE BROBSON                    FILED: June 12, 2017
    Petitioner United Refining Company petitions for review of an order
    of the Environmental Hearing Board (Board), dated July 7, 2016, which dismissed
    Petitioner’s appeal of an oil permit issued by Respondent Department of
    Environmental Protection (Department) to Intervenor John D. Branch (Branch).
    Petitioner contends that the Board’s decision is not supported by substantial
    evidence and violates Pennsylvania environmental law and Article I, Section 27 of
    the Pennsylvania Constitution, commonly referred to as the Environmental Rights
    Amendment. We now affirm.
    I.    BACKGROUND
    The following facts are undisputed based upon the parties’ stipulation
    of facts and the filings of record. Since 1902, Petitioner has owned and operated
    an 83-acre petroleum refinery in Warren, Pennsylvania (Property), which extends
    approximately 1.6 miles along the north shore of the Allegheny River.         The
    subsurface below the Property includes the Warren 1st and Warren 2nd Sands, and
    the Glade and Clarendon Sands. The top of the Clarendon Sands is approximately
    780 feet below the surface of the Property. Petitioner has constructed several
    aboveground storage tanks on the Property, including Tank 234 located on the
    northern portion of the Property. Tank 234 has the capacity to contain 3.6 million
    gallons of gasoline. Tank 234 has a steel floor, concrete ring wall, and an earthen
    dike designed to contain 110% of its contents. It sits on fill materials, soils,
    gravels, silt sands, and clays, and the bedrock is approximately 75 feet below the
    bottom of the tank. Petitioner inspects Tank 234 every four years, and it last
    inspected the tank in November 2014 and discovered no problems.
    Since 1990, Petitioner has installed over 100 monitoring wells on the
    Property. Petitioner has never drilled an oil or natural gas well on the Property,
    although the Department’s records indicate that four oil or natural gas wells were
    previously drilled on the Property. In 2001, Petitioner discovered an oil plume
    below Tank 234, and the plume measured approximately 265 feet long by 180 feet
    wide at the time the parties entered into their stipulation. Petitioner has recovered
    in excess of 12,500 gallons of oil from the plume. Petitioner has used crude oil at
    the Property but not in the area of Tank 234. There is no direct evidence of
    unplugged wells near or under Tank 234 or anywhere else on the Property, and
    Petitioner is unaware of any property damage, surface damage, or environmental
    harm caused by hydraulically fracturing wells in the Glade or Clarendon Sands in
    Warren, Pennsylvania.
    Branch has been in the oil and gas business for 31 years and in the
    drilling business for 15 years. He has drilled approximately 60 oil and gas wells
    within the City of Warren, Pennsylvania.        On September 16, 2014, Branch
    submitted a permit application to the Department for authorization to drill an oil
    2
    well—Well 61—in Warren, Pennsylvania. Pursuant to the application, Branch
    planned to drill Well 61 on a slant, with the top-hole location across the street from
    the Property and the bottom-hole location under the Property. At the time Branch
    submitted the permit application, he also submitted five other permit applications
    for wells located near the Property. Prior to the Department’s approval of the
    permit for Well 61, Branch met with representatives of Petitioner to tour the plant
    and discuss his proposed drilling plans under the Property.
    On October 24, 2014, Petitioner expressed concerns to the
    Department regarding Branch’s proposed Well 61 and other proposed wells closest
    to Tank 234, including a concern that fracking pressures could reach historic wells
    and be released through unplugged wells to the surface. On November 5, 2014,
    Branch responded to the Department regarding Petitioner’s concerns. In so doing,
    Branch informed the Department that it was his opinion that any wells in the area
    that were not plugged with cement would likely already have been plugged
    naturally, as there is anywhere from 55 feet to 95 feet of gravel in the valley of
    Warren. To avoid risks in response to Petitioner’s concerns, Branch stated that he
    would not frack in the Warren 1st or Warren 2nd formations and that he would
    utilize conductivity and video logs when he drilled the new wells and would avoid
    hydraulically fracturing in the vicinity of zones indicated by these logs as having
    excessive water. Branch stated that he and his team would closely watch the
    pressure gauges when hydraulically fracturing and, if the gauges indicated
    connection with another well, would cease operations immediately.             Finally,
    Branch advised the Department that he would conduct hydraulic fracturing with
    smaller amounts of sand and water to control the length of the fractures. Branch
    3
    also altered the proposed termination point of Well 61, so as to avoid the vicinity
    of the oil plume below Tank 234.
    The    Department       issued       permits   for   the   six    wells    on
    November 12, 2014, including the permit for Well 61.1                One of the special
    conditions for the permits was that fracking operations would not be conducted in
    the Warren 1st or Warren 2nd formations. Thereafter, Petitioner appealed the
    issuances of the permits to the Board, identifying its concern that energy released
    by Branch’s fracking could be conveyed through an unplugged well and result in
    damage to Petitioner and the surrounding community, including potentially a
    large-scale fire or explosion, as well as a release of oil into the water of the
    Commonwealth.
