Myco Mechanical, Inc. v. The City of York ( 2022 )


Menu:
  •           IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Myco Mechanical, Inc.,                    :
    Appellant      :
    :   No. 590 C.D. 2021
    v.                           :   SUBMITTED: June 3, 2022
    :
    The City of York                          :
    BEFORE:      HONORABLE RENÉE COHN JUBELIRER, President Judge
    HONORABLE ELLEN CEISLER, Judge
    HONORABLE BONNIE BRIGANCE LEADBETTER, Senior Judge
    OPINION NOT REPORTED
    MEMORANDUM OPINION BY
    SENIOR JUDGE LEADBETTER                                 FILED: October 12, 2022
    Myco Mechanical, Inc. appeals from an order of the Court of Common
    Pleas of York County granting the City of York’s motion for summary judgment in
    its entirety. We affirm.
    This matter originated with the conversion of the City’s Old City Hall
    at 50 West King Street, York, Pennsylvania, into headquarters for the City’s police
    department. A heating ventilation and air conditioning (HVAC) contractor, Myco
    entered into a 2012 contract with the City for $1,043,000. (Dec. 5, 2014 Compl., ¶
    5.) In order to coordinate the work and enable the various trades to work efficiently,
    the City required Myco and the other prime contractors to agree to perform their
    respective work within the time frames provided in the project schedule incorporated
    into the bid documents. (Id., ¶¶ 6 and 7.) Myco’s work was dependent upon the
    other trades’ timely completion of work as set forth in that schedule. (Id., ¶ 13.)
    In November 2012, the City issued Myco a notice to proceed triggering
    the start of the 400-day duration of Myco’s work. (Id., ¶ 10.) Myco mobilized for
    work with a start date in late November 2012 but had to demobilize when
    predecessor work was incomplete. (Id., ¶¶ 14 and 15.) Myco remobilized and
    commenced work in January 2013. (Id., ¶ 16.) Ultimately, the City extended the
    project schedule to reflect an August 2014 completion date for Myco’s work. (Id.,
    ¶ 11.) The delay from the originally scheduled completion date in December 2013
    to the actual completion date in August 2014 resulted in an additional 129 days for
    Myco. (Id., ¶ 20.) Myco averred that the delay was caused by the City’s failure to
    timely coordinate the other prime contractors and to complete the necessary
    precursor work. (Id., ¶¶ 21 and 22.) In addition, Myco alleged that the City delayed
    the project by failing to have the site available for work at the initial stages and at
    various times throughout, thereby preventing Myco from completing its work. (Id.,
    ¶ 24.) Myco alleged: “As a direct and proximate result of the construction delays
    caused by [the City], Myco [] incurred additional costs to complete its work on the
    [p]roject beyond those originally contemplated by its contract . . . .” (Id., ¶ 25.)
    In December 2014, Myco commenced a civil action against the City
    seeking $258,200.36 in direct damages, plus interest, penalties, and counsel fees.
    The complaint included four counts: (1) breach of contract (City unilaterally
    modified and extended time for completion of Myco’s work on the project); (2)
    unjust enrichment (in the alternative); (3) breach of implied contract (in the
    alternative); and (4) a claim under what is commonly called the Prompt Pay Act.1 In
    February 2015, the City filed an answer and new matter therein asserting a
    1
    Sections 3931 through 3939 of the Commonwealth Procurement Code, 62 Pa.C.S. §§ 3931-
    3939, are frequently referred to as the Prompt Pay Act.
    2
    counterclaim. Following extensive discovery, the City filed the September 2020
    motion for summary judgment on liability that is presently at issue. The trial court
    granted the City’s motion in its entirety and Myco’s appeal to this Court followed.2
    The success of Myco’s case depends upon the applicability of the
    exculpatory “no damages for delay” clause found in the parties’ contract, which
    provides for an extension of time but not monetary consideration in the case of delay.
    The clause, which the City maintains constitutes Myco’s sole remedy for a delay
    claim, states:
    § 8.3.3 Delays and Extensions of Time. No payment or
    compensation or claim for damages shall be made to the
    Contractor as compensation for damages for any delays or
    hindrances from any cause whatsoever in the progress of
    the Work, notwithstanding whether such delays be
    avoidable or unavoidable. The Contractor’s sole remedy
    for delays shall be an EXTENSION OF TIME ONLY,
    pursuant to and only in accordance with this Paragraph
    8.3; such extension to be a period equivalent to the time
    lost by reason of any and all of the aforesaid causes, as
    determined by the Architect. In consideration for this
    grant of a time extension, neither the Owner or Architect
    shall be held responsible for any loss or damage or
    increased costs sustained by the Contractor through any
    delays caused by the Owner or Architect, or any other
    Contractor, or on account of the aforesaid causes or any
    other cause of delay. In the event the Contractor shall
    choose to litigate this clause or issue and loses said
    2
    The entry of summary judgment is proper where the pleadings, depositions, answers to
    interrogatories, and admissions on file, together with the affidavits, if any, show that there is no
    genuine issue of material fact and that the moving party is entitled to judgment as a matter of law.
