Chesapeake Thermite Welding, LLC, d/b/a CTW v. DOT ( 2022 )


Menu:
  •          IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Chesapeake Thermite Welding, LLC,       :
    d/b/a CTW,                              :
    :
    Petitioner     :
    :
    v.                      : No. 548 C.D. 2021
    : Argued: June 23, 2022
    Department of Transportation,           :
    :
    Respondent     :
    BEFORE:     HONORABLE MICHAEL H. WOJCIK, Judge
    HONORABLE CHRISTINE FIZZANO CANNON, Judge
    HONORABLE MARY HANNAH LEAVITT, Senior Judge
    OPINION NOT REPORTED
    MEMORANDUM OPINION
    BY JUDGE WOJCIK                                     FILED: October 17, 2022
    Chesapeake Thermite Welding, LLC d/b/a CTW (CTW) petitions for
    review of the determination of the Acting Executive Deputy Secretary (Secretary)
    of the Department of Transportation (Department) that dismissed CTW’s bid protest
    regarding the Intermodal Terminal Rehabilitation project in Beaver, Pennsylvania
    (Project), because CTW lacked standing to file a protest against the Department and
    because the protest is barred by sovereign immunity. CTW presents three issues for
    our review. First, CTW argues that the Department’s Bureau of Rail Freights, Ports,
    and Waterways (Bureau) lacked compelling justification to reject CTW’s bid, and
    that the Secretary’s determination was arbitrary and capricious, an abuse of
    discretion, or an error of law. Second, CTW argues that the Rail Freight Preservation
    and Improvement Act (Act)1 which, in relevant part, authorizes the Department to
    provide grants to railroad companies to undertake capital projects to maintain,
    improve, and rehabilitate rail freight transportation services, does not except such
    grants from competitive bidding under the Procurement Code, 62 Pa. C.S. §§101-
    4604, where the grantee is an agent of the Department. Third, CTW argues that the
    contract between the Department and grantee is a contract for procurement of
    construction, subject to Section 102(f) of the Procurement Code, 62 Pa. C.S. §102(f).
    After careful review, we conclude that the contract for the Project is not a contract
    for procurement of construction under the plain language of Section 102(f) of the
    Procurement Code, because its primary purpose is not to procure construction for
    the Department, but rather to procure construction for the grantee, a private entity.
    Accordingly, we affirm the Secretary’s May 4, 2021 determination.
    The relevant facts as found by the Secretary are as follows. CTW filed
    a protest on March 11, 2021, regarding the Project. Secretary 5/4/21 Determination
    at 1. The protest concerned the invitation to bid under which a private company,
    Pittsburgh Intermodal Terminals, Inc. (PIT), through its Project manager, Railroad
    Solutions, Inc. (RSI), solicited bids on December 24, 2020. Id. After review, PIT
    ultimately awarded the contract to Keystone Railroad Services (KRS) and not to
    CTW. Id. at 7. The Project is to be funded by a grant made through the Rail Freight
    Assistance Program (RFAP), one of the grants authorized by the Act, to assist in the
    construction or rehabilitation of local railroad lines primarily used by businesses
    within the Commonwealth. Id. The RFAP provides 70% of the funding for the
    1
    Act of July 5, 1984, P.L. 587, No. 119, 55 P.S. §§696.1-696.11.
    2
    Project, and the owner, in this case PIT, provides the remaining 30% of the funding.
    Id.
    The Secretary determined that CTW’s protest was timely under the
    Procurement Code, which the Department does not dispute. Secretary 5/4/21
    Determination at 1-2.         The Secretary also determined that a hearing was not
    necessary to render a decision, which CTW does not dispute. Id. The Department
    filed a motion to dismiss on March 18, 2021, requesting the summary dismissal of
    CTW’s protest because CTW lacked standing to file its protest, and because the
    Department lacked jurisdiction over a private procurement under the Procurement
    Code. Id. at 3. The Department noted that CTW’s counsel previously represented
    a different entity, K.W. Reese, Inc. (KWR), in a protest “containing the same set of
    facts” present here, and that CTW’s protest should be dismissed for the same
    reasons.2 Id. The Secretary stated that here, as in the earlier KWR case, she must
    resolve “exactly what role the Department played, who the active parties are in this
    bid protest, which parties entered into the ensuing contract, and whether or not [the
    Department] is a contract holder as defined in the Procurement Code.” Id. The
    2
    The Secretary’s January 22, 2020 Determination in the KWR protest may be found in the
    Reproduced Record (R.R.) at 141a-48a. The Secretary summarized the KWR Determination as
    follows:
    [KWR] filed a bid protest on a project that was partially funded
    (70%) through the RFAP administered by the Bureau, grantor, in
    which a private company, Mineral Manufacturing Corp[oration],
    was the grantee. The resulting contract of the bidding process was
    between two private entities, Mineral Manufacturing Corp[oration]
    and Track Builders, Inc.; not the Department [] or the Bureau. Thus,
    under the Procurement Code, [KWR] lacked standing and the claim
    was barred by sovereign immunity.
    Secretary 5/4/21 Determination at 4, n.6. The parties did not represent, nor did our research reveal,
    that KWR appealed the Secretary’s decision in that matter.
    3
    Secretary determined that here, as in the earlier KWR Determination, the
    Department “is not the contract holder or the purchasing agent” as defined under the
    Procurement Code, and granted the Department’s motion to dismiss. Id. at 4.
    Nevertheless, the Secretary addressed CTW’s and the Department’s arguments as if
    she had reached the merits of the case. Id.
