Lobar Assoc., Inc. v. PA Turnpike Comm. ( 2019 )


Menu:
  •             IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Lobar Associates, Inc.,                            :
    Petitioner                      :
    :
    v.                                  :   No. 1038 C.D. 2018
    :   Argued: March 12, 2019
    Pennsylvania Turnpike Commission,                  :
    Respondent                        :
    BEFORE:        HONORABLE MARY HANNAH LEAVITT, President Judge
    HONORABLE P. KEVIN BROBSON, Judge
    HONORABLE BONNIE BRIGANCE LEADBETTER, Senior Judge
    OPINION
    BY PRESIDENT JUDGE LEAVITT                                                FILED: August 1, 2019
    Lobar Associates, Inc. (Contractor) petitions for review of an order of
    the Board of Claims (Board) that sustained the preliminary objections of the
    Pennsylvania Turnpike Commission (Commission) and dismissed Contractor’s
    claim for lack of jurisdiction. The Board held that Contractor’s claim was barred by
    the six-month statute of limitations set forth in Section 1712.1(b) of the
    Commonwealth Procurement Code, 62 Pa. C.S. §1712.1(b).1 Contractor argues that
    the Board erred in its determination of when Contractor’s claim accrued. Discerning
    no such error by the Board, we affirm.
    Background
    On June 18, 2014, Contractor agreed to construct a 2,431-square-foot
    material testing laboratory at mile marker 113.82 of the Pennsylvania Turnpike (the
    1
    Section 1712.1(b) of the Procurement Code states:
    (b) Filing of claim.--A claim shall be filed with the contracting officer within six
    months of the date it accrues. If a contractor fails to file a claim or files an untimely
    claim, the contractor is deemed to have waived its right to assert a claim in any
    forum. Untimely filed claims shall be disregarded by the contracting officer.
    62 Pa. C.S. §1712.1(b).
    Somerset Project) for the Commission. Contractor completed the work in June 2016.
    On July 27, 2016, Contractor submitted a “supplemental work order” to the
    Commission, requesting additional compensation of $150,925.19 for changes to the
    project made by the Commission during construction. Reproduced Record at 676a
    (R.R. __). On September 21, 2016, the Commission responded that it would pay
    $35,233.05 for the supplemental work. Contractor responded with a request for
    further review, which was denied by the Commission on October 17, 2016.
    On March 27, 2017, Contractor submitted an administrative claim to
    the Commission’s contracting officer, seeking $418,767.42 for the supplemental
    work and delay damages attributable to the Commission’s project design changes.
    The Commission conducted an administrative hearing. It denied Contractor’s claim
    as untimely because it was not submitted within six months of the Commission’s
    September 21, 2016, determination that it would pay $35,233.05 for the
    supplemental work.
    Thereafter, on September 14, 2017, Contractor filed a three-count claim
    against the Commission with the Board asserting breach of contract, unjust
    enrichment, and violation of the Contractor and Subcontractor Payment Act, 73 P.S.
    §§501-516.2 Contractor sought a judgment in excess of $418,767.42, plus interest,
    costs of suit and attorney fees.
    Contractor’s claim stated that the Somerset Project began as a publicly
    bid project. However, the Commission then made an “unwieldy and confusing
    2
    Act of February 17, 1994, P.L. 73, as amended, 73 P.S. §§501-516. The Contractor and
    Subcontractor Payment Act sets guidelines for prompt payment. Section 9 of the Contractor and
    Subcontractor Payment Act, 73 P.S. §509. Interest may be assessed on payments unreasonably
    held. Section 9(d) of the Contractor and Subcontractor Payment Act, 73 P.S. §509(d). A
    contractor that withholds payment in bad faith can be subjected to a one percent penalty and
    attorney fees. Section 12 of the Contractor and Subcontractor Payment Act, 73 P.S. §512.
    2
    attempt to convert [the] publicly bid project into a JOC [job-order contract] project.”
    Claim, ¶2 at 1; R.R. 8a.3 The claim alleged that this conversion resulted in “an
    incomplete design to start the [p]roject and thus one that changed and morphed as
    the [p]roject proceeded.” Claim, ¶3 at 2; R.R. 9a. The design changes required
    Contractor to perform work beyond the scope of the contract. Claim, ¶5 at 2; R.R.