    Marks v. Tasman, 
    589 A.2d 205
    , 206 (Pa. 1991). The record must be viewed in the light most
    favorable to the non-moving party, and all doubts as to the existence of a genuine issue of material
    fact must be resolved against the moving party. Our review of an order granting summary
    judgment involves only an issue of law. Hence, our review is plenary. Bourgeois v. Snow Time,
    Inc., 
    242 A.3d 637
     (Pa. 2020).
    3
    litigation, the Contractor shall reimburse the Owner and
    the Architect for their reasonable attorney’s and expert
    witness fees and all other costs and expenses incurred by
    them in the litigation.
    (City’s Mot. for Summ. J., ¶ 8; Reproduced Record “R.R.” at 54a.)
    Exculpatory provisions such as “no damages for delay” clauses are
    disfavored under the law. Vinikoor v. Pedal Pa., Inc., 
    974 A.2d 1233
    , 1238 (Pa.
    Cmwlth. 2009). Nonetheless, they are generally enforceable but “cannot be raised
    as a defense where (1) there is an affirmative or positive interference by the owner
    with the contractor’s work, or (2) there is a failure on the part of the owner to act on
    some essential matter necessary to the prosecution of the work.” Guy M. Cooper,
    Inc. v. E. Penn Sch. Dist., 
    903 A.2d 608
    , 613 (Pa. Cmwlth. 2006).
    Courts have found sufficient affirmative or positive interference to
    overcome the applicability of the “no damages for delay clause” where the owner
    but not the contractor was aware of pre-bidding problems with availability, access,
    or design. 
    Id. at 613-14
    . For example, in Coatesville Contractors & Engineers, Inc.
    v. Borough of Ridley Park, 
    506 A.2d 862
     (Pa. 1986), the owner knew of a preexisting
    access problem caused by an undrained lake. In Department of Highways v. S.J.
    Groves & Sons Co., 
    343 A.2d 72
     (Pa. Cmwlth. 1975), the owner knew that a
    contractor would not have access to a portion of the construction site for a fourteen-
    week period while a utility removed and replaced cable conduits.
    Likewise, “an owner cannot insulate itself from a delay damage claim
    where it fails to perform an essential contractual duty.” Guy M. Cooper, 
    903 A.2d at 614
    . Where an owner responsible for contractor cooperation directed a contractor
    to proceed but the contractor was prevented from accessing the work area for five
    months due to another contractor, the Supreme Court found that the owner had failed
    to perform an essential duty. Gasparini Excavating Co. v. Pa. Tpk. Comm’n, 187
    
    4 A.2d 157
     (Pa. 1963). Another such example occurred when an owner that assumed
    responsibility for negotiating the relocation of a water line failed to do so
    expeditiously thereby precluding access while others relocated the water line. State
    Highway & Bridge Auth. (Penn-DOT) v. Gen. Asphalt Paving Co., 
    405 A.2d 1138
    (Pa. Cmwlth. 1979).
    Here, Myco asserted four sources of delay that allegedly established
    active interference or neglect on the City’s part sufficient to overcome the
    enforceability of the “no damages for delay” clause: discovery of additional asbestos
    requiring remediation; discovery of lead-based paint requiring abatement; delivery
    delay of air handling and condenser units by Johnson Controls; and Verizon’s delay
    in performing information technology “IT” work. Myco’s first argument, that
    material facts remained disputed, somewhat overlaps its second argument, that
    certain periods of delay should be attributable to the City and constitute a defense to
    the “no damages for delay” clause. We elaborate on the alleged sources of delay
    where warranted.
    I.
