Capital City Holdings, LLC v. DOT ( 2022 )


Menu:
  •             IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Capital City Holdings, LLC              :
    :
    v.                       :
    :
    Commonwealth of Pennsylvania,           :
    Department of Transportation,           :   No. 407 C.D. 2021
    Appellant             :   Submitted: May 6, 2022
    BEFORE:        HONORABLE RENÉE COHN JUBELIRER, President Judge
    HONORABLE CHRISTINE FIZZANO CANNON, Judge
    HONORABLE BONNIE BRIGANCE LEADBETTER, Senior Judge
    OPINION NOT REPORTED
    MEMORANDUM OPINION
    BY JUDGE FIZZANO CANNON                     FILED: August 31, 2022
    The Commonwealth of Pennsylvania, Department of Transportation
    (Department), appeals from the March 9, 2021 order of the Court of Common Pleas
    of Dauphin County (trial court). The trial court found the Department’s action
    resulted in de facto takings under the Eminent Domain Code (Code)1 of two
    properties owned by Capital City Holdings, LLC (CCH), overruled the Department’s
    Preliminary Objections to a Petition for Appointment of Board of Viewers (Board
    of Viewers Petition) filed by CCH, and granted the Board of Viewers Petition. Upon
    review, we affirm.
    1
    26 Pa.C.S. §§ 101-1106.
    I. Background
    This matter involves the effect of the Department’s proposed plan to
    widen and reconstruct the I-83 Capital Beltway surrounding Harrisburg (Beltway
    Project) on two commercial properties owned by CCH and located at 3570 Paxton
    Street, Harrisburg (Paxton Street Property), and 535 South Cameron Street,
    Harrisburg (Cameron Street Property). See Trial Court Memorandum Opinion dated
    March 9, 2021 (Trial Court Opinion)2 at 1. The Beltway Project is a large highway
    improvement project originally planned in 2003 and divided into three sections that
    were developed simultaneously to ensure continuity and compatibility of the
    sections. See id. at 3. The Paxton Street Property is part of Section 2 of the Beltway
    Project, whereas the Cameron Street Property is part of Section 3. See id. The
    Department obtained funding for Sections 2 and 3 of the Beltway Project in 2016.3
    See id. Once the Department obtains the requisite environmental clearances,4 the
    Department will be able to begin the right-of-way acquisition process for affected
    properties located within the respective project Sections. See id. at 3-4. Actual
    construction of the Sections will not occur until the final project design has been
    approved, all required rights of way have been condemned, and all affected utilities
    have been relocated. See id. at 4.
    2
    On July 15, 2021, the trial court issued an opinion pursuant to Pennsylvania Rule of
    Appellate Procedure 1925(a) that adopted the previously filed Trial Court Opinion as its Pa.R.A.P.
    1925(a) opinion. See Trial Court Pa.R.A.P. 1925(a) Opinion dated July 15, 2021.
    3
    The Department obtained funding for Section 1 in 2006 and began construction thereon
    in 2016. See Trial Court Opinion at 3.
    4
    Each section of the Beltway Project requires an environmental clearance of some kind,
    be it a Categorical Exclusion, an Environmental Assessment, or an Environmental Impact
    Statement. See Trial Court Opinion at 3. The Department received a Categorical Exclusion for
    Section 3 and an Environmental Assessment for Section 2 in October of 2019 and June of 2020,
    respectively.
    2
    As part of the environmental approval process, the Department held a
    public open house regarding Beltway Project Sections 2 and 3 on October 18, 2018
    (October 2018 Open House), to share the Department’s intended designs for
    Sections 2 and 3 with the public and obtain public feedback.5 See Trial Court
    Opinion at 4.       While not detailed enough to indicate the full impact of the
    Department’s proposal, aerial map diagrams of proposed Sections 2 and 3 shown at
    the October 2018 Open House did indicate that the new highway would be placed
    directly on the Paxton Street Property, and that the front of the Cameron Street
    Property would also be affected.6 See id. at 4-5. At the time of the October 2018
    Open House, the Department projected construction on Beltway Project Sections 2
    and 3 to begin approximately five years later, or sometime around 2022 or 2023,
    with required private property condemnations scheduled to commence one and a
    half to two years before the start of construction. See id. at 5. When finally approved
    by the Department in November 2019, the plans for Sections 2 and 3 of the Beltway
    Project remained relatively unchanged from those produced at the October 2018
    Open House. See id.