    9a. In addition, Contractor sought delay damages for expenses it incurred due to
    delays caused by the design changes. Claim, ¶6 at 2; R.R. 9a. Contractor’s claim
    asserted damages of $150,925.19 for the supplemental work and delay damages of
    $267,842.23. Claim, ¶7 at 2: R.R. 9a.
    The Commission filed preliminary objections, asserting that the Board
    lacked jurisdiction because Contractor’s claim was barred by the six-month statute
    of limitations in Section 1712.1(b) of the Procurement Code. The Commission also
    asserted that Contractor failed to exhaust its administrative remedy and failed to state
    a claim for unjust enrichment. The Board held an evidentiary hearing on the question
    of its jurisdiction.
    Contractor presented the testimony of Carl Barker, its project manager
    for the Somerset Project.4 He has worked with hundreds of job order contracts, but
    the Somerset Project was his first with the Commission. The contract established a
    fixed price for the completion of the Somerset Project, but it also authorized
    3
    A “job order” is defined by Section 101.03 of the Contract as the “contractor’s authorization
    issued by the Commission, in conjunction with a Purchase Order, to perform all work required to
    complete the Detailed Scope of Work for the amounts in the Price Proposal within the agreed upon
    schedule.” R.R. 54a.
    4
    Barker was employed by Contractor from April 2015 through January 2018.
    3
    supplemental job orders that would add work credits to, or deletions from, the
    contract’s fixed price. 5
    Barker’s contact at the Commission was Robert Kleimenhagen, the
    project manager. At the outset, Kleimenhagen instructed Barker to keep an Excel
    spreadsheet to document extra work Contractor performed on the Somerset Project.
    Rather than address each project change as it arose, Kleimenhagen explained that
    the Commission would review the spreadsheet at the end of construction. Barker
    thought this was unusual for such a large project, but he complied with
    Kleimenhagen’s directive. At the conclusion of the project, Contractor submitted a
    supplemental job order and spreadsheet seeking $150,925.19 for additional work.
    Barker testified that he sent the supplemental job order request via
    email on July 27, 2016, to Gary Madey, the Commission’s construction manager.
    Barker explained that the spreadsheet had to be uploaded using the Commission’s
    collaborative software, known as “Kahua,” and Madey was the person who handled
    this software. Notes of Testimony, 3/12/2018, at 53 (N.T. __); R.R. 388a. Barker
    copied Kleimenhagen on the email to Madey. On August 26, 2016, Kleimenhagen
    responded that he hoped to complete the review by September and requested
    additional information from Barker. Barker did not respond to Kleimenhagen’s
    email.
    On September 21, 2016, Kleimenhagen sent Barker an email with an
    attached spreadsheet.       The email explained that the Commission’s entire
    construction management team had reviewed Barker’s spreadsheet and compared it
    to the project design drawings, specifications, special provisions and on-site
    5
    The Commission describes the job order contract between the Commission and Contractor as an
    “umbrella contract” from which individual “job orders” or “projects” could be awarded.
    Commission Brief at 9.
    4
    construction inspections.    The email concluded that Contractor was owed
    $35,233.05, and not $150,925.19. Contractor was advised to submit a supplemental
    job order for the work items for which the Commission was willing to pay.
    On October 6, 2016, Barker sent Kleimenhagen an email requesting
    further review because Contractor did not accept the amount of $35,233.05. Barker
    did not specifically request, but expected, a meeting.      On October 17, 2016,
    Kleimenhagen responded with an email that reiterated the line-by-line account of
    what the Commission agreed to pay pursuant to the September 21, 2016, email.
    Barker testified that he believed the Commission’s October 17, 2016,
    email was the final determination. He did not believe the September 21, 2016, email
    was a final determination because the job order contract required a “collaborative
    process” whereby the parties would “review and discuss” all supplemental job
    orders. With the October 17, 2016, email, Barker realized the Commission would
    not meet and discuss the supplemental job order at issue.
    On cross-examination, Barker was asked about Contractor’s delay
    damages, which were not included in its July 27, 2016, supplemental job order.