    Myco first argues that the trial court erred in granting the motion for
    summary judgment where material facts remain disputed, especially those that Myco
    raised in its response to the motion via the expert report from Damian Cassin of
    Progressive Construction Management (PCM Report).3 (June 16, 2017 PCM Report
    3
    Pursuant to Pennsylvania Rule of Civil Procedure 1035.3, it was Myco’s burden to produce
    facts arising from the summary judgment record to contradict the City’s motion for summary
    judgment. Contrary to the City’s suggestion, expert reports are among the documents that a court
    may consider as part of a motion for summary judgment. In fact, “the summary judgment standard
    requires a trial court to view the non-moving party’s expert reports, and all reasonable inferences,
    in a light most favorable to the non-moving party, and the trial court cannot ‘sua sponte assail
    them’ if their conclusions are ‘sufficiently supported[.]’” Bourgeois, 242 A.3d at 652 (citation
    omitted).
    5
    at 1-32; R.R. at 770a-801a.) In support, Myco cites six conclusions from the PCM
    Report:
    1. “[A]s noted in this report, the presence of
    abatement impacted not only initial demolition and
    subsequent progress, but regularly resulted in interference
    with access.” R.R. [at] 777a.
    2. [I]nability to proceed with employee relocation
    due to the lack of an IT prime contract delayed the “critical
    activity of Stair 2 Demolition on the third floor” for 39
    days. R.R. [at] 777a.
    3.    [A]batement      work     was     required[.]
    “[P]redecessor activity required before demolition could
    proceed.”
    4. “[L]imited work had proceeded on the project
    due to delays in relocation and on-going abatement.” R.R.
    [at] 781a.
    5. “[T]he Engineer requiring performance
    specifications which his own basis of design equipment
    manufacturer apparently could not provide” caused a
    three-month delay[.] R.R. [at] 783a.
    6. “[T]he IT feed, and subsequent interior main
    service feed and system programming, installed by
    Verizon will comprise the single largest delay to the
    project.” R.R. [at] 776a.
    (Myco’s Br. at 17-18.)
    The first, third, and fourth conclusions from the PCM Report are
    interrelated. Turning to the first conclusion, there is no dispute that abatement
    impacted the initial demolition and subsequent progress, as well as interference with
    access. As for the third conclusion, there is no dispute that abatement was required
    before demolition could proceed. Turning to the fourth conclusion, that only limited
    work on the project had proceeded due to delays in relocation and continuing
    6
    abatement, there similarly is no dispute that there was delay and that work could not
    always proceed.
    The second and sixth conclusions are also interrelated. The second
    conclusion provides that the inability to proceed with employee relocation due to the
    lack of an IT prime contract delayed the Stair 2 Demolition on the third floor for
    thirty-nine days. The sixth conclusion states that “the IT feed, and subsequent
    interior main service feed and system programming, installed by Verizon will
    comprise the single largest delay to the project.” (R.R. at 776a.) However, the fact
    that there were delays attributable to IT-related issues is not in dispute. The IT
    contractor whose job it was to get the project ready for the utility networks,
    Computer Support Services, Inc. (CSSI), was the entity that caused unanticipated
    delay. As the summary judgment record reflects, this issue was communicated to
    the bidders and incorporated into the contract. In addition, the contractors were
    continuously updated. (See City’s Mot. For Summ. J., Ex. 101, “Project Manual,
    Addendum No. 2 Bid Form”; Ex. 102, “Re-bid Addendum A”; Ex. 103, “Re-Bid
    Addendum C”; Ex. 104, “Re-Bid Addendum E”; and Ex. 105, “Re-Bid Addendum
    F”; R.R. at 621a-33a.) As for Verizon, the City gave Myco the notice to proceed in
    November 2012 and the contract with Verizon did not start until June 2013, well
    after the project started. (May 7, 2021 Trial Ct. Op. at 30.) In addition, Myco failed
    to provide a document identifying IT problems with Verizon or any other entity
    between November 20, 2012 and January 7, 2013.
    The fifth conclusion, which pertains to the City’s contract with Johnson
    Controls to provide two air handling units and one condensing unit, states that there
    was a three-month delay as a result of “the Engineer [Uday Patel, architect Buchart
    Horn’s employee] requiring performance specifications which his own basis of
    7
    design equipment manufacturer apparently could not provide[.]” (R.R. at 783a.)
    However, the summary judgment record does not reflect undisputed material facts
    pertaining to Johnson Controls. In determining that Myco failed to establish active
    interference or neglect on the City’s part, the trial court emphasized the timeline of
    when Myco alleged the delay occurred, when the design specifications for these
    units were resolved, and when the units were shipped. Myco alleged delay for the
    period of January 2014 to March 2014. However, all three units had shipped by July
    2013. In addition, in many instances Uday Patel reviewed the specifications in a
    shorter period of time than that required under the contract. (May 7, 2021 Trial Ct.