    Ted Keleman is an auto broker7 and owner of CCH. See Trial Court
    Opinion at 6. Beginning in 2007, Keleman operated an automobile retail venture
    called Manheim Car King (Manheim) out of the two CCH properties in question.
    See id. Manheim rented and used the Paxton Street Property as its retail showroom
    5
    The Department conducted a second public open house on November 19, 2019. See Trial
    Court Opinion at 5.
    6
    These diagrams ultimately became part of the environmental reports finalized thereafter.
    See Trial Court Opinion at 5.
    7
    Auto brokers buy traded-in vehicles from new car dealerships for resale to third parties
    through auctions and other platforms. See Trial Court Opinion at 6.
    3
    and the Cameron Street Property as a repair and service center intended to support
    the retail side of the venture. See id. However, near the end of 2017, and prior to
    the October 2018 Open House, Keleman decided to shutter the Manheim operations
    at both the Paxton Street Property and the Cameron Street Property.8 See id.
    Thereafter, Keleman listed both properties for lease. See Trial Court
    Opinion at 6. Specifically, on November 27, 2017, Keleman signed a real estate
    listing agreement that authorized a listing of the Paxton Street Property for lease at
    $4,000 per month, triple net.9 See id. at 7. This listing agreement was amended on
    April 12, 2018, to authorize the sale of the Paxton Street Property for $750,000. See
    id. CCH thereafter received two offers to purchase the Paxton Street Property for
    $775,000. See id. The first offer came from Bay, LLC (Bay), an outfit that intended
    to utilize the Paxton Street Property as a marijuana dispensary, and was contingent
    on Bay receiving a marijuana dispensary permit from the Commonwealth. See id.
    The second offer came from Rhada, Inc. (Rhada), a Dunkin Donuts franchisee that
    intended to open a Dunkin Donuts location at the site. See id.
    CCH ultimately accepted Bay’s offer to purchase the Paxton Street
    Property, keeping Rhada’s offer in reserve in case the Bay deal fell through. See
    Trial Court Opinion at 8. On November 7, 2018, the Bay offer did fall through for
    reasons unrelated to the potential condemnation of the Paxton Street Property as a
    result of the Beltway Project. See id. Thereafter, on January 10, 2019, Rhada’s
    consultant contacted CCH’s real estate agent to inquire whether the Paxton Street
    8
    Keleman’s decision to shutter Manheim’s operations was in response to learning of
    employee theft, not in response to the Beltway Project. See Trial Court Opinion at 6.
    9
    “Triple net” refers to a real estate leasing arrangement whereby the leasing tenant is
    responsible for all taxes, insurance, and common area maintenance costs associated with a property
    in addition to the monthly lease amount. See Trial Court Opinion at 7 n.6.
    4
    Property was still available for purchase. See id. The October 2018 Open House
    having occurred, CCH’s real estate agent disclosed to Rhada’s consultant the
    possibility of the condemnation of the entire Paxton Street Property within three to
    four years.10 See id. Rhada did not submit another offer to purchase the Paxton
    Street Property. See id. CCH did thereafter receive an offer to lease the Paxton
    Street Property at a rate of $4,000 per month to a fireworks retailer, but the deal was
    not consummated based on concerns over the potential condemnation of the
    property. See id. CCH received no further comparable offers to purchase or lease
    the Paxton Street Property. See id. at 9.
    Regarding the Cameron Street Property, Keleman listed this property
    for lease on December 4, 2017, and thereafter amended the listing to authorize the
    property to be offered for sale at $399,000. See Trial Court Opinion at 6-7. On
    August 16, 2018, WR Acquisitions, LLC (WRA), a laundromat operator, offered to
    purchase the Cameron Street Property for $375,000, and the parties entered into an
    agreement of sale on October 31, 2018. See id. at 9. While neither CCH nor WRA
    knew of the potential condemnation of a portion of the Cameron Street Property at
    the time of the agreement of sale, the fact was discovered during the sales contract’s
    due diligence period. See id. WRA ultimately terminated the sales contract based
    on concerns regarding the effect such a condemnation would have on needed parking
    at the Cameron Street Property. See id.