    Barker explained that he was still working on the delay claims at that time. Barker
    acknowledged that the job order contract required prompt notification of any claim
    for delay damages.
    Barker was also questioned about a January 5, 2017, letter from the
    Commission’s counsel to Contractor’s counsel. In that letter the Commission
    expressed its disagreement with Contractor’s assumption that the deadline for filing
    an administrative claim with the Commission was six months after Kleimenhagen’s
    October 17, 2016, email, i.e., April 17, 2017. The letter stated that Kleimenhagen’s
    5
    earlier email of September 21, 2016, was the final determination, and Contractor had
    six months from that date to file a claim, i.e., March 21, 2017.
    Janice Fleming-White, a member of Contractor’s legal department,
    testified. She reviewed the September 21, 2016, email and concluded that it did not
    constitute a final decision. Upon review of the October 17, 2016, email she prepared
    a letter of intent to file a claim, which was sent to Kleimenhagen the next day.
    The Commission presented the testimony of Kleimenhagen, who stated
    that he was the project manager for the Somerset Project, the contract representative
    and the contracting officer. Michael Baker International served as the construction
    manager, and it assigned Madey to inspect the Somerset Project.
    Kleimenhagen confirmed that he instructed Barker to keep a record of
    the work that was deleted or added to the project and to submit all work changes in
    a supplemental job order at the conclusion of the contract. Kleimenhagen’s directive
    did not relate to the notice of delay damages; the contract requires that a claim for
    delay damages be asserted within ten calendar days of the act that caused the delay.
    The contract also required Contractor to file a notice of intent to submit a delay
    damages claim to the contracting officer in writing within ten days of the act or
    omission.
    Kleimenhagen testified that Contractor submitted the supplemental job
    order request on July 27, 2016. On August 24, 2016, Kleimenhagen emailed Barker
    requesting additional documentation to finish the review, but Barker did not respond.
    Kleimenhagen then sent the September 21, 2016, email partially denying the claim.
    Attached to the email was a spreadsheet with a line-by-line analysis of costs the
    Commission accepted or rejected, followed by a notation “pay” or “no pay.” N.T.
    142; R.R. 477a.
    6
    Kleimenhagen noted that Barker’s email of October 6, 2016, did not
    point out any errors in the Commission’s review. It simply expressed disagreement
    and requested a further review. On October 17, 2016, Kleimenhagen responded to
    Barker, stating that the review had been completed, as reported in the Commission’s
    September 21, 2016, email. Contractor then issued a notice of claim on October 18,
    2016.
    On cross-examination, Kleimenhagen was questioned about his status
    as the Commission’s contract representative. Kleimenhagen responded that he was
    assigned this job by his supervisor, but he conceded there was no written
    confirmation of his appointment. Kleimenhagen was then asked about an email
    Madey sent to Barker in 2015 in which Madey identified himself as the contract
    representative. Kleimenhagen explained that he drafted the email for Madey to send,
    but it looked, mistakenly, as if Madey was the author.
    Madey testified regarding his review of the supplemental job order.6
    When Contractor submitted the supplemental job order and spreadsheet, Madey
    prepared his own spreadsheet. He looked at each of the 237 line items submitted and
    compared each with the terms of the contract and the construction plans. If the item
    listed represented additional work requested by the Commission, he wrote “pay” on
    the line. N.T. 212; R.R. 547a. If the item listed was required under the original
    contract, he wrote “no pay.” 
    Id. There were
    items that Contractor had included in
    its proposal but did not perform, which he also listed as “no pay.” Madey stated that
    the spreadsheet was produced by collaboration between Michael Baker, Inc., and the
    6
    Madey was not questioned about the 2015 email wherein he referred to himself as the contract
    representative.
    7
    Commission. The Commission’s construction management team did one review,
    and it was completed by September 21, 2016.
    The Board sustained the Commission’s preliminary objection to its
    jurisdiction. The Board found that Contractor’s claim accrued on September 21,
    2016.    Accordingly, when Contractor filed its administrative claim to the
    Commission on March 27, 2017, the six-month statute of limitations in Section
    1712.1(b) of the Procurement Code had run.
