Iron Hill Co. v. Cairone Construction Co. ( 2022 )


Menu:
  • J-S36016-21
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
    IRON HILL COMPANY,                         :   IN THE SUPERIOR COURT OF
    :        PENNSYLVANIA
    Appellant               :
    :
    v.                            :
    :
    CAIRONE CONSTRUCTION CO.                   :
    :
    Appellee                :       No. 513 EDA 2021
    Appeal from the Orders October 16, 2020
    In the Court of Common Pleas of Philadelphia County
    Civil Division at No(s): Case ID 200300428
    BEFORE:      LAZARUS, J., KING, J., and COLINS, J.*
    MEMORANDUM BY KING, J.:                             FILED FEBRUARY 23, 2022
    Appellant, Iron Hill Company, appeals from the orders entered in the
    Philadelphia County Court of Common Pleas, which denied its petition to
    vacate    the    arbitration award entered in favor        of Appellee, Cairone
    Construction Company, and granted Appellee’s petition to confirm the
    arbitration award in its favor. We affirm.
    The trial court opinion set forth the relevant facts and procedural history
    of this case as follows:
    Appellant is a corporation organized under the laws of the
    Commonwealth of Pennsylvania with its principal place of
    business in Norristown, Pennsylvania. Appellee is a limited
    liability company organized under the laws of the
    Commonwealth of Pennsylvania with its principal place of
    business in Jenkintown, Pennsylvania.        The underlying
    matter arises out of an appeal of an arbitration award.
    ____________________________________________
    *   Retired Senior Judge assigned to the Superior Court.
    J-S36016-21
    In 2016, Appellant contracted Appellee to construct
    trampoline pits for an indoor park in Hackensack, New
    Jersey.[1] The project commenced in December 2016 and,
    through the course of the project, numerous revisions were
    made to the original plans for the trampoline pits. Based
    upon these changes[,] Appellee submitted Change Order
    Requests to Appellant. The Change Order Requests outlined
    the additional work performed as well as the associated
    additional cost. Appellee continued working on the project
    and performed on the project.
    On or about August 24, 2018, Appellee submitted a Demand
    for Arbitration to the American Arbitration Association
    (“AAA”).[2] Subsequently, Appellant filed a Response and
    ____________________________________________
    1 Appellant was awarded the contract for construction of the trampoline park
    and Appellant awarded the subcontract to Appellee to build the trampoline
    pits.
    2 Originally, Appellee had sued Appellant in New Jersey. After Appellant
    objected on the basis of the arbitration clause and the case was dismissed,
    Appellee initiated arbitration proceedings. The arbitration clause contained in
    the parties’ agreement states:
    Dispute Resolution
    Any controversy or claim arising out of or relating to this
    contract, [or] the breach thereof, shall be settled by
    arbitration in accordance with the Construction Industry
    Arbitration Rules of the American Arbitration Association,
    and judgment upon the [award] rendered by the
    arbitrator(s) may be entered in any court having jurisdiction
    thereof. The parties specifically waive any rights under
    state law to move to set the arbitration decision aside
    and/or appeal, thus the arbitration decision shall be final
    and binding. Any attorney’s fees incurred by the contractor
    in enforcement of arbitration under this contract shall be
    recoverable by the general contractor and will be paid by
    the subcontractor. Subcontractor also agrees to be a party
    to any arbitration between or among the general contractor,
    owner, and/or other subcontractors if named as a party by
    (Footnote Continued Next Page)
    -2-
    J-S36016-21
    Counterclaim, claiming a set-off for settling Subcontractor
    Liens for two (2) of Appellee’s subcontractors. On June 20,
    and June 21, 2019, a hearing was conducted before AAA
    Arbitrator Mary Jo Gilsdorf, Esquire, in Philadelphia,
    Pennsylvania.
    On August 9, 2019, the Arbitrator: (1) found in favor of
    Appellee and against Appellant, in regard to the unpaid
    contract balance and the unsigned change orders; and, (2)
    found in favor of Appellant and against Appellee, in regard
    to Appellant’s counterclaim for settling the subcontractor
    liens. On August 9, 2019, after accounting for the set-off,
    the Arbitrator awarded Appellee $88,958.48 (the “2019
    Arbitration Award”). After the inclusion of administrative
    fees, the 2019 Arbitration Award total accrued to
    $98,623.48, plus interest at 6.3 percent from August 24,
    2018, until the date of payment.
    On September 5, 2019, Appellant filed a Petition to Vacate
    the 2019 Arbitration Award in the Court of Common Pleas of
    Montgomery County, Pennsylvania, under Docket Number
    19-21802 (First Petition to Vacate). On February 6, 2020,
    the First Petition to Vacate was denied by the Honorable
    Steven C. Tolliver, Senior.[3] Appellant did not file a motion
    ____________________________________________
    the general contractor, and subcontractor shall be bound by
    such arbitration decision. Both parties agree that this
    subcontract shall be governed by the laws of the State of
    Pennsylvania.
