D.N. Hommrich v. Com. of PA, PA PUC ( 2020 )


Menu:
  •              IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    David N. Hommrich,                  :
    :
    Petitioner :
    :
    v.                     : No. 674 M.D. 2016
    : Submitted: August 2, 2019
    Commonwealth of Pennsylvania,       :
    Pennsylvania Public Utilities       :
    Commission,                         :
    :
    Respondent :
    BEFORE:         HONORABLE MARY HANNAH LEAVITT, President Judge
    HONORABLE MICHAEL H. WOJCIK, Judge
    HONORABLE BONNIE BRIGANCE LEADBETTER, Senior Judge
    OPINION
    BY JUDGE WOJCIK                                                    FILED: May 12, 2020
    Before this Court for disposition, in our original jurisdiction, are the
    parties’ cross Applications for Summary Relief to Petitioner David N. Hommrich’s
    (Hommrich) “Amended Petition for Review in the Nature of a Complaint for
    Declaratory and Injunctive Relief” (Amended Petition) under the Declaratory
    Judgments Act (DJA).1             Specifically, Hommrich seeks a declaration that
    Respondent Pennsylvania Public Utility Commission’s (PUC)2 regulations on
    alternative energy projects are invalid and unenforceable. In turn, the PUC seeks
    1
    42 Pa. C.S. §§7531-7541.
    2
    We note that the proper designation for the PUC is the “Public Utility Commission,” not
    “Utilities” as designated by Hommrich in the pleadings and caption. See 66 Pa. C.S. §301.
    the dismissal of Hommrich’s Amended Petition because the regulations are valid
    and enforceable or, alternatively, an evidentiary hearing. For the reasons that
    follow, we grant in part and deny in part the parties’ cross Applications for
    Summary Relief.
    I. Background
    In January 2017, Hommrich filed his Amended Petition challenging
    the PUC’s regulations3 pertaining to net metering as unauthorized under the
    Alternative Energy Portfolio Standards Act (AEPS Act),4 and seeking a declaration
    of invalidity in addition to other relief. The PUC responded by filing preliminary
    objections, which this Court sustained in part and overruled in part, thereby leaving
    only the issue of whether the challenged regulatory provisions are invalid and
    unenforceable under the AEPS Act.               See Hommrich v. Pennsylvania Public
    Utilities Commission (Pa. Cmwlth., No. 674 M.D. 2016, filed July 28, 2017).5 The
    PUC then filed an Answer and New Matter to the Amended Petition, to which
    Hommrich responded.           Thereafter, the parties filed the cross Applications for
    Summary Relief now before us.
    3
    The regulations were adopted on December 15, 2006, and appear in Title 52 of Chapter
    75 of the Pennsylvania Code, 52 Pa. Code §§75.1-75.72. Those pertaining to net metering are
    set forth in subchapters A and B, 52 Pa. Code §§75.1-75.17, which were amended on November
    19, 2016.
    4
    Act of November 30, 2004, P.L. 1672, as amended, 73 P.S. §§1648.1-1648.8.
    5
    In Hommrich, the procedural history of this case as well as the facts alleged in the
    Amended Petition are set forth in detail.
    2
    II. Issues
    Hommrich asserts that the PUC does not have statutory authority to
    promulgate certain regulations establishing eligibility criteria for net metering.
    Even if it did, Hommrich contends that the regulations run afoul of the AEPS Act
    and this Court’s holding in Sunrise Energy, LLC v. FirstEnergy Corp.,
    
    148 A.3d 894
    , 901 (Pa. Cmwlth. 2016), appeal denied, 
    169 A.3d 1025
    (Pa. 2017).
    Specifically, Hommrich challenges the following regulations:
    52 Pa. Code §75.1 – Definitions of “customer-generator” and “utility”
    52 Pa. Code §75.12 – “Virtual meter aggregation”
    52 Pa. Code §75.13(a)(1)
    52 Pa. Code §75.13(a)(5)
    52 Pa. Code §75.16 – Large customer-generators
    52 Pa. Code §75.17
    Hommrich maintains that there are no issues of material fact that would serve to
    preclude this Court from determining that these regulations are invalid, even when
    viewing the evidence in a light most favorable to the PUC. For these reasons,
    Hommrich asks this Court to declare the challenged regulations as invalid and
    unenforceable.
    The PUC counters that Hommrich has failed to prove on the pleadings
    that the PUC lacked authority to promulgate the challenged regulations or that the
    challenged regulations are unreasonable. The PUC’s authority derives from the
    AEPS Act as well as the Public Utility Code (Code).6 The PUC argues that its
    6
    66 Pa. C.S. §§101-3316.
    3
    regulations reflect a reasonable interpretation of the AEPS Act and that it is
    entitled to great deference as the administrative agency with expertise on the
    subject. Accordingly, the PUC asks this Court to dismiss Hommrich’s Amended
    Petition or, in the alternative, hold an evidentiary hearing to establish material
    facts.
    III. Discussion
    A. Legal Standards
    1. Summary Relief
    Rule 1532(b) of the Pennsylvania Rules of Appellate Procedure
    provides that “the court may on application enter judgment if the right of the
    applicant thereto is clear.” Pa. R.A.P. 1532(b); see Scarnati v. Wolf, 
    173 A.3d 1110
    , 1118 (Pa. 2017) (“The standard for granting summary relief turns upon
    whether the applicant’s right to relief is clear. Summary relief on a petition for
    review is similar to the relief provided by a grant of summary judgment.
    Pa. R.A.P. 1532, Official Note.”) (footnote omitted).          “Summary judgment is
    appropriate where, after the close of pleadings, ‘there is no genuine issue of any
    material fact as to a necessary element of the cause of action or defense which
    could be established by additional discovery or expert report.’” 
