KNS Dev., LP v. ZHB of the Twp. of Loyalsock & Loyalsock Twp. ( 2021 )


Menu:
  •          IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    KNS Development, LP,               :
    :
    Appellant   :
    :
    v.                      : No. 672 C.D. 2020
    : Argued: December 8, 2020
    Zoning Hearing Board of the        :
    Township of Loyalsock and          :
    Loyalsock Township                 :
    BEFORE:    HONORABLE ANNE E. COVEY, Judge
    HONORABLE MICHAEL H. WOJCIK, Judge
    HONORABLE ELLEN CEISLER, Judge
    OPINION NOT REPORTED
    MEMORANDUM OPINION
    BY JUDGE WOJCIK                                      FILED: July 14, 2021
    KNS Development (KNS) appeals from the June 15, 2020 order of the
    Court of Common Pleas of Lycoming County (trial court) denying its land use
    appeal from the decision of the Zoning Hearing Board (ZHB) of Loyalsock
    Township (Township). Upon review, we affirm.
    I.    Background
    On March 25, 2019, the Township issued an excavation permit to KNS
    for 2355 East Third Street (the Property) pursuant to the Township’s zoning
    ordinance (Ordinance).1,2 Reproduced Record (R.R.) at 217a-21a. The permit
    provided that earthmoving activity was approved based upon an attached erosion
    and sedimentation control plan for Auto World. Id. The permit also provided that
    there was an 8-foot area, that was not to be excavated per the application submitted
    by KNS. On June 26, 2019, KNS corrected a typographical error regarding the slope
    of the excavation. Id. at 222a.
    On August 14, 2019, the Township’s zoning officer sent a notice of
    violation (Notice) to KNS. R.R. at 212a-13a. The Notice stated that upon inspection
    of the Property, the Township’s engineer found that KNS had exceeded the
    permitted scope of work by over-excavating and, therefore, was in violation of
    Section 215-111 of the Ordinance.3 Id. The Township’s engineer’s findings were
    1
    Loyalsock Township Zoning Ordinance of 1994, §§215-1-112.
    2
    Interestingly, KNS had begun excavation work on the Property prior to obtaining a
    permit. Reproduced Record (R.R.) at 117a-19a; 228a-33a. KNS only obtained a permit for the
    excavation after a Township official had emailed KNS. Id.
    3
    Specifically, the Township’s engineer found the following instances which exceeded the
    permitted scope of work:
    1 Present excavation along the Western and Northern property
    lines on the [] Plan specifies an 8[-]foot minimum setback from
    property lines where excavation was specified to begin. [My]
    findings show cut and grading up to these property lines, which
    does not coincide with the approved [] Plan.
    2. Present excavation along the Eastern property line on the []
    Plan specifies an un-dimensioned setback line where excavation
    was specified to begin. Our findings also show cut and grading
    up to these property lines, which does not coincide with the
    approved [] Plan.
    (Footnote continued on next page…)
    2
    attached to the Notice. Id. at 225a-26a. The Notice directed KNS to submit new
    plans within 10 days of receipt, or the Township would revoke KNS’s open zoning
    permit. Id. at 212a-13a.
    Section 215-111 of the Ordinance provides that failure to secure a
    permit “previous to erection, addition, remodeling, alteration or use of any building,
    structure or land, or portion thereof . . . shall be a violation of this chapter.” R.R. at
    101a-02a. Section 215-111 also states the required contents for a notice of violation.4
    3. As shown on my Asbuilt Plan, a portion of the cut slope on
    the Northern and Eastern lines extend beyond the property lines.
    4. As shown on my Asbuilt Plan, all constructed cut slopes
    shown are in compliance with the 0.5:1 maximum slope shown
    on the approved [] Plan, except the one tying into the
    neighboring (proposed Bank) cut slope at the South end, which
    is approximately 02:1.
    R.R. at 225a.
    4
    Section 215-111(A) of the Ordinance provides:
    A.      Notice of Violation. The enforcement notice shall be
    sent to the owner of record of the parcel on which the
    violation has occurred, to any person who has filed a written