    The Honorable Thomas W. Renwand, Chief Judge and Chairman of
    the Board, conducted a hearing at which the parties presented their stipulation of
    facts and the testimony of Timothy Ruth (Ruth), a geologist and employee of
    Petitioner; Craig Lobins (Lobins), a professional geologist who is employed by the
    Department as the Northwest District Oil & Gas Manager; and Branch. Following
    the hearing, the Board issued an adjudication, dated July 7, 2016, dismissing the
    appeal relating to Well 61 and upholding the permit issued by the Department for
    Well 61.
    In addition to findings based upon the facts summarized above, the
    Board made findings based upon the testimony received during the hearing. For
    instance, with regard to the geology, the Board found that there are various layers
    1
    Although the Department granted all of the well permits, Branch allowed the permits
    for the wells other than Well 61 to expire without drilling the wells.
    4
    of bedrock between 75 and 750 feet below the surface of the Property, and that
    fracking would take place at various depths between 750 and 850 feet below the
    Property. Well 61 would be located a little less than 300 feet from Tank 234, the
    distance between Tank 234 and where the hydraulic fracturing would occur in
    Well 61 is approximately 300 to 360 feet, and the fractures would travel 150 feet
    horizontally and would be 600 to 800 feet below the surface of the Property. With
    regard to the oil plume, the Board found that it consists of multiple components
    and is likely from multiple sources.
    With regard to the testimony of Lobins, presented on behalf of the
    Department, the Board found that Lobins was very familiar with conventional well
    drilling and instances where conventional wells fracked into abandoned oil and gas
    wells. Lobins issued the permit for Well 61, was aware that Branch planned to use
    a slant drilling technique, and had no problem with the use of that technique.
    Furthermore, Lobins testified that the fracking of Well 61 would break away from
    Tank 234 and would be too far underground to impact Tank 234, the plume, or the
    Property. He opined that, because no fracturing would occur in the Warren 1st or
    Warren 2nd formations and because fractures would stay in the zones being
    fractured, there would be no effects on Tank 234 or the plume. The Board also
    found that both Lobins and Branch testified that the drilling of Well 61 is unlikely
    to create fractures impacting the plume or Tank 234, communicate with any
    undocumented wells, impact groundwater, or impact the surface.
    Based on its findings, the Board concluded that Petitioner had not met
    its burden to prove by a preponderance of the evidence that the Department abused
    its discretion by acting unreasonably and/or in violation of the laws of the
    Commonwealth when issuing the permit. In so doing, the Board explained that it
    5
    dismissed Petitioner’s appeal on the basis that Petitioner had not met its burden of
    proof because Petitioner failed to present sufficient expert testimony to
    demonstrate actual risks associated with the drilling.
    II.     ANALYSIS
    On appeal to this Court,2 the issues are as follows:3 (1) whether the
    Board incorrectly applied the burden of proof; (2) whether the Board erred in
    concluding that the Department’s issuance of the permit for Well 61 was
    reasonable and in accordance with the law; and (3) whether issuance of the permit
    violates Article I, Section 27 of the Pennsylvania Constitution.4
    2
    “Our scope of review of an order of the Board is whether the Board committed an error
    of law or a constitutional violation, or whether any necessary findings of fact are not supported
    by substantial evidence.” The Ainjar Trust v. Dep’t of Envtl. Prot., 
    806 A.2d 482
    , 487
    (Pa. Cmwlth. 2002).
    3
    Petitioner’s brief includes a statement of the questions involved, and the Department’s
    and Branch’s briefs contain counter-statements of the questions involved, all of which phrase the
    issues differently. The issues now set forth by the Court fairly represent the issues presented by
    the parties.
    4
    On March 14, 2017, during the pendency of this appeal, Branch filed with this Court a
    motion to dismiss this appeal on the basis of mootness, asserting that he “spud” Well 61 on
    November 9, 2015, to avoid expiration of the permit; drilled Well 61 to total depth as of
    September 27, 2016; received written approval from the Department to hydraulically fracture
    Well 61 on December 27, 2016; began hydraulically fracturing Well 61 on March 2, 2017; and
    finished hydraulically fracturing Well 61 on March 3, 2017, without incident or any known
    adverse effect to the environment, Tank 234, the surface, or anything else. Branch argued that in
    light of the completion of the fracturing, the appeal became moot. The Department joined in
    Branch’s motion. Petitioner objected to the dismissal, contending that the matter is not moot
    because the permit authorizes Branch to engage in future fracking and operations of Well 61,
    thereby causing Petitioner to remain at risk. Petitioner also appeared to disagree with Branch’s
    contention that no harm resulted from hydraulically fracturing Well 61. By order dated
    March 24, 2017, the Court denied the motion to dismiss.