    For any claim subject to, but not resolved by mediation, the
    method of binding dispute resolution shall be Litigation in a
    court of competent jurisdiction.
    (Contract Between Contractor and Subcontractor, 12/15/16, at 3-4; R.R. at
    35a-36a).
    3 In its order, the court stated that Appellant’s petition to vacate was denied
    and dismissed because the parties had arbitrated their dispute in Philadelphia
    County. In a footnote to the order, the court stated: “Pursuant to 42 Pa.C.S.A.
    § 7321.28, [Appellant] may move for judicial relief in the court of the county
    where the arbitration was held.” (Order of Montgomery County Court of
    (Footnote Continued Next Page)
    -3-
    J-S36016-21
    for reconsideration or an appeal within thirty (30) days of
    the date of the entry of the order denying the First Petition
    to Vacate.
    On March 5, 2020, Appellant filed a second Petition to
    Vacate the 2019 Award in the Court of Common Pleas of
    Philadelphia County, Pennsylvania (Second Petition to
    Vacate). On [May 4], 2020, Appellee filed a Petition to
    confirm the 2019 Award in Philadelphia Common Pleas
    Court. On October 13, 2020, oral argument was held
    regarding Appellant’s Second Petition to Vacate and
    Appellee’s Petition to Confirm the 2019 Award. On October
    16, 2020, [by separate orders,] the trial court granted
    Appellee’s Petition to Confirm and denied Appellant’s Second
    Petition to Vacate.
    On November 10, 2020, Appellant timely filed a Notice of
    Appeal of both this court’s October 1[6], 2020, Orders to
    the Commonwealth Court of Pennsylvania (“Commonwealth
    Court”), which appeal [the] Commonwealth Court docketed
    at 1160 CD 2020. On November 16, 2020, this court issued
    a [Rule] 1925(b) Order seeking Appellant’s Statement of
    [Errors] Complained Of within twenty-one (21) days. On
    December 7, 2020, Appellant timely filed the required [Rule]
    1925(b) Statement.        On February 19, 2021, the
    Commonwealth Court transferred the instant appeal to the
    Superior Court of Pennsylvania (“Superior Court”), which
    appeal the Superior Court docketed at 513 EDA 2021.
    (Trial Court Opinion, filed March 29, 2021, at 1-3) (internal citations omitted).
    Appellant raises the following two issues for our review:
    Did the trial court err in finding that Appellant waived the
    right to seek judicial review of the underlying arbitration
    award for irregularities in the proceedings that resulted in
    the rendition of an unjust, inequitable, or unconscionable
    award?
    ____________________________________________
    Common Pleas, 2/6/20, at 1 n.1; R.R. at 157a). See also 42 Pa.C.S.A. §
    7321.28 (stating motion relating to application for judicial relief must be made
    in court of county in which arbitration hearing was held).
    -4-
    J-S36016-21
    Did the trial court err in denying Appellant’s Petition to
    Vacate Arbitration Award and granting Appellee’s Petition to
    Confirm Arbitration Award, where irregularities in the
    underlying arbitration proceedings resulted in the rendition
    of an unjust, inequitable, or unconscionable award?
    (Appellant’s Brief at 4).
    As a preliminary matter, Appellee argues the Philadelphia County Court
    of Common Pleas trial court had no jurisdiction to rule on the merits of
    Appellant’s second petition to vacate, where Appellant filed the petition more
    than 30 days after entry of the arbitration award based on Appellant’s initial
    improper filing of the first petition to vacate in Montgomery County.      To
    resolve this issue, we must first decide which arbitration principles apply in
    this case. This Court has explained:
    Chapter 73 of the Pennsylvania Judicial Code governs
    statutory, common law and judicial arbitration. Section
    7301-7320 of Subchapter A apply to statutory arbitration
    proceedings and are known collectively as the Pennsylvania
    Uniform Arbitration Act (“UAA”). Section 7341 and 7342 of
    Subchapter B apply to common law arbitration
    proceedings.[4] Whether an arbitration agreement is subject
    to the UAA (Sections 7301-7320 of Subchapter A) or
    common law (Sections 7341-7342 of Subchapter B)
    arbitration principles depends on whether the agreement is
    ____________________________________________
    4 On June 28, 2018, the General Assembly approved legislative amendments
    creating revised statutory arbitration standards under Pennsylvania law,
    effective July 1, 2019. See 2018 Pa. Legis. Serv. Act 2018-55 (H.B. 1644);
    see also 42 Pa.C.S.A. §§ 7321.1-7321.31. Section 7342 was also amended
    to incorporate some of these revised standards in the legislative framework
    applicable to common law arbitrations in Pennsylvania. See 42 Pa.C.S.A. §
    7342(a). Here, the parties entered the contract containing the arbitration
    clause at issue in 2016 and the arbitration hearings took place in June 2019,
    before the amendments took effect on July 1, 2019. Thus, we will apply the
    law in place before the amendments took effect.