    After the termination of the sale agreement with WRA, CCH received
    no comparable offer for purchase or lease of the Cameron Street Property. See Trial
    Court Opinion at 9. Eventually, CCH leased the Cameron Street Property at $1,500
    10
    In fact, CCH’s real estate agent began disclosing the fact of the potential condemnation
    to all potential purchasers of the Paxton Street Property following the October 2018 Open House,
    as required by the National Association of Realtors. See Trial Court Opinion at 8.
    5
    per month, which rate was below the market value of the property, but which
    Keleman accepted in an effort to cover the property’s carrying costs. See id. at 9-
    10.
    As a result of the inability to either sell or lease the Paxton Street
    Property or the Cameron Street Property at sufficient amounts or rates, the properties
    have lost money. See Trial Court Opinion at 10. CCH had to utilize money from
    other businesses owned by Keleman to cover the loans, utilities, taxes, and insurance
    on both properties, which expenses the properties continue to incur.                  See id.
    Additionally, Keleman’s inability to cover the loan payment on the Paxton Street
    Property caused the lender, First National Bank, to call due the entire balance of this
    and two other loans it held on two of Keleman’s other real estate holding companies,
    despite Keleman having missed no payments on those other loans. See id. To cover
    the loans, First National Bank confiscated Keleman’s bank account.                    See id.
    Ultimately, Keleman was forced to take money from a retirement account and a
    savings account to cover the remaining loan balances.11 See id. Had Keleman not
    covered these loans, First National Bank would have foreclosed on all his properties.
    See id.
    CCH filed the Petition on January 24, 2020, alleging a de facto taking
    of both the Paxton Street Property and the Cameron Street Property and seeking the
    appointment of a board of viewers to evaluate the value of the properties. See Trial
    Court Opinion at 10; see also Petition. The Department filed the Preliminary
    Objections, alleging that (1) the mere publication of information about the Beltway
    11
    The amount owed on the three separate loans totaled $496,446.12. See Trial Court
    Opinion at 10. First National Bank confiscated $340,917.73 from Keleman’s personal bank
    account to cover the balance. See id. As discussed supra, Keleman used a retirement account and
    a savings account to cover the remaining balance. See id.
    6
    Project over a short period of time is not an exceptional circumstance that
    substantially deprived CCH of the beneficial use and enjoyment of its properties; (2)
    the economic hardships CCH allegedly has suffered are not the consequence of the
    Department’s exercise of its power of eminent domain; (3) the location of the
    proposed Beltway Project is not fixed such that condemnation of the Paxton Street
    Property and the Cameron Street Property is inevitable; (4) the Petition failed to
    specify whether the alleged de facto taking is a total or partial taking of either
    property; and (5) the Petition fails to sufficiently describe, as required by law, the
    properties allegedly condemned.            See Trial Court Opinion at 10-11; see also
    Preliminary Objections.          Following a hearing and argument, the trial court
    determined that the Department’s actions resulted in de facto takings of both the
    Paxton Street Property and the Cameron Street Property in their entirety as of the
    October 2018 Open House and granted CCH’s request to appoint a board of viewers
    to assess the value of the properties at that time.12 This appeal followed.13
    II. Issues
    On appeal, the Department argues that the trial court erred by
    overruling the Preliminary Objections and granting the Petition. See Department Br.
    at 5-6 & 27-54. First, the Department argues that the trial court erred by holding
    that the Cameron Street Property was the subject of a de facto taking. See id. at 27-
    12
    The trial court indicated that it would appoint a board of viewers in a separate order. See
    Trial Court Opinion at Order.
    13
    “This Court’s scope of review of a trial court’s ruling on preliminary objections to a
    petition for appointment of [a board of] viewers is limited to determining whether there is
    competent evidence in the record to support the necessary findings and whether the trial court
    committed an error of law.” Ristvey v. Dep’t of Transp., 
    52 A.3d 425
    , 429 n.3 (Pa. Cmwlth. 2012).