    The Secretary found that here, similar to the KWR case, the Department
    entered into a Rail Freight Grant Agreement (Grant Agreement) with PIT, 3 which
    “succinctly enumerates the role of the Department in this matter.” Secretary 5/4/21
    Determination at 4. The Secretary determined that the Grant Agreement is clear that
    the Department’s role in the Project is as a “grantor, with an oversight on how these
    monies are expended.” Id.; see also R.R. at 165a. The Secretary also determined
    that the Grant Agreement required PIT to secure competitive bids for expenditures
    exceeding $5,000, to develop bid specifications, advertise, open bids, and award the
    contract to the lowest responsive bidder. Secretary 5/4/21 Determination at 4; see
    also R.R. at 169a.
    CTW argued that because the Department required PIT to comply with
    competitive bidding laws, that PIT was acting as an agent for the Department, citing
    in support Pennsylvania Federation of Teachers v. School District of Philadelphia,
    
    484 A.2d 751
     (Pa. 1984), which struck down as unconstitutional part of the Public
    School Employees’ Retirement Code4 that increased the basic retirement
    contribution rate for Public School Employees’ Retirement System members prior
    to the effective date of the legislation. In so doing, the Supreme Court rejected the
    Commonwealth’s argument that public school districts are independent employers
    3
    The Grant Agreement may be found in the Reproduced Record at 165a-78a.
    4
    24 Pa. C.S. §§8101 - 8535.
    4
    and are not part of the Commonwealth. Pennsylvania Federation of Teachers, 484
    A.2d at 753. The Secretary determined that CTW’s argument that PIT was the
    Department’s agent was “not well taken because there is a significant distinction
    between a public school and a private company.” Secretary 5/4/21 Determination at
    5. The Secretary determined that it is well established that public school districts
    are agents of the Commonwealth, to which the legislature delegated the
    responsibility to provide public education, and that school districts are publicly
    owned and operated, which the Supreme Court explained in Pennsylvania
    Federation of Teachers. Id. In contrast, the Secretary determined that PIT is a
    “privately owned entity” and the grant funds are merely to assist in defraying the
    cost of construction, maintenance and repair performed on rail lines owned by a
    private entity within the Commonwealth. Id.; see also R.R. at 165a. The Secretary
    determined that “evidence of a state government providing grants with a private
    entity is not sufficient to establish control by a government agency, and such
    relationship as grantor/grantee does not automatically transform a private entity into
    an agent of the government.” Secretary 5/4/21 Determination at 5.
    The Secretary next addressed CTW’s argument that because the Project
    is funded by an RFAP grant with a primary purpose of construction, that the grant is
    not a grant but is rather a “procurement contract” under Section 102(f) of the
    Procurement Code. Secretary 5/4/21 Determination at 5-7. CTW argued generally
    that railway projects are public improvements that may not be altered without the
    approval of the Commonwealth or the Public Utility Commission, citing McNulty
    Brothers Company v. Pennsylvania Railroad Company, 
    116 A. 362
     (Pa. 1922),
    Bachrach v. Huntingdon & Broad Top Mountain Railroad & Coal Company, 
    133 A. 641
     (Pa. 1926), and the Pennsylvania Law Encyclopedia, 41 P.L.E. Railroads §4
    5
    (Matthew Bender & Company, Inc. 2022). CTW further argued that the Bureau
    Project Management Policy describes the grant as necessary to assist the Bureau in
    the development and construction of rail improvement projects, and deems the grant
    funded projects to be construction. R.R. at 131a-34a. CTW further argued that
    because the Project work is construction related, that Section 102(f) of the
    Procurement Code should apply.
    The Department responded that bid protest procedures set forth in
    Section 1711.1(a) of the Procurement Code, 62 Pa. C.S. §1711.1(a), apply only to
    contracts as defined in the Procurement Code, and not to grants. Section 102(f) of
    the Procurement Code, 62 Pa. C.S. §102(f), states:
    This part does not apply to grants. For purposes of this
    part, a grant is a furnishing of assistance by the
    Commonwealth or any person, whether financial or
    otherwise, to any person to support a program. This term
    does not include an award whose primary purpose is to
    procure construction for the grantor. Any contract
    resulting from such an award is not a grant but a
    procurement contract. (Emphasis added.)
    The Secretary reviewed Section 102(f) of the Procurement Code and
    determined “[t]hat exception does not apply here, however, because the primary
    purpose of the construction that comprises the Project is for the benefit of PIT and
    not the Department,” and that the exception argued by CTW is “simply not
    applicable.” Secretary 5/4/21 Determination at 6. The Secretary further explained
    that even if Section 102(f) of the Procurement Code applied for sake of argument,
    any contract resulting from the award would be between PIT and the successful
    contractor, and would therefore not satisfy the definition of “contract” under Section
    103 of the Procurement Code, 62 Pa. C.S. §103, which requires that all contracts
    6
    with the Commonwealth be reviewed and signed under the Commonwealth
    Attorneys Act.5 Secretary 5/4/21 Determination at 6.
    The Secretary further explained that the contract defined in Section 103
    of the Procurement Code, 62 Pa. C.S. §103, does not apply to the contract objected
    to by CTW, stating:
    PIT is a private corporation and neither the Department
    nor any other Commonwealth agency is or will be a party
    to the contract awarded by PIT to Kennedy Railroad
    Services (“KRS”)[, the successful bidder on the Project].
    The Department’s sole involvement in the Project is that
    of grantor. The Department is merely providing funding
    to a private corporation, PIT, to assist with rehabilitating
    its privately-owned infrastructure, which is unlike a school
    district or a state highway which is a publicly owned
    entity. When these definitions are applied to this
    procurement, which is the subject of [CTW’s] [p]rotest, it
    is clear that the protest procedures set forth in the
    Procurement Code do not apply since none of the critical
    elements of the definitions have been satisfied.
    Secretary 5/4/21 Determination at 7.