    6
    At the outset, we note that Petitioner’s overarching theme in this
    appeal is that the Department’s approval of the permit for Well 61 is at odds with
    the purposes of what is commonly referred to as the Oil and Gas Act, 58 Pa. C.S.
    §§ 3201-3274, which Petitioner characterizes as assuring safe oil and gas
    development. Petitioner even suggests that “this is not a case . . . that requires a
    close reading of statutory language or an analysis of legislative intent.”
    (Petitioner’s Br. at 19.)   While Petitioner asserts that the permit violates the
    purposes of the Oil and Gas Act by threatening the health and safety of the
    environment, its personnel and facilities, and the surrounding residents, Petitioner
    does not assert that issuance of the permit actually violates a substantive provision
    of the Oil and Gas Act.
    Pursuant to Section 3211(e.1) of the Oil and Gas Act, 58 Pa. C.S.
    § 3211(e.1), the Department may deny a permit for an oil or gas well for any of the
    following reasons:
    (1) The well site for which a permit is requested is in
    violation of any of this chapter or issuance of the permit
    would result in a violation of this chapter or other
    applicable law.
    (2) The permit application is incomplete.
    (3) Unresolved objections to the well location by the coal
    mine owner or operator remain.
    (4) The requirements of section 3225 (relating to
    bonding) have not been met.
    (5) The department finds that the applicant, or any parent
    or subsidiary corporation of the applicant, is in
    continuing violation of this chapter, any other statute
    administered by the department, any regulation
    promulgated under this chapter or a statute administered
    by the department or any plan approval, permit or order
    of the department, unless the violation is being corrected
    to the satisfaction of the department. . . .
    7
    (6) The applicant failed to pay the fee or file a report
    under section 2303(c) (relating to administration), unless
    an appeal is pending. . . .
    If none of the six statutory reasons for denial exist, then the Department is required
    to issue the permit within 45 days. Section 3211(e) of the Oil and Gas Act, 58 Pa.
    C.S. § 3211(e). Third parties, such as Petitioner, have a right to appeal to the
    Board the Department’s issuance of a permit. Section 4 of the Environmental
    Hearing Board Act, Act of July 13, 1988, P.L. 530, 35 P.S. § 7514. The Board
    must determine whether a party appealing the issuance of a permit has
    demonstrated its case by a preponderance of the evidence.          See 25 Pa. Code
    § 1021.122(a).    Petitioner had the burden before the Board to show by a
    preponderance of the evidence that the Department acted arbitrarily or abused its
    discretion when it issued the permit for Well 61. See 25 Pa. Code § 1021.122;
    Pa. Trout v. Dep’t of Envtl. Prot., 
    863 A.2d 93
    , 105 (Pa. Cmwlth. 2004) (“[A]
    party protesting [the Department’s] issuance of a permit has the burden to show, on
    the record produced before the [Board], issuance of the permit was arbitrary or was
    an abuse of discretion.”).
    A. Whether the Board Incorrectly Applied the Burden of Proof
    Petitioner argues that the Board incorrectly applied the burden of
    proof by requiring Petitioner to establish that damage to persons or the
    environment from the drilling of Well 61 was more likely than not. Petitioner
    contends that the Board should have required Petitioner to show, by a
    preponderance of the evidence, only that the Department’s decision to grant the
    permit was unreasonable, arbitrary and capricious, an abuse of discretion, or
    contrary to law. Petitioner relies on one passage of the Board’s opinion, which
    provides: “In other words, a party cannot simply come forward with a laundry list
    8
    of potential problems, and then rest their case.           They must prove by a
    preponderance of the evidence that these problems are likely to occur.” (Board’s
    Adjudication at 8, attached to Petitioner’s Br. as Ex. “A.”) Petitioner contends that
    by focusing on the likelihood of harm rather than the Department’s decision, the
    Board asked the wrong question. Under this faulty approach, as characterized by
    Petitioner, any risky activity, no matter the magnitude of harm that could
    potentially result, would be deemed to be acceptable unless a party could prove
    that it likely would occur. Petitioner argues that this standard is incorrect, because
    in order to meet its burden of proof, it is not necessary for Petitioner to show that a
    release or explosion at Tank 234 is more likely than not to occur or is a scientific
    certainty. Thus, Petitioner asserts that the Department erred by evaluating the
    preponderance of the evidence in the context of whether it had been shown that a
    catastrophic event was more likely to occur than not, rather than the question
    presented by the appeal—i.e., whether the Department’s action in granting the
    permit under these circumstances was unreasonable or contrary to law.
