McLogie Properties Inc. v. Kidder Twp. ZHB ( 2023 )


Menu:
  •           IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    McLogie Properties Inc.,                  :
    Appellant                :
    :
    v.                           :
    :
    Kidder Township Zoning                    :   No. 1136 C.D. 2021
    Hearing Board                             :   Submitted: June 7, 2023
    BEFORE:      HONORABLE RENÉE COHN JUBELIRER, President Judge
    HONORABLE PATRICIA A. McCULLOUGH, Judge
    HONORABLE ANNE E. COVEY, Judge
    HONORABLE CHRISTINE FIZZANO CANNON, Judge
    HONORABLE ELLEN CEISLER, Judge
    HONORABLE LORI A. DUMAS, Judge
    HONORABLE STACY WALLACE, Judge
    OPINION
    BY JUDGE FIZZANO CANNON                       FILED: June 30, 2023
    McLogie Properties Inc. (McLogie) appeals from an order of the Court
    of Common Pleas of Carbon County (trial court) docketed on September 16, 2021.
    The trial court affirmed a May 2021 decision of the Kidder Township (Township)
    Zoning Hearing Board (ZHB) denying McLogie’s request for variance relief. Upon
    review, we reverse the trial court’s order.
    I. Background
    In June 2019, McLogie purchased an unimproved lot located in the
    Township. Reproduced Record (RR) at 256a & 317a-20a. On August 9, 2019,
    McLogie filed a zoning permit application with the Township to build a three-story
    single-family residence on the property. RR at 44a; Township Br., App.
    At that time, Robert Dobosh (Dobosh) was the Township’s zoning and
    building/code enforcement officer. As such, Dobosh worked with McLogie during
    preliminary inspections of the property. See RR at 30a-31a, 227a & 271a. Dobosh
    then retired, and two different individuals filled his two positions: Cindy Norato
    (Norato) became the Township’s zoning officer, and the Township outsourced the
    position of building/code enforcement officer to Dave Williams (Williams) of
    Building Inspection Underwriters. See id. at 31a, 226a-27a, 236a & 249a.
    Norato approved McLogie’s zoning application in September 2019 and
    issued McLogie a zoning permit for a house and deck on the property. RR at 46a &
    226a. Once the zoning permit was in place as required, Willams issued McLogie a
    building permit in October 2019, which allowed McLogie to begin construction of
    the house and deck in accordance with the plan. Id. at 226a.
    After construction was underway, McLogie discovered that the
    foundation’s front elevation was approximately 11 feet lower than what had been
    portrayed in its original plans. RR at 261a & 272a. McLogie halted construction in
    November 2019 and sought guidance from Williams, who told McLogie to submit
    an updated plan to the Township showing McLogie’s proposal for moving forward.
    Id. at 247a & 260a-63a. McLogie revised the plan to add a basement with a ceiling
    height of eight and one-half feet. RR at 261a-62a & 273a-75a. Williams approved
    the revised plan. RR at 247a-50a; Supplemental Reproduced Record (SRR) at 727b-
    28b. Williams neither informed Norato of the revised plan nor instructed McLogie
    to do so. Williams did not revoke the building permit that was in place.
    2
    McLogie completed construction according to the revised plan. RR at
    263a-64a. Township personnel inspected the home multiple times while it was being
    built and then issued a certificate of occupancy to McLogie in July 2020. Id. at 66a
    & 263a-64a. However, Norato did not learn of the revised plan until Williams
    mentioned it in a telephone call in September 2020. Id. at 227a. In October 2020,
    Norato sent an enforcement notice to McLogie, asserting that McLogie had
    constructed the basement without obtaining a required zoning permit. Id. at 300a.
    Norato relied on Section 180-19 of the Township’s Zoning Ordinance,1 which limits
    the maximum height of all buildings on lots zoned R2 residential, like the McLogie
    property, to no more than 35 feet and 3 stories. Id. at 300a.              With the added
    basement, the building exceeded both the height limit and the maximum number of
    stories. Id.
    McLogie appealed the enforcement notice to the ZHB and also sought
    a variance for the home as already constructed. RR at 303a-06a & 314a-15a. The
    ZHB held a public hearing in April 2021, at which both Norato and Williams
    testified.
    Norato explained that she had issued a zoning permit to McLogie in
    September 2019 based on the original plan, had been unaware of the revised plan
    until September 2020, and had promptly issued a citation once she learned of
    McLogie’s noncompliance with the Zoning Ordinance. RR at 222a, 225a-32a, 234a-
    35a & 238a-39a. Norato admitted that no one had informed McLogie in 2019 that
    Dobosh’s responsibilities had been divided between Norato and Williams, and she
    acknowledged that this lack of communication may have caused some confusion.
    Id. at 235a-37a.
    1
    Kidder Township Zoning Ordinance, Carbon County, Pa., as amended (2017).
    3
    Williams testified that as the Township’s building/code enforcement
    officer, he had no authority to compel compliance with the Zoning Ordinance.2 RR
    at 246a-48a. He stated that he had reviewed the revised plan only for compliance
    with the Pennsylvania Construction Code Act.3 Id.
    One of McLogie’s principals, Kevin Kolodgie (Kolodgie), testified that
    the company’s representatives had been unaware that they needed separate zoning
    approval from Norato, as they had dealt solely with Williams after Dobosh’s
    retirement and had believed that only Williams’s approval was needed for
    construction to move forward. RR at 260a-66a. Kolodgie also estimated that
    bringing the home into compliance with the Zoning Ordinance’s height restrictions
    would cost more than $50,000. Id. at 266a. Thomas O’Connell, a contractor
    employed by McLogie for the project, likewise testified that he and other McLogie
    representatives had discussed the need for a revised plan with Williams in 2019 and
    had gone to Williams for guidance and for approval of the revised plan. Id. at 272a-
    74a.
