In Re: Appeal of Penneco Environmental Solutions, LLC from the decision of The ZHB of the Borough of Plum ~ Appeal of: Borough of Plum ( 2019 )


Menu:
  •           IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    In Re: Appeal of Penneco                     :
    Environmental Solutions, LLC                 :
    from the decision of The Zoning              :      No. 931 C.D. 2018
    Hearing Board of the Borough of Plum         :      Argued: February 11, 2019
    :
    Appeal of: Borough of Plum                   :
    BEFORE:        HONORABLE RENÉE COHN JUBELIRER, Judge
    HONORABLE ROBERT SIMPSON, Judge
    HONORABLE P. KEVIN BROBSON, Judge
    OPINION
    BY JUDGE SIMPSON                             FILED: March 8, 2019
    In this zoning appeal, the Borough of Plum (Borough) asks whether
    the Court of Common Pleas of Allegheny County1 (trial court) erred in reversing
    the decision of the Zoning Hearing Board of the Borough of Plum (ZHB), that
    denied Penneco Environmental Solutions, LLC’s (Penneco) substantive validity
    challenge to Borough Ordinance No. 731-004 (zoning ordinance).                  The ZHB
    denied Penneco’s substantive validity challenge on the ground that it was not ripe
    for review where Penneco had not yet obtained federal and state permits for the
    proposed conversion of its production oil and gas well into an underground
    injection well. Agreeing that the ZHB erred in concluding Penneco’s substantive
    validity challenge was not ripe for review, we affirm the trial court.
    1
    The Honorable Joseph M. James presided.
    I. Background
    The ZHB made the following findings. Sedat, Inc. (Sedat) owns the
    property located at 1800 Old Leechburg Road in the Borough (property). Penneco
    is an affiliate of Sedat. The property lies in a rural residential zoning district.
    Since approximately 1989, Penneco Oil Company (Penneco Oil)
    operated a gas production well on the property. Penneco Oil has a permit from the
    Pennsylvania Department of Environmental Protection (DEP) to operate the gas
    production well. Penneco, whose association to Penneco Oil is unknown, seeks to
    convert the well from a producing well to an underground injection well. An
    underground injection well serves to dispose of exploration and production fluids
    from oil and gas operations by placing the fluids into porous geologic formations.
    The disposal of waste products from oil and gas operations is subject to the
    oversight of the U.S. Environmental Protection Agency (EPA).
    In March 2016, Penneco submitted an application to the EPA
    requesting permission to operate an underground injection well on the property.
    About six months later, Penneco filed a substantive validity challenge to the zoning
    ordinance with the ZHB. Penneco challenged the zoning ordinance claiming it
    excluded the operation of an underground injection well in all zoning districts in
    the Borough. Penneco also asserted the zoning ordinance was preempted by state
    and federal law. The parties consented to postponement of a hearing before the
    ZHB on the validity challenge until after the EPA conducted a public hearing on
    Penneco’s application to the EPA to operate the injection well on the property.
    2
    In June 2017, the Borough publicly announced its plan to adopt or
    propose a new zoning ordinance. The EPA subsequently conducted a hearing at
    which it received public comment regarding Penneco’s proposed injection well.
    In August 2017, Penneco requested that its substantive validity
    challenge be placed on the ZHB’s agenda. A few weeks later, Penneco and the
    ZHB agreed to list the matter on the ZHB’s October 2017 agenda. A hearing
    ensued before the ZHB.
    In its subsequent decision, the ZHB explained:
    The current status of the EPA’s consideration of the
    permit is that subsequent to the hearing the EPA is
    considering and responding to the public comments from
    that meeting and comments that were submitted
    subsequent to that during the comment period. It is
    Penneco’s understanding that the EPA intends to respond
    to those comments by the end of 2017 and then will go
    on through the remaining permitting process in early
    2018.
    ZHB Dec., 11/17/17, Finding of Fact (F.F.) No. 18.
    Penneco represented that it would file an application with DEP for a
    permit to operate the injection well if the EPA gave its approval, as EPA approval
    must precede DEP approval. As a result, Penneco had not yet submitted an
    application to DEP. Penneco will not be permitted to operate an injection well on
    the property if the EPA and DEP do not grant the required permits and approvals.