    The Secretary then addressed additional arguments regarding CTW’s
    standing to file a bid protest against the Department, as governed by Section 1711.1
    of the Procurement Code. Secretary 5/4/21 Determination at 7-9. The Department
    argued that PIT, not the Department, was the purchasing agency responsible for
    soliciting bids and awarding contracts under the Grant Agreement, and that PIT, not
    the Department, will be a party to the resulting contract with KRS. Id. at 7. Relevant
    here, Section 103 of the Procurement Code defines purchasing agency as “[a]
    Commonwealth agency authorized by this part or by other law to enter into contracts
    for itself or as the agent of another Commonwealth agency.” 62 Pa. C.S. §103. In
    5
    Act of October 15, 1980, P.L. 89, as amended, 71 P.S. §§732-101-732-506.
    7
    relevant part, Section 1711.1(a) of the Procurement Code permits a bidder aggrieved
    in connection with the solicitation or award of a contract to “protest to the head of
    the purchasing agency in writing.” 62 Pa. C.S. §1711.1(a). Section 1711.1(b) of the
    Procurement Code requires the disappointed bidder to file its protest “with the head
    of the purchasing agency.” 62 Pa. C.S. §1711.1(b).
    The Secretary reviewed these statutory provisions and determined that
    the Procurement Code does not authorize disappointed bidders to protest to anyone
    other than the head of the purchasing agency, nor does it authorize anyone other than
    the head of the purchasing agency to entertain bid protests. Secretary 5/4/21
    Determination at 8. The Secretary determined that the plain language of the
    Procurement Code “does not authorize the Secretary to entertain this protest since
    the ensuing contract is between two private entities[,] PIT and KRS, and not a
    Commonwealth agency.” Id. The Secretary determined that “there appears to be no
    conflict or ambiguity” in Sections 102 and 103 of the Procurement Code which both
    refer to “Commonwealth agencies under any contract.” Id. at 9.
    CTW argued that because the Bureau sets forth, oversees, and approves
    all aspects of the bidding process, it should be required to address bid protests even
    when the bidding process is managed by a third party, such as RSI. Secretary 5/4/21
    Determination at 9. The Secretary reviewed the exhibits attached to CTW’s bid
    protest and found those documents “contrary to establishing any plausible basis for
    concluding that the Bureau has any contractual rights or obligations relative to a
    contract holder or owner” under the Procurement Code. Id. at 9-10 (emphasis in
    original). The Secretary noted that CTW was in possession of the Project bid
    package when it submitted its bid. Id. at 10. See also R.R. at 21a-85a. In the Project
    bid package, PIT is referred to as the “Owner” responsible for inviting bids to
    8
    perform the Project. R.R. at 23a. The Project bid package further explains that the
    Project Manager (here, RSI) assists the Owner with administering the
    Commonwealth’s grant requirements. Id. at 26a. The Project bid package also states
    that “[t]he Owner alone will determine whether a given Bidder is sufficiently
    qualified and experienced to properly commence, perform and complete the
    [P]roject and work herein specified.” Id.
    CTW further argued that, pursuant to the Bureau Project Management
    Policy, PIT must provide “compelling justification” for rejecting CTW’s low bid,
    and that PIT failed to conduct an appropriate investigation to justify denying CTW’s
    bid. Secretary 5/4/21 Determination at 10-11; see also R.R. at 131a-34a. The
    Bureau Project Management Policy provides specifications for grant-funded rail
    projects that apply to rail grant project agreements (like the Grant Agreement here).
    The Secretary reviewed the Bureau Project Management Policy and determined that
    “it is clear that during the bidding process PIT, the Owner, was the decision maker
    and actual investigator, not [the Department] or the Bureau.” Secretary 5/4/21
    Determination at 11. After review of the Project bid package, including the Bureau
    Project Management Policy, the Secretary determined that
    CTW cannot utilize the bid protest procedures set forth in
    the Procurement Code because the Department was not the
    purchasing agency that issued the solicitation and the
    Department did not enter into a contract with KRS. These
    threshold requirements have not been met and therefore
    the protest procedures are not available to CTW to
    challenge the contract award made by a private company.
    Id.
    The Secretary then addressed the Department’s argument that CTW’s
    protest is barred by sovereign immunity. The Secretary explained that aggrieved
    bidders must use Section 1711.1 of the Procurement Code to challenge the
    9
    solicitation or award of a contract, or a contractor may pursue a contract claim under
    Section 1712.1 of the Procurement Code, 62 Pa. C.S. §1712.1, as the “sole avenues
    of relief against the Department.” Secretary 5/4/21 Determination at 11-12. The
    Secretary further explained that the Commonwealth enjoys sovereign immunity
    under article I, section 11 of the Pennsylvania Constitution.6 In Section 1702 of the
    Procurement Code, 62 Pa. C.S. §1702, the General Assembly reaffirmed the
    Commonwealth’s sovereign immunity except for claims against Commonwealth
    agencies brought under Section 1711.1 or 1712.1 of the Procurement Code, but only
    to the extent set forth in the Procurement Code. Secretary 5/4/21 Determination at
    11-12.
    The Department argued that our Supreme Court’s holding in Scientific
    Games International, Inc. v. Commonwealth, 
    66 A.3d 740
     (Pa. 2013), reaffirms the
    Commonwealth’s sovereign immunity from contract claims except as permitted by
    Section 1711.2 of the Procurement Code, vesting exclusive jurisdiction over contract
    claims with the Board of Claims, and rejecting this Court’s original jurisdiction to
    provide equitable relief outside the Procurement Code.                      CTW disputes the
    applicability of Scientific Games because that case addressed jurisdiction over
    contract disputes when a solicitation is cancelled, which is not at issue here. The
    Secretary agreed with CTW but determined that this distinction “in no way
    diminishes the force of the well-established doctrine of sovereign immunity” under
    the Procurement Code “which is designedly structured to accord immunity, subject
    to specific and limited exceptions.” Secretary 5/4/21 Determination at 12.
    6
    Pa. Const. art. I, §11. Article I, section 11 states in relevant part: “Suits may be brought
    against the Commonwealth in such manner, in such courts and in such cases as the Legislature
    may by law direct.”