    In April 2021, the ZHB denied both McLogie’s appeal of the zoning
    enforcement notice and its request for a dimensional variance. RR at 298a, 393a. In
    its subsequent written decision in May 2021, the ZHB found McLogie’s evidence
    concerning Williams’s approval of the revised plan to be neither credible nor
    probative. The ZHB also determined that the Township had provided adequate
    reasons for issuing the enforcement notice. The ZHB held that McLogie had failed
    to satisfy the standard for obtaining a dimensional variance, was not entitled to a
    2
    However, as discussed in Section II, the building/code enforcement officer has related
    responsibilities, such as informing the applicant of all needed permits (including zoning permits)
    and revoking or refusing to issue a building permit until a needed zoning permit has been obtained.
    3
    Act of November 10, 1999, P.L. 491, as amended, 35 P.S. §§ 7210.101-7210.1103.
    4
    variance by estoppel or a vested right variance, and had waived its right to obtain
    relief via equitable estoppel. ZHB Decision, Findings of Fact (F.F.) ¶¶ 36-44;
    Conclusions of Law (C.L.) ¶¶ 6-17.
    McLogie appealed the ZHB’s decision to the trial court, asserting that
    McLogie was entitled to a variance by estoppel or, in the alternative, that the
    Township was equitably estopped from enforcing the Zoning Ordinance’s height and
    story restrictions in this instance. RR at 21a-24a & 404a-17a. The trial court took
    no additional evidence. In an order docketed on September 16, 2021, the trial court
    denied McLogie’s appeal. Trial Ct. Order, 9/16/21 at 1-2. The trial court determined
    that McLogie had properly preserved its equitable estoppel claim but that substantial
    evidence supported both the ZHB’s denial of relief under that theory and its refusal
    to grant McLogie a variance by estoppel. Id. McLogie then appealed to this Court.
    II. Discussion
    On appeal to this Court, McLogie repeats its assertions that the ZHB
    abused its discretion by denying a variance by estoppel and, similarly, by failing to
    conclude that with regard to the property at issue, the Township was equitably
    estopped from enforcing the Zoning Ordinance’s restrictions on residential building
    heights and number of stories. McLogie’s Br. at 19-30. The material facts are
    undisputed; thus, these assertions present issues of law.4 We agree with McLogie
    that it is entitled to a variance by estoppel and, in the alternative, that the ZHB should
    4
    Where a trial court reviewing a zoning decision takes no additional evidence, our review
    is limited to a determination of whether the ZHB committed an abuse of discretion or an error of
    law. Valley View Civic Ass’n v. Zoning Bd. of Adjustment, 
    462 A.2d 637
    , 639-40 (Pa. 1983).
    However, where the issues presented on appeal are questions of law, our standard of review is de
    novo and the scope of review is plenary. City of Clairton v. Zoning Hearing Bd. of Clairton, 
    246 A.3d 890
    , 896 n.8 (Pa. Cmwlth. 2021) (citing Braun v. Wal-Mart Stores, Inc., 
    106 A.3d 656
    , 663
    n.8 (Pa. 2014)).
    5
    be equitably estopped from enforcing the height and story restrictions of the Zoning
    Ordinance under the circumstances of this case.5
    The ZHB insists that neither a variance by estoppel nor equitable
    estoppel is available to McLogie. The ZHB suggests that McLogie, rather than the
    building/code enforcement officer, was required to inform the zoning officer of the
    changes to the construction plan, and that McLogie knew or should have known it
    had to get zoning approval separate and apart from the building/code enforcement
    officer’s approval. ZHB Br. at 2. We reject these assertions by the ZHB.6
    5
    Although McLogie has not couched its argument in terms of a vested right, we note that
    the circumstances here satisfy the requirements for relief on that ground, as well: (1) due diligence
    in attempting to comply with the zoning ordinance; (2) good faith throughout the proceedings; (3)
    expenditure of substantial unrecoverable funds; (4) expiration, without appeal, of the period during
    which an appeal could have been taken from approval of the permit; and (5) failure to prove that
    individual property rights or the public health, safety or welfare would be adversely affected by
    the use of the permit. Petrosky v. Zoning Hearing Bd. of Upper Chichester Twp., 
    402 A.2d 1385
    (Pa. 1979).
    6
    We note that McLogie’s legal argument contains few citations of authority, which raises
    a potential waiver under Rule 2119(a) of the Pennsylvania Rules of Appellate Procedure,
    Pa.R.A.P. 2119(a). As this Court has explained, however:
    Rule 2119(a) . . . does not mandate citations to authority for every
    argument. The rule requires parties to support their arguments with
    “such discussion and citation of authorities as are deemed
    pertinent.” [Pa.R.A.P. 2119(a).] This Court declines to find waiver
    of arguments that contain no legal citations but are otherwise
    sufficiently developed to allow meaningful appellate review. See,
    e.g., Herzog v. Unemployment Comp. Bd. of Rev[.] (Pa. Cmwlth.,
    No. 437 C.D. 2010, . . . filed October 14, 2010), . . . (petitioner’s
    failure to provide legal citation did not waive uncomplicated
    argument that was factually developed); Arthur v. Unemployment
    Comp. Bd. of Rev[.] (Pa. Cmwlth., No. 593 C.D. 2009, . . . , filed
    October 20, 2009), . . . (appellate court will not refuse to review an
    issue based solely on absence of legal citations, if the argument is
    sufficiently developed to permit meaningful review). These
    decisions are consistent with the provisions of Rule 2119(a) and
    offer persuasive authority on this issue. See 
    210 Pa. Code §69.414
    (a).
    6
    A. Variance by Estoppel
    A party seeking a variance by estoppel must satisfy four elements: (1)
    the municipality’s failure to enforce the zoning ordinance for a long period, when
    the municipality knew or should have known of the violation but acquiesced in the
    illegal use; (2) good faith and innocent reliance by the landowner on the validity of
    the use throughout the proceedings; (3) substantial expenditures by the landowner
    in reliance on the belief that the use was permitted; and (4) unnecessary hardship
    from denial of the variance, such as the cost to demolish an existing building.
    Skarvelis v. Zoning Hearing Bd. of Dormont, 
    679 A.2d 278
    , 281 (Pa. Cmwlth. 1996).