    3
    Based on these findings, the ZHB made the following conclusions of
    law. Ripeness is defined as the presence of an actual controversy. In re Borough
    of Blakely, 
    25 A.3d 458
    (Pa. Cmwlth. 2011). The ripeness doctrine requires an
    evaluation of “the fitness of the issues” for determination, as well as the hardship
    to the parties of withholding judicial consideration. Am. Council of Life Ins. v.
    Foster, 
    580 A.2d 448
    , 451 (Pa. Cmwlth. 1990). The ZHB determined no actual
    controversy yet existed here, and one may never exist, because Penneco had not
    yet received the required approvals from the EPA and DEP.
    The ZHB stated that the issue of whether the zoning ordinance is
    invalid because, as alleged, it is exclusionary or preempted is of no consequence if
    the EPA and DEP do not grant the required approvals. The ZHB explained that, if
    it invalidated the zoning ordinance, Penneco would not be permitted to operate its
    proposed injection well because it lacked the requisite federal and state approvals.
    The ZHB further determined this matter would be moot if those approvals were not
    granted.       The ZHB also stated the zoning ordinance imposes no hardship on
    Penneco unless Penneco receives the required approvals. For these reasons, the
    ZHB denied Penneco’s substantive validity challenge. Penneco appealed to the
    trial court.
    Without taking additional evidence, the trial court reversed. The trial
    court stated that, contrary to the ZHB’s determinations, under Pennsylvania law,
    municipalities may not require outside agency permits before providing zoning
    approval.       Therefore, the trial court determined the ZHB erred in concluding
    Penneco’s substantive validity challenge was not ripe for review.
    4
    Further, the trial court determined Penneco met its burden of proving
    the zoning ordinance improperly excluded a recognized, legitimate business
    activity; thus, the trial court held the zoning ordinance was de jure exclusionary
    and invalid. As a result, the trial court determined Penneco was entitled to site-
    specific relief as to its proposed underground injection well on the property. The
    Borough now appeals to this Court.
    II. Issue
    The Borough raises only one issue on appeal.2 It asserts the ZHB
    properly denied Penneco’s substantive validity challenge for lack of ripeness.
    Whether the zoning ordinance is de jure exclusionary, and whether, if so, Penneco
    is entitled to site-specific relief, are not matters before us in this appeal.
    III. Discussion
    A. Contentions
    The Borough argues that “[r]ipeness has been defined as the presence
    of an actual controversy; it requires a court to evaluate the fitness of the issues for
    judicial determination, as well as the hardship to the parties of withholding court
    consideration.” 
    Blakely, 25 A.3d at 466
    . The Borough further asserts a court
    should look to “existing facts” when evaluating the ripeness of an issue. Borough
    of Centralia v. Commonwealth, 
    658 A.2d 840
    , 842 (Pa. Cmwlth. 1995). Here, it
    2
    Because the parties presented no additional evidence after the ZHB’s decision, our
    review is limited to determining whether the ZHB committed an abuse of discretion or an error
    of law. Penn Street, L.P. v. E. Lampeter Twp. Zoning Hearing Bd., 
    84 A.3d 1114
    (Pa. Cmwlth.
    2014).
    5
    contends no actual controversy exists as Penneco has yet to receive final, un-
    appealable approval from either the EPA or DEP.
    The Borough maintains that, when a ZHB member questioned
    Penneco’s counsel as to the effect that denial of approval by the EPA or DEP could
    have on Penneco’s proposed injection well, Penneco’s counsel stated:
    It’s possible that the [ZHB] could grant Penneco’s
    petition and Penneco from the [ZHB] has the authority to
    go forward with placing an underground injection well at
    its proposed location, but if the EPA or DEP rejects
    [Penneco’s] permit or places other conditions on it, then
    Penneco is certainly subject to that federal and state
    authority.
    Reproduced Record (R.R.) at 103a-04a.
    Without EPA or DEP approval, the Borough argues, Penneco will
    have no ability to develop the property for purposes of installing an injection well.
    R.R. at 104a. Thus, the Borough asserts, absent approval of both outside agencies,
    and the issuance of necessary permits, Penneco was deprived of no legal rights. 