    In a similar vein, Petitioner also contends that the Board applied the
    wrong burden of proof to Petitioner’s evidence regarding the existence of the old
    wells, which it claims are generating the oil plume. It asserts that instead of
    requiring Petitioner to show the existence of an unplugged well with a
    preponderance of the evidence, the Board imposed a higher standard by requiring
    Petitioner to prove the existence of an unplugged well as an “established scientific
    fact.” (Petitioner’s Br. at 32.) Petitioner contends that, at most, it needed only to
    show that the well is likely to exist. Specifically, Petitioner maintains that it
    provided extensive testimony regarding the underground plume of oil below
    Tank 234 that had been detected, sampled, and studied for a period of many years.
    9
    It also provided evidence to show that the plume exists and that it is highly
    unlikely to have originated from a spill or release of oil from the refinery.
    Petitioner asserts that, overall, it provided evidence that the most reasonable and
    likely explanation for the oil plume is an abandoned well, yet the Board did not
    consider the existence of an unplugged well causing or contributing to the
    underground plume because it was not shown by Petitioner to be a “scientific fact.”
    This is a key issue because, according to Petitioner, once there is recognition of the
    existence of an unplugged well, then the entire analysis of the reasonableness of
    the Department’s issuance of the permit changes. The unplugged well establishes
    a clear prime pathway for the impact and energy of the fracking to be
    communicated outside of the planned zone of fracturing and presents a much
    greater risk to Tank 234. Thus, Petitioner maintains that the application of the
    wrong burden of proof as to whether an abandoned or unplugged well exists on the
    Property changed the entire dynamic of the Board’s analysis of the likelihood of
    the risk presented by the permit and the reasonableness of the Department’s action
    in issuing the permit.
    The Board, in its opinion, set forth a detailed explanation of the
    burden of proof when it wrote:
    The burden to show that the permit should not have been
    issued is on the party challenging the permit.
    [Petitioner], therefore, must prove by a preponderance of
    the evidence that the permits should not have been
    issued. To prove one’s case by a “preponderance of the
    evidence” means that the “evidence in favor of the
    proposition must be greater than that opposed to it. . . . It
    must be sufficient to satisfy an unprejudiced mind as to
    the existence of the factual scenario sought to be
    established.” Therefore, [Petitioner] was required to
    present evidence that the Department’s issuance of the
    permit to . . . Branch was not appropriate or did not
    10
    conform with the applicable law or was unreasonable,
    and its evidence must be greater than the evidence
    showing that the issuance of the permit was appropriate
    or in accordance with the applicable law.
    In other words, an appellant must come forward
    and prove their allegations by a preponderance of the
    evidence. They may not simply raise an issue and then
    speculate that all types of unforeseen calamities may
    occur. When they raise technical issues they must come
    forward with technical evidence. In many cases, such as
    this one, they need expert testimony to prove their
    claims. In other words, a party cannot simply come
    forward with a laundry list of potential problems and then
    rest their case. They must prove by a preponderance of
    the evidence that these problems are likely to occur.
    (Board’s Adjudication at 8 (internal citations omitted) (emphasis added).)
    With regard to its application of the burden of proof, the Board then
    further explained that it recognized Petitioner’s witness, Ruth, as an expert in the
    field of geology but not in the area of drilling oil and gas wells or the intricacies of
    hydraulic fracturing. Although Ruth raised legitimate concerns about the risks of
    drilling a well at the proposed location, his testimony was not sufficient to satisfy
    the burden of proof. The Board wrote:
    The evidence regarding unplugged wells in the vicinity
    of Tank 234 is speculative, rather than established
    scientific fact. [Petitioner] concedes that there may not
    be any wells in that location. Even more importantly, the
    testimony does not provide a scientific basis for how the
    drilling of Well . . . 61 would impact either the plume or
    Tank 234.
    (Board’s Adjudication at 9 (emphasis added).) Thus, Ruth’s concerns were not
    supported by his testimony.
    It is important to note that Ruth’s testimony regarding his concerns
    was not the only testimony considered by the Board. Rather, the Board considered
    11
    the expert testimony of the Department’s witness, Lobins, and the testimony of
    Branch. The Board wrote:
    Mr. Lobins testified that the safeguards in the permit that
    allow hydraulic fracturing to occur in only certain zones
    will allow the drilling to take place without any impact to
    the surface or the structures on it. Mr. Lobins testified
    that even if there are unplugged wells and even if those
    unplugged wells were impacted by the drilling (big if’s
    based on his testimony), he opined that there would be
    little or no impact to any of the structures on [Petitioner’s
    P]roperty and that any impacts could be quickly and
    easily addressed. Mr. Branch, an experienced oil and gas
    operator, who also was qualified as an expert, testified as
    to his drilling plan and about the many wells he has
    drilled without incident in this locale. The expert
    testimony as a whole leads us to conclude that there is
    justification under the law to issue the oil and gas permit
    under appeal.