    -5-
    J-S36016-21
    in writing and expressly provides for arbitration under the
    UAA.     Absent an express statement in the arbitration
    agreement, or a subsequent agreement by the parties which
    calls for the application of the UAA statutory provisions in
    Subchapter A, an agreement to arbitrate is conclusively
    presumed to be at common law and subject to the
    provisions of Subchapter B.
    Sage v Greenspan, 
    765 A.2d 1139
    , 1141 (Pa.Super. 2000), appeal denied,
    
    566 Pa. 684
    , 
    784 A.2d 119
     (2001) (internal citations omitted). In other words,
    a written agreement to arbitrate which fails to specify the application of either
    common law or statutory rules is properly considered as common law
    arbitration.   Snyder v. Cress, 
    791 A.2d 1198
    , 1200 (Pa.Super. 2002).
    Further, “[a]n agreement to arbitrate in accordance with the Rules of the AAA
    is an agreement pursuant to common law arbitration.” Midomo Co., Inc. v.
    Presbyterian Housing Development Co., 
    739 A.2d 180
    , 183 (Pa.Super.
    1999). See also Bucks Orthopaedic Surgery Assoc., P.C. v. Ruth, 
    925 A.2d 868
    , 871 (Pa.Super. 2007) (stating same).
    Here, the parties’ arbitration clause states, in relevant part: “Any
    controversy or claim arising out of or relating to this contract, [or] the breach
    thereof, shall be settled by arbitration in accordance with the Construction
    Industry Arbitration Rules of the American Arbitration Association[.]”
    (Contract Between Contractor and Subcontractor, 12/15/16, at 3; R.R. at
    35a). As the parties did not specify for the application of the UAA statutory
    provisions in Subchapter A, or another similar statute, the agreement to
    -6-
    J-S36016-21
    arbitrate is presumed to be at common law.5 See Snyder, 
    supra;
     Sage,
    
    supra.
         The parties’ reference to be bound by the Rules of AAA further
    demonstrates that common law arbitration principles apply in this case. See
    Bucks, 
    supra;
     Midomo, 
    supra.
    The statutes governing common law arbitration before the amendments
    took effect stated:
    § 7341. Common law arbitration
    The award of an arbitrator in a nonjudicial arbitration which
    is not subject to Subchapter A (relating to statutory
    arbitration) or a similar statute regulating nonjudicial
    arbitration proceedings is binding and may not be vacated
    or modified unless it is clearly shown that a party was denied
    a hearing or that fraud, misconduct, corruption or other
    irregularity caused the rendition of an unjust, inequitable or
    unconscionable award.
    42 Pa.C.S.A. § 7341 (effective until June 30, 2019).6
    § 7342. Procedure
    (a) General rule.—The following provisions of
    Subchapter A (relating to statutory arbitration) shall be
    applicable to arbitration conducted pursuant to this
    subchapter:
    Section 7303 (relating to validity of agreement to arbitrate).
    Section 7304 (relating to court proceedings to compel or
    stay arbitration).
    ____________________________________________
    5 Based on the law cited in the briefs on appeal, the parties appear to agree
    that common law arbitration principles apply.
    6 We note that even if the amended versions of the statutes at issue applied,
    the statutes relevant to this appeal were substantially similar before and after
    the amendments.
    -7-
    J-S36016-21
    Section 7305 (relating to appointment of arbitrators by
    court).
    Section 7309 (relating to witnesses, subpoenas, oaths and
    depositions).
    Section 7317 (relating to form and service of applications to
    court).
    Section 7318 (relating to court and jurisdiction).
    Section  7319        (relating    to    venue     of   court
    proceedings).
    Section 7320 (relating to appeals from court orders), except
    subsection (a)(4).
    (b) Confirmation and judgment.—On application of
    a party made more than 30 days after an award is made by
    an arbitrator under section 7341 (relating to common law
    arbitration), the court shall enter an order confirming the
    award and shall enter a judgment or decree in conformity
    with the order. Section 7302(d)(2) (relating to special
    application) shall not be applicable to proceedings under this
    subchapter.