    7
    39. Specifically, the Department claims that CCH failed to prove exceptional
    circumstances stemming from the immediate, necessary, and unavoidable
    consequences of the potential condemnation existed that substantially deprived CCH
    of the use and enjoyment of the Cameron Street Property. See id. at 29-33.
    Additionally, the Department claims that CCH has not been deprived of the use of
    the Cameron Street Property, and that CCH has a remedy under the Code even if
    impacted by the imminence of a condemnation. See id. at 34-39. Second, the
    Department argues alternatively that, even if a de facto taking occurred in relation
    to the Cameron Street Property, the trial court erred by holding that the entire
    property was subject to the taking when the Beltway Project required the
    condemnation of only a portion of the Cameron Street Property. See id. at 39-42.
    Third, the Department claims that the trial court erred by holding that the Paxton
    Street Property was subject to a de facto taking. See id. at 42- 52. As with the
    Cameron Street Property, the Department argues that CCH failed to prove the
    existence of exceptional circumstances stemming from the immediate, necessary,
    and unavoidable consequence of the potential condemnation that deprived it of the
    beneficial use and enjoyment of the Paxton Street Property. See id. Fourth, the
    Department argues that, if the de facto takings are upheld, the trial court erred by
    determining that the takings occurred as of the October 2018 Open House. See id.
    at 52-53. In its fifth and final claim, the Department argues that the trial court erred
    by finding a damage value for the taking of the Paxton Street Property, as such a
    finding will prejudice any future board of viewers proceedings or determinations.
    See id. at 54.
    8
    III. Discussion
    Section 502(c) of the Code allows a property owner that asserts that its
    property interest has been condemned without the filing of a declaration of taking to
    file a petition for the appointment of [a board of] viewers setting forth the factual
    basis of the petition.      See 26 Pa.C.S. § 502(c)(1).        “[T]he Code provides
    the exclusive method and practice governing eminent domain proceedings,
    including de facto takings, and [] preliminary objections are the exclusive method of
    raising objections to a petition for appointment of viewers alleging a de
    facto taking.” York Rd. Realty Co., L.P. v. Cheltenham Twp., 
    136 A.3d 1047
    , 1050
    (Pa. Cmwlth. 2016) (quoting Gerg v. Twp. of Fox, 
    107 A.3d 849
    , 852 (Pa. Cmwlth.
    2015)) (emphasis in original) (brackets omitted); see also Pileggi v. Newton Twp.,
    
    245 A.3d 377
     n.4 (Pa. Cmwlth. 2021) (“Preliminary objections are the exclusive
    method under the [] Code of raising legal and factual objections to a petition for
    appointment of viewers which alleges a de facto taking.” (quoting German v. City
    of Phila., 
    683 A.2d 323
    , 325 n.5 (Pa. Cmwlth. 1996)); Section 502 of the Code, 26
    Pa.C.S. § 502. However,
    [i]n eminent domain proceedings, preliminary objections
    serve a broader purpose than ordinary preliminary
    objections and are intended as a procedure to
    expeditiously resolve threshold legal issues[.] Indeed, the
    trial court must first determine whether a de facto taking
    has occurred before sending the matter to a board of
    view[ers] to determine damages.
    Hill v. City of Bethlehem, 
    909 A.2d 439
    , 442 n.8 (Pa. Cmwlth. 2006) (internal
    citations omitted). Therefore, when preliminary objections are filed in a de facto
    taking case,
    9
    [a] trial court must determine first whether, as a matter of
    law, the averments of the petition for the appointment of
    [a board of] viewers, taken as true, in addition to any
    stipulated facts, are sufficient to state a cause of action for
    a de facto taking. If not, the preliminary objections must
    be sustained and the petition dismissed or allowed to be
    amended.
    Hill, 
    909 A.2d at 443
     (quoting Stein v. City of Phila., 
    557 A.2d 1137
    , 1140 (Pa.
    Cmwlth. 1989)).