    request to receive enforcement notices regarding that parcel
    and to any other person requested, in writing, by the owners
    of record. The enforcement notice shall state at least the
    following:
    1.     The name of the owner of record and any other
    person against whom the municipality intends to take action.
    2.      The location of the property in violation.
    3.     The specific violation with a description of the
    requirements which have not been met, citing in each
    instance the applicable provisions of this chapter.
    (Footnote continued on next page…)
    3
    KNS appealed the Notice to the ZHB. No further enforcement action
    was taken by the Township. On October 16, 2019, the ZHB held a hearing. R.R. at
    105a-96a. At the hearing, KNS challenged the validity of the Notice and whether
    KNS was in violation of any provisions of the Ordinance. KNS challenged the
    Township’s failure to cite a specific violation of the Ordinance in the Notice. KNS
    also argued that the Notice provided only 10 days to remedy the violations when the
    Ordinance provided 30 days. Id. at 153a; 190a.
    On October 21, 2019, the ZHB denied KNS’s appeal, and made the
    following relevant findings of fact:
    21. The August 14, 2019 [Notice] gives fair notice to
    [KNS] of the substance of the violation . . . .
    22.    [KNS] presented no testimony indicating that the
    project was in fact in compliance with the setback and
    slope requirements as shown on the plan.
    4.    The date before which the steps for compliance must
    be commenced and the date before which steps must be
    completed.
    5.      That the recipient of the notice has the right to appeal
    to the [ZHB], provided that said appeal is made to [ the ZHB]
    within 30 days from the receipt of the written notice of
    violation in accordance with procedures set forth in this
    chapter.
    6.      That failure to comply with the written notice within
    30 days from the receipt of the written notice violation,
    unless extended by appeal to the [ZHB], constitutes a
    violation, with possible sanctions clearly described.
    R.R. at 101a-02a. The language of Section 215-111(A) mirrors Section 616.1(c) of the
    Pennsylvania Municipalities Planning Code (MPC), Act of July 31, 1968, P.L. 805, as amended,
    added by the Act of December 21, 1988, P.L. 1329, 53 P.S. §10616.1(c).
    4
    23. The [ZHB] finds that the project is not in
    compliance with the setback and slope requirements
    imposed by the permit that was issued.
    R.R. at 242a.
    Based on the foregoing findings, the ZHB concluded:
    1.     [KNS] failed to meet the burden of proof to
    establish that the [Notice] was improper.
    2.    Due process was afforded to all parties in these
    proceedings.
    3.    Notice was provided to all concerned, as required
    by the [Ordinance] and the [MPC].
    4.     [KNS] failed to meet the burden of proof to
    establish that the [Notice] was improper.
    5.      Therefore, the appeal should be denied.
    R.R. at 242a-43a.
    On November 20, 2019, KNS filed a land use appeal with the trial court
    arguing that the Notice was defective based on the lack of specificity of what
    sections of the Ordinance were allegedly violated, and the limited period of time in
    which KNS was given to comply. R.R. at 244a-49a. On May 1, 2020, while the
    land use appeal was pending before the trial court, KNS filed a motion for leave to
    supplement the record with newly obtained documents based on a Right-to-Know
    Law5 request. That same day, KNS filed a memorandum of law in which it asserted
    that the ZHB erred by placing the burden of proof on KNS to show that the Notice
    was improper.
    5
    Act of February 14, 2008, P.L. 6, 65 P.S. §§67.101-67.3104.
    5
    On June 15, 2020, without taking additional evidence, the trial court
    disposed of the land use appeal and the motion for leave to supplement the record.
    R.R. at 446a-51a. Regarding the land use appeal, the trial court found that the Notice
    cited [S]ection 215-111 of the Ordinance, which details
    what constitutes a violation of [the] Ordinance’s Zoning
    Chapter. Nothing in this [S]ection expressly states that