    10
    The Secretary determined that, “in light of these facts” CTW’s protest
    must be dismissed “on the basis that the Department is not the contract owner, is not
    acting on behalf of another Commonwealth agency” and “is not a purchasing
    agency” as defined in the Procurement Code. Secretary 5/4/21 Determination at 13.
    Because CTW’s protest is not within the “category of administrative procurement
    protests” authorized by Section 1711.1 of the Procurement Code, the Secretary
    dismissed CTW’s protest against the Department for lack of standing, and because
    it is barred by sovereign immunity. Id. CTW then petitioned the Court for review.7
    As to the first issue, CTW argues that it had no other avenue to pursue
    its bid protest than under Section 1711.1 of the Procurement Code, and that the
    Secretary erred in dismissing its protest for lack of jurisdiction. CTW argues that in
    Brayman Construction Corporation v. Department of Transportation, 
    30 A.3d 560
    (Pa. Cmwlth. 2011) (Brayman II), our Court granted Brayman’s motion for summary
    judgment and a permanent injunction barring the Department from using a short-list
    process, instead of a lowest responsible bidder process, to award a design-build
    construction contract.         In Brayman II, the issue was whether a design-build
    construction contract was exempt from competitive bidding as a professional
    services contract, and our Court held that it was not, because the Procurement Code
    defines design-build construction contracts as a type of construction contract.
    7
    Our standard of review in a bid protest under the Procurement Code is as follows:
    The [C]ourt shall hear the appeal, without a jury, on the record of
    determination certified by the purchasing agency. The court shall
    affirm the determination of the purchasing agency unless it finds
    from the record that the determination is arbitrary and capricious, an
    abuse of discretion or is contrary to law.
    62 Pa. C.S. §1711.1(i).
    11
    Brayman II, 
    30 A.3d at 565
    . Brayman II did not involve a grant, nor was there a
    contract between private parties at issue.
    CTW argues that our Court’s holding in Brayman II should be extended
    to permit CTW to seek equitable relief from the Department, even if the contract at
    issue might not technically be within the purview of the Procurement Code. 8 CTW
    then argues that the Secretary, sitting in equity, could have found there was no
    “compelling justification” for PIT to reject CTW’s low bid, which it argues applies
    to PIT by way of the Bureau Project Management Policy. See R.R. at 131a-34a.
    CTW then proceeds to argue against the merits of PIT’s rejection of CTW’s bid,
    disagreeing with the reasons given in PIT’s denial letter. See 
    id.
     at 127a. CTW
    avers, without reference to the record below, that because PIT did not conduct any
    investigation before rejecting CTW’s bid “any negative information could only have
    come from [Project manager] RSI,” and RSI’s information “is wrong.” See CTW’s
    brief at 16-17.       CTW argues that because PIT failed to provide compelling
    justification to deny CTW’s low bid, the Secretary arbitrarily and capriciously
    disregarded PIT’s actions or erred as a matter of law when she dismissed CTW’s
    protest for lack of standing.
    8
    CTW also argues that if it lacks standing as a disappointed bidder under the Procurement
    Code, it could be granted taxpayer status even though it is a Virginia limited liability company.
    The Department denies that CTW qualifies for taxpayer standing, and CTW did not develop or
    offer support for this argument. Therefore, we find that CTW waived any taxpayer standing claim,
    because it failed to present argument in its brief to this Court. See Pa. R.A.P. 2119(a) (“The
    argument shall be divided into as many parts as there are questions to be argued; and shall have at
    the head of each part . . . the particular point treated therein, followed by such discussion and
    citation of authorities as are deemed pertinent.”); Commonwealth v. Spotz, 
    716 A.2d 580
    , 585 n.5
    (Pa. 1998), cert. denied, 
    526 U.S. 1070
     (1999) (holding that the failure to develop issue in appellate
    brief results in waiver); Browne v. Department of Transportation, 
    843 A.2d 429
    , 435 (Pa. Cmwlth.
    2004) (“At the appellate level, a party’s failure to include analysis and relevant authority results in
    waiver.”).
    12
    The Department responds that Brayman II is distinguishable from the
    facts presented here, and does not expand the Department’s jurisdiction over protests
    not covered by the Procurement Code. The Department rejects CTW’s attempts to
    introduce information not contained in the record below, relating to CTW’s
    disagreement with the reasons for PIT’s denial of CTW’s bid. The Department
    points to PIT’s denial letter, which acknowledges that CTW submitted the lowest
    bid for the Project, but notes that Section E of the Project bid package clearly states
    that “price alone is not the sole qualification for the contract to be awarded and that
    [PIT] alone will determine whether a [b]idder is sufficiently qualified and
    experienced.” R.R. at 127a; see also 
    id.
     at 26a. The Department responds that PIT,
    and not the Department, was responsible for reviewing CTW’s bid and assessing
    CTW’s record and experience with other projects in the Commonwealth. PIT
    concluded that it must reject CTW’s bid for several reasons including, without
    limitation, CTW’s limited access to credit for a project of this size and concerns
    about the construction schedule, as well as “significant concerns regarding the
    quality of work at prior projects and jobsite safety practices.” 
    Id.
     at 127a. The
    Department responds that although the Secretary correctly concluded that CTW’s
    bid protest did not fall under the Procurement Code, the Secretary correctly analyzed
    the merits of the denial, reached a well-reasoned conclusion, and was not arbitrary
    or capricious, and the decision was not contrary to law. The Department rejects
    CTW’s argument that PIT failed to provide “compelling justification” to reject
    CTW’s bid, when the Bureau Project Management Policy, by its stated terms,
    applies to the Department’s Grant Agreement with PIT, and not to PIT’s rejection
    of CTW’s bid. 
    Id.
     at 131a-34a.