    Op. at 29.) Consequently, “the design specifications for all three units were resolved,
    and all three units had been shipped, well before the period of time in which Myco
    alleges a delay occurred.” (Id.)
    Moreover, the trial court noted Myco’s seeming acknowledgment that
    it was paid the entire amount to which it was entitled. In support, the trial court cited
    Myco’s answer to interrogatory No. 24 of the City’s second set of interrogatories:
    Interrogatory No. 24.
    Are you contending that you performed additional work in
    the project—beyond what you bid for the work—that you
    have not been paid for? If so, identify all such additional
    unpaid work.
    Answer:
    No.
    (May 7, 2021 Trial Ct. Op. at 4.)
    Accordingly, the six assertions from the PCM Report do not indicate
    that there are genuine issues of material fact that directly contradict the facts that the
    8
    trial court found dispositive regarding the City’s actions pertaining to the periods of
    delay.
    II.
    Myco next argues that the City’s actions constituted active interference
    or neglect sufficient to overcome any defense involving the “no damages for delay
    clause” and, therefore, should have precluded the trial court’s entry of summary
    judgment. To that end, Myco asserts that the delays in the project were caused by
    the City’s failure to have the proposed site available for work at the start of the
    project and at various times throughout thereby preventing Myco from performing
    and completing its work in a timely and orderly fashion. As noted, the four alleged
    sources of delay arguably attributable to the City are as follows: discovery of
    additional asbestos requiring remediation; discovery of lead-based paint requiring
    abatement; delivery delay of air handling and condenser units by Johnson Controls;
    and Verizon’s delay in performing IT work. In addition, Myco contends that the
    City waived any defense related to the “no damages for delay” clause by processing,
    approving, and paying some delay claims during the course of the project.
    In determining that Myco failed to sufficiently demonstrate either
    active interference or neglect on the City’s part, the trial court copiously considered
    the four alleged sources of delay. Turning first to asbestos, the trial court concluded
    that there was no evidence in the summary judgment record upon which a reasonable
    inference could be made that the City was hiding information from Myco or had not
    disclosed information regarding asbestos-containing materials. To the contrary, the
    trial court found that the City advised Myco that asbestos existed at the site and that
    more could be discovered once the renovation and demolition commenced. In
    addition, the trial court noted that an asbestos survey was included in the bid
    9
    specifications explaining that, even though a thorough inspection had been
    conducted, more asbestos-containing materials could be found in a structure of the
    general age and size of Old City Hall. (May 7, 2021 Trial Ct. Op. at 25.) As the
    trial court concluded: “While the . . . record certainly reflects that there were issues
    with additional asbestos being discovered throughout the [p]roject—and
    specifically, when demolition and construction commenced . . . we find that Myco
    has not demonstrated that the delay, which resulted from those issues, was due to or
    caused by any active interference or neglect on the part of the City.” (Id. at 26.)
    Turning to lead-based paint, the trial court similarly rejected Myco’s
    contention that the City failed to recognize the presence of lead or the necessity for
    remediation before commencing work. Noting Myco’s alleged period of delay
    attributable to lead (November 20, 2012 to January 7, 2013),4 the trial court found
    that the record revealed that lead was not discovered until February 26, 2013, well
    after Myco’s alleged period of delay. In addition, the record reflected that once the
    general contractor requested information regarding lead, the issue was promptly
    addressed. (Id. at 28.)
    As for Myco’s contention that the City knew about the lead-based paint
    when the contracts were bid, Myco cites the deposition testimony of David Rudolph,
    the City’s superintendent of the electrical bureau and building maintenance.
    Rudolph testified that lead abatement work was originally to be performed when the
    contracts were bid. (Apr. 27, 2016 Dep. of David Rudolph, Notes of Test. “N.T.” at
    28-29; R.R. at 881a-82a.) In addition, he stated that lead abatement work added only
    a week to the project schedule and that it was not a big issue. To that end, he testified
    that the same company simultaneously did lead and asbestos abatement at the time
    4
    (Myco’s Oct. 16, 2019 Am. Resps. & Objs. to the City’s Fourth Set of Interrogs., ¶ 4(3);
    R.R. at 595a.)
    10
    of remediation. (N.T. at 29-30; R.R. at 882a.) While it is true that he later provided
    a supplemental affidavit stating that he was mistaken in answering that he was aware
    of lead paint in the building before the bid process, he reiterated that lead abatement
    was not a big issue and did not interfere with Myco’s work. (Jan. 12, 2021 Rudolph
    Aff. at 1-2; Suppl. R.R. “S.R.R.” at 8b-9b.)