    The Board rejected Contractor’s contention that Kleimenhagen was not
    the contract representative with authority to deny payment on Contractor’s
    supplemental job order. The contract defined the Commission’s “representative” as
    “the authorized representative acting on behalf of the Director of Facilities and
    Energy Management Operations or the Chief Engineer.” R.R. 588a. The contract
    made the “representative” the one to “decide differences concerning the performance
    of the work covered by the contract.” R.R. 598a. Although Madey identified
    himself in an email as the Commission’s “designated representative” on the
    Somerset Project, the Board accepted Kleimenhagen’s testimony that he was the
    actual contract “representative.” This finding was supported by other evidence.
    For example, Contractor sent the supplemental work order to Madey,
    but it was Kleimenhagen who responded. It was Kleimenhagen who advised Barker
    that if Contractor submitted a revised proposal, “I will process the supplemental Job
    Order ASAP.” R.R. 681a. These communications showed that Kleimenhagen was
    the contract “representative,” and at no point did Contractor question
    Kleimenhagen’s authority to so act. Indeed, Contractor sought further review from
    Kleimenhagen, and Contractor accepted his October 17, 2016, email as a final
    determination.
    8
    The Board rejected Contractor’s argument that the September 21, 2016,
    email was not a final determination. The email stated that the Commission had
    “completed the review” of Contractor’s supplemental job order request and that the
    “entire construction management team” had compared the submission with the
    project specifications. The email specifically identified what would not be paid,
    with line-by-line notations, and this constituted a denial. The Board also rejected
    Contractor’s assertion that Kleimenhagen’s October 17, 2016, email implied that
    additional review had been undertaken by the Commission subsequent to September
    21, 2016. Contractor now petitions for this Court’s review.
    Appeal
    On appeal,7 Contractor raises several issues, which we have reordered
    and combined into three for purposes of our review. First, Contractor argues that
    the Board erred in finding that Kleimenhagen was the contract “representative” with
    authority to make a determination on Contractor’s supplemental job order. Second,
    Contractor contends that even if Kleimenhagen could issue a determination, the
    Board erred in holding that Contractor’s claim accrued on September 21, 2016,
    because Contractor reasonably interpreted the email Kleimenhagen sent on that date
    as merely starting the contractually mandated collaborative review process, to which
    the Commission did not adhere. Relatedly, Contractor contends that the Board erred
    in failing to consider actions by the Commission after September 21, 2016,
    indicating that it did not consider Kleimenhagen’s email to be a final determination.
    7
    In reviewing a Board decision this Court determines whether the Board committed an error of
    law, whether the necessary findings were supported by substantial evidence, or whether
    constitutional rights were violated. Wayne Knorr, Inc. v. Department of Transportation, 
    973 A.2d 1061
    (Pa. Cmwlth. 2009). Our standard of review of an order sustaining preliminary objections
    based on an issue of law is de novo, and our scope of review is plenary. Buchart Horn, Inc. v.
    Department of Transportation, 
    1 A.3d 960
    (Pa. Cmwlth. 2010).
    9
    Third, Contractor asserts that the Board erred in finding that any confusion over the
    procedure the Commission followed was cleared up by the January 5, 2017, letter
    from the Commission’s general counsel; Contractor argues that letter was
    misleading.
    Discussion
    I. Kleimenhagen’s Authority
    In its first issue, Contractor argues the Board erred in finding that
    Kleimenhagen was the Commission’s named contract “representative” with
    authority to make a determination on Contractor’s supplemental job order.8
    Contractor cites Kleimenhagen’s testimony that there was nothing in writing
    appointing him as contract representative. The only person who asserted, in writing,
    that he was the Commission’s contract representative was                             Madey, the
    Commission’s construction manager. Because Kleimenhagen lacked the requisite
    authority, Contractor asserts that Kleimenhagen’s September 21, 2016, email to
    Barker was not a final determination that caused Contractor’s claim to accrue.
    8
    Section 101.03 of the parties’ contract defines the “representative” as “[t]he authorized
    representative acting on behalf of the Director of Facilities and Energy Management Operations
    or the Chief Engineer.” R.R. 588a. Pursuant to Section 105.01 of the contract, the named contract
    representative is authorized to:
    [1] determine the appropriateness of each task in the Price Proposal[;]
    [2] determine whether an item of work is a Prepriced Task or a Non-Prepriced Task;
    [3] determine the quantity of the kinds of work and the quality of material for which
    payment will be made under the contract;
    [4] determine the answer to questions in relation to the project and its construction;
    and
    [5] decide differences concerning the performance of the work covered by the
    contract.