    Scarnati, 173 A.3d at 1118
    (quoting Pa. R.C.P. No. 1035.2(a)).           Conversely, “[w]here there are
    material issues of fact in dispute or if it is not clear that the applicant is entitled to
    judgment as a matter of law, the application will be denied.” Sherman v. Kaiser,
    
    664 A.2d 221
    , 225 (Pa. Cmwlth. 1995). “A fact is considered material if its
    resolution could affect the outcome of the case under the governing law.” Hospital
    & Healthsystem Association of Pennsylvania v. Commonwealth, 
    77 A.3d 587
    , 602
    (Pa. 2013).
    4
    Hommrich maintains that there are no genuine issues of material fact
    in dispute and that this matter is ripe for summary relief.       However, in its
    alternative request for relief, the PUC suggests that an evidentiary hearing may be
    necessary to establish material facts. The dispute centers over whether the PUC
    has the authority to enact the challenged regulations and whether those regulations
    contradict the AEPS Act. Such issues may be resolved based on comparison of
    statutory and regulatory provisions as a matter of law.      See Marcellus Shale
    Coalition v. Department of Environmental Protection, 
    193 A.3d 447
    , 460 (Pa.
    Cmwlth.), appeal quashed, 
    198 A.3d 330
    (Pa. 2018). Thus, we conclude that the
    parties’ cross Applications for Summary Relief seeking a determination as to
    whether the regulations are unlawful and unenforceable are ripe for disposition
    without an evidentiary hearing.
    2. DJA
    Section 7533 of the DJA states:
    Any person interested under a deed, will, written
    contract, or other writings constituting a contract, or
    whose rights, status, or other legal relations are affected
    by a statute, municipal ordinance, contract, or franchise,
    may have determined any question of construction or
    validity arising under the instrument, statute, ordinance,
    contract, or franchise, and obtain a declaration of rights,
    status, or other legal relations thereunder.
    42 Pa. C.S. §7533 (emphasis added). The DJA was enacted “to curb the courts’
    tendency to limit the availability of judicial relief to only cases where an actual
    wrong has been done or is imminent.” Bayada Nurses, Inc. v. Department of
    Labor and Industry, 
    8 A.3d 866
    , 874 (Pa. 2010). The purpose of the DJA is “to
    5
    settle and to afford relief from uncertainty and insecurity with respect to rights,
    status, and other legal relations” and, accordingly, the DJA should “be liberally
    construed and administered.” 42 Pa. C.S. §7541(a); accord Office of Governor v.
    Donahue, 
    98 A.3d 1223
    , 1229 (Pa. 2014) (citation omitted); Funk v. Wolf, 
    144 A.3d 228
    , 251 (Pa. Cmwlth. 2016), aff’d, 
    158 A.3d 642
    (Pa. 2017).           As we
    previously determined in Hommrich, “[a] DJA action is the appropriate means to
    settle and afford relief from uncertainty and insecurity with respect to the
    regulations and [Hommrich’s] putative status as a customer generator.” Slip op. at
    16.
    B. AEPS Act and Regulations
    In 2004, the Pennsylvania legislature recognized the need for
    environmentally cleaner alternatives to fossil fuel energy production, and as a
    result, it passed the AEPS Act. The AEPS Act incentivizes alternative energy
    producers to generate their own energy utilizing one of the approved alternative
    energy production methods, such as wind and solar power, and sell any excess
    energy not used to the Electric Distribution Companies (EDCs). Section 2 of the
    AEPS Act, 73 P.S. §1648.2. Section 5 of the AEPS Act requires EDCs to purchase
    any net energy produced by these alternative energy providers at the full retail
    value. Section 5 of the AEPS Act, 73 P.S. §1648.5. Colloquially speaking, this
    provision allows the meter to run backwards. Of particular import here, Section 5
    of the AEPS Act further provides:
    The [PUC] shall develop technical and net metering
    interconnection rules for customer-generators intending
    to operate renewable onsite generators in parallel with
    the electric utility grid, consistent with rules defined in
    other states within the service region of the regional
    6
    transmission organization [(RTO)] that manages the
    transmission system in any part of this Commonwealth.
    The [PUC] shall convene a stakeholder process to
    develop Statewide technical and net metering rules for
    customer-generators. The [PUC] shall develop these
    rules within nine months of the effective date of this act.
    73 P.S. §1648.5 (emphasis added).         Pursuant to this legislative rule-making
    authority, the PUC adopted the regulations establishing technical and net metering
    interconnection rules for customer-generators that are subject to this litigation.
    1. Legislative Rule-Making
    The Supreme Court of Pennsylvania “has long recognized the
    distinction in administrative agency law between the authority of a rule adopted
    pursuant to an agency’s legislative rule-making power and the authority of a rule
    adopted pursuant to interpretive rule-making power.” Popowsky v. Pennsylvania
    Public Utility Commission, 
    910 A.2d 38
    , 53 (Pa. 2006) (citations omitted).
    “Legislative rule-making is an exercise of legislative power by an administrative
    agency, pursuant to a grant of legislative power by the legislative body, and is
    valid and is as binding upon a court as a statute if it is: (a) within the granted
    power, (b) issued pursuant to proper procedure, and (c) reasonable.” Id.; accord
    Tire Jockey Service, Inc. v. Department of Environmental Protection, 
    915 A.2d 1165
    , 1186 (Pa. 2007).        “Generally, a legislative regulation establishes ‘a
    substantive rule creating a controlling standard of conduct.’”             Borough of
    Pottstown v. Pennsylvania Municipal Retirement Board, 
    712 A.2d 741
    , 743 (Pa.
    1998) (quoting Slippery Rock Area School District v.                   Unemployment
    Compensation Board of Review, 
    983 A.2d 1231
    , 1236 (Pa. 2009)).