    Here, regarding the first element, acquiescence by the municipality,
    there is no dispute that the Township failed to enforce the zoning ordinance’s height
    and story restrictions for a year while construction was ongoing, and that, during that
    time, the Township knew about the change in the building plan, conducted multiple
    inspections as the construction progressed, and issued an occupancy permit for the
    finished house. Although a year of inaction is a comparatively short time to support
    this element, the ongoing construction, the Township’s knowledge, and Williams’s
    Hillside Villas Condo. Ass’n v. Bottaro Dev. Co., 
    177 A.3d 456
    , 465 n.9 (Pa. Cmwlth. 2018).
    Here, McLogie’s argument presented a sufficiently developed argument to allow
    meaningful appellate review, as well as to preserve the issue it raised. McLogie cited and quoted
    multiple admissions by Township witnesses – facts that are not disputed – and cited, at least
    minimally, the requirements of the Uniform Construction Code, 
    34 Pa. Code §§ 401.1-405.42
    , as
    adopted by the Township. See Kidder Twp. Code, § 83-2 (adopting the Uniform Construction
    Code and incorporating it by reference). As explained further in the next section, those
    requirements include informing a building permit applicant of other permit requirements or
    approvals needed, as well as assuring that those other permits or approvals have been obtained
    before issuing a building permit. McLogie may not have cited the specific sections of the Uniform
    Construction Code and accompanying regulations on which it was relying, but it nonetheless stated
    the requirements of those sections and explained the Township’s undisputed failure to meet those
    requirements. Accordingly, we will not decline to entertain McLogie’s argument based on the
    lack of legal citations.
    7
    express approval of the revised building plan, along with the multiple inspections
    and the occupancy permit, all establish acquiescence by the Township. Cf. Skarvelis,
    
    679 A.2d at
    281-82 (citing Knake v. Zoning Hearing Bd. of Dormont, 
    459 A.2d 1331
    (Pa. Cmwlth. 1983) (variance by estoppel where borough knew the use was
    impermissible for 27 years but issued a building permit for the impermissible use);
    Three Rivers Youth v. Zoning Bd. of Adjustment for the City of Pittsburgh, 
    437 A.2d 1064
     (Pa. Cmwlth. 1981) (inaction by municipality for 7 years plus issuance of
    building permit by municipality and reliance by landowner on zoning officer’s
    interpretation of zoning regulation); Twp. of Haverford v. Spica, 
    328 A.2d 878
     (Pa.
    Cmwlth. 1974) (inaction by municipality for 36 years and issuance of building
    permit with knowledge of intended construction)).
    Regarding the second element, good faith reliance by the landowner,
    the record establishes that no one told McLogie that Dobosh’s former work functions
    had been divided between two separate people and were not being performed solely
    by Williams. Importantly, the applicable statute and regulations all appeared to
    indicate that the building code officer was responsible for approving the revised
    building plan. The Township adopted all of these provisions and incorporated them
    by reference in its code or ordinances when it adopted the Uniform Construction
    Code. Kidder Twp. Code, § 83-2.
    The applicable statutory provision states, in pertinent part:
    A code administrator shall review a construction plan of a
    building permit application upon submission and shall
    issue a notice of construction plan approval on a building
    permit application within the periods set forth in this
    section if the construction plans comply with the
    Construction Code Act and any other applicable municipal
    construction code ordinance. The municipality shall also
    provide a list of all other required permits necessary prior
    8
    to issuance of the building permit. The municipality will
    not be liable for the completeness of any list. When a
    construction plan has been approved, a code administrator
    shall issue a building permit immediately upon receipt of
    all other required permits or approvals related to the
    construction . . . .
    Section 502(a)(1) of the Construction Code Act, 35 P.S. § 7210.502(a)(1) (emphasis
    added). A “code administrator” is “[a] municipal code official, a construction code
    official, a third-party agency or the Department of Labor and Industry.” Section 103
    of the Construction Code Act, 35 P.S. § 7210.103 (emphasis added).             Thus,
    Williams, as a construction code official employed by Building Inspection
    Underwriters, the Township’s contracted third-party agency, was the Township’s
    “code administrator” with the statutory responsibilities accompanying that title.
    Three important requirements emerge from this provision: (1) the building/code
    enforcement officer was the primary contact and the person responsible to assure
    that other needed permits or approvals had been procured before issuing a building
    permit; (2) the Township was required to inform McLogie of all required permits –
    not the converse; and (3) all such permits had to be obtained before the code officer
    issued a building permit.
    The building/code enforcement officer’s function in this regard is
    underscored by the following related Uniform Construction Code provisions:
    § 403.62. Permit requirements and exemptions.
    (a) An owner or authorized agent who intends to
    construct, enlarge, alter, repair, move, demolish or change
    the occupancy of a residential building or erect, install,
    enlarge, alter, repair, remove, convert or replace an
    electrical, gas, mechanical or plumbing system regulated
    by the Uniform Construction Code shall first apply to the
    building code official and obtain the required permit under
    § 403.62a (relating to permit application). [Emphasis
    added.]
    9
    
    34 Pa. Code § 403.62
    (a).
    § 403.62a. Permit application.
    (a) Applications for a permit required under § 403.62
    (relating to permit requirements and exemptions) shall be
    submitted to the building code official in accordance with
    this section.
    (b) A permit applicant shall submit an application to the
    building code official and attach construction documents
    with plans and specifications and all other permits or
    approvals related to the construction required by § 403.102(n)
    (relating to municipalities electing to enforce the Uniform
    Construction Code).
    ....
    (e) The application must contain a site plan showing the
    size and location of the new construction and existing
    structures on the site and the structures’ distance from lot
    lines. If the construction involves demolition, the site plan
    must indicate construction that is to be demolished and the
    size and location of existing structures and construction
    that will remain on the site or plot. A building code official
    may waive or modify the site plan requirement when the
    permit application is for an alteration or a repair or if the
    waiver is warranted for other reasons. [Emphasis added.]
    
    34 Pa. Code § 403
    .62a(a), (b) & (e).
    § 403.63. Grant, denial and effect of permits.