    breaching a permit constitutes a violation, nor are any of
    the specific violations for which [KNS] was cited, such as
    [KNS’s] intrusion into the eight-foot setback, expressly
    listed as a violation within this [S]ection. However, as
    noted in the Brief filed jointly by the [ZHB] and the
    Township, the Pennsylvania Commonwealth Courts [sic]
    have recognized that “[a] violation of a condition imposed
    by the zoning board is the equivalent of a violation of the
    zoning ordinance.”
    The [Notice] generally provides that [KNS] failed
    to follow its submitted excavation plans and went outside
    the scope of work sanctioned by the permit. The [Notice]
    incorporates by reference [the Township’s engineer’s]
    letter of August 12, 2019[.] The August 12 letter breaks
    down each alleged permit violation in detail. This letter
    was sent to [KNS] in conjunction with the [Notice]. The
    [c]ourt concludes that the [Notice], in citing the violation
    of the permit and in clearly detailing each permit violation
    in the incorporated August 12 [l]etter, satisfied the
    statutory requirement that the enforcement notice cite each
    applicable ordinance provision violated.
    R.R. at 449a.
    The trial court determined that KNS had more than 300 days to comply
    with the Notice because of the appeals that KNS had filed in the matter. R.R. at
    450a. Therefore, the trial court, citing Three Rivers Aluminum Company, Inc. v.
    Zoning Hearing Board of Marshall Township, 
    618 A.3d 1165
    , 1168 (Pa. Cmwlth.
    1992), and noting that KNS’s challenge was procedural and not substantive, held
    that the ZHB was justified in determining that the Notice’s failure to provide
    6
    sufficient time to remedy the violation was not a valid basis for setting aside the
    Notice. R.R. at 450a.
    The trial court denied KNS’s motion to supplement the record, finding
    that KNS had failed to adequately justify the relevance of the proffered evidence.
    R.R. at 448a. Lastly, the trial court found that KNS had waived the burden of proof
    issue that was raised in its memorandum of law because it failed to raise that claim
    in the land use appeal notice. 
    Id.
     at 451a. KNS then filed the instant appeal to this
    Court.
    II.   Discussion
    On appeal, KNS argues that the Notice failed to satisfy the requirements
    of Section 616.1(c)(3) of the MPC, 53 P.S. §10616.1(c)(3), because the Notice failed
    to include a citation to the specific provisions of the Ordinance that KNS had
    allegedly violated. KNS also argues that the trial court erred by sua sponte raising
    the issue of the ZHB’s shifting of the burden of proof to KNS, and then finding that
    KNS had waived that argument. Lastly, KNS contends that the ZHB erred when it
    shifted the burden to KNS to prove that the Notice was improper.
    In a land use appeal where the trial court does not take additional
    evidence, our scope of review is limited to determining whether the ZHB committed
    an error of law or abuse of discretion. Riverfront Development Group, LLC v. City
    of Harrisburg, 
    109 A.3d 358
    , 363 n.8 (Pa. Cmwlth. 2015). A notice of violation
    must cite the specific ordinance section which the township alleges that the
    landowners have violated. Township of Maidencreek v. Stutzman, 
    642 A.2d 600
    ,
    602 (Pa. Cmwlth. 1994); Section 616.1(c) of the MPC, 53 P.S. §10616.1(c)(3).
    7
    The Notice in this case stated that the “reviewing engineer found that
    [KNS’s] designed excavation plan was not followed, and [KNS] went outside the
    scope of work that [it was] permitted for per the zoning permit. [KNS is] currently
    in violation of [Ordinance S]ection 215-111 for failing to follow the approved
    permit.” R.R. at 103a (emphasis added). The Notice also enclosed the Township’s
    engineer’s report.
    Section 215-111 of the Zoning Ordinance provides:
    Failure to comply with any provision of this chapter.
    Failure to secure a zoning permit or a [ZHB] Certificate,
    when required, previous to erection, addition, remodeling,
    alteration or use of any building, structure or land, or
    portion thereof, or prior to the change or extension of a