    The decision of whether a compensable taking has
    occurred requires an initial determination that the act
    complained of was, in fact, an exercise of eminent domain
    power. Acts not done in the exercise of the right of
    eminent domain and not the immediate, necessary or
    unavoidable consequences of such exercise cannot be the
    basis of a proceeding in eminent domain.
    German, 
    683 A.2d at 326-27
    .
    “A de facto taking is not a physical seizure of property; rather, it is an
    interference with one of the rights of ownership that substantially deprives the owner
    of the beneficial use of his property.”
    14 York, 136
     A.3d at 1050-51 (quoting In re
    Borough of Blakely, 
    25 A.3d 458
    , 463-64 (Pa. Cmwlth. 2011)) (emphasis omitted).
    The law is well settled that
    [i]n order to prove a de facto taking, the property owner
    must establish exceptional circumstances that
    substantially deprived him of the beneficial use and
    enjoyment of his property. This deprivation must be
    caused by the actions of an entity with eminent domain
    powers. Also, the damages sustained must be an
    14
    “The beneficial use of the property includes not only its present use, but all potential
    uses, including its highest and best use.” York, 136 A.3d at 1051.
    10
    immediate, necessary and unavoidable consequence of the
    exercise on the entity’s eminent domain powers.
    Id. at 1050-51 (quoting Blakely, 
    25 A.3d at 463-64
    ) (emphasis and footnote omitted).
    Thus,
    [a] property owner carries a heavy burden of proof in de
    facto condemnation proceedings and must show that: (1)
    the condemnor has the power to condemn the land under
    eminent domain procedures; (2) [] exceptional
    circumstances have substantially deprived him of the use
    and enjoyment of his property; and (3) the damages
    sustained were the immediate, necessary, and unavoidable
    consequences of the exercise of the eminent domain
    power.
    In Re Mountaintop Area Joint Sanitary Auth., 
    166 A.3d 553
    , 561 (Pa. Cmwlth.
    2017); see also York, 136 A.3d at 1050-51. No bright line test exists to determine
    whether a government action has resulted in a de facto taking; each case presents a
    fact-specific inquiry. See York, 136 A.3d at 1050-51. “[W]hen determining whether
    a de facto taking has occurred, we focus on the governmental action in question.”
    Mountaintop Area Joint Sanitary Auth., 166 A.3d at 561.
    Pennsylvania courts have explained that certain specific actions do not,
    individually, “substantially deprive an owner of the use and enjoyment of his
    property such as to constitute a de facto taking.” Standard Invs. Corp. v. Com., 
    28 Pa. D. & C. 3d 294
    , 304 (C.P. Pa. 1982), aff’d sub nom. Dep’t of Transp. v. Standard
    Invs. Corp., 
    472 A.2d 282
     (Pa. Cmwlth.),15 aff’d, 
    485 A.2d 392
     (Pa. 1984). Such
    actions include: (1) the inclusion of a property in the planning stage of a program
    15
    In Standard Investments, this Court affirmed based on the opinion of the Court of
    Common Pleas of Bucks County, the holdings of which we expressly affirmed. See Dep’t of
    Transp. v. Standard Invs. Corp., 
    472 A.2d 282
    , 282 (Pa. Cmwlth.), aff’d, 
    485 A.2d 392
     (Pa. 1984).
    11
    or project; (2) the recording of a plan or project’s “ultimate” plans; (3) approval
    and/or funding of renewal or redevelopment projects; (4) notices to and/or
    negotiations with affected property owners; (5) acquisition of properties by
    agreement; (6) governmental actions generating publicity regarding a program or
    project; (7) holding public hearings on a program or project; (8) posting maps of the
    program or project near a landowner’s property; and (9) condemning other
    properties in a landowner’s neighborhood. See id. at 304. However, these actions
    and other factors may combine in a manner such that the totality of the circumstances
    may render a property unmarketable and thereby substantially deprive the plaintiff
    of its use and enjoyment of the property. See id. at 305-06; Dep’t of Transp. v.
    Lawton, 
    412 A.2d 214
    , 216 (Pa. Cmwlth. 1980).