    (a) A building code official shall grant or deny a permit
    application, in whole or in part, within 15 business days of
    the filing date or the application is deemed approved. If
    the drawings were prepared by a design professional who
    is licensed or registered under the laws and regulations of
    the Commonwealth and the application contains a
    certification by the licensed or registered design
    professional that the plans meet the applicable standards
    of the Uniform Construction Code and ordinance as
    appropriate, a building code official shall grant or deny a
    permit application, in whole or in part, within 5 business
    days of the filing date or the application is deemed
    10
    approved. Reasons for denial must be in writing,
    identifying the elements of the application which are not
    in compliance with the relevant provisions of the Uniform
    Construction Code and ordinance as appropriate and
    providing a citation to the relevant provisions of the
    Uniform Construction Code and ordinance as appropriate,
    and sent to the permit applicant. The building code official
    and the applicant may agree in writing to extend the
    deadline by a specific number of days.
    (b) A building code official shall examine the construction
    documents and shall determine whether the construction
    indicated and described is in accordance with the Uniform
    Construction Code and other pertinent laws or ordinances
    as part of the application process. [Emphasis added.]
    
    34 Pa. Code § 403.63
    (a) & (b).
    § 403.65. Certificate of occupancy.
    (a) A residential building may not be used or occupied
    without a certificate of occupancy issued by a building
    code official.
    (b) A building code official shall issue a certificate of
    occupancy after receipt of a final inspection report that
    indicates compliance with the Uniform Construction Code
    and ordinance within 5 business days or within 10 business
    days in cities of the first class . . . . [Emphasis added.]
    
    34 Pa. Code § 403.65
    (a) & (b).
    § 403.102 Municipalities Electing to Enforce the Uniform
    Construction Code
    ....
    (n) A municipality will provide a list of all other required
    permits necessary before issuance of the building permit.
    A municipality will not be liable for the completeness of
    any list. [Emphasis added.]
    
    34 Pa. Code § 403.102
    (n).
    11
    The Uniform Construction Code provisions above demonstrate that an
    applicant for a building permit does not inform the Township that additional zoning
    approval is required for a revised plan; the Township informs the applicant. Here,
    the building permit was issued in October 2019 by Williams, the Township’s
    building/code enforcement officer. As the Uniform Construction Code indicates,
    the building permit could not have been issued if the necessary zoning permits or
    approvals had not been obtained first.7 See 
    34 Pa. Code §§ 403.62
    (a); 403.62a(a),
    (b) & (e); 403.63(a) & (b); 403.65(a) & (b); 403.102(n). It was the Township’s duty
    to assure that those approvals were in place.
    Similarly, the building permit could be revoked only by the building
    code official following a change in the construction plan if he determined that the
    change mandated additional permit approvals. The Construction Code Act requires
    a code administrator to review a construction plan to confirm the issuance of all other
    required permits before approving the construction and issuing a building permit.
    35 P.S. § 7210.502. Thereafter, “[a]ll revisions or changes to construction plans so
    7
    We note that the Township’s web page relating to zoning and development regulations
    states:
    Attention:
    Kidder Township is contracted with Building Inspection
    Underwriters of Pennsylvania, Inc. [(BIU)] to issue all Township
    Building Permits and provide services such as review of plans and
    other construction documents, inspect construction, plumbing and
    mechanical inspections. Please be advised that BIU will not
    commence work on building permits until Kidder Township has first
    issued a zoning permit authorizing such work and shall not take any
    action until all fees are paid and all required documents are properly
    submitted.
    Kidder Twp., “Zoning and Building,” https://kiddertownship.org/zoning-and-building/ (last
    visited June 29, 2023).
    12
    approved . . . shall necessitate an additional plan review prior to the issuing of the
    building permit.” Id. The clear import of this statute is that the code administrator
    must review all plan changes to determine whether all other necessary permits have
    been obtained, just as he reviewed the original plan. See id. If the plan changes
    require additional permits, the code administrator must either withhold approval of
    the changes or revoke the building permit pending the issuance of the additional
    permits. Pennsylvania courts have long applied the maxim omnia praesumuntur rite
    esse acta, which this Court has explained as follows:
    It is, as a general rule, presumed that a public official
    properly and regularly discharges his duties, or performs
    acts required by law, in accordance with the law and the
    authority conferred on him, and that he will not do any act
    contrary to his official duty or omit to do anything which
    such duty may require.
    Collier v. City of Phila. (Pa. Cmwlth., No. 649 C.D. 2016, filed Mar. 6, 2017), slip
    op. at 9 n.108 (quoting Beacom v. Robison, 
    43 A.2d 640
    , 643 (Pa. Super. 1945))9
    (quotation marks omitted). Our courts have applied this maxim in various contexts.
    For example, in Harshman v. Dunbar Township, 
    11 Pa. Super. 638
    ,
    642-44 (1899), a township had a standing contract for road repair under which the
    regular contractor failed to perform. A statute required the township to give the
    regular contractor advance notice and an opportunity to cure its breach before hiring
    a new contractor. Thus, the township argued that its agreement with the new
    contractor was invalid and it did not have to pay him. However, the Superior Court
    explained that the new contractor could rely on its agreement with the township and
    8
    This unreported decision is cited as persuasive authority pursuant to Section 414(a) of
    this Court’s Internal Operating Procedures. 
    210 Pa. Code § 69.414
    (a).
    9
    Superior Court decisions are persuasive authority for this Court. Lerch v. Unemployment
    Comp. Bd. of Rev., 
    180 A.3d 545
    , 550 (Pa. Cmwlth. 2018).
    13
    had no duty to inquire whether the proper notice had been given to the original
    contractor before he accepted a contract from the township:
    He had the right to presume that the preliminary acts
    necessary to enable the [township] commissioners to enter
    into the contract had been performed by them. It was not
    his imperative duty to inquire of the contractors whether
    or not the notice required by the act had been given. That
    was an official duty incumbent upon the commissioners.
    When the commissioners made the contract, they must be
    deemed to have asserted that the preliminaries necessary
    to the making of that contract had been performed. As was
    said in the argument of the appellee, the plaintiff was
    bound to know the law, but he was not bound to know
    facts. As to the latter, so far as the duties of the
    commissioners were concerned, he could rightfully
    presume their existence and that the duties of the
    commissioners under the law had been performed.