    R.R. 598a.
    10
    The Commission responds that Kleimenhagen testified that he was
    appointed the contract representative for the Somerset Project by his director.
    Further, the Commission routinely assigned the project manager to serve as the
    contract representative and the contracting officer. Kleimenhagen testified that
    Contractor was well aware of this practice because it has completed dozens of
    construction projects with the Commission over many years. Kleimenhagen drafted
    the 2015 email that identified the author as the contract representative, and Madey
    sent it to Contractor.    Although it was not clear that the email referred to
    Kleimenhagen as the contract representative, Contractor did not treat Madey as the
    actual contract representative.
    We agree with the Board’s conclusion that Kleimenhagen had authority
    to issue a determination on Contractor’s supplemental job order. Barker emailed the
    supplemental job order to Madey, with a copy to Kleimenhagen, and the responses
    on August 26 and September 21, 2016, came from Kleimenhagen. Barker did not
    testify that he considered the September 21, 2016, email to be a preliminary
    communication because Kleimenhagen had authored it. In fact, Barker testified he
    had no idea who was the contract representative. Barker further testified that he
    considered the October 17, 2016, email, which was also authored by Kleimenhagen,
    to be the Commission’s final decision. This inconsistency cannot be reconciled with
    Contractor’s premise that Kleimenhagen was not authorized to act as the
    Commission’s contract representative.
    Further, the Board credited Kleimenhagen’s testimony that he was the
    contract representative. This testimony is supported by Kleimenhagen’s September
    21, 2016, email to Barker, which states:
    The [Commission] has completed the review of your
    supplemental job order request submitted on July 27, 2016.
    11
    Please find attached an EXCEL spreadsheet which provides an
    explanation for each category/line in the proposal, and our
    position on whether the line item will be paid or not by the
    [Commission]. The entire construction management team [the
    Commission, the construction project manager and inspector,
    and the project architect] thoroughly reviewed your submission
    by comparing it to the project design drawings, specifications,
    special provisions, and on-site inspections during construction.
    Our determination is the acceptable additional work costs
    submitted by [Contractor] is $35,233.05 not $150,925.19.
    R.R. 681a (emphasis added). This email demonstrated Kleimenhagen’s authority to
    speak for the Commission.
    There is no support for Contractor’s claim that Kleimenhagen lacked
    authority. Further, Contractor’s legal department deemed Kleimenhagen’s October
    17, 2016, email to speak for the Commission, thereby triggering Contractor’s right
    to file a notice of claim. In sum, substantial evidence supports the Board’s factual
    finding that Kleimenhagen was the contract representative on the project.
    II. Accrual Date of Contractor’s Claim
    Contractor contends that the Board erred in finding that Contractor’s
    claim accrued on September 21, 2016, because Kleimenhagen’s email of that date
    was not a final determination on Contractor’s supplemental job order. Contractor
    observes that the email did not use terms such as “will not be paid” or “denied.” Nor
    did Kleimenhagen assert in his subsequent email of October 17, 2016, that the claim
    had already been denied. Contractor maintains that it reasonably interpreted the
    September 21, 2016, email as starting the contractually mandated review process,
    which required that a supplemental job order follow the same process for developing
    a new job order. This collaborative process required the parties to “meet and
    discuss” the matter before a final determination was made, and the Commission did
    not satisfy this requirement. Barker requested further review on October 6, 2016,
    12
    because he assumed there would be a meeting prior to a final determination.
    Contractor asserts that the Commission’s actions after September 21, 2016, also
    show that it did not consider Kleimenhagen’s communication of that date to be a
    final determination.
    Our Supreme Couort has addressed the accrual of a claim under the
    Procurement Code.       In Darien Capital Management, Inc. v. Public School
    Employes’ Retirement System, 
    700 A.2d 395
    , 397 (Pa. 1997), the Court stated as
    follows:
    A claim accrues when 1) a claimant is first able to litigate his or
    her claim, e.g., when the amount due under the claim is known
    and the claimant is capable of preparing a concise and specific
    written statement detailing the injury, and 2) the claimant is
    affirmatively notified that he or she will not be paid by the
    Commonwealth.