    13
    As to the second issue, CTW argues that although the bid solicitation
    and resulting contract will be between two private parties, its bid protest should still
    proceed under the Procurement Code because PIT is an agent of the Department.
    CTW argues that Section 7(b) of the Act, 55 P.S. §696.7(b), which authorizes the
    Commonwealth to provide assistance to preserve, rehabilitate and improve rail
    freight services, requires “competitive bids” to be secured “before any purchase or
    sale, by contract, or otherwise is made or before any contract is awarded for
    construction . . . repairs or maintenance or for rendering any services to the
    [D]epartment.” CTW argues that the phrase “or otherwise” should be interpreted to
    apply to grants. CTW further argues that PIT should be considered an agent of the
    Department, based on the persuasive, if not controlling, holding in Pennsylvania
    Federation of Teachers, 
    484 A.2d 751
    . CTW argues that under the traditional
    agency law, because the bid protest provisions in the Procurement Code are
    applicable to the Department, they should also be applicable to PIT as the
    Department’s agent.
    The Department rejects CTW’s argument that PIT acted as the
    Department’s agent for the Project, and focuses on the plain language of the
    Procurement Code that provides protest procedures for bids or contracts for
    Commonwealth contracts, and not for contracts between private parties or for grants.
    The Department responds that Pennsylvania Federation of Teachers does not
    support a finding that PIT acted as the Department’s agent, because PIT is a private
    entity and not a public school. The Department further responds that Section 102 of
    the Procurement Code applies to “Commonwealth agencies under any contract,” and
    does not apply to a contract between a private entity, PIT, and the bid winner, another
    private entity, KRS. The Department further responds that Section 103 of the
    14
    Procurement Code further defines contract as an agreement “for the procurement of
    construction . . . executed by all parties in accordance with . . . the Commonwealth
    Attorney’s Act.” 62 Pa. C.S. §103. The Department argues that because the contract
    awarded will be between PIT and KRS, two private entities, to which the Department
    is not a party, this contract does not fall within the Procurement Code definition.
    The Department further responds that CTW concedes that per Section
    102(f) of the Procurement Code, 62 Pa. C.S. §102(f), bid protest procedures do not
    apply to grants. The Department argues that our Supreme Court’s holding in U.S.
    Venture, Inc. v. Commonwealth, 
    255 A.3d 321
     (Pa. 2021), further supports the
    interpretation that the Procurement Code does not apply to grants. In U.S. Venture,
    the Supreme Court analyzed whether two grant agreements awarded by the
    Department of Community and Economic Development (DCED) to U.S. Venture to
    construct or upgrade fuel stations by adding compressed natural gas pumps should
    be considered “procurement contracts” to “procure construction for the grantor
    [here, DCED,]” under Section 102(f) of the Procurement Code. Id. at 323. Because
    the construction contract did not procure construction for DCED, but procured
    construction for a private entity on property which it owned, the Supreme Court held
    that the resulting contract did not meet the Procurement Code definition of
    “contract.” Id. at 340. Although U.S. Venture sought review of a contract dispute
    by the Board of Claims under Section 1711.2 of the Procurement Code, and not a
    bid protest under Section 1711.1, the Department argues that the Supreme Court’s
    analysis of Section 102(f) of the Procurement Code should also apply here. The
    Department argues that U.S. Venture further applies because, herein, the record
    contains no evidence that the contract on which CTW bases its bid protest is
    primarily to benefit the Department; the language in the Grant Agreement defines
    15
    the Department as grantor; and the Bid package defines PIT as Owner. In its reply
    brief, CTW argues that U.S. Venture is completely distinguishable from this case
    because it involved different enabling legislation, different grants, and a contract
    dispute rather than a bid protest.
    As to the third issue CTW argues that because railroads are considered
    public improvements under McNulty Brothers Company, 
    116 A. 362
    , and Bachrach,
    
    133 A. 641
    , the contract resulting from the RFAP grant should be deemed a
    procurement contract “whose primary purpose is to procure construction for the
    grantor” under Section 102(f) of the Procurement Code. CTW also cites 41 P.L.E.
    Railroads §4 for the proposition that “[w]hen public lands or the lands of others are
    taken in any quantity for the construction and operation of a railroad, the railroad
    becomes a public highway for the public benefit, subject to the police power of the
    Legislature and the regulation of the Public Utility Commission.” CTW argues that
    Section 2 of the Act, 55 P.S. §696.2, which is the enabling legislation for the RFAP
    grant, clearly states that the purpose of the RFAP grant is to provide “State financial
    assistance for the preservation and improvement of essential rail freight
    transportation services, systems[,] and facilities,” which the legislature found to be
    essential for the provision of “efficient and coordinated rail freight transportation
    services” within the Commonwealth. 55 P.S. §696.2(b), 696.2(a)(3). CTW argues
    that because the RFAP grant benefits the Commonwealth, the resulting contract
    should be viewed as one which procures construction for the Commonwealth as
    grantor.
    The Department rejects CTW’s interpretation of Section 102(f) of the
    Procurement Code, and responds that the RFAP grant does not procure construction
    for the Department as grantor, but rather procures construction for PIT, a private
    16
    entity and owner of the railroad property. The Department further responds that the
    contract resulting from the RFAP grant is not a contract as defined in the
    Procurement Code because it is a contract between PIT and KRS, two private
    entities, to which the Commonwealth is not a party, and which does not require
    review under the Commonwealth Attorneys Act.
    The Department further argues that the Secretary correctly determined
    that the Commonwealth’s sovereign immunity barred CTW’s bid protest, as limited
    by the waiver for bid protests and contract claims under the plain language of the
    Procurement Code. The Department argues that Section 1702(a) of the Procurement
    Code “reaffirms” the Commonwealth’s sovereign immunity, except for the specific
    provisions in Section 1702(b) of the Procurement Code, which waives sovereign
    immunity to claims against Commonwealth agencies “brought in accordance with
    [S]ections 1711.1 (relating to protests of solicitations or awards) and 1712.1 (relating
    to contract controversies) . . . but only to the extent set forth in this chapter.” The
    Department argues that CTW may not seek relief from the Commonwealth except
    as outlined in Section 1711.1 of the Procurement Code, which CTW may not do
    because of the reasons already discussed.