    
    Id. at 644
    . Similarly, in Danville State Hospital for the Insane v. Bellefonte Borough
    Overseers of the Poor, 
    129 A. 901
     (Pa. 1894), our Supreme Court held that, where
    a borough’s overseers of the poor had statutory authority to send insane paupers to
    a state mental hospital, others dealing with the overseers were not required to inquire
    into the regularity of their official actions before accepting and expecting payment
    for such patients; the overseers’ acts were presumed to be rightly done. 
    Id.
     at 902 &
    904. See also Alexander v. Zerbe Twp. Poor Dist., 
    63 Pa. Super. 356
    , 359, 361-62
    (1916) (holding that a doctor contracted to provide medical services to the poor was
    entitled to payment and was not required to inquire into the regularity of the
    overseers’ directive that he provide shots to specific patients; the overseers’ acts
    were presumed to be rightly done).
    Here, as set forth above, before approving the change in the
    construction plan, the Township, through its code administrator, had a legal duty to
    ascertain whether a new zoning permit would be required for the particular plan
    14
    change. See 35 P.S. § 7210.502. Notably, the Township’s duty also included the
    Zoning Officer’s obligation to inspect the construction for compliance with the
    zoning ordinance before a certificate of use10 was issued. Kidder Twp. Code § 180-
    170.G.(3) (mandating that “[t]he Zoning Officer shall inspect such structure or land
    related to an application for [a] certificate [of use]. If the Zoning Officer determines
    . . . that such work conforms with this chapter and applicable Township codes,
    approvals and permits, then the certificate of use shall be issued.”). We therefore
    conclude that the maxim omnia praesumuntur rite esse acta should be applied in this
    case as well. Thus, as a matter of law, McLogie was entitled to assume the Township
    had performed its statutory and regulatory duties to assure that the plan change
    complied with applicable zoning. Accordingly, as a matter of law, McLogie acted
    reasonably in relying on Williams’s approval of the revised building plan,
    Williams’s failure to revoke the existing permit upon plan revision, the Township’s
    acquiescence in the construction under the originally issued building permit, and the
    Township’s subsequent issuance of the occupancy permit. The trial court erred in
    viewing McLogie’s reasonable reliance as a question of fact and ruling on that issue
    on the basis of a credibility finding. The law provided the basis for McLogie’s
    reliance.
    Regarding the third element, substantial expenditures in reliance on the
    validity of the use, McLogie built a basement with an eight and one-half foot ceiling
    in reliance on the validity of its building permit. Regarding the fourth element,
    unnecessary hardship from denial of a variance, there was testimony that McLogie
    10
    The Township’s zoning ordinance defines a “certificate of use” as “[a] document issued
    by the Township stating that a newly constructed or altered building, structure, and/or use complies
    with [the zoning ordinance].” Kidder Twp. Code § 180-12. Although the Kidder Township Code
    does not define an “occupancy permit,” the two terms appear to be synonymous.
    15
    would have to expend about $50,000 to fill in the basement. Thus, the last two
    elements are related here, in that McLogie incurred additional construction expense
    to build the basement and would incur substantial additional expense again in order
    to fill and regrade the area. Both expenses could have been avoided had the
    Township followed its own ordinance provisions.
    Finally, we note that the record does not suggest that the height and
    story violations create any practical problem of obscuring anyone’s view or access
    to light and air. Indeed, the Township’s proposed solution is not to reduce the height
    of the residence by removing the upper story, but rather, to fill in and raise the ground
    level so as to eliminate one of the home’s exits, that from the basement level – in
    other words, to raise the ground, not lower the building. Such a requirement would
    make no difference in the height of the house in relation to neighboring structures.
    In summary, the original plan here did not require any zoning relief
    before the original building permit was issued. Later, an issue arose regarding the
    front elevation of the property, and a basement was added to the plan. The revised
    plan showing the change was presented to the same building/code enforcement
    officer in November 2019 and he, at a minimum, approved the new foundation for
    the basement at that time. The same building/code enforcement officer did not
    indicate that any zoning relief was required or that another plan needed to be
    submitted. The Township did not revoke the building permit, which it should have
    done if it believed zoning relief was required in connection with the building plan
    change shown in the new plan. Instead, the Township allowed McLogie to continue
    to build under the prior building permit over the next nine months. The Township
    inspected the property multiple times while it was being built. The Township issued
    a certificate of occupancy for the property in July 2020, indicating that the property
    16
    was in compliance with Township codes and ready for use. In September 2020, the
    zoning officer realized that the property was not in compliance as built, and in
    October 2020, almost a year after approval of the revised building plan, the zoning
    officer issued an enforcement notice. Denial of a variance by estoppel under these
    undisputed facts was an error of law.
    B. Equitable Estoppel
    Refusal to apply equitable estoppel here was also an error of law. We
    recognize that the Township cannot be “liable” under the Uniform Construction
    Code for failing to notify McLogie of the need for zoning relief. 35 P.S. § 7210.502(a);
    see also 
    34 Pa. Code § 403.102
    (n). However, that does not mean that the Township
    cannot be equitably estopped from imposing an untimely zoning requirement.
    Black’s Law Dictionary defines “liable” as: “1. Responsible or answerable in law;
    legally obligated . . . . 2. Subject to or likely to incur a fine, penalty, etc.” Liable,
    Black’s Law Dictionary (11th ed. 2019). By contrast, it defines “estoppel” as:
    1. A bar that prevents one from asserting a claim or right
    that contradicts what one has said or done before or what
    has been legally established as true. . . . 3. An affirmative
    defense alleging good-faith reliance on a misleading
    representation and an injury or detrimental change in
    position resulting from that reliance.
    Estoppel, Black’s Law Dictionary (11th ed. 2019). Thus, the two terms are not
    interchangeable. A provision restricting the Township’s liability should not be read
    as precluding the application of estoppel principles where appropriate.