    Id. The Borough
    further contends that, at the October 2017 ZHB hearing,
    Penneco’s counsel indicated that the EPA and DEP permits remained outstanding.
    R.R. at 123a. Specifically, Penneco’s counsel stated: “We are here today asking
    with our petition for the Borough, but the EPA permit, once that is approved, then
    we would go through the DEP permitting process.” 
    Id. As such,
    the Borough
    maintains, the ZHB’s actions have not affected the immediate use of the property,
    and any alleged loss is purely conjectural. Centralia.
    6
    The Borough argues Penneco’s lack of the necessary federal and state
    approvals renders any alleged injury or deprivation hypothetical, and, therefore,
    not ripe for consideration. Centralia. The Borough contends the current situation,
    where a lack of existing facts renders an issue unripe, is analogous to the situation
    presented in Centralia. The Borough asserts that, as of the date it filed its brief to
    this Court, there exist no facts or actions taken by the Borough or the ZHB that
    impacted Penneco’s use of the property, and any asserted loss by Penneco is
    hypothetical. 
    Id. For its
    part, the ZHB argues Penneco filed its challenge, claiming the
    zoning ordinance excluded the operation of an underground injection well in all
    zoning districts in the Borough, and that the zoning ordinance was preempted by
    state and federal law. In order to operate an underground injection well, the ZHB
    asserts, Penneco concedes it is required to obtain EPA and DEP approval. At the
    time Penneco challenged the zoning ordinance, it lacked approval from either
    agency.
    Without an actual controversy, the ZHB argues, a matter is not
    suitable for judicial determination. The ZHB asserts it denied Penneco’s challenge
    because there was no actual controversy, as Penneco had yet to obtain regulatory
    permission from the relevant federal and state agencies. Thus, the ZHB contends,
    the matter was not ripe for determination.
    The ZHB maintains that, before obtaining EPA or DEP approval,
    Penneco challenged the zoning ordinance claiming it excluded the operation of
    7
    underground injection wells in all zoning districts, and that the zoning ordinance
    was preempted by federal and state law. R.R. at 12a.
    The ZHB argues it decided no actual controversy existed, and one
    may never exist, because Penneco had yet to receive the required approvals from
    the EPA and DEP. F.F. No. 18. Under the ripeness doctrine, the ZHB asserts, this
    Court should refrain from making a determination as the answer would be based on
    Penneco’s assertions of speculative, hypothetical events that may or may not occur
    in the future. The ZHB contends a determination by the ZHB regarding the
    validity of the zoning ordinance would have been speculative and based on
    hypothetical events because Penneco had yet to receive the necessary federal and
    state approvals.
    Penneco counters that the trial court correctly reversed the ZHB
    because the ZHB erred in denying Penneco’s challenge to the validity of the
    exclusionary zoning ordinance. Penneco argues the Borough waived all bases for
    appeal except for that stated in its question presented and argued in its brief—that
    the ZHB correctly denied Penneco’s challenge to the zoning ordinance for want of
    “ripeness” where Penneco had not received permits for its proposed use from state
    or federal agencies. Appellee Penneco Environmental Solutions, LLC’s Br. at 10.
    Penneco asserts Pennsylvania law is clear that a municipality may not
    require outside agency permits or approvals before providing zoning approval.
    Penneco contends that, while it is undisputed that at the time of the ZHB hearing it
    had not yet received federal and state permits to operate an underground injection
    8
    well, that is not an appropriate basis upon which the ZHB could deny Penneco’s
    challenge to the validity of the exclusionary zoning ordinance. Nevertheless,
    Penneco maintains, the ZHB denied Penneco’s challenge on that basis, committing
    reversible error. Therefore, Penneco requests that this Court affirm the trial court’s
    reversal of the ZHB and the grant of site-specific relief.
    Penneco asserts its substantive validity challenge was ripe for review
    by the ZHB because the zoning ordinance’s failure to provide for the use of an
    underground injection well anywhere in the Borough directly and presently
    prevented Penneco’s proposed use of the property. See, e.g., Braksator v. Zoning
    Hearing Bd. of Northampton Twp., 
    641 A.2d 44
    , 45 (Pa. Cmwlth. 1994) (holding
    that a landowner is directly affected when “prevented from doing something that
    he wants to do[,]” and appeal was ripe where landowners were “presently faced
    with a choice” as to their development).