    (Board’s Adjudication at 9 (emphasis added).)
    The Board finished its preponderance of the evidence analysis by
    concluding that the weight of evidence did not demonstrate that Branch’s drilling
    of an oil and gas well is likely to impact Tank 234 or the Property adversely. It
    noted that “[t]he facts and expert testimony do not prove by a preponderance of the
    evidence that drilling would damage or otherwise impact [Tank 234, the] plume, or
    [the P]roperty.” (Board’s Adjudication at 10.)
    We agree with Petitioner that, to the extent that the Board’s discussion
    of the burden of proof could be interpreted to require Petitioner to prove every
    factual detail by a preponderance of evidence or require Petitioner to prove that it
    was more likely than not that harm would occur, such an interpretation would
    impose a higher burden than required. The Board was required to determine
    whether, based upon its factual findings, Petitioner proved by a preponderance of
    12
    the evidence that the Department acted arbitrarily or abused its discretion. We can
    envision a scenario where the likelihood of the harm occurring is significant but
    less than fifty percent likely. The severity of the possible harm, however, could be
    so immense that issuing a permit could be determined to be abuse of discretion.
    To require a petitioner to prove a fifty percent or greater likelihood that the harm
    will occur would unduly restrict the Board’s ability to consider the reasonableness
    of the issuance of a permit under this or any other similar scenario.
    We are not convinced that the Board in this case, however, wrongly
    applied the burden of proof to the evidence presented. Petitioner had the burden to
    prove, by a preponderance of evidence, that the Board’s issuance of the permit was
    arbitrary or an abuse of discretion. 25 Pa. Code § 1021.122; Brockway Borough
    Mun. 
    Auth., 131 A.3d at 587
    ; Pa. 
    Trout, 863 A.2d at 105
    . The appeal involved
    technical issues, and expert testimony is required where the issues require
    scientific or specialized knowledge or experience to understand. Dep’t of Transp.
    v. Agric. Lands Condemnation Approval Bd., 
    5 A.3d 821
    , 828-29 (Pa.
    Cmwlth. 2010). After weighing the evidence and testimony presented, the Board
    found that Petitioner did “not provide a scientific basis for how the drilling of
    Well 61 will impact either the plume or Tank 234.” (Board’s Adjudication at 9.)
    The Board essentially found that even if it were to accept that an unplugged well
    existed in the vicinity of Tank 234 or Well 61, Petitioner still did not present
    testimony as to how the drilling or fracturing of Well 61 could communicate with
    the unplugged well or negatively impact either the plume or Tank 234. Absent
    some supporting expert testimony or facts, Petitioner could not prove by a
    preponderance of the evidence that the permit for Well 61 should not have been
    issued. In other words, Petitioner did not support its claims with credible expert
    13
    testimony and, thus, failed to meet its burden of proof.                     By contrast, the
    Department and Branch provided credible testimony from expert witnesses that
    refuted Petitioner’s concerns.5
    B. Whether the Department’s Issuance of the Permit for Well 61 Was
    Reasonable and in Accordance With the Law
    1. Abnormally Dangerous Activity
    With regard to whether the Board erred in concluding that the
    Department’s issuance of the permit for Well 61 was reasonable and in accordance
    with the law, Petitioner approaches this issue by focusing on what it characterizes
    as the “unique characteristics of Branch’s proposed project” and by asserting that
    the nature of the project requires a greater deal of scrutiny. (Petitioner’s Br. at 34.)
    Petitioner points out that even the Board recognized that this was a “unique”
    permitting situation. (Board’s Adjudication at 10.) Petitioner analogizes Branch’s
    proposed project—drilling and fracking underneath an oil refinery and a
    3.6 million gallon gasoline storage tank in close proximity to an underground oil
    plume evidencing the potential for an abandoned well and near a neighborhood—
    which it characterizes as unique and dangerous, to the tort concept of an
    abnormally dangerous activity. As such, Petitioner asserts that issuance of the
    permit for Well 61 should be subject to a higher degree of scrutiny and that the
    Department’s evaluation of the application was far below the appropriate level of
    5
    The Board is the sole finder of fact and, as such, has sole discretion regarding witness
    credibility, weight of the evidence, and resolution of evidentiary conflicts. Brockway Borough
    Mun. Auth. v. Dep’t of Envtl. Prot., 
    131 A.3d 578
    , 587 (Pa. Cmwlth. 2016). On appeal of a
    Board decision, “this Court does not ‘accept invitations to reevaluate evidence and credibility
    determinations.’” Sunoco, Inc. v. Dep’t of Envtl. Prot., 
    865 A.2d 960
    , 969-70 (Pa.