    Equitable estoppel may arise from “an informal promise implied by
    one’s words, deeds, or representations” that induces reasonable reliance by another
    to his detriment. In re Jackson, 
    280 A.3d 1074
    , 1083 (Pa. Cmwlth. 2022). Thus,
    17
    the two essential elements of equitable estoppel are inducement and justifiable
    reliance. Belleville v. David Cutler Grp., 
    118 A.3d 1184
    , 1199 (Pa. Cmwlth. 2015).
    Equitable estoppel may be asserted against the government. Jackson, 280 A.3d at
    1083; see also Chester Extended Care Ctr. v. Dep’t of Pub. Welfare, 
    586 A.2d 379
    ,
    382 (Pa. 1991). “The inducement may be words or conduct and the acts that are
    induced may be by commission or forbearance provided that a change in condition
    results causing disadvantage to the one induced.” Belleville, 
    118 A.3d at 1199
    (quoting Zitelli v. Dermatology Educ. & Rsch. Found., 
    633 A.2d 134
    , 139 (Pa.
    1993)); see also Jackson, 280 A.3d at 1083.
    Here, McLogie relied to its detriment on Williams’s approval of the
    revised construction plan, failure to revoke the building permit upon plan revision,
    and failure to inform McLogie that additional zoning approval must be sought; it
    also relied on the Township’s multiple inspections during the construction, and the
    issuance of an occupancy permit when construction was complete. If the ZHB is
    allowed to enforce the zoning ordinance against McLogie now, the property either
    cannot be used, or extreme measures must be taken. Either will be a clear detriment
    to McLogie.
    For these reasons, we conclude that McLogie has established both
    inducement and reliance. Accordingly, besides a variance by estoppel, McLogie is
    also entitled, in the alternative, to the application of the doctrine of equitable estoppel
    to preclude the Township from enforcing the height and story limitations to the
    building construction at issue. The ZHB and the trial court erred by concluding
    otherwise.
    18
    III. Conclusion
    Based on the foregoing discussion, we conclude that McLogie is
    entitled to a variance by estoppel, and further, that the ZHB is equitably estopped
    from enforcing the zoning ordinance’s height and story limitations against McLogie
    in the circumstances of this case. Accordingly, the trial court’s order affirming the
    ZHB’s decision is reversed.
    __________________________________
    CHRISTINE FIZZANO CANNON, Judge
    19
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    McLogie Properties Inc.,            :
    Appellant          :
    :
    v.                       :
    :
    Kidder Township Zoning              :   No. 1136 C.D. 2021
    Hearing Board                       :
    ORDER
    AND NOW, this 30th day of June, 2023, the order of the Court of
    Common Pleas of Carbon County docketed on September 16, 2021 is REVERSED.
    __________________________________
    CHRISTINE FIZZANO CANNON, Judge
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    McLogie Properties Inc.,               :
    Appellant             :
    :
    v.                               :   No. 1136 C.D. 2021
    :
    Kidder Township Zoning Hearing         :
    Board                                  :   Submitted: June 7, 2023
    BEFORE:     HONORABLE RENÉE COHN JUBELIRER, President Judge
    HONORABLE PATRICIA A. McCULLOUGH, Judge
    HONORABLE ANNE E. COVEY, Judge
    HONORABLE CHRISTINE FIZZANO CANNON, Judge
    HONORABLE ELLEN CEISLER, Judge
    HONORABLE LORI A. DUMAS, Judge
    HONORABLE STACY WALLACE, Judge
    DISSENTING OPINION
    BY JUDGE CEISLER                                            FILED: June 30, 2023
    I respectfully dissent from the majority’s conclusion that Appellant McLogie
    Properties Inc. (McLogie) is entitled to estoppel-based relief regarding its revised
    plans. This is for two reasons. First, from a procedural standpoint, I believe that
    McLogie has waived this argument. As our Supreme Court has explained,
    our rules of appellate procedure are explicit that the
    argument contained within a brief must contain “such
    discussion and citation of authorities as are deemed
    pertinent.” Pa. R.A.P. 2119(a). “[W]here an appellate brief
    fails to provide any discussion of a claim with citation to
    relevant authority or fails to develop the issue in any other
    meaningful fashion capable of review, that claim is
    waived. It is not the obligation of [an appellate court . . . ]
    to formulate [an a]ppellant’s arguments for him.” Com[.]
    v. Johnson, . . . 
    985 A.2d 915
    , 924 ([Pa.] 2009) (internal
    citations omitted). Moreover, because the burden rests
    with the appealing party to develop the argument
    sufficiently, an appellee’s failure to advocate for waiver is
    of no moment. See Connor v. Crozer Keystone Health
    Sys., 
    832 A.2d 1112
    , 1118 (Pa. Super. 2003).
    Wirth v. Com., 
    95 A.3d 822
    , 837 (Pa. 2014).
    Here, McLogie argued that Dave Williams, Kidder Township’s building/code
    enforcement officer, was legally required to notify it regarding the need for
    additional zoning approvals, but did not support this assertion with cites to specific
    ordinances or statutory provisions or, for that matter, any legal analysis. Instead,
    McLogie presented this argument through two passing references in its brief to the
    Uniform Construction Code (Uniform Construction Code or UCC),1 which read as
    follows:
    Mr. Williams’ testimony . . . reflects miscommunication
    related to the project. ([Reproduced Record (R.R.)] at
    529a-254a). Mr. Williams testified that the “Pennsylvania
    UCC requires that I tell applicants for building permits that
    they might need to go through zoning and get a zoning
    permit for their work. That is the expressed limit of my
    responsibility regarding zoning.” ([R.R.] at 248a). Yet,
    despite this requirement, Mr. Williams could not recall
    whether he advised McLogie of this or informed McLogie
    that [it] had to proceed separately with zoning. (Id.).
    McLogie’s Br. at 14.
    Here, the record is replete with evidence of negligence.
    (See Hearing Transcript, generally). Mr. Williams, as
    testified by himself, Ms. Norato, Kidder Township’s
    zoning officer,] Mr. Kolodgie, [one of McLogie’s
    principals,] and Mr. O’Connell, [a contractor employed by
    McLogie for the project,] approved the Revised Plans.