    As for the Johnson Controls delay issue, our determination in Section I
    of this opinion—that there were no undisputed material facts with regard to this
    particular delay—applies here. Accordingly, we agree with the trial court that this
    delay did not constitute active interference or neglect on the part of the City
    sufficient to overcome the applicability of the “no damages for delay” clause.
    Turning to the delay attributed to Verizon, Myco asserts that the City’s
    knowledge of a contract dispute with Verizon before the project started and failure
    to communicate that fact to the bidders constituted active interference sufficient to
    preclude the applicability of the “no damages for delay” clause. In rejecting Myco’s
    assertion, we refer to our determination in Section I concluding that Myco failed to
    establish that any issues with Verizon constituted genuine issues of material fact that
    directly contradicted the facts that the trial court found to be dispositive.
    Accordingly, we agree with the trial court that Myco failed to establish active
    interference on the City’s part with respect to any delays related to Verizon.
    As for the City’s alleged waiver of the defense pertaining to the “no
    damages for delay” clause, the City acknowledges that it paid out monies to certain
    contractors due to unforeseen difficulties. (City’s Br. at 17.) However, the City
    made the payments pursuant to a “concealed or unknown conditions” clause
    providing:
    § 3.7.4 Concealed or Unknown Conditions. If the
    Contractor encounters conditions at the site that are (1)
    11
    concealed physical conditions that differ materially from
    those indicated in the Contract Documents or (2) unknown
    physical conditions of an unusual nature, that differ
    materially from those ordinarily found to exist and
    generally recognized as inherent in construction activities
    of the character provided for in the Contract Documents,
    the Contractor shall promptly provide notice to the Owner
    and the Architect before conditions are disturbed and in no
    event later than 21 days after first observance of the
    conditions. The Architect will promptly investigate such
    conditions and, if the Architect determines that they differ
    materially and cause an increase or decrease in the
    Contractor’s cost of, or time required for, performance of
    any part of the Work, will recommend an equitable
    adjustment in the Contract Sum or Contract Time, or both.
    If the Architect determines that the conditions at the site
    are not materially different from those indicated in the
    Contract Documents and that no change in the terms of the
    Contract is justified, the Architect shall promptly notify
    the Owner and Contractor in writing, stating the reasons.
    If either party disputes the Architect’s determination or
    recommendation, that party may proceed as provided in
    Article 15.
    (Contract, ¶ 3.7.4; R.R. at 858a-59a.)
    The City’s payment pursuant to a “concealed or unknown conditions”
    clause does not preclude the applicability of the “no damages for delay” clause. In
    other words, the employment of one clause does not necessarily preclude the
    applicability or constitute waiver of another clause. Notably, the two contractual
    provisions pertain to different subjects and project delays may or may not be
    attributable to concealed or unknown conditions. In addition, the entire contract
    should be read as a whole, an interpretation must seek to give effect to all of its
    provisions, and one provision should not be interpreted in a manner which results in
    another portion being annulled. Commonwealth by Shapiro v. UPMC, 
    208 A.3d 898
    , 911 (Pa. 2019). As the trial court concluded, the issue before it was whether
    12
    the “no damages for delay clause” was a valid exculpatory provision and whether
    Myco established an exception to overcoming the clause’s enforceability. (May 7,
    2021 Trial Ct. Op. at 24; R.R. at 936a.)
    III.
    Finally, Myco maintains that the trial court erred in concluding that the
    City met its burden of proving that the exculpatory provision was valid and
    enforceable. As stated, these clauses are generally enforceable as long as the
    recognized exceptions do not apply. Upon review of the summary judgment record,
    we agree with the trial court that Myco failed to come forward with evidence
    sufficient to contradict the City’s summary judgment motion. Accordingly, we
    affirm.
    _____________________________________
    BONNIE BRIGANCE LEADBETTER,
    President Judge Emerita
    Judge Fizzano Cannon did not participate in the decision for this case.
    13
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Myco Mechanical, Inc.,                  :
    Appellant      :
    :   No. 590 C.D. 2021
    v.                           :
    :
    The City of York                        :
    ORDER
    AND NOW, this 12th day of October, 2022, the order of the Court of
    Common Pleas of York County is hereby AFFIRMED.
    _____________________________________
    BONNIE BRIGANCE LEADBETTER,
    President Judge Emerita
    

Document Info

Docket Number: 590 C.D. 2021

Judges: Leadbetter, President Judge Emerita

Filed Date: 10/12/2022

Precedential Status: Non-Precedential

Modified Date: 12/13/2024