    7
    “An interpretative rule on the other hand depends for its validity not
    upon a Law-making grant of power, but rather upon the willingness of a reviewing
    court to say that it in fact tracks the meaning of the statute it interprets.”
    
    Popowsky, 910 A.2d at 53
    .           Legislative regulations are binding whereas
    interpretative regulations are merely entitled to deference. Slippery 
    Rock, 983 A.2d at 1236
    . All regulations, whether legislative or interpretative, “must be
    consistent with the statute under which they were promulgated.” 
    Popowsky, 910 A.2d at 53
    .
    Here, Section 5 of the AEPS Act constitutes a legislative grant of
    power.    Consequently, we engage in a legislative rule-making analysis to
    determine the validity of the challenged regulations. See Tire Jockey; Popowsky.
    Although the parties agree that the challenged regulations were adopted following
    the appropriate procedures, they disagree regarding the other prongs of the validity
    test. Therefore, our focus is on whether the challenged regulations fall within the
    PUC’s granted power and are reasonable. Tire Jockey; Popowsky.
    a. PUC’s Granted Power
    “To determine whether a regulation is adopted within an agency’s
    granted power, we look for statutory language authorizing the agency to
    promulgate the legislative rule and examine that language to determine whether the
    rule falls within the grant of authority.” Marcellus Shale Coalition v. Department
    of Environmental Protection, 
    216 A.3d 448
    , 459 (Pa. Cmwlth.), appeals quashed,
    
    223 A.3d 655
    (Pa. 2019) (citing Slippery 
    Rock, 983 A.2d at 1239-41
    ).            We
    consider “the purpose of the statute and its reasonable effect” and whether “the
    regulation is consistent with the enabling statute.”
    Id. “Clearly[,] the
    legislature
    8
    would not authorize agencies to adopt binding regulations inconsistent with the
    applicable enabling statutes.” Slippery 
    Rock, 983 A.2d at 1241
    . “When . . . a
    regulation presents ‘an actual conflict with the statute,’ we cannot reasonably
    understand the regulation to be within the agency’s ambit of authority, and the
    statute must prevail.” Marcellus 
    Shale, 216 A.3d at 459
    (quoting AMP Inc. v.
    Commonwealth, 
    814 A.2d 782
    , 786 (Pa. Cmwlth. 2002), aff’d, 
    852 A.2d 1161
    (Pa.
    2004)). Indeed, “a regulation that is at variance with a statute is ineffective to
    change the statute’s meaning.” Geisinger Health System v. Bureau of Workers’
    Compensation Fee Review Hearing Office (SWIF), 
    138 A.3d 133
    , 139 (Pa.
    Cmwlth. 2016). “That is so because ‘the power of an administrative agency to
    prescribe rules and regulations under a statute is not the power to make law, but
    only the power to adopt regulations to carry into effect the will of the Legislature
    as expressed by the statute.’”
    Id. (quoting Volunteer
    Firemen’s Relief Association
    of the City of Reading v. Minehart, 
    227 A.2d 632
    , 635-36 (Pa. 1967)). “When an
    agency adopts regulations at variance with the statute, the regulations, and not the
    statute, fall by the wayside.”
    Id. (citing Union
    Electric Corporation v. Board of
    Property Assessment, Appeals and Review of Allegheny County, 
    721 A.2d 823
    (Pa.
    Cmwlth. 1998), rev’d on other grounds, 
    746 A.2d 581
    (Pa. 2000)).
    Sometimes, the General Assembly confers broad power.                   For
    example, in Section 201(a) of the Unemployment Compensation Law,7 the General
    Assembly vested power in the Department of Labor and Industry (L&I) “to adopt,
    amend, and rescind such rules and regulations . . . as it deems necessary or
    suitable. Such rules and regulations shall not be inconsistent with the provisions of
    7
    Act of December 5, 1936, Second Ex. Sess., P.L. (1937) 2897, as amended, 43 P.S.
    §761(a).
    9
    this act.” In Slippery Rock, our Supreme Court described this power as “broad”
    and one that encompassed L&I’s authority “to define by regulation terms otherwise
    undefined by the statute.” Slippery Rock, 
    983 A.2d 1239
    . In Pennsylvania Human
    Relations Commission v. Uniontown Area School District, 
    313 A.2d 156
    , 168-71
    (Pa. 1973), the Supreme Court held that similar statutory language in Section 7(d)
    of the Pennsylvania Human Relations Act8 allowed the PHRC to promulgate a
    regulation that defined “de facto segregation” in such a way that it imposed strict
    desegregation standards and new accompanying duties on public schools. In other
    chapters relating to alternative energy, the General Assembly has yielded similar
    broad authority to other agencies.             See, e.g., Section 7 of Alternative Fuels
    Incentive Act9 (“The [Department of Environmental Protection (DEP)] shall
    promulgate regulations necessary to carry out the purposes of this act.”); Section
    607 of Alternative Energy Investment Act10 (“The [Pennsylvania Housing Finance
    Agency] shall promulgate guidelines necessary for the administration and
    enforcement of this act.”).
    In contrast, the powers the General Assembly conferred to the PUC
    under the AEPS Act are much narrower.                  Sunrise 
    Energy, 148 A.3d at 901
    .
    Section 5 of the AEPS Act authorizes the PUC to “develop technical and net
    metering interconnection rules for customer-generators intending to operate
    8
    Act of October 27, 1955, P.L., as amended, 43 P.S. §957(d) (authorizing the
    Pennsylvania Human Relations Commission (PHRC) “[t]o adopt, promulgate, amend and
    rescind rules and regulations to effectuate the policies and provisions of this act”).
    9
    Act of November 29, 2004, P.L. 1376, 73 P.S. §1647.7.