    nonconforming use, building or structure, shall be
    violation of this chapter.
    R.R. at 101a (emphasis added).
    KNS asserts that the Notice fails to state a specific section of the
    Ordinance that was allegedly violated as required by Section 616.1(c)(3) of the
    MPC, and is therefore defective and unenforceable. KNS argues that Section 215-
    111 does not set forth any substantive zoning requirements, such as uses or setback
    requirements in any specific zoning district, and it does not state that the alleged
    permit violation is itself an Ordinance violation. We find no merit in this argument.
    The plain language of Section 215-111 states that a failure to obtain a
    permit prior to the alteration of land is a violation of that Section. KNS had obtained
    a permit for excavation, but performed work outside the scope of the permit. Under
    the Ordinance, KNS was required to obtain a permit for the additional excavation
    work prior to performing it. Therefore, the ZHB and trial court correctly determined
    8
    the Notice’s citation to Section 215-111 satisfied the statutory requirement that the
    enforcement notice cite the applicable ordinance provision that had been violated.
    We are similarly unpersuaded by KNS’s argument that the trial court
    sua sponte raised the issue of waiver. Section 1003-A(a) of the MPC provides that
    “[land] use appeals shall be entered as of course by the prothonotary or clerk upon
    the filing of a land use appeal notice which concisely sets forth the grounds on which
    the appellant relies.” 53 P.S. §11003-A(a), added by Act of December 21, 1988,
    P.L. 1329 (emphasis added). Section 1002-A of the MPC requires that “[a]ll appeals
    from all land use decisions . . . shall be filed within 30 days after entry of the decision
    . . . .” 53 P.S. §11002-A, added by Act of December 21, 1988, P.L. 1329. As this
    Court has explained:
    [T]he grounds for appeal requirement of Section [1003-
    A(a)] plays a necessary role by winnowing the scope of a
    land use appeal. Allowing land use appellants the right to
    raise new issues after expiration of the appeal period
    would not only afford them a substantial advantage not
    currently provided by the [MPC] but would also expand
    litigation in an area already heavily burdened.
    Gall v. Zoning Hearing Board of Upper Milford Township, 
    723 A.2d 758
    , 760 (Pa.
    Cmwlth. 1999) (citations omitted).
    The ZHB decision from which KNS appealed was rendered on October
    21, 2019. R.R. at 243a. KNS filed the notice of its land use appeal on November
    20, 2019, within the 30-day appeal period. 
    Id.
     at 244a-49a. However, KNS failed
    to raise the burden of proof issue in its notice of land use appeal. 
    Id.
     KNS’s May 1,
    2020 memorandum of law raised the burden of proof issue for the first time.
    However, the memorandum of law was filed 163 days after the expiration of the 30-
    day appeal period. 53 P.S. §11002-A.
    9
    The trial court properly determined that the burden of proof issue was
    waived by KNS. See Gall, 
    723 A.2d at 760
    . The trial court did not do so sua sponte
    as KNS argues, but addressed the issue because KNS untimely raised the claim in
    the May 1, 2020 memorandum of law. Having determined KNS waived its burden
    of proof issue, we need not address the merits.
    Accordingly, the order of the trial court is affirmed.
    MICHAEL H. WOJCIK, Judge
    Judge Fizzano Cannon did not participate in the decision of this case.
    10
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    KNS Development, LP,                :
    :
    Appellant    :
    :
    v.                       : No. 672 C.D. 2020
    :
    Zoning Hearing Board of the         :
    Township of Loyalsock and           :
    Loyalsock Township                  :
    ORDER
    AND NOW, this 14th day of July, 2021, the order of the Court of
    Common Pleas of Lycoming County dated June 15, 2020, is AFFIRMED.
    __________________________________
    MICHAEL H. WOJCIK, Judge
    

Document Info

Docket Number: 672 C.D. 2020

Judges: Wojcik

Filed Date: 7/14/2021

Precedential Status: Non-Precedential

Modified Date: 11/21/2024