    Additionally, Pennsylvania courts have found that de facto takings
    implicating a right to the appointment of a board of viewers to determine appropriate
    compensation can occur where an impending condemnation, even if not yet
    finalized, impacts a property to the point where it no longer generates sufficient
    income to cover taxes and/or mortgages, and thus threatens loss of the property. See
    Conroy-Prugh Glass Co. v. Dep’t of Transp., 
    321 A.2d 598
    , 602 (Pa. 1974).
    Therefore, “[i]f there has been [] an interim deprivation of use[] or exposure to loss,
    then the principle of de facto taking becomes applicable to accelerate the time when
    the governmental authority must make compensation.” Standard Invs., 
    28 Pa. D. & C. 3d at 302-03
    .
    Here, the trial court found that exceptional circumstances did exist that
    impacted CCH’s beneficial use and enjoyment of its properties. See Trial Court
    Opinion at 15. The trial court found CCH showed that the subject properties were
    unable to be sold or leased at the prices at which they could have been sold or leased
    12
    prior to the October 2018 Open House, and that the offers received on the properties
    following the October 2018 Open House were significantly lower than those
    received before. See 
    id.
     Thus, the trial court concluded, “the evidence shows that
    the marketability of the subject properties was greatly affected by the publicity of
    the [Beltway] Project and the [October 2018] Open House that was held to inform
    the public of the proposed plans for the [Beltway] Project.” 
    Id.
     Additionally, the
    trial court found the evidence illustrated that, following the October 2018 Open
    House, the properties were unable to generate sufficient income to cover tax and
    loan payments. See id. at 16. Thus, the trial court determined that CCH sustained
    its burden of showing exceptional circumstances necessary to justify a finding that
    a de facto taking occurred with respect to each property. See id.
    We find no error in the trial court’s determination. Pennsylvania courts
    have found de facto takings occurred under circumstances similar to the instant
    matter. In Standard Investments, the trial court found, and this Court affirmed, a de
    facto taking occurred where escalating public awareness of an increasing likelihood
    of condemnation rendered a property unmarketable, resulting in a failure of the
    property to generate adequate income to cover taxes or existing mortgages. See
    Standard Invs., 
    28 Pa. D. & C. 3d at 310-11
    . Likewise, in Conroy-Prugh, our
    Supreme Court found a de facto taking occurred where a loss of tenants following
    public hearings on a non-finalized project resulted in insufficient income to pay taxes
    and threatened loss of property. See Conroy-Prugh, 321 A.2d at 602. Additionally,
    in Lawton, this Court found that proof of loss of rental income, unmarketability of
    the property, and the threat of loss at a sheriff’s sale for unpaid taxes established a
    de facto taking cause of action. Lawton, 412 A.2d at 217.
    13
    Here, the evidence illustrated that, prior to the October 2018 Open
    House, CCH received offers of $775,000 and $375,000 to purchase the Paxton Street
    Property and the Cameron Street Property, respectively. The evidence further
    illustrated that, after the October 2018 Open House and the disclosure of the possible
    condemnation of the properties to prospective purchasers/lessors of the properties
    by CCH’s real estate agent, apprehension regarding the potential condemnation of
    the Cameron Street Property resulted in the termination of that sales agreement.
    CCH did not receive any offers to purchase or lease either property for amounts
    approaching the offers it had received before the October 2018 Open House.16 While
    CCH was able to lease the Cameron Street Property after the October 2018 Open
    House, the rent received was significantly below market value and was accepted
    only in an effort to cover the property’s carrying costs. Additionally, following the
    October 2018 Open House, the properties’ income decreased to a point where they
    no longer generated adequate funds to cover the loans and taxes due thereon, thus
    subjecting the properties to possible foreclosure/loss.17 While any of these actions
    in isolation may not have warranted a finding of de facto taking, the totality of this
    evidence adequately supports the trial court’s conclusion that exceptional
    circumstances adequate to justify a de facto taking existed with respect to each
    property. See Standard Invs., 
    28 Pa. D. & C. 3d at
    302-03 & 305-06; see also
    Lawton, 412 A.2d at 217; Conroy-Prugh, 321 A.2d at 602.