    Specifically, Penneco contends, Pennsylvania law is clear that
    municipalities may not require outside agency permits before providing zoning
    approval. Lehigh Asphalt Paving & Constr. Co. v. Bd. of Supervisors of E. Penn
    Twp., 
    830 A.2d 1063
    (Pa. Cmwlth. 2003).              Thus, courts repeatedly reject
    arguments that federal or state permits are prerequisites to challenging the validity
    of an ordinance or seeking zoning approval. See Hydropress Envtl. Servs., Inc. v.
    Twp. of U. Mount Bethel, Cty. of Northampton, 
    836 A.2d 912
    (Pa. 2003); Lehigh
    Asphalt; see also Seneca Res. Corp. v. Highland Twp., No. 15-60 ERIE, 
    2016 WL 1213604
    , at *4 (W.D. Pa. Mar. 29, 2016) (unreported) (stating that because a
    developer must obtain zoning approval to obtain a DEP permit, a municipality may
    9
    not require the developer to obtain a DEP permit before challenging the validity of
    an ordinance; otherwise, such reasoning would invoke “images of the proverbial
    cat chasing its tail”); Pa. Gen. Energy Co., LLC v. Grant Twp., C.A. No. 14-209
    ERIE, 
    2015 WL 6001550
    , at *9 (W.D. Pa. Oct. 14, 2015) (unreported) (rejecting
    township’s argument that “focuse[d] on the proposition that [the applicant] must
    obtain both … DEP and EPA permits as a ‘condition precedent’ for standing to
    pursue this legal action”; “lack of a DEP permit is irrelevant to the legal claims
    pled in this case”).
    For example, Penneco maintains, addressing the issue of standing to
    challenge the validity of an ordinance, the Pennsylvania Supreme Court noted that
    the ordinance at issue did “not require that a party receive a permit from [DEP]
    before receiving a permit from the [t]ownship,” but only required that a DEP
    permit be obtained “prior to the onset of site application.” 
    Hydropress, 836 A.2d at 916-17
    . Thus, the Court in Hydropress held, “the [t]ownship’s reliance on [DEP]
    approval as a prerequisite to standing is unfounded as [the applicant] is free to seek
    a permit from the [t]ownship without [DEP] approval as long as it obtains a [DEP]
    permit prior to” conducting any activities requiring such a permit. 
    Id. As in
    Hydropress, Penneco argues, the express terms of the zoning ordinance here do not
    require a party to obtain approvals from federal or state agencies as a pre-condition
    to receiving zoning approval or substantively challenging the zoning ordinance.
    Likewise, Penneco argues, in the context of a special exception
    application, this Court explained that the Pennsylvania Municipalities Planning
    10
    Code3 (MPC), “does not require the prior issuance of state permits before a ZHB
    decision” can be made. Lehigh 
    Asphalt, 830 A.2d at 1074
    . Rather, federal and
    state permits are not prerequisites to zoning approval because “[n]othing in the
    MPC or the particular ordinance … relieves the ZHB of its statutory duty to decide
    the application nor does the absence of a DEP permit hamper the ZHB’s ability to
    perform that duty.” Id.; accord Oasis v. Zoning Hearing Bd. of S. Annville Twp.,
    
    94 A.3d 457
    , 463 (Pa. Cmwlth. 2014).
    At most, Penneco asserts, while this Court consistently holds that
    local municipalities must approve zoning applications even where federal and state
    permits will be required, but have not yet been obtained, it acknowledges that in
    some cases a zoning permit may include a condition that the applicant obtain
    necessary federal and state permits before beginning development, rather than
    rejecting an application outright. See, e.g., In re Drumore Crossings, L.P., 
    984 A.2d 589
    (Pa. Cmwlth. 2009).
    Here, Penneco contends, contrary to the above authority, the ZHB did
    not consider any specific conditions related to ancillary permits, but instead
    rejected Penneco’s substantive validity challenge outright.              As such, Penneco
    maintains, the ZHB’s denial of Penneco’s substantive validity challenge on the
    basis that Penneco had not yet received EPA and DEP permits was an error of law.