    Cmwlth. 2005) (citing Birdsboro and Birdsboro Mun. Auth. v. Dep’t of Envtl. Prot., 
    865 A.2d 969-70
    (Pa. Cmwlth. 2005)).
    14
    care under the circumstances of this case, such that issuance of the permit
    constitutes arbitrary, capricious, and unreasonable decision-making.
    The concept of abnormally dangerous activity applies to strict liability
    causes of action and is inapplicable to the instant matter which is governed by
    statute. Also, while not binding on this Court, the United States District Court for
    the Middle District of Pennsylvania has held that hydraulic fracturing is not an
    abnormally dangerous activity under Pennsylvania law. See Ely v. Cabot Oil &
    Gas Corp., 
    38 F. Supp. 3d 518
    , 534 (M.D. Pa. 2014). Thus, we reject Petitioner’s
    argument.
    2. Reasonable Level of Scrutiny
    Petitioner contends that even if the Department was not required to
    apply strict scrutiny, the Board still erred in affirming the issuance of the permit for
    Well 61 because the Department failed to apply a reasonable level of scrutiny.
    Specifically, Petitioner points to: (1) what it refers to as the “lack of evaluation”
    by the Department’s program manager, Lobins;6 (2) the uniqueness of the situation
    (i.e., use of a slant drill under a large gasoline tank near an oil plume);7 (3) the
    Department’s “faulty” analysis of the risk posed by the proximity of Well 61 to
    6
    With regard to this point, Petitioner refers to Lobins’ uncertainty as to whether he was
    aware of Petitioner’s concerns at the time the Department issued the permit and lack of
    understanding as to how those concerns had been evaluated.
    7
    Petitioner asserts that the potential for encountering an abandoned well is greater for a
    slant well that travels a distance horizontally compared to a vertical well that is in a single, fixed
    location. Petitioner argues that the Department improperly utilized Branch’s prior well projects
    in Warren, Pennsylvania, as a basis to evaluate the permit application for Well 61, because those
    projects did not involve circumstances similar to those in the matter now before the Court. In
    fact, Lobins testified that of the 41,000 well permits he had been involved in issuing, the permit
    for Well 61 was the only one that involved drilling under a refinery. (R.R. at 373a.)
    15
    Tank 234, which was prepared only for purposes of this litigation;8 (4) the
    Department’s “deficient Zone of Capture calculation”;9 (5) an overreliance on the
    hope that any abandoned wells would have been naturally plugged; and (6) the
    Department’s implicit knowledge that risk is presented by these circumstances.
    (Petitioner’s Br. at 37, 41.)
    Petitioner’s contention that the Board erred in concluding that the
    issuance of the permit was not unreasonable due to lack of adequate scrutiny by the
    Department appears to be based in part on Petitioner’s misperception that the
    Board, in considering the reasonableness and legality of a permit, must confine its
    review to the information considered by the Department at the time it issued the
    permit. It is important to remember that the Board is not tasked with the duty to
    review the Department’s decision-making process. Rather, the Board reviews the
    Department’s issuance of a permit de novo, meaning it can properly consider
    evidence produced after the Department’s action in question and in anticipation of
    litigation. On appeal from a decision of the Board, the Court “must review the
    adjudication of the Board rather than the administrative action which was reviewed
    by the Board.”        Warren Sand & Gravel Co., Inc. v. Dep’t of Envtl. Prot.,
    
    341 A.2d 556
    , 565 (Pa. Cmwlth. 1975). The Board’s de novo review allows it to
    8
    Petitioner contends that the Department’s evaluation of the risk was erroneous. An
    exhibit introduced by the Department depicting a 200-foot radius around the endpoint of Well 61
    is, according to Petitioner, inaccurate and misleading because the zone of capture should have
    been placed at a different location. Petitioner notes that the Department, during the hearing,
    admitted that the zone of capture should have been placed at a different location. (R.R. at 348a,
    386a.)
    9
    Petitioner contends that the Department further erred by using just a 200-foot zone of
    capture and asserts that the Department should have used a 500-foot zone of capture based on
    proposed 2013 regulations that were never adopted.
    16
    admit and consider evidence that was not before the Department when it made its
    initial decision, including evidence developed since the filing of the appeal. The
    Board determines the reasonableness and legality of the Department’s actions
    based upon the record developed before the Board.
    Here, the Board heard testimony regarding the concerns expressed by
    Petitioner, including those identified by Petitioner in connection with the lack of
    scrutiny argument Petitioner now raises. Those concerns involve factual matters,
    and the Board considered the evidence before it in reaching its decision.10 As
    discussed above, it is immaterial whether the Department considered the same
    matters when issuing the permit.