    The Department argues that in Scientific Games, 
    66 A.3d 740
    , the
    Supreme Court held that the waiver of sovereign immunity is limited by the language
    of the Procurement Code. Specifically:
    The Procurement Code establishes administrative
    processes to address disputes arising in the procurement
    setting. On account of the doctrine of sovereign immunity,
    however, contractors, bidders, and offerors have limited
    recourse and remedies. Relative to controversies in
    matters arising from procurement contracts with
    Commonwealth agencies, the Board of Claims retains
    exclusive jurisdiction (subject to all jurisdictional
    17
    prerequisites), which is not to be supplanted by a court of
    law through an exercise of original jurisdiction.
    Scientific Games, 66 A.3d at 760. The Department argues that the Supreme Court
    considered Scientific Games in U.S. Venture, where the Supreme Court held that
    “Section 102(f) [of the Procurement Code] preserves sovereign immunity for
    disputes involving grants, and the provision in its entirety must be construed in favor
    of preserving sovereign immunity.” U.S. Venture, 255 A.3d at 337. The Department
    argues that the plain language of Section 102(f) of the Procurement Code, as
    interpreted by Scientific Games and U.S. Venture, prohibits CTW from seeking
    equitable relief against the Commonwealth outside the Procurement Code, because
    such actions are barred by sovereign immunity. In its reply brief, CTW argues that
    U.S. Venture is distinguishable from its bid protest, because the enabling legislation
    and resulting grant were not RFAP grants.
    We reject CTW’s first argument and affirm the Secretary’s May 4, 2021
    Determination because it was not arbitrary or capricious nor not contrary to law, as
    defined by the applicable standard of review in Section 1711.1(i) of the Procurement
    Code.    The additional standard proposed by CTW, that PIT must provide
    “compelling justification” to reject the low bidder, found in the Bureau Project
    Management Policy, is not applicable here. The Bureau Project Management Policy
    states that “[i]t is understood and agreed that, unless otherwise indicated in writing
    in an executed Rail Grant Project Agreement, the specifications hereinafter set forth
    apply to and become part of all Rail Grant Projects[.]” R.R. at 131a.
    Here, the Grant Agreement between the Department and PIT specifies
    the applicable standard that “[f]or contracted or subcontracted work, the [g]rantee[,
    here PIT,] shall determine the lowest responsive bidder,” and then the grantee shall
    forward “a copy of all bids as received . . . and the determination of the selected
    18
    bidder” to the Department. R.R. at 169a. The Project bid package specifies that the
    owner, here PIT, alone will determine whether a given bidder is sufficiently qualified
    and experienced to perform the Project. Id. at 26a. It further states that the owner
    may investigate as it deems necessary to determine the bidder’s ability to perform
    the work, including the bidder’s “record and experience” in performing work on
    other Department grants. Id. The Project bid package further states that the owner
    will award the contract “to the lowest responsive and responsible” bidder. Id. at 27a.
    In considering whether a bidder is responsible, the owner may consider the bidder’s
    equipment, manpower, performance on other Department projects, and construction
    schedule. Id. Any history of untimely project completion, unauthorized substitution
    of materials, other departures from bid specifications, or any pending or threatened
    litigation on other Department grant projects “may be deemed to demonstrate that
    the [b]idder does not satisfy the threshold as a responsible [b]idder.” Id. PIT
    followed its Grant Agreement and the terms of the Project bid package when it
    rejected CTW’s low bid and gave numerous reasons for the rejection, even though
    CTW does not agree with those reasons. Id. at 127a.
    We also reject CTW’s second argument that PIT is an agent for the
    Department, given the plain language of the Procurement Code, Grant Agreement,
    and Project bid package, all of which designate the Department as grantor, and PIT
    as grantee or owner, with the resulting contracts between PIT and KRS, both private
    entities. We decline to extend the holding of Brayman II as urged by CTW, because
    the underlying facts of Brayman II did not involve a grant-funded project, or a
    construction contract between two private parties, which are the facts before us here.
    Brayman II involved a construction contract between the Department and the
    contractor to replace a bridge along an interstate highway. Brayman II, 
    30 A.3d at
    19
    561. Because the project in Brayman II involved a contract between the Department
    and a contractor to make improvements on a public road, and did not involve a grant,
    or a contract between private parties to make improvements on private property, it
    is distinguishable from the Project here.
    Pennsylvania Federation of Teachers does not advance CTW’s
    argument that PIT’s grant-funded Project to improve freight railroad facilities on its
    own property makes it an agent for the Department or for the Commonwealth. We
    agree with the Secretary who determined that CTW’s argument that PIT was the
    Department’s agent was “not well taken because there is a significant distinction
    between a public school and a private company.” Secretary 5/4/21 Determination at
    5. We agree that public school districts are agents of the Commonwealth, to which
    the legislature delegated the responsibility to provide public education, and that
    school districts are publicly owned and operated, which the Supreme Court
    explained in Pennsylvania Federation of Teachers, 484 A.2d at 753. In contrast,
    PIT is a privately owned entity, and the grant funds are being provided by the
    Department to assist in defraying the cost of construction, maintenance and repair
    performed on rail lines owned by PIT. We agree with the Secretary’s determination
    that “evidence of a state government providing grants [to] a private entity is not
    sufficient to establish control by a government agency, and such relationship as
    grantor/grantee does not automatically transform a private entity into an agent of the
    government.” Secretary 5/4/21 Determination at 5.