    (See [i]d.). Mr. Williams further advised McLogie
    following his approval that it was “good to go” with
    construction of the residence as modified. (See [i]d.). This
    was clearly a negligent misrepresentation on behalf of
    [Kidder] Township given the position taken by [Appellee
    Kidder Township Zoning Hearing Board (Board)] that Mr.
    Williams’[] authority related to building issues only (even
    though he, nor Ms. Norato, nor anyone else from [Kidder]
    Township ever advised McLogie that Mr. Dobosh’s duties
    1
    
    34 Pa. Code §§ 401.1-405.42
    .
    EC - 2
    had been split between two individuals). (See [i]d.).
    Additional evidence of negligence by [Kidder] Township
    as detailed at length before includes:
    ....
    Mr. Williams never advised McLogie that it might have to
    get a zoning permit for the Revised Plans even though
    “Pennsylvania UCC requires” that information be
    conveyed. (Id. at 31:4-5, 50:10-20).
    McLogie’s Br. at 29-30. This discussion falls far short of what can be considered a
    sufficiently developed claim that Williams’ putative failure to fulfill his alleged
    duties justifies relief in McLogie’s favor by estoppel. Therefore, to the extent that
    such an argument could have been presented, McLogie has waived it.
    Second, I believe that this argument, even if it had been properly presented to
    us, would not justify reversal. In general, local municipalities are vested with
    authority to adopt the UCC, through both the Construction Code Act2 and the
    attendant regulations present in the Uniform Construction Code, via ordinance. See
    35 P.S. § 7210.501(a);3 
    34 Pa. Code § 403.102
    . Kidder Township has exercised this
    authority by adopting the UCC by reference. See Kidder Twp. Code § 83-2.4
    Under the UCC, applicants are required to apply for and obtain building
    permits from a municipality’s building code official for things that are regulated
    under the UCC. See 
    34 Pa. Code §§ 403.62
    , 403.62a. The UCC delineates the
    building code official’s authority and duties as follows, in relevant part:
    (a) A building code official shall grant or deny a permit
    application, in whole or in part, within 15 business days of
    the filing date or the application is deemed approved. If
    the drawings were prepared by a design professional who
    2
    Act of November 10, 1999, P.L. 491, as amended, 35 P.S. §§ 7210.101-7210.1103.
    3
    Section 501(a) of the Construction Code Act.
    4
    Kidder Township Code, Carbon County, Pa., as amended (2005).
    EC - 3
    is licensed or registered under the laws and regulations of
    the Commonwealth and the application contains a
    certification by the licensed or registered design
    professional that the plans meet the applicable standards
    of the Uniform Construction Code and ordinance as
    appropriate, a building code official shall grant or deny a
    permit application, in whole or in part, within 5 business
    days of the filing date or the application is deemed
    approved. Reasons for denial must be in writing,
    identifying the elements of the application which are not
    in compliance with the relevant provisions of the Uniform
    Construction Code and ordinance as appropriate and
    providing a citation to the relevant provisions of the
    Uniform Construction Code and ordinance as appropriate,
    and sent to the permit applicant. The building code official
    and the applicant may agree in writing to extend the
    deadline by a specific number of days.
    (b) A building code official shall examine the construction
    documents and shall determine whether the construction
    indicated and described is in accordance with the Uniform
    Construction Code and other pertinent laws or ordinances
    as part of the application process.
    (c) A building code official shall stamp or place a notation
    on each page of the set of reviewed construction
    documents that the documents were reviewed and
    approved for Uniform Construction Code compliance
    before the permit is issued. The building code official shall
    clearly mark any required nondesign changes on the
    construction documents. The building code official shall
    return a set of the construction documents with this
    notation and any required changes to the applicant. The
    applicant shall keep a copy of the construction documents
    at the work site open to inspection by the construction
    code official or an authorized representative.
    ....
    (e) A building code official may issue a permit for the
    construction of the foundations or other parts of a building
    or structure before the construction documents for the
    whole building or structure are submitted if the permit
    applicant previously filed adequate information and
    detailed statements for the building or structure under the
    EC - 4
    Uniform Construction Code. Approval under this section
    is not assurance that the building code official will issue a
    permit for the entire building or structure.
    (f) Issuance of a permit does not bar prosecution or other
    legal action for violations of the [Construction Code A]ct,
    the Uniform Construction Code or a construction
    ordinance. A building code official may suspend or revoke
    a permit issued under the Uniform Construction Code
    when the owner does not make the required changes
    directed by the building code official under subsection (c),
    when the permit is issued in error, on the basis of
    inaccurate or incomplete information or in violation of any
    act, regulation, ordinance or the Uniform Construction
    Code.
    ....
    
    34 Pa. Code § 403.63
    (a)-(c), (e)-(f). The Construction Code Act contains similar
    language and, in addition, explicitly states that a municipality must provide an
    applicant with a list of necessary permits prior to issuing a building permit, but
    cannot be held “liable” for the completeness of that list. See 35 P.S. § 7210.502(a).5
    Finally, the UCC states that a building code official shall issue a certificate of
    occupancy after receiving a final inspection report that shows compliance with the
    Uniform Construction Code and the municipality’s ordinance adopting the UCC, but
    “may suspend or revoke a certificate of occupancy when the certificate was issued
    in error, on the basis of incorrect information supplied by the permit applicant, or
    in violation of the Uniform Construction Code.” 
    34 Pa. Code § 403.65
     (emphasis
    added).
    Tying all of this statutory and regulatory language together leads to the
    following conclusions. First, a building code official is responsible for reviewing
    building plan applications to ensure that they comply with the UCC and any local
    construction code ordinances, and can approve such applications only in the event
    5
    Section 502(a) of the Construction Code Act.