    3. Issuance of Permit Without Further Special Conditions
    Petitioner contends that the Department erred by issuing the permit to
    Branch without including, as express permit conditions, safe drilling and operating
    practices that Branch proposed and upon which the Department relied in making
    its decision to grant the permit.
    The Department’s authority to attach special conditions to a permit is
    discretionary, and the Board can properly substitute its own discretion for that of
    the Department and thereby order the issuance of permits subject to certain special
    conditions. Pequea Twp. v. Herr, 
    716 A.2d 678
    , 686 (Pa. Cmwlth. 1998). It
    appears that the Board chose not to substitute its discretion in this case because,
    10
    “[Q]uestions of resolving conflicts in the evidence, witness credibility, and evidentiary
    weight are within the exclusive discretion of the [Board], the fact finding agency, and are not
    matters for a reviewing court.” Pa. 
    Trout, 863 A.2d at 104
    . Thus, we may not substitute our
    judgment for that of the Board. 
    Id. To the
    extent that Petitioner invites us to do just that—i.e.,
    reconsider the evidence in a light more favorable to its position—we cannot do so.
    17
    having weighed the evidence, including expert testimony, it concluded that there
    was insufficient evidence of harm to justify imposition of additional special
    conditions.11    By asking this Court to conclude that special conditions were
    necessary, Petitioner is essentially asking this Court to reweigh the evidence and
    make credibility determinations regarding the validity of Petitioner’s concerns,
    which is beyond our purview. The Board already weighed this evidence and made
    credibility determinations that properly supported its decision. The Board accepted
    Lobins’ and Branch’s testimony that communication was unlikely to occur
    between Well 61 and the plume, an unplugged well, or Tank 234. Conversely, the
    Board found that Ruth’s testimony regarding the existence of unplugged wells in
    the vicinity of Tank 234 or the plume was speculative, and Petitioner failed to
    present evidence supporting a “scientific basis for how the drilling of Well . . . 61
    will impact either the plume or Tank 234.” (Board’s Adjudication at 9.)
    Moreover, Petitioner provides no evidence showing that the
    additional conditions were necessary to ensure the permit’s compliance with the
    law. Branch testified that these measures were added safety precautions; he did
    not testify that they were necessary to drill. (R.R. at 262a.) Lobins testified that
    the only special condition that he believed should be added to the permit was the
    condition that Branch would not hydraulically fracture in the Warren 1st or Warren
    2nd formations. Thus, the Board did not err in concluding that the Department did
    not act unreasonably in failing to impose additional conditions on the permit for
    11
    The Department did include in the permit for Well 61 a prohibition against drilling in
    the Warren 1st and Warren 2nd formations.
    18
    Well 61, and the Board did not err in not imposing those additional conditions on
    the permit itself.
    C. Whether Issuance of the Permit Violates Article I, Section 27 of the
    Pennsylvania Constitution
    As to the alleged violation of the Pennsylvania Constitution, Petitioner
    argues that the Board erred in allowing the Department to issue Branch the permit
    for Well 61 because the Commonwealth’s natural resources will be injured in
    violation of Article I, Section 27 of the Pennsylvania Constitution, which provides:
    The people have a right to clean air, pure water, and to
    the preservation of the natural, scenic, historic and
    esthetic values of the environment. Pennsylvania’s
    public natural resources are the common property of all
    the people, including generations yet to come. As trustee
    of these resources, the Commonwealth shall conserve
    and maintain them for the benefit of all the people.
    We agree with the Department and Branch, however, that Petitioner failed to raise
    his constitutional claim before the Board. Issues not raised before the Board are
    waived before the Commonwealth Court.12                 Ingram v. Dep’t of Envtl. Prot.,
    
    595 A.2d 733
    , 738 (Pa. Cmwlth. 1991).
    12
    When determining whether an action violates Article I, Section 27 of the Pennsylvania
    Constitution, this Court must weigh the following considerations:
    (1) Was there compliance with all applicable statutes and regulations relevant to
    the protection of the Commonwealth’s public natural resources? (2) Does the
    record demonstrate a reasonable effort to reduce the environmental incursion to a
    minimum? (3) Does the environmental harm which will result from the
    challenged decision or action so clearly outweigh the benefits to be derived
    therefrom that to proceed further would be an abuse of discretion?
    Payne v. Kassab, 
    312 A.2d 86
    , 94 (Pa. Cmwlth. 1973), aff’d, 
    361 A.2d 263
    (Pa. 1976). If we
    were to consider this argument, we would conclude that all of the prongs of the Payne test weigh
    in favor of constitutionality, and the Board did not err in concluding that the Department did not
    violate Article I, Section 27 by issuing the permit for Well 61 to Branch.