    Both prongs must be satisfied for a claim to accrue and only then will the statute of
    limitations commence. Ferguson Electric Company, Inc. v. Department of General
    Services, 
    3 A.3d 681
    , 686 (Pa. Cmwlth. 2010). A refusal to pay need not contain the
    words “will not be paid” or “denied.” 
    Id. Nor is
    it mandatory that the refusal state
    that it is a “final decision” or advise the recipient of the “right to appeal.” 
    Id. A claim
    accrues when the refusal communicates that payment will not be made. 
    Id. The September
    21, 2016, email from Kleimenhagen to Barker states, in
    relevant part, as follows:
    The [Commission] has completed the review of your
    supplemental job order request submitted on July 27, 2016.
    Please find attached an EXCEL spreadsheet which provides an
    explanation for each category/line in the proposal, and our
    position on whether the line item will be paid or not by the
    [Commission]. The entire construction management team [the
    Commission, the construction project manager and inspector,
    13
    and the project architect] thoroughly reviewed your submission
    by comparing it to the project design drawings, specifications,
    special provisions, and on-site inspections during construction.
    Our determination is the acceptable additional work costs
    submitted by [Contractor] is $35,233.05 not $150,925.19.
    I have created JOC Project 02-2015-G-009.01 in the E-Gordian
    system, and respectfully request that you submit a revised
    proposal for the “pay” items listed in the attached EXCEL
    spreadsheet at your earliest convenience. Once I receive the
    proposal in E-Gordian, I will process the supplemental Job Order
    ASAP.
    R.R. 681a. Contractor asserts that this language did not trigger the accrual of its
    claim against the Commission. We disagree.
    Kleimenhagen’s email specifies the total amount of the supplemental
    work order that the Commission would pay. A spreadsheet was attached, listing the
    237 line items Contractor sought payment for and the cost of each item. A notation
    is made after every single item stating “pay” or “no pay.” A reason is listed for each
    item for which payment was denied. The email states the review was “completed,”
    and “our determination is the acceptable additional work costs submitted by
    [Contractor] is $35,233.05 not $150,925.19.” R.R. 681. In sum, the September 21,
    2016, email meets both prongs of the standard set forth in Darien Capital
    Management, i.e., Contractor was able to state the amount due under its claim and
    had been notified that it would not be paid that amount by the Commission.
    Notwithstanding the unequivocal denial communicated by the
    September 21, 2016, email, Contractor maintains that it reasonably interpreted it to
    initiate the contractually mandated review process, which requires a supplemental
    job order to follow the same process for developing a new job order.             This
    collaborative process required the parties to “meet and discuss” the matter before a
    14
    final determination was made. The Commission responds that the plain language of
    the contract does not support Contractor’s argument. The collaborative process set
    forth in the contract relates to the development of a job order. It makes no sense to
    follow this procedure for work already completed. The Board agreed, as do we.
    Section 109.03(a) of the contract states that a “supplemental job order”
    will be developed in accordance with the “procedures for developing a job order.”
    R.R. 632a. More specifically, Section 109.03(a) states:
    Work specified in Sections 104.02 [regarding alterations to
    detailed scope of work] and 104.03 [deleted from contract] will
    be paid, if authorized in writing by the Representative, as a
    Supplemental Job Order developed in accordance with the
    procedures for developing a Job Order set forth in the Special
    Provisions. Compensation will be limited to the work authorized
    in writing and actually performed. Work performed before
    written authorization will be at the Contractor’s risk.
    A Supplemental Job Order identifying the work to be done and
    the price to be paid therefore will be processed before or during
    the performance of the work. To avoid interrupting the project,
    written authorization to perform the work [is permissible from
    specified project personnel].
    
    Id. (emphasis added).