    We also reject CTW’s third argument that its bid protest falls within the
    exception in Section 102(f) of the Procurement Code, as an award the primary
    purpose of which “is to procure construction for the grantor” based on the plain
    language of the Procurement Code, and the guidance provided by Scientific Games
    20
    and U.S. Venture. At issue is the interpretation of Section 102(f) of the Procurement
    Code, and specifically, whether the “primary purpose” of the RFAP grant awarded
    to PIT “is to procure construction for the grantor.” 62 Pa. C.S. §102. When
    presented with issues of statutory interpretation, this Court’s standard of review is
    de novo and our scope of review is plenary. Whitmoyer v. Workers’ Compensation
    Appeal Board (Mountain Country Meats), 
    186 A.3d 947
    , 954 (Pa. 2018).
    We are mindful, as always, that the object of statutory
    interpretation is to ascertain the intent of the General
    Assembly, the best indicator of which is the plain language
    of the statute itself. 1 Pa. C.S. §1921(a)(b); Department of
    Labor & Industry v. [Workers’ Compensation Appeal
    Board] (Lin & [Eastern] Taste), 
    187 A.3d 914
    , 922 (Pa.
    2018).      Where statutory language is clear and
    unambiguous, this Court must give effect to the words of
    the statute. Crown Castle NG [East] LLC v. Pennsylvania
    Public Utility Commission, 
    234 A.3d 665
    , 674 (Pa. 2020).
    When interpreting a statute, courts may not look beyond
    the plain meaning of a statute under the guise of pursing
    its spirit. Id.; see also Warrantech Consumer Products
    Services, Inc. v. Reliance Insurance Company in
    Liquidation, 
    96 A.3d 346
    , 354 (Pa. 2014).
    City of Johnstown v. Workers’ Compensation Appeal Board (Sevanick), 
    255 A.3d 214
    , 221 (Pa. 2021).
    Section 102(f) of the Procurement Code excepts grants from the bid
    protest process. CTW does not dispute the Project is a grant-funded project. Section
    102(f) provides that a grant may be a procurement contract, and thus, subject to the
    bid protest process, only if the primary purpose of the award is “to procure
    construction for the grantor.” The Act and the Grant Agreement clearly designate
    the Department as the grantor and PIT as the Project owner. As such, the primary
    purpose of the award is to procure construction for PIT, and not the Department.
    21
    We are unpersuaded by CTW’s argument that railway projects may not
    be altered without the approval of the Commonwealth or the Public Utility
    Commission because they are public improvements, or that the “primary purpose”
    of the RFAP grant here is to procure construction for the Department as grantor. In
    McNulty Brothers, cited by CTW, our Supreme Court considered whether a
    subcontractor on a railway project could enforce a mechanics lien against a railroad
    company for work it performed on a railroad office building connected to the freight
    station. McNulty Brothers, 116 A. at 363. The Court held that the subcontractor
    could not enforce the agreement because the “defendant railroad company is a public
    service corporation, and no property reasonably necessary to the enjoyment and
    operation of its franchise can be sold on such writ.” Id. In Bachrach, also cited by
    CTW, the Supreme Court addressed the rights of bondholders to payment on bonds
    issued and secured by a railroad company’s mortgage, which was given to certain
    trustees for the protection of the bondholders. Bachrach, 133 A. at 641. The Court
    held the bondholders “had no legal right to enforce an attachment against this money,
    which equitably belongs to the trustees, for the benefit of all the bondholders.” Id.
    at 642. Although both McNulty and Bachrach address limits to enforcing liens or
    bond payments against railroad property, neither case holds that railroads are public
    property whereby a construction project to improve railroad property equates to a
    construction project to improve Department property.
    We agree with CTW that railroads are subject to regulation by the
    Public Utility Commission, and are “public utility corporations” with the power of
    eminent domain. See e.g., Sections 1103 and 1511 of the Business Corporation Law
    of 1988, 15 Pa. C.S. §§1103 and 1511. However, these characteristics do not erase
    the distinction between PIT, a private rail company, and the Department, for
    22
    purposes of interpretating Section 102(f) of the Procurement Code. In Pierce v.
    Commonwealth, 
    104 Pa. 150
     (1883), the Supreme Court analyzed whether a railroad
    company was a private corporation, where its board of directors’ election was
    subject to the cumulative voting provision in former article 16, section 4 of the
    Pennsylvania Constitution that was then in effect. The Court held that the provision
    applied to the railroad’s election of directors because “[r]ailroad and canal
    companies are private corporations.” Pierce, 
    104 Pa. at 155
    . The Court favorably
    cited earlier case law to determine that “a railroad company is not public, nor does
    it stand in the place of the public; it is but a private corporation over whose rails the
    public may travel if [it] choose[s] to ride in its cars.” 
    Id.
     The Court further stated:
    Indeed, we regard it a misnomer to attach even the name
    “quasi[-]public corporation” to a railroad company, for it
    has none of the features of such corporations, if we except
    its qualified right of eminent domain, and this is because
    of the right reserved to the public to use its way for travel
    and transportation. Its officers are not public officers, and
    its business transactions are as private as those of a
    banking house. Its road may be called a quasi[-]public
    highway, but the company itself is a private corporation
    and nothing more.
    
    Id.
     Although the RFAP grant authorized by the legislature and issued by the
    Department is designed to provide a general economic benefit to citizens of the
    Commonwealth through improved rail freight operations, the Project primarily
    benefits PIT, the private owner of the rail freight station improved by the grant.
    Because the grant here does not have the primary purpose to procure construction
    for the Department, CTW’s bid protest is not permitted by Section 102(f) of the
    Procurement Code.
    This interpretation is supported by the fact that the resulting contract,
    which CTW protests, is between PIT and KRS, to which the Department is not a
    23
    party. Therefore, the contract does not meet the definition of “contract” in Section
    103 of the Procurement Code. A contract is defined in relevant part in Section 103
    of the Procurement Code, as a written agreement for the procurement of construction
    “executed by all parties in accordance with . . . the “Commonwealth Attorneys Act.”