    10
    Act of July 9, 2008, P.L. 1873 (Spec. Sess. No. 1), 73 P.S. §1649.607.
    10
    renewable onsite generators in parallel with the electric utility grid . . . .” 73 P.S.
    §1648.5.       What is missing is the broad grant of authority to do whatever is
    necessary to effectuate the enabling statute.11 See
    id. In Sunrise
    Energy, this Court examined the PUC’s regulatory
    authority under the AEPS Act in addressing a jurisdictional issue. There, the
    PUC12 argued that it had primary jurisdiction over a contract dispute between a
    customer-generator and an EDC regarding their net metering arrangement under
    the AEPS Act. We examined the AEPS Act to determine whether it conferred any
    authority on the PUC to resolve such disputes and, ultimately, we determined it did
    not. Sunrise 
    Energy, 148 A.3d at 901
    . We opined that the PUC’s authority under
    the AEPS Act is “narrow” in scope and, essentially, is limited to establishing
    “technical and net metering interconnection rules.”
    Id. The Act
    “does not give the
    PUC power to act beyond this narrow authorization.”
    Id. (emphasis added)
    (citing
    Section 5 of the AEPS Act, 73 P.S. §1648.5).
    The PUC argues that reliance on Sunrise Energy is misplaced because
    this Court merely held that the PUC lacked exclusive adjudicatory authority over
    certain issues arising under the AEPS Act pursuant to the judicial doctrine of
    11
    We also note that the General Assembly did not delegate exclusive authority under the
    AEPS Act to the PUC, but rather authorized interagency responsibility with regard to
    environmental and health and safety standards. Specifically, Section 7(b) of the AEPS Act,
    discussed infra, confers upon the DEP the power to “ensure that all qualified alternative energy
    sources meet all applicable environmental standards and shall verify that an alternative energy
    source meets the standards set forth in section 2,” which is where the AEPS Act defines, inter
    alia, “alternative energy sources.” 73 P.S. §1648.7(b). Section 6 of the AEPS Act directs the
    PUC to cooperate with L&I to develop health and safety standards, as needed, regarding
    facilities generating energy from alternative energy sources. Section 6 of the AEPS Act,
    73 P.S. §1648.6.
    12
    In Sunrise Energy, the PUC filed an amicus curiae brief.
    11
    primary jurisdiction.   We did not address the PUC’s legislative rule-making
    authority, much less hold that the PUC lacked legislative rule-making authority to
    promulgate net metering regulations.          Although our specific focus was on
    jurisdiction, our broader focus was on the PUC’s authority under the AEPS Act,
    which is the issue at hand. Therefore, our determination that the PUC’s authority
    under the AEPS Act is limited to establishing “technical and net metering
    interconnection rules” is equally applicable.
    Nevertheless, the PUC maintains that its authority to promulgate the
    challenged net metering regulations is not solely under the AEPS Act. Rather, the
    PUC maintains that it has the authority to promulgate the regulations implementing
    the AEPS Act under its general legislative rule-making authority to regulate public
    utilities and the services they provide, including the service of interconnection and
    net metering of onsite generation. Specifically, the PUC posits that its authority to
    regulate public utilities derives from Sections 501, 508, 1501, 1504 and 2807(e) of
    the Code, 66 Pa. C.S. §§501, 508, 1501, 1504 and 2807(e).
    Section 501 of the Code sets forth the general powers delegated to the
    PUC. 66 Pa. C.S. §501. Pursuant thereto, the PUC is authorized to “enforce,
    execute and carry out, by its regulations, orders, or otherwise, all and singular, the
    provisions of [the Code] . . . .” 66 Pa. C.S. §501(a). Further, the PUC:
    shall have general administrative power and authority to
    supervise and regulate all public utilities doing business
    within this Commonwealth. The [PUC] may make such
    regulations, not inconsistent with law, as may be
    necessary or proper in the exercise of its powers or for
    the performance of its duties.
    66 Pa. C.S. §501(b). Section 508 of the Code authorizes the PUC to vary, reform
    and revise contracts entered into between any public utility and any person,
    12
    corporation or municipal corporation. 66 Pa. C.S. §508. Section 1501 gives the
    PUC the “sole and exclusive jurisdiction to promulgate rules and regulations for
    the allocation of natural or artificial gas supply by a public utility.” 66 Pa. C.S.
    §1501. Section 1504 of the Code allows the PUC to prescribe regulations and
    rules governing standards of service and facilities of public utilities. 66 Pa. C.S.
    §1504. Section 2807 of the Code authorizes the PUC to establish regulations
    governing EDCs. 66 Pa. Code §2807.
    Further, the PUC maintains that it has the authority to enact and
    enforce its regulations pursuant to Sections 501 (general powers), 502 (pertaining
    to enforcement proceedings by the PUC), 701 (pertaining to complaints regarding,
    inter alia, any violation of any law or “of any regulation or order of the [PUC]”)
    and 3301(a) (pertaining to civil penalties for, inter alia, any failure to “comply
    with any regulation or final direction, requirement, determination or order made by
    the [PUC] . . . ”). 66 Pa. C.S. §§501, 502, 701, and 3301(a).
    We recognize the PUC’s broad authority in regulating public utilities
    under the Code. As this Court recently opined, “the General Assembly intended
    the PUC to occupy the field of public utility regulation, in the absence of an
    express grant of authority to the contrary.” Delaware Riverkeeper Network v.
    Sunoco Pipeline L.P., 
    179 A.3d 670
    , 692 (Pa. Cmwlth.), appeal denied, 
    192 A.3d 1106
    (Pa. 2018). However, we are not dealing with “public utilities” here. See 66
    Pa. C.S. §102 (definition of “public utility”). Rather, the AEPS Act applies to
    “customer-generators,” which by definition are not public utilities. See Section 2
    of the AEPS Act, 73 P.S. §1648.2.        We, therefore, conclude that the PUC’s
    authority in this matter derives solely from the AEPS Act, and not the Code.