    EC - 5
    that the official finds them to be compliant. Second, a building code official must
    also review applications to determine whether they comply with “other pertinent
    laws or ordinances,” but approval of an application is only contingent upon its
    compliance with the UCC and local construction code ordinances. Third, before
    issuing a building permit, a municipality must provide an applicant with a list of
    what other permits they need to obtain, but the municipality cannot be held liable for
    the completeness of that list. In other words, a municipality cannot be held
    responsible if, for example, its officials issue a building permit but fail to inform an
    applicant that they also need to obtain additional zoning permits in order to move
    forward with the affected construction project. Finally, the issuance of a certificate
    of occupancy is only predicated upon whether the building has been inspected for
    compliance with the UCC, not upon whether the building is in compliance with all
    relevant laws and ordinances. Accordingly, McLogie had no legal basis to rely on
    Williams’ approval of the revised plans, the subsequent issuance of a certificate of
    occupancy, and/or the fact that Williams did not tell McLogie that it needed to secure
    additional zoning approval, as proof that it was free to move forward with
    developing its parcel of land in accordance with the revised plans.
    McLogie’s only recourse, then, was to argue that it relied in good faith upon
    Williams’ actions when forming the belief that it did not need to secure additional
    governmental review in order to move forward with construction, and thus was
    entitled to estoppel-based relief. The Board, in relevant part, concluded that
    [McLogie] knew it had to get zoning approval separate and
    apart from [Williams’] approval; [McLogie] specifically
    applied for a 34[-]foot[-]high building and submitted plans
    to [Norato] with only three (3) stories; and . . . the Zoning
    Permit itself was approved with the comment “as per
    submitted plans[,]” meaning [McLogie] had actual
    EC - 6
    knowledge that the Zoning Permit was only approved as
    per the plans showing three (3) stories.
    Board’s Decision, Conclusions of Law ¶¶6, 8. Furthermore, McLogie was, at
    minimum, put on notice by the zoning permit it received from Kidder Township on
    September 6, 2019, that Norato was Kidder Township’s zoning officer, as well as
    that this permit only authorized the construction of a “[n]ew home & deck [a]s per
    [McLogie’s] plot plan [for its property.]” R.R. at 46a; Kidder Twp.’s Br., App. As
    such, the Board did not abuse its discretion in determining that McLogie was not
    entitled to a variance by estoppel, because, in the Board’s reasoned view, McLogie
    had not innocently relied upon Williams’ approval of the revised plans and knew, or
    should have known, that the only way it could get zoning approval for its revised
    plans was through Norato, not Williams.6
    Furthermore, though the Board erroneously concluded that McLogie had
    waived its equitable estoppel argument, that error is ultimately harmless. See
    DiSanto v. Bd. of Comm’rs of Susquehanna Twp. (Pa. Cmwlth., No. 679 C.D. 2016,
    filed June 1, 2017), slip op. at 4-6, 
    2017 WL 2376522
    , at *2;7 In re Kreider, 
    808 A.2d 340
    , 343 (Pa. Cmwlth. 2002). What is fatal to that claim is the same thing that
    deprived McLogie of the ability to secure a variance by estoppel: the Board’s
    determination that McLogie unjustifiably relied on Williams’ approval of the revised
    plans and failed to seek or gain a new zoning permit from Norato. See DiSanto, slip
    6
    A local governing body abuses its discretion when it makes factual findings that are not
    supported by substantial evidence. Miravich v. Twp. of Exeter, Berks Cnty., 
    54 A.3d 106
    , 110 n.4
    (Pa. Cmwlth. 2012). “Substantial evidence” constitutes “such relevant evidence as a reasonable
    mind might accept as adequate to support a conclusion.” Valley View Civic Ass’n v. Zoning Bd. of
    Adjustment, 
    462 A.2d 637
    , 640 (Pa. 1983).
    7
    Unreported Commonwealth Court opinions issued after January 15, 2008, may be cited
    for their persuasive value. See Internal Operating Procedures of the Commonwealth Court Section
    414(a), 
    210 Pa. Code § 69.414
    (a).
    EC - 7
    op. at 7, 
    2017 WL 2376522
    , at *3 (“This Court has repeatedly held that equitable
    estoppel will not lie where the party asserting estoppel knew or should have known
    that the alleged promisor was without authority to effectuate the alleged promise.”).8
    Given that the Board appropriately exercised its discretion as factfinder, we are
    bound by its credibility determinations9 and cannot disturb its conclusion that
    McLogie did not rely in good faith upon Williams’ approval of the revised plans.
    In sum, I would affirm the Court of Common Pleas of Carbon County’s
    (Common Pleas) September 16, 2021 order, through which Common Pleas affirmed
    the Board’s denial of McLogie’s request for relief, and respectfully dissent from the
    majority opinion on that basis.
    __________________________________
    ELLEN CEISLER, Judge
    8
    “It is well settled that this Court may affirm on other grounds where the grounds for
    affirmance exist.” Thorpe v. Com., 
    214 A.3d 335
    , 339 n.8 (Pa. Cmwlth. 2019) (citing Karl Smith
    Dev. Co. v. Borough of Aspinwall, 
    558 A.2d 181
    , 185 n.6 (Pa. Cmwlth.1989)).
    9
    It is well settled that we must avoid the inclination to measure and assess the multitude
    of factors and considerations that support a zoning ruling, and “must exercise self-restraint as to
    substituting our opinions far removed from the particular zoning hearing for the well-considered
    decision of [the Board].” Cohen v. Zoning Bd. of Adjustment of City of Phila., 
    276 A.2d 352
    , 355
    (Pa. Cmwlth. 1971). “It is, after all, the sole function of the Board, in the performance of its role
    as fact finder, to evaluate witness credibility and assign evidentiary weight.” Lower Allen Citizens
    Action Grp., Inc. v. Lower Allen Twp. Zoning Hearing Bd., 
    500 A.2d 1253
    , 1258 (Pa. Cmwlth.
    1985) (punctuation omitted). Indeed, the “Board as fact finder is the ultimate judge of credibility
    and resolves all conflicts in the evidence,” Eichlin v. Zoning Hearing Board of New Hope Borough,
    
    671 A.2d 1173
    , 1175 (Pa. Cmwlth. 1996), and has “the power to reject even un-contradicted
    testimony if it finds it lacking in credibility.” Lower Allen, 500 A.2d at 1258.
    EC - 8