    16
    We acknowledge that CCH was able to lease the Cameron Street Property after the
    October 2018 Open House, but note that the $1,500 monthly rent was below market value and
    accepted only in an effort to cover the property’s carrying costs.
    17
    We note that Keleman’s ability to satisfy his properties’ outstanding loan balances
    through the use of his personal funds does not alter the fact that the reduction of income from the
    properties placed them in danger of foreclosure in the first place. See Standard Invs., 28 Pa. D &
    C. 3d at 308-09.
    14
    We also disagree with the Department to the extent it argues that the
    trial court erred by finding a de facto condemnation occurred regarding the entirety
    of the Cameron Street Property. As the trial court noted, “based on the plans as set
    forth by [the Department], the Cameron Street Property will essentially be
    landlocked with no ingress or egress.” Trial Court Opinion at 18. The Department’s
    actions also affected the entirety of the Cameron Street Property in terms of its
    market value. The prospective buyer cancelled the agreement to purchase the
    Cameron Street Property based on concerns about the effect the partial
    condemnation would have on the practical use of the entire property. See Standard
    Invs., 
    28 Pa. D. & C. 3d at 308-09
     (finding a de facto taking as to entire property
    entitling the appointment of a board of viewers where proposed taking of portion of
    property resulted in lost income and an inability to generate income through an
    appropriate sale of entire property). As discussed supra, the trial court properly
    determined that a de facto taking occurred with reference to the Cameron Street
    Property. The effect of the alleged partial condemnation on the overall market value
    of the Cameron Street Property is a matter for the board of viewers to determine.
    Further, we find no error with the trial court’s assignment of the
    October 18, 2018 date to the de facto takings at issue in this matter. The evidence
    illustrated that the October 2018 Open House commenced the period of decline in
    the income-producing and sale value of both the Paxton Street Property and the
    Cameron Street Property. At a minimum, the October 2018 Open House represented
    the point in time after which CCH’s real estate agent’s ethical obligation required
    disclosure of the potential condemnation to potential purchasers and lessors, which
    disclosure directly resulted in the termination of a sale agreement for the Cameron
    Street Property. To hold that the de facto taking should be dated from the Petition’s
    15
    filing date would fail to acknowledge the diminution in the properties’ value prior
    to the filing of the Petition, which diminution in value exposed the properties to
    possible loss and is the very change in value upon which CCH based its claim of de
    facto takings in the first place, and upon which the trial court based its finding that
    de facto takings had, in fact, occurred.
    Finally, we are not persuaded by the Department’s argument that the
    trial court prejudiced a future damages proceeding by stating in a footnote that the
    fair market value of the Paxton Street Property was $775,000 prior to the October
    2018 Open House. See Department Br. at 54. In the footnote in question, the trial
    court restated the testimony of CCH’s expert placing the fair market value of the
    Paxton Street Property at $775,000 as a function of an offer received to purchase
    that property before the October 2018 Open House. See Trial Court Opinion at 15
    n.8.   As the Department notes, the assessment of damages/values in matters
    involving de facto takings rests with the appointed board of viewers.                     See
    Department Br. at 54; see also 26 Pa.C.S. § 512(5). Thus, the board of viewers will
    not be bound by the trial court’s restatement and/or assessment of the testimony
    given. The Department’s argument that the trial court’s footnote has prejudiced
    future proceedings lacks merit.18
    IV. Conclusion
    For the above reasons, we affirm the trial court’s March 9, 2021 order.
    _______________________________
    CHRISTINE FIZZANO CANNON, Judge
    18
    We further note that the Department retains a right to appeal from a future board of
    viewers’ determination should it feel aggrieved thereby. See 26 Pa.C.S. § 516(a)(1).
    16
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Capital City Holdings, LLC           :
    :
    v.                        :
    :
    Commonwealth of Pennsylvania,        :
    Department of Transportation,        :   No. 407 C.D. 2021
    Appellant          :
    ORDER
    AND NOW, this 31st day of August, 2022, the March 9, 2021 order of
    the Court of Common Pleas of Dauphin County is AFFIRMED.
    __________________________________
    CHRISTINE FIZZANO CANNON, Judge