    13
    Under the AEPS Act, the PUC’s authority is limited to developing “technical and
    net metering interconnection rules.” Section 5 of the AEPS Act, 73 P.S. §1648.5.
    b. Reasonable
    In deciding whether a legislative regulation is reasonable:
    The court may not substitute its own judgment for that of
    the agency. To demonstrate that the agency has
    exceeded its administrative authority, it is not enough
    that the prescribed system of accounts shall appear to be
    unwise or burdensome or inferior to another. Error or
    lack of wisdom in exercising agency power is not
    equivalent to abuse. What has been ordered must appear
    to be so entirely at odds with fundamental principles as to
    be the expression of a whim rather than an exercise of
    judgment.
    Tire 
    Jockey, 915 A.2d at 1186
    (internal quotations and citations omitted); accord
    Slippery 
    Rock, 983 A.2d at 1242
    . “[A]ppellate courts must accord deference to the
    agency and may only overturn an agency determination if the agency acted in bad
    faith or the regulations constituted a manifest or flagrant abuse of discretion or a
    purely arbitrary execution of the agency’s duties or functions.” 
    Popowsky, 910 A.2d at 55
    ; accord Tire 
    Jockey, 915 A.2d at 1186
    . However, when there is
    express, contradictory language in the statute conferring regulatory authority, a
    proposed regulation would be deemed “unreasonable.”                 See Keith v.
    Commonwealth, 
    151 A.3d 687
    , 695 (Pa. Cmwlth. 2016). Nevertheless, “where
    legislative rules are adopted within the agency’s granted power and issued pursuant
    to proper procedure, they enjoy a presumption of reasonableness.” Marcellus
    
    Shale, 216 A.3d at 460
    . With these principles in mind, we examine each of the
    challenged regulations to determine whether the PUC acted within the scope of its
    14
    delegated authority under the AEPS Act and, if so, whether the regulations are
    reasonable.
    2. Challenged Regulations
    a. 52 Pa. Code §75.1 – Definitions of “Customer-Generator” & “Utility”
    Section 2 of the AEPS Act defines “customer-generator” as:
    A nonutility owner or operator of a net metered
    distributed generation system with a nameplate capacity
    of not greater than 50 kilowatts[13] if installed at a
    residential service or not larger than 3,000 kilowatts at
    other customer service locations, except for customers
    whose systems are above three megawatts[14] and up to
    five megawatts who make their systems available to
    operate in parallel with the electric utility during grid
    emergencies as defined by the [RTO] or where a
    microgrid is in place for the primary or secondary
    purpose of maintaining critical infrastructure, such as
    homeland security assignments, emergency services
    facilities, hospitals, traffic signals, wastewater treatment
    plants or telecommunications facilities, provided that
    technical rules for operating generators interconnected
    with facilities of an electric distribution company,
    electric cooperative or municipal electric system have
    been promulgated by the Institute of Electrical and
    Electronic Engineers [(IEEE)]] and the [PUC].
    73 P.S. §1648.2.
    Section 2 of the AEPS Act defines “net metering” as:
    The means of measuring the difference between the
    electricity supplied by an electric utility and the
    electricity generated by a customer-generator when any
    13
    A kilowatt or “kW” is “[a] unit of power representing 1,000 watts. A kW equals
    1/1000 of a MW.” 52 Pa. Code §75.1.
    14
    A megawatt or “MW” is “[a] unit of power representing 1,000,000 watts. An MW
    equals 1,000 kWs.” 52 Pa. Code §75.1.
    15
    portion of the electricity generated by the alternative
    energy generating system is used to offset part or all of
    the customer-generator’s requirements for electricity.
    Virtual meter aggregation on properties owned or leased
    and operated by a customer-generator and located within
    two miles of the boundaries of the customer-generator’s
    property and within a single electric distribution
    company’s service territory shall be eligible for net
    metering.
    73 P.S. §1648.2 (emphasis added). Thus, a nonutility owner or operator of a net-
    metered facility may utilize net metering so long as “any portion” of the electricity
    that the customer-generator generates is used to offset part of the customer-
    generator’s electrical requirement.
    Id. The General
    Assembly directed the PUC to
    establish “rules for customer-generators.” 73 P.S. §1648.5 (emphasis added).
    Under the regulations, the PUC provides its own definition of
    “customer-generator”:
    A retail electric customer that is a nonutility owner or
    operator of a net metered distributed generation system
    with a nameplate capacity of not greater than 50
    kilowatts if installed at a residential service or not larger
    than 3,000 kilowatts at other customer service locations,
    except for customers whose systems are above 3
    megawatts and up to 5 megawatts who make their
    systems available to operate in parallel with the electric
    utility during grid emergencies as defined by the [RTO]
    or where a microgrid is in place for the primary or
    secondary purpose of maintaining critical infrastructure,
    such as homeland security assignments, emergency
    services facilities, hospitals, traffic signals, wastewater
    treatment plants or telecommunications facilities,
    provided that technical rules for operating generators
    interconnected with facilities of an EDC, electric
    cooperative or municipal electric system have been
    promulgated by the [IEEE] and the [PUC].
    16
    52 Pa. Code §75.1 (emphasis added). When compared to the statutory definition,
    the definitions are virtually identical but for the PUC’s addition of “a retail electric
    customer that is” to qualify nonutility owner or operator.
    Moreover, the AEPS Act does not define “utility.” The PUC defines
    “utility” as:
    (i) A business, person or entity whose primary purpose,
    character or nature is the generation, transmission,
    distribution or sale of electricity at wholesale or retail.