    19
    III.   CONCLUSION
    For the reasons set forth above, the Board did not err in concluding
    that Petitioner failed to establish that the Department’s issuance of a permit for
    Well 61 to Branch was unreasonable or contrary to law. Accordingly, the order of
    the Board is affirmed.
    P. KEVIN BROBSON, Judge
    20
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    United Refining Company,             :
    Petitioner     :
    :
    v.                        :   No. 1321 C.D. 2016
    :
    Department of Environmental          :
    Protection,                          :
    Respondent    :
    ORDER
    AND NOW, this 12th day of June, 2017, the order of the
    Environmental Hearing Board is AFFIRMED.
    P. KEVIN BROBSON, Judge
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    United Refining Company,                  :
    Petitioner              :
    :   No. 1321 C.D. 2016
    v.                           :
    :   Argued: April 4, 2017
    Department of Environmental               :
    Protection,                               :
    Respondent               :
    BEFORE:      HONORABLE P. KEVIN BROBSON, Judge
    HONORABLE PATRICIA A. McCULLOUGH, Judge
    HONORABLE MICHAEL H. WOJCIK, Judge
    DISSENTING OPINION BY
    JUDGE McCULLOUGH                                     FILED: June 12, 2017
    As recognized by the Environmental Hearing Board (Board), this
    matter involves a unique and unprecedented process of slant drilling by John D,
    Branch (Applicant), posing unknown dangers, particularly in the area near an
    active refinery.     The Board’s decision reflects these concerns where it states:
    “[T]his case is unique as Mr. Lobins [the expert testifying for the Department of
    Environmental Protection (Department)], himself, indicated.        It is out of the
    ordinary for the Department to receive an application for an oil and gas permit that
    allows drilling by a third party underneath an oil and gas refining company in full
    operation and in close proximity to a 3.6 million gallon gasoline storage tank.”
    (Board op. at 10.)
    Despite dismissing the appeal of United Refining Company (United
    Refining), the Board further expressed concern for the process in which the
    Department engaged, calling for a “more transparent” process and improved
    communication among the parties, which the Board suggested as “a more robust
    permitting application process.” (Board op. at 11.)        The Majority aptly cites
    section 3211(e.1) of the Oil and Gas Act, 58 Pa.C.S. §3211(e.1), dealing with the
    sole grounds on which the Department may deny a well permit. Subsection (3)
    states as a specific ground for denial: “Unresolved objections to the well location
    by the coal mine owner or operator.”            58 Pa.C.S. §3211(e.1)(3) (emphasis
    added).
    Notwithstanding the above, the Board identified two significant
    questions or objections left unresolved by the Department when it granted the
    application for the permit: (1) “[H]ow would the fracking of the well impact the
    surface?” and, (2) “How would the fracks propagate into the unplugged wells at
    the depths and distances where the fracking would take place?” (Board op. at 10.)
    Clearly, under the Board’s own analysis, there are “unresolved objections” which
    need to be answered by the Board.
    This Court’s review under the Oil and Gas Act is to ascertain whether
    the permitted use was shown to have been “necessary for the safe operation of a
    particular mine. . . .” Foundation Coal Resources Corporation v. Department of
    Environmental Protection, 
    993 A.2d 1277
    , 1290 (Pa. Cmwlth. 2010) (dealing with
    the prior version of this statute and applying the standards for denial in a case in
    which this Court affirmed the issuance of oil and gas drilling permits).
    Here, the unprecedented and unique method of fracking was to occur
    underneath an active refinery. United Refining raised concerns about safe drilling
    and operating practices and the Board expressed concerns and questions about the
    issuance of the permits. Applicant proposed five safeguards to address United
    Refining’s expressed concerns about Applicant’s operations: (1) there would be no
    fracking in the Warren 1st or Warren 2nd formations; (2) conductivity and video
    PAM - 2
    logs would be used when new wells were drilled and hydraulic fracturing in the
    vicinity of zones indicated by the logs as having excessive water would be
    avoided; (3) the pressure gauges would be closely monitored while fracking, and if
    the gauges indicated connection with another well, operations would cease
    immediately; (4) fracking would be conducted with smaller amounts of sand and
    water to control the length of the fractures; and, (5) the proposed termination point
    of Well 61 was altered to avoid the vicinity of the oil plume below Tank 234.
    Nonetheless, when the Department issued the permits, it imposed only
    the first of these special conditions proposed by Applicant.        In light of the
    unresolved objections and the unprecedented use of this fracking method in a
    potentially dangerous zone, it is incumbent upon the Board to address the
    remaining four proposals as special conditions to the permits.
    Accordingly, I would vacate and remand to the Board to resolve the
    unresolved objections and questions identified by the Board in its dismissal of the
    appeal, and to impose any special conditions necessary to alleviate the same upon
    remand.
    ________________________________
    PATRICIA A. McCULLOUGH, Judge
    PAM - 3