    Penneco further argues the Borough cites no relevant authority to
    support its legal arguments. It asserts the Borough cites only two cases in its brief
    3
    Act of July 31, 1968, P.L. 805, as amended, 53 P.S. §§10101-11202.
    11
    to attempt to support its assertion that Penneco’s validity challenge was not ripe for
    review by the ZHB. Penneco contends these cases, Blakely and Centralia, are
    distinguishable and do not provide a basis for the Borough’s appeal.
    Moreover, Penneco maintains, the improper, exclusionary zoning
    ordinance presents an actual controversy ripe for judicial review, because it stands
    as an obstacle to Penneco’s ability to obtain a DEP permit. See 53 P.S. §10916.14;
    DEP Policy for Consideration of Local Comprehensive Plans and Zoning
    Ordinances in DEP Review of Authorizations for Facilities and Infrastructure
    (DEP Land Use Policy) at 55; see also Seneca. Therefore, Penneco asserts, this
    Court, like the trial court, should conclude the ZHB erred in denying Penneco’s
    substantive validity challenge based on a lack of ripeness.6
    B. Analysis
    Pursuant to Section 916.1(a)(1) of the MPC: “A landowner who, on
    substantive grounds, desires to challenge the validity of an ordinance … or any
    provision thereof which prohibits or restricts the use or development of land in
    which he has an interest shall submit the challenge … to the [ZHB] under [S]ection
    4
    Section 916.1 of the MPC was added by the Act of December 21, 1988, P.L. 1329.
    5
    See DEP Land Use Policy, Doc. No. 012-0200-001, available at
    http://www.depgreenport.state.pa.us/elibrary/GetDocument?docId=7448&DocName=POLICY%
    20FOR%20CONSIDERATION%20OF%20LOCAL%20COMP%20PLANS%20AND%20ZON
    ING%20ORD%20IN%20DEP%20REVIEW%20OF%20PERMITS%20FOR%20FAC%20AND
    %20INFRASTRUCTURE.PDF%20%20%3Cspan%20style%3D%22color%3Ablue%3B%22%3
    E%3C%2Fspan%3E# (last visited February 15, 2019).
    6
    In a footnote, Penneco explains, in March 2018, the EPA granted Penneco’s permit for
    the underground injection well, authorizing Penneco to operate its well in the Borough. See EPA
    Permit No. PAS2D701BALL.
    12
    909.1(a) [of the MPC,] [53 P.S. §10909.1(a)7] ….” See also Section 1204.2 of the
    zoning ordinance (“The [ZHB] shall hear challenges to the validity of th[e]
    [zoning] [o]rdinance … raising substantive questions.”). This is the procedure
    Penneco followed here.
    Rather than considering the merits of Penneco’s challenge, however,
    the ZHB denied it on the ground it was not ripe for review, as Penneco had not yet
    obtained (and could possibly never obtain) EPA and DEP approval for its proposed
    underground injection well. See ZHB Op., Concls. of Law Nos. 4-8. The ZHB
    erred in denying Penneco’s substantive validity challenge on this basis.
    The rationale behind the ripeness doctrine is “to prevent the courts,
    through avoidance of premature adjudications, from entangling themselves in
    abstract disagreements over administrative policies ….” 
    Braksator, 641 A.2d at 45
    (citation omitted). The criteria a court will consider are: (1) whether the issues are
    adequately developed for judicial review; and (2) what hardship the parties will
    suffer if review is delayed.         
    Id. (citing Foster).
       “This Court will only take
    jurisdiction over a particular matter where a[n] … ordinance has actually been
    applied to a litigant.” 
    Id. Here, Penneco’s
    substantive validity challenge is ripe for review.
    Through its petition, Penneco claimed that, as presently written, the zoning
    ordinance does not permit Penneco’s proposed underground injection well, the use
    it seeks to commence, in any zoning district throughout the Borough. R.R. at 63a-
    7
    Section 909.1(a) of the MPC was added by the Act of December 21, 1988, P.L. 1329.
    13
    83a. Thus, it asserted, the zoning ordinance, on its face, directly prohibits its
    proposed use. As such, the issue of whether the zoning ordinance was, in fact, de
    jure exclusionary was sufficiently developed for review by the ZHB. Braksator.