    The “Procedure for Developing a Job Order” is set forth in
    Special Provision 9.00 of the Contract. It provides:
    As the need exists, the Commission will notify the contractor of
    a project. The Commission and the contractor will review the
    project and discuss, at a minimum:
    a. the general scope of the work
    b. alternatives for performing the work and value
    engineering;
    c. access to the site and protocol for admission;
    15
    d. hours of operation;
    e. staging area;
    f. requirements for professional services, sketches,
    drawings, and specifications;
    g. construction schedule;
    h. the presence of hazardous materials;
    i. date on which the Price Proposal is due.
    R.R. 571a-72a. Once this initial process is completed, the contractor prepares a price
    proposal, which the Commission reviews to determine its reasonableness. The
    Commission is authorized to accept or reject the price proposal for any reason.
    The contractual procedure for developing a job order requires a
    discussion to determine what work will be done, how it will be done, when it will be
    done and what it will cost. This presupposes that the work has not yet been
    completed. Similarly, Section 109.03(a) states that the supplemental job order will
    be “processed before or during the performance of the work.” R.R. 632a. These
    requirements cannot be applied to the type of supplemental job order at issue here,
    i.e., one for work that has already been completed.
    The Board rejected Contractor’s claim that a supplemental job order
    was to be negotiated in accordance with the procedures for developing a job order.
    The Board explained as follows:
    Based on the Board’s reading of the [contract], as well as our
    years of experience in resolving contract claims, a supplemental
    job order, like a change order (which was to accompany same
    here per the General Provisions) is the process used when both
    contractor and owner/agency agree the work is beyond the scope
    of the original design/specifications and determine that they can
    negotiate a price for the new work and add it to the contract
    16
    before the new work is done without delaying the project. It is
    not the process prescribed or utilized when the parties do not
    agree as to whether the disputed work is or is not within the
    original scope of the contract or have not determined to resolve
    the issue before the alleged extra work occurs. Instead the
    process prescribed here by [] Kleimenhagen (i.e. continue with
    the work, keep track of what the contractor believes to be extra
    work, and seek resolution at the end of the project) is the more
    typical method for resolution of such disputed tasks as we have
    here in this case.
    Based on the plain language of the [c]ontract, particularly that of
    Section 109.03 of the General Provisions, to which [Contractor]
    wishes strictly to hold the [Commission], we conclude that,
    strictly speaking, this provision is not applicable to a claim for
    extra work made after the work was performed and done prior
    to written authorization. Therefore, to the extent [Contractor]
    claims the [Commission’s] denial of its request for additional
    payment was ineffective for failure to observe the supplemental
    job order process, we disagree.
    Board Adjudication at 33 (underlining in original) (emphasis added).
    We agree with the Board’s analysis. Where uncertainty existed about
    whether certain work was within the scope of the contract, Contractor was directed
    to do the work and then submit an invoice. Contractor followed this procedure and
    received the Commission’s agreement to pay the invoice for supplemental work, in
    part, on September 21, 2016. Notably, in his October 6, 2016, response, Barker did
    not request a meeting or ask when one would be scheduled. Instead, Barker asked
    Kleimenhagen to “further review[]” the determination and “contact our office if you
    have any questions.” R.R. 716a.9
    9
    In full, Barker’s email response to Kleimenhagen stated:
    Attached is our response to the [Commission’s] offer for a Supplemental Work
    Order.
    17
    Contractor argues that the Commission’s actions after September 21,
    2016, signaled that the Commission did not make a final determination on that date.
    Contractor notes that Kleimenhagen took more than a week to respond to Barker’s
    October 6, 2016, email, which implies that another review was conducted.
    Additionally, when Contractor filed its claim, the Commission held a hearing prior
    to dismissing it as untimely, which would not have been necessary unless it was
    uncertain about the meaning of the September 21, 2016, email. Contractor argues
    that the Board erred in failing to consider these points in determining the date that
    Contractor’s claim accrued.
    Contractor’s      argument      lacks    merit.       The    Board      credited
    Kleimenhagen’s testimony that he was at a conference in California when Barker
    sent the October 6, 2016, email, so he did not review it until October 11, 2016.
    Because of other work, he was not able to respond until October 17, 2016. Simply,
    Contractor’s belief that the lapse of time between the Commission’s two emails
    shows that a second review occurred lacks a foundation in the record. Likewise,
    nothing can be read into the Commission’s holding a hearing on Contractor’s claim
    before it dismissed it as untimely. We agree with the Board on this point.