    62 Pa. C.S. §103. Section 103 of the Commonwealth Attorneys Act states that “[n]o
    party to an action, other than a Commonwealth agency . . . shall have standing to
    question the authority of the legal representation of the agency.” 71 P.S. §732-103.
    A Commonwealth attorney did not review or approve the contract between PIT and
    KRS, the Department is not a party to the contract, and the Department did not
    execute the contract. Therefore, the contract to which CTW objects is not subject to
    the Procurement Code.
    This interpretation is further supported by the Supreme Court’s
    decision in Scientific Games, which held that a contract between two private entities
    arising out of a grant-funded project is not within the contract dispute provisions of
    the Procurement Code. Scientific Games, 66 A.3d at 759. The Court stated “[t]he
    Procurement Code establishes the administrative processes to address disputes
    arising in the procurement setting.     On account of the doctrine of sovereign
    immunity, however, contractors, bidders, and offerors have limited recourse and
    remedies.” Id. at 760. Although the Commonwealth agency and grant program in
    Scientific Games are different from the ones at issue here, the interpretation of the
    Procurement Code remedies is applicable and persuasive.
    Accordingly, we affirm the Secretary’s determination.
    MICHAEL H. WOJCIK, Judge
    24
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Chesapeake Thermite Welding, LLC,       :
    d/b/a CTW,                              :
    :
    Petitioner      :
    :
    v.                      : No. 548 C.D. 2021
    :
    Department of Transportation,           :
    :
    Respondent      :
    ORDER
    AND NOW, this 17th day of October, 2022, the Determination of the
    Acting Executive Deputy Secretary of the Department of Transportation dated May
    4, 2021, is AFFIRMED.
    __________________________________
    MICHAEL H. WOJCIK, Judge
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Chesapeake Thermite Welding, LLC, :
    d/b/a CTW,                        :
    Petitioner      :
    :
    v.                     :            No. 548 C.D. 2021
    :            Argued: June 23, 2022
    Department of Transportation,     :
    Respondent      :
    BEFORE:         HONORABLE MICHAEL H. WOJCIK, Judge
    HONORABLE CHRISTINE FIZZANO CANNON, Judge
    HONORABLE MARY HANNAH LEAVITT, Senior Judge
    OPINION NOT REPORTED
    CONCURRING OPINION
    BY SENIOR JUDGE LEAVITT                              FILED: October 17, 2022
    I join the majority’s decision. I write separately to note that this
    construction of the Commonwealth Procurement Code1 exposes the Department of
    Transportation to the type of equity action available to challenge the award of a
    contract as a misuse of state funds.
    Section 1711.1(a) of the Procurement Code provides a right of protest
    to “[a] bidder or offeror, a prospective bidder or offeror or a prospective contractor
    that is aggrieved in connection with the solicitation or award of a contract[.]” 62 Pa.
    C.S. §1711.1(a). Prior to the enactment of the Procurement Code, only a taxpayer
    had standing to challenge the award of a contract to a party that did not submit the
    lowest bid on grounds that it wasted taxpayer dollars. The litigant had to be a
    taxpayer because a disappointed bidder has no property interest in the award of a
    contract and, thus, is not aggrieved. See Michael Facchiano Contracting, Inc. v.
    Pennsylvania Turnpike Commission, 
    621 A.2d 1058
    , 1059-60 (Pa. Cmwlth. 1993);
    1
    62 Pa. C.S. §§101-2311.
    Lutz Appellate Printers, Inc. v. Department of Property and Supplies, 
    403 A.2d 530
    ,
    532 (Pa. 1979).       The Procurement Code changed this paradigm by giving
    disappointed bidders the opportunity to challenge the solicitation or the award of a
    public contract.
    “The enactment of the Procurement Code, however, has not taken
    away the right of taxpayers to bring an action in equity before this Court to enjoin
    the award of a contract when the bidding requirements were not followed.” Direnzo
    Coal Company v. Department of General Services, Bureau of Purchases, 
    779 A.2d 614
    , 617 n.4 (Pa. Cmwlth. 2001). “An aggrieved taxpayer, who lacks standing to
    file a protest under the Procurement Code, may still file an equity action in this
    Court’s original jurisdiction to protest the award of a contract.” 
    Id.,
     see also
    Pennhurst Medical Group, P.C. v. Department of Public Welfare, 
    796 A.2d 423
    , 426
    (Pa. Cmwlth. 2002).
    Here, Pittsburgh Intermodal Terminals, Inc. (PIT) received a grant from
    the Commonwealth to rehabilitate local railroad lines, as authorized under the Rail
    Freight Preservation and Improvement Act.2 Because public monies are involved in
    the grant, the Department of Transportation required PIT to hire the lowest
    responsive bidder to do the work. Reproduced Record at 169a. Chesapeake
    Thermite Welding, LLC d/b/a CTW, cannot pursue the disappointed bidder
    provisions of the Procurement Code. However, all it has to do is find a Pennsylvania
    taxpayer to serve as the plaintiff in an equity action in this Court’s original
    jurisdiction to challenge the Department of Transportation’s expenditure of public
    funds.3 Balsbaugh v. Department of General Services, 
    815 A.2d 36
    , 40 (employees
    2
    Act of July 5, 1984, P.L. 587, No. 119, 55 P.S. §§696.1-696.11.
    3
    In the instant case, however, Chesapeake Thermite Welding, LLC concedes that it is a Virginia
    Company and not a taxpayer of the Commonwealth. CTW Brief at 13 n.7.
    MHL-2
    of subcontractors used by the disappointed bidder had standing to bring complaint
    in equity because they were taxpayers in the Commonwealth).
    ____________________________________________
    MARY HANNAH LEAVITT, President Judge Emerita
    MHL-3