    (ii) The term excludes building or facility owners or
    operators that manage the internal distribution system
    serving the building or facility and that supply electric
    power and other related power services to occupants of
    the building or facility.
    52 Pa. Code §75.1.
    In short, the PUC’s regulation alters the AEPS Act’s requirement that
    a customer-generator simply be a “nonutility owner or operator” of a net metering
    facility by adding the requirement that the customer-generator must be “a retail
    electric customer that is a nonutility owner or operator” of a net metering facility.
    52 Pa. Code §75.1. The PUC then defined the term “utility,” which is not defined
    in the AEPS Act, to include any business whose purpose is the “generation,
    transmission, distribution or sale of electricity at wholesale or retail.”
    Id. According to
    the PUC, to qualify as a “customer-generator,” the entity must have a
    need for electricity from the EDC independent from its need for electricity needed
    to power its generation facilities. See 52 Pa. Code §75.12. The PUC claims that
    had the General Assembly intended to permit generation facilities to qualify for net
    metering benefits regardless of their electric need at the generation site, it would
    17
    not have used the term “customer-generator” to identify the entities that qualify for
    net metering under the AEPS Act.
    By the same token, the General Assembly did not add such
    restrictions to its statutory definition of “customer-generator.” In fact, the General
    Assembly took steps to broaden, not restrict, the pool of alternative energy sources
    with the 2007 amendments. When the General Assembly amended the definition
    of customer-generator in 2007, it increased the kilowatt capacity from 1,000 to
    3,000 kilowatts and the amount of system megawatts from one to two megawatts
    to three to five megawatts. Compare 73 P.S. §1648.2 with former Section 2 of the
    AEPS Act, formerly 73 P.S. §1648.2 (2007). Prior to the 2007 amendments, the
    definition of “net metering” measured “the electricity generated by a customer-
    generator when the renewable electricity generated by the alternative energy
    generating system is intended primarily to offset part or all of the customer-
    generator’s requirements for electricity.”       Former 73 P.S. §1648.2 (2007)
    (emphasis added). Under the current definition, a nonutility owner or operator of a
    net-metered facility may utilize net metering so long as “any portion” of the
    electricity that the customer-generator generates is used to offset part of the
    customer-generator’s electrical requirement. 73 P.S. §1648.2 (emphasis added).
    Moreover, the PUC’s restrictions run contrary to the purpose of the
    AEPS Act. The purpose of the AEPS Act is to encourage the development of
    energy generated from renewable and environmentally beneficial sources. See
    Historical and Statutory Notes to AEPS Act. Even the PUC recognizes that the
    “unquestioned purpose of the AEPS Act is to promote alternative energy
    generation.” Respondent’s Brief at 9. However, the PUC’s definitions restrict the
    field of qualifying participants and, in the process, curtail the development of
    18
    alternative renewable energy in the Commonwealth.
    Id. To illustrate,
    under the
    AEPS Act, Hommrich qualifies as a customer-generator; under the regulations, he
    does not.
    The General Assembly authorized the PUC to establish “rules for
    customer-generators,” a term defined by statute.        73 P.S. §1648.5 (emphasis
    added). The General Assembly did not task the PUC with redefining or restricting
    eligibility standards as established in the AEPS Act. The challenged definitions do
    just that. The regulatory definitions modify the express statutory language by
    adding new criteria and requirements that limit the ability of certain customer-
    generators to net meter excess generation of energy. In so doing, the PUC is
    legislating who can and cannot utilize net metering by providing greater
    restrictions than the legislature prescribed and has acted beyond its legislative rule-
    making power.
    Although the PUC argues that its regulations reflect a reasonable
    interpretation of the AEPS Act and that it should be accorded great deference as
    the administrative agency with expertise on the subject, the PUC cannot alter the
    AEPS Act. By redefining these terms and adding requirements that the legislature
    did not see fit to include, the PUC has stepped beyond its appropriate legislative
    mandate and into the realm of making law.          Such changes amount to policy
    decisions that require legislative review. For these reasons, we conclude that the
    PUC’s regulatory definitions of          “customer-generator” and “utility” are
    unenforceable because they redefine statutory eligibility standards and curtail the
    development of alternative energy in conflict with the AEPS Act.
    19
    b. 52 Pa. Code §75.12 - “Virtual Meter Aggregation”
    Next, the PUC’s regulations define “Virtual meter aggregation” as:
    The combination of readings and billing for all meters
    regardless of rate class on properties owned or leased and
    operated by a customer-generator by means of the EDC’s
    billing process, rather than through physical rewiring of
    the customer-generator’s property for a physical, single
    point of contact. Virtual meter aggregation on properties
    owned or leased and operated by the same customer-
    generator and located within 2 miles of the boundaries of
    the customer-generator’s property and within a single
    EDC’s service territory shall be eligible for net metering.
    Service locations to be aggregated must be EDC service
    location accounts, held by the same individual or legal
    entity, receiving retail electric service from the same
    EDC and have measureable electric load independent of
    the alternative energy system. To be independent of the
    alternative energy system, the electric load must have a
    purpose other than to support the operation,
    maintenance or administration of the alternative energy
    system.
    52 Pa. Code §75.12 (emphasis added).
    As defined in the AEPS Act, the definition of “net metering” merely
    requires that “any portion of the electricity generated by the alternative energy
    generating system is used to offset part or all of the customer-generator’s
    requirements for electricity . . . .” 73 P.S. §1648.2 (emphasis added). As part of
    that definition, the AEPS Act provides: “Virtual meter aggregation on properties
    owned or leased and operated by a customer-generator and located within two
    miles of the boundaries of the customer-generator’s property and within a single
    electric distribution company’s service territory shall be eligible for net metering.”