    III. January 5, 2017, Letter from Commission’s Counsel
    Finally, Contractor challenges the Board’s conclusion that the
    Commission cleared up any confusion over the date Contractor’s claim accrued with
    [Attachment:] [Contractor] is in receipt of your email dated 9/21/16 with
    revisions/acceptance of items on our … Submission Breakdown of additional work
    performed on the above referenced project. We disagree with your proposed
    approval of $35,233.05 out of $150,925.19 of additional work which was directed
    by the [Commission] and performed by our firm. We respectfully request that these
    changes be further reviewed and paid for.
    Please feel free to contact our office if you have any questions. Thank you.
    R.R. 716a, 722a (emphasis in attachment omitted).
    18
    a letter from its general counsel to Contractor’s counsel on January 5, 2017. More
    specifically, the Board concluded that the letter of Commission’s counsel
    cleared up any possible confusion engendered by the loose usage
    of the “supplemental job order” term and indicated that
    [Contractor’s] request for payment was finally denied on the
    September 21, 2016 date, at the latest.
    Board Adjudication at 35.
    Contractor argues that the letter from the Commission’s counsel did not
    state that the Commission made and communicated its final determination through
    Kleimenhagen’s email to Barker on September 21, 2016. Further, the letter was
    confusing because it posited that Contractor’s claim could have accrued on several
    different dates. The Commission responds that the letter expressly disagreed with
    Contractor’s suggestion that it had until April 17, 2017, to file a claim.
    To begin, counsel’s letter, sent to Contractor’s counsel, stated that the
    Commission
    disagrees with [Contractor’s] position as to the present
    procedural posture of its Claim. Accordingly, we respectfully
    disagree with your assumption that [Contractor’s] Claim is to be
    filed on or before April 17, 2017.
    R.R. 797a. The letter then went on to address several matters, such as the lack of
    specificity in Contractor’s notice of claim and Contractor’s assertion that
    Kleimenhagen’s October 17, 2016, email represented the Commission’s final
    determination.   The Commission’s counsel reasoned that Barker’s request for
    “further review” in his email of October 6, 2016, demonstrated that Contractor
    understood that its request for payment had been denied on September 21, 2016.
    The letter challenged Contractor’s failure to file a notice of intent to file a claim
    19
    within ten days of the September 21, 2016, email and questioned why Contractor did
    not “suggest that its claim is due by March 21, 2017, six (6) months from that earlier
    and identical determination.” R.R. 798a.
    We reject Contractor’s characterization of the letter as not stating that
    “the Commission believed that [Contractor’s] claim accrued as of September 21,
    2016.” Contractor Brief at 36. The letter acknowledged Contractor’s belief that the
    October 17, 2016, email constituted the denial of the claim and then explained why
    that belief was incorrect. The letter stated that the September 21, 2016, email denied
    Contractor’s work costs and established the administrative claim was due by March
    21, 2017, i.e., six months from the September 21, 2016 email. There was nothing
    confusing here. The Commission expressed its position that Contractor’s claim
    accrued on September 21, 2016. Contractor chose to ignore this warning, to its own
    detriment.10
    Conclusion
    For all the above reasons, we affirm the order of the Board.11
    _____________________________________
    MARY HANNAH LEAVITT, President Judge
    Judge Fizzano Cannon did not participate in the decision in this case.
    10
    Of course, the extra-contractual statement by the Commission’s counsel is not dispositive of
    what the job order contract required of the parties.
    11
    Judge Fizzano Cannon did not participate in the decision in this case.
    20
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Lobar Associates, Inc.,                 :
    Petitioner           :
    :
    v.                          :   No. 1038 CD 2018
    :
    Pennsylvania Turnpike Commission,       :
    Respondent             :
    ORDER
    AND NOW, this 1st day of August, 2019 the order of the Board of
    Claims, dated June 28, 2018, in the above-captioned matter is hereby AFFIRMED.
    _____________________________________
    MARY HANNAH LEAVITT, President Judge
    

Document Info

Docket Number: 1038 C.D. 2018

Judges: Leavitt, President Judge

Filed Date: 8/1/2019

Precedential Status: Precedential

Modified Date: 8/1/2019