    In addition, Penneco will suffer hardship if consideration is delayed as
    it already expended resources surveying the site and creating a plat map in
    connection with its validity challenge.      R.R. at 36a.   Penneco also expended
    resources applying for an EPA permit and undergoing a public hearing before the
    EPA in connection with its proposed underground injection well. F.F. Nos. 9, 14.
    Moreover, it appears Penneco’s inability to obtain a merits review by the ZHB will
    delay its ability to obtain a DEP permit because, prior to commencing review of a
    permit application, DEP requires information as to a proposal’s compliance with
    applicable local ordinances. See DEP Land Use Policy at 5.
    Further, in Lehigh Asphalt, this Court held, where an applicant sought
    a special exception for its proposed quarry expansion, and the ordinance did not
    require presentation of a DEP permit prior to the ZHB’s consideration of the
    requested zoning relief, the ZHB erred in denying the application as incomplete on
    the ground the applicant did not provide a DEP permit. We stated: “Nothing in the
    MPC or the particular ordinance applicable here relieves the ZHB of its statutory
    duty to decide the application nor does the absence of a DEP permit hamper the
    ZHB’s ability to perform that duty.” 
    Id. at 1074.
    Here, as in Lehigh Asphalt, neither the MPC nor the zoning ordinance
    requires submission of an EPA or DEP permit with an applicant’s substantive
    14
    validity challenge as a prerequisite to review by the ZHB. Thus, the ZHB erred in
    denying Penneco’s challenge on that basis. Id.; accord Hydropress (party had
    standing to challenge ordinance and seek permit from township where it applied
    for permit from DEP and ordinance did not require party to receive DEP permit
    before receiving township approval).
    In addition, this Court repeatedly holds that, where permits from an
    agency outside a municipality are required for a land development proposal,
    approving the proposal with a condition that outside agency permits are received,
    as opposed to outright denial, is appropriate. See, e.g., Whitehall Manor, Inc. v.
    Planning Comm’n of City of Allentown, 
    79 A.3d 720
    (Pa. Cmwlth. 2013); In re
    McGlynn, 
    974 A.2d 525
    (Pa. Cmwlth. 2009); Kohr v. L. Windsor Twp. Bd. of
    Supervisors, 
    910 A.2d 152
    (Pa. Cmwlth. 2006); CACO Three, Inc. v. Bd. of
    Supervisors of Huntington Twp., 
    845 A.2d 991
    (Pa. Cmwlth. 2004); Morris v. S.
    Coventry Twp. Bd. of Supervisors, 
    836 A.2d 1015
    (Pa. Cmwlth. 2003). Indeed,
    our Supreme Court cautions that when assessing the propriety of conditional
    approval, the practicalities of the situation must be considered.    Broussard v.
    Zoning Bd. of Adjustment of City of Pittsburgh, 
    907 A.2d 494
    (Pa. 2006) (grant of
    special exception with conditions where applicant showed willingness and ability
    to satisfy conditions and where it was reasonable that approval precede formal
    execution of binding contract for off-site parking). Here, the ZHB did not consider
    any conditions on Penneco’s requested zoning relief relating to Penneco obtaining
    EPA or DEP permits; instead, it issued an outright denial of Penneco’s substantive
    validity challenge.
    15
    In addition, this case is distinguishable from Blakely and Centralia,
    the two takings cases cited by the Borough.              First, in Centralia, the
    Commonwealth, its Department of Community Affairs, and the Columbia County
    Redevelopment Authority (redevelopment authority) initiated a program to
    relocate the borough’s residents based on health and safety threats from a long-
    burning fire in the borough’s underground mines. A small number of residents
    declined to relocate. The redevelopment authority notified these residents that it
    would condemn their surface properties.        However, the borough owned the
    subsurface areas of the properties, which included mineral and coal reserves.
    The borough filed a petition for appointment of a board of viewers,
    alleging the planned surface acquisition of the borough’s remaining occupied
    properties and relocation of residents would result in a de facto taking of the
    subsurface mineral and coal reserves. Ultimately, this Court held the borough’s
    petition was not ripe for review where it did not aver existing facts that could
    establish a de facto taking. Rather, it merely alleged the redevelopment authority
    will effect a de facto taking once it completed the acquisition and relocation plan.