    Id. 20 The
    PUC’s definition of “virtual meter aggregation” adds a new
    component that the customer-generator must have a “measurable electric load
    independent” of the customer-generator’s system. 52 Pa. Code §75.12. For there
    to be independent load, the electric load must “have a purpose other than to
    support” the customer-generator’s alternative energy system.
    Id. These requirements
    concerning independent load are found nowhere in the AEPS Act.
    Although we recognize the PUC’s concerns regarding unrestricted net metering,
    such eligibility restrictions are matters for the General Assembly, not the PUC, to
    legislate. Therefore, this regulation is unenforceable because it is beyond the
    PUC’s authority.
    c. 52 Pa. Code §75.13(a)(1)
    Next, the PUC’s regulations provide:
    (a) EDCs and [default service providers (DSPs)] shall
    offer net metering to customer-generators that generate
    electricity on the customer-generator’s side of the meter
    using Tier I or Tier II alternative energy sources, on a
    first come, first served basis. To qualify for net metering,
    the customer-generator shall meet the following
    conditions:
    (1) Have electric load, independent of the alternative
    energy system, behind the meter and point of
    interconnection of the alternative energy system. To be
    independent of the alternative energy system, the electric
    load must have a purpose other than to support the
    operation, maintenance or administration of the
    alternative energy system.
    52 Pa. Code §75.13(a)(1) (emphasis added). Pursuant to the regulation, customer-
    generators must have an “independent load” in order to net meter. As discussed
    21
    above, there is no corollary for this eligibility requirement in the AEPS Act. For
    the same reasons, this regulation is likewise unenforceable.
    d. 52 Pa. Code §§75.13(a)(5) and 75.17
    Under the regulations, any application for a proposed net metering
    facility with a nameplate capacity exceeding 500 kilowatts must be approved by
    the PUC.    52 Pa. Code §75.13(a)(5).      Specifically, Section 75.13(a)(5) of the
    regulations provides:
    An alternative energy system with a nameplate capacity
    of 500 kW or more must have [PUC] approval to net
    meter in accordance with §75.17 . . . .
    52 Pa. Code §75.13(a)(5).
    In turn, Section 75.17(a) of the regulations establishes the application
    process for obtaining the PUC’s approval of customer-generator status.
    Specifically, Section 75.17 provides:
    (a) This section establishes the process through which
    EDCs obtain [PUC] approval to net meter alternative
    energy systems with a nameplate capacity of 500 kW or
    greater.
    (b) An EDC shall submit a completed net metering
    application to the [PUC’s] Bureau of Technical Utility
    Services [(Bureau)] with a recommendation on whether
    the alternative energy system complies with the
    applicable provisions of this chapter and the EDC’s net
    metering tariff provisions within 20 days of receiving a
    completed application.      The EDC shall serve its
    recommendation on the applicant.
    (c) The net metering applicant has 20 days to submit a
    response to the EDC’s recommendation to reject an
    application to the [Bureau].
    22
    (d) The [Bureau] will review the net metering
    application, the EDC recommendation and applicant
    response, and make a determination as to whether the
    alternative energy system complies with this chapter and
    the EDC’s net metering tariff.
    (e) The [Bureau] will approve or disapprove the net
    metering application within 10 days of an EDC’s
    submission recommending approval. If disapproved, the
    [Bureau] will describe in detail the reasons for
    disapproval. The [Bureau] will serve its determination
    on the EDC and the applicant.
    (f) The [Bureau] will approve or disapprove the net
    metering application within 5 days of an applicant’s
    response to an EDC’s recommendation to deny approval,
    but no more than 30 days after an EDC submits an
    application with a recommendation to deny approval,
    whichever is earlier. The [Bureau] will serve its
    determination on the EDC and the applicant.
    (g) The applicant and the EDC may appeal the
    determination of the [Bureau] in accordance with §5.44
    (relating to petitions for reconsideration from actions of
    the staff).
    52 Pa. Code §75.17.
    Hommrich argues that this regulatory application process runs afoul
    of the AEPS Act because it gives the PUC the ultimate authority to approve net
    metering on facilities with a 500 kW capacity or greater. Although the General
    Assembly did not authorize the PUC to redefine statutory terms and alter eligibility
    standards, it did task the PUC with the development of “technical and net metering
    interconnection rules.” 73 P.S. §1648.5. The General Assembly authorized the
    PUC to carry out its responsibilities under the AEPS Act, which encompasses not
    only the development of but also ensuring the compliance with those rules. See
    Section 7(a) of the AEPS Act, 73 P.S. §1648.7(a). The application process set
    23
    forth in Sections 75.13(a)(5) and 75.17 of the regulations is a systematic and
    reasonable way for the PUC to ensure compliance with the AEPS Act and
    applicable regulations.
    Relying on Section 7(b) of the AEPS Act, 73 P.S. §1648.7(b),
    Hommrich argues that the PUC has no power to ensure compliance because the
    General Assembly conferred this authority exclusively to the DEP. However, this
    Section merely provides that “[t]he [DEP] shall ensure that all qualified alternative
    energy sources meet all applicable environmental standards and shall verify that an
    alternative energy source meets the standards set forth in [S]ection 2.” 73 P.S.
    §1648.7(b) (emphasis added). First, the AEPS Act and the PUC’s regulations are
    not environmental standards. Second, to be considered an “alternative energy
    source,” the source must meet one of the delineated sources for the production of
    electricity, including solar photovoltaic, wind power, hydropower, etc., each of
    which are defined under Section 2 of the AEPS Act, 73 P.S. §1648.2. Section 2 of
    the AEPS Act expressly names the DEP in the municipal solid waste definition as
    the entity with the authority to determine compliance with the environmental
    standards of the federal Clean Air Act, 42 U.S.C. §§ 7401-7671q, and the Solid
    Waste Management Act.15 The DEP’s responsibilities under the AEPS Act are
    limited and specific. Neither “customer-generator” status nor “net metering” is a
    standard that any “alternative energy source” must meet to be considered an
    “alternative energy source” under the AEPS Act. See
    id. Although the
    DEP is
    vested with the authority to ensure compliance with environmental standards and
    alternative energy source standards, this authority does not divest the PUC of its
    authority pertaining to “technical and net metering interconnection rules.” We,
    15
    Act of July 7, 1980, P.L. 380, as amended, 35 P.S. §§6018.101 - 6018.1003.