    The borough alleged the planned condemnation of all remaining surface properties
    would ultimately result in the “destruction and elimination of [b]orough
    government and effective elimination of the [b]orough as an entity.” 
    Id. at 842.
    Thus, the borough alleged its rights to the subsurface mineral and coal reserves
    would ultimately escheat to the Commonwealth. Given the hypothetical nature of
    these averments, we held the borough’s petition was not ripe for review as no
    actual controversy existed. To that end, the borough did not aver facts “which are
    certain to occur …. ” 
    Id. Thus, we
    reasoned:
    16
    The averments in [the borough’s] petition are
    hypothetical. No party has presently restricted [the
    borough’s] right to mine. There is no allegation that [the
    borough] cannot now mine the subsurface areas it owns
    because surface areas will be taken and residents will be
    relocated. Nor can it be established at this point that [the
    borough] will cease to exist or will be definitely
    prevented from mining in the future. In sum, there has
    been no de facto taking of [the borough’s] right to use
    and enjoy the subsurface. It could be said that, in a
    sense, there may eventually be a de facto taking of the
    borough itself, but not the rights to the subsurface. Apart
    from the plain circumstance that governmental activity
    has not affected the immediate use of the property, any
    threatened loss of the property is conjectural.
    
    Id. at 843
    (citation omitted).
    More recently, in Blakely, relying on Centralia, we upheld a common
    pleas court’s order that dismissed a landowner’s petition for appointment of a
    board of viewers. There, the landowner claimed he could not build homes on lots
    he owned because the borough installed a plastic drainage pipe in a ditch that cut
    off vehicular access to his property from an adjacent road. The landowner alleged
    this prohibited him from building homes along the road, and, in order to develop
    the lots, he would need to replace at least part of the plastic pipe with reinforced
    concrete pipe.
    Contrary to the landowner’s assertions, this Court explained, among
    other things: (1) the borough never informed the landowner he could not build
    homes on the lots; (2) the landowner did not consult the planning commission or
    submit actual plans to the borough; (3) the landowner did not explain why access
    was not possible from another road abutting the landowner’s property; and (4) the
    17
    landowner did not explain how he intended to resolve his need for variances for the
    lots. Thus, we held the landowner’s claims of injury and substantial deprivation of
    the use of his property were speculative; as a result, his de facto taking claim was
    premature.
    Unlike Blakely and Centralia, the case before us does not involve a
    claimed de facto taking. Additionally, unlike the speculative claims at issue in
    those cases, here Penneco filed its petition with the ZHB challenging the
    substantive validity of the zoning ordinance on the ground that it presently
    excludes Penneco’s proposed use in all zoning districts throughout the Borough.
    R.R. at 63a-83a. Thus, before the ZHB, Penneco asserted: “There’s no mechanism
    by which Penneco can apply to the Borough for this use.” R.R. at 136a. Further,
    Penneco planned for its proposed underground injection well by surveying the
    property and creating a plat map, which it submitted as an exhibit to its petition
    challenging the validity of the zoning ordinance. R.R. at 36a. Also, as stated
    above, Penneco expended resources applying for an EPA permit to operate its
    proposed underground injection well, and it underwent a hearing on the
    application. Further, as indicated above, Penneco’s petition is ripe for review
    because it impacts Penneco’s ability to obtain a DEP permit.
    IV. Conclusion
    Based on the foregoing, we affirm the trial court’s determination that
    the ZHB erred in concluding Penneco’s substantive validity challenge was not ripe
    for review. Because this is the sole issue raised by the Borough in its brief on
    appeal, we do not consider the propriety of the trial court’s determinations that
    18
    Penneco met its burden of proving the zoning ordinance is, in fact, impermissibly
    exclusionary, or that Penneco is entitled to site-specific relief.
    ROBERT SIMPSON, Judge
    19
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    In Re: Appeal of Penneco               :
    Environmental Solutions, LLC           :
    from the decision of The Zoning        :   No. 931 C.D. 2018
    Hearing Board of the Borough of Plum   :
    :
    Appeal of: Borough of Plum             :
    ORDER
    AND NOW, this 8th day of March, 2019, the order of the Court of
    Common Pleas of Allegheny County is AFFIRMED.
    ROBERT SIMPSON, Judge