    24
    therefore, conclude that Sections 75.13(a)(5) and 75.17 of the regulations fall
    within the PUC’s granted power, do not run afoul of the AEPS Act, and were
    promulgated based upon a reasonable interpretation of it.
    e. 52 Pa. Code §75.16 - Large customer-generators
    Finally, Section 2 of the AEPS Act addresses the requirements of a
    net-metered facility’s operation during a grid emergency in the definition of
    “customer-generator.” 73 P.S. §1648.2. Specifically, non-residential customer-
    generators operating systems above three megawatts and up to five megawatts,
    must make their system “available to operate in parallel with the electric utility
    during grid emergencies as defined by the [RTO]” or when a “microgrid is in place
    for the primary or secondary purpose of maintaining critical infrastructure . . . .”
    Id. The PUC
    classifies systems operating with a capacity between three to
    five megawatts as “large customer-generators.” 52 Pa. Code §75.16. The PUC
    established rules for operation for large customer-generators.        52 Pa. Code
    §75.16(a). Specifically, the PUC’s regulations provide:
    (b) A retail electric customer may qualify its alternative
    energy system for customer-generator status if it makes
    its system available to operate in parallel with the grid
    during grid emergencies by satisfying the following
    requirements:
    (1) The alternative energy system is able to
    provide the emergency support consistent with the RTO
    tariff or agreement.
    (2) The alternative energy system is able to
    increase and decrease generation delivered to the
    distribution system in parallel with the EDC’s operation
    of the distribution system during the grid emergency.
    25
    (c) A retail electric customer may qualify its alternative
    energy system located within a microgrid for customer-
    generator status if it satisfies the following requirements:
    (1) The alternative energy system complies with
    IEEE Standard 1547.4.
    (2) The customer documents that the alternative
    energy system exists for the primary or secondary
    purpose of maintaining critical infrastructure.
    52 Pa. Code §75.16(b), (c).
    Under subsection (b), “large customer-generators” must provide
    support that is consistent with the RTO tariff and the system must be able to
    increase or decrease generation in parallel with an EDC’s operation of the
    distribution system during a grid emergency. 52 Pa. Code §75.16(b)(1), (2). The
    RTO’s tariff or agreement defines what a grid emergency is in that RTO. The
    ability to increase or decrease generation is the technical ability to operate in
    parallel with the electric utility during grid emergencies as required by the AEPS
    Act.
    Hommrich argues that the AEPS Act contains no requirement that a
    customer-generator’s system be designated as an emergency-type support resource
    by an RTO. Rather, the AEPS Act only requires that the customer-generator’s
    system be “available.” Contrary to Hommrich’s argument, it is not enough for the
    system to be “available.” The AEPS Act makes it clear that the system must be
    physically capable of operating “in parallel” during a grid emergency.
    73 P.S. §1648.2. The PUC’s regulatory provisions provide technical guidance for
    what is required to “operate in parallel” during a “grid emergency.”
    Under subsection (c), the PUC requires an alternative energy system
    to comply with IEEE Standard 1547.4, which is the standard for microgrids, and
    26
    that the customer must document that the alternative energy system exists for the
    primary or secondary purpose of maintaining critical infrastructure.           This
    subsection provides technical criteria that closely aligns with the requirements set
    forth in the AEPS Act. See 73 P.S. §1648.2. Upon review, the large customer-
    generator provisions set forth in Section 75.16 of the regulations are within the
    PUC’s legislative rule-making authority, consistent with the language in the AEPS
    Act, and reasonable.
    IV. Conclusion
    In sum, the General Assembly authorized the PUC to promulgate
    “technical and net metering interconnection rules.” Section 5 of the AEPS Act,
    73 P.S. §1648.5. By redefining and restricting eligibility standards established by
    the AEPS Act, the PUC has acted beyond its grant of legislative rule-making
    authority. Therefore, the definitions of “customer-generator” and “utility” as set
    forth in Section 75.1, and “virtual meter aggregation” as set forth in Section 75.12
    and Section 75.13(a)(1) of the PUC’s regulations, overreach and contradict the
    AEPS Act and are therefore beyond the scope of authority and unreasonable.
    However, Sections 75.13(a)(5), 75.16, and 75.17 of the regulations fall within the
    grant of legislative rule-making authority and are reasonable. Accordingly, we
    grant in part and deny in part the parties’ cross Applications for Summary Relief
    consistent with the foregoing opinion.
    MICHAEL H. WOJCIK, Judge
    27
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    David N. Hommrich,                  :
    :
    Petitioner :
    :
    v.                     : No. 674 M.D. 2016
    :
    Commonwealth of Pennsylvania,       :
    Pennsylvania Public Utilities       :
    Commission,                         :
    :
    Respondent :
    ORDER
    AND NOW, this 12th day of May, 2020, consistent with the foregoing
    opinion, the parties’ cross Applications for Summary Relief are GRANTED IN
    PART and DENIED IN PART, and we hereby DECLARE the following
    regulations invalid and unenforceable: 52 Pa. Code §§75.12 and 75.13(a)(1), and
    the definitions of “customer-generator” and “utility” contained in 52 Pa. Code
    §§75.1.
    __________________________________
    MICHAEL H. WOJCIK, Judge