    42 Pa.C.S.A. § 7342 (effective until June 30, 2019) (emphasis added). “This
    Court has consistently interpreted section 7342(b) to require that any
    challenge to the arbitration award be made in an appeal to the Court of
    Common Pleas, by filing a petition to vacate or modify the arbitration award
    within 30 days of the date of the award.” U.S. Claims, Inc. v. Dougherty,
    
    914 A.2d 874
    , 877 (Pa.Super. 2006), appeal denied, 
    593 Pa. 729
    , 
    928 A.2d 1291
     (2007). “A party must raise alleged errors in the arbitration process in
    a timely petition to vacate or modify the arbitration award or the claims are
    forever waived.” 
    Id.
    -8-
    J-S36016-21
    Section 7319 of the Statutory Arbitration Act, applicable in common law
    arbitration proceedings pursuant to Section 7342(a), provides:
    § 7319. Venue of court proceedings
    Except as otherwise prescribed by general rules:
    (1) An initial application to a court under this
    subchapter shall be made to the court of the county in which
    the agreement prescribes that the arbitration hearing shall
    be held or, if the hearing has been held, in the county
    in which the hearing was held.
    (2) If an application to a court cannot be made under
    paragraph (1) the application shall be made to the court in
    the county where the adverse party resides or has a place
    of business or, if he has no residence or place of business in
    this Commonwealth, to the court of any county.
    (3) All subsequent applications to a court shall be
    made to the court hearing the initial application unless that
    court otherwise directs.
    42 Pa.C.S.A. § 7319 (emphasis added).
    In Mulnix v. Toll Brothers, Inc., No. 3248 EDA 2018, 
    2020 WL 7353363
     (Pa.Super. Dec. 15, 2020) (unpublished memorandum),7 this Court
    considered a procedural posture similar to this case. There, Toll Brothers filed
    a petition to vacate a final arbitration award in the Bucks County Court of
    Common Pleas, even though the arbitration hearings took place in
    Philadelphia.     The appellees subsequently filed a petition to confirm the
    arbitration award in the Philadelphia County Court of Common Pleas.         The
    ____________________________________________
    7 We may rely on unpublished cases from this Court filed after May 1, 2019
    for persuasive value. See Pa.R.A.P. 126(b).
    -9-
    J-S36016-21
    Philadelphia trial court granted the appellees’ petition to confirm, and Toll
    Brothers appealed.
    On appeal, the appellees claimed, inter alia, that Toll Brothers’ petition
    to vacate should be treated as a legal nullity because it was not filed in the
    proper venue, i.e., the Philadelphia County Court of Common Pleas. This Court
    acknowledged that “the proper venue for Toll Brothers’ petition to vacate is
    indisputably situated in Philadelphia County, which was the location of the
    arbitration hearings in the instant case.” Id. at *4. Nevertheless, this Court
    explained:
    With respect to Toll Brothers’ petition to vacate that was
    filed in an incorrect venue, Pennsylvania law provides a
    straightforward solution to such erroneous submissions:
    If an appeal or other matter is taken to or brought
    in a court … of this Commonwealth which does not
    have jurisdiction of the appeal or other matter, the
    court … shall not quash such appeal or dismiss the
    matter, but shall transfer the record thereof to the
    proper tribunal of this Commonwealth, where the
    appeal or other matter shall be treated as if
    originally filed in the transferee tribunal on the
    date when the appeal or other matter was first
    filed …
    42 Pa.C.S. § 5103(a) (emphasis added).
    Instantly, there is no dispute that Toll Brothers’ petition to
    vacate was filed within thirty days of the entry of a final
    award by the arbitrator.       Pursuant to the imperative
    language of § 5103(a) quoted above, the petition to vacate
    should have been transferred to the Philadelphia County
    Court of Common Pleas and, critically, treated as if it had
    been timely filed.
    *     *      *
    - 10 -
    J-S36016-21
    … The mere fact that Toll Brothers’ petition was filed in the
    wrong venue does not render it a legal nullity. See, e.g.,
    Commonwealth v. Gross, [
    627 Pa. 383
    , 396, 
    101 A.3d 28
    , 36 (2014)] (“As venue is predominantly a procedural
    matter, and pertains to the locality most convenient to the
    proper disposition of a matter, dismissal is disproportionate
    and unjust where a court merely finds another judicial
    district provides a more appropriate forum.” (internal
    citations and quotation marks omitted)).
    Mulnix, supra at *4-*5 (some internal citations omitted).
    Instantly, the parties arbitrated their dispute in Philadelphia County.
    The arbitrator entered the award in favor of Appellee on August 9, 2019.
    Within 30 days, Appellant filed the first petition to vacate in Montgomery
    County on September 5, 2019.         During the proceedings in Montgomery
    County, Appellee objected on the basis of improper venue.           The record
    suggests the issue of improper venue was also discussed at a hearing before
    the Montgomery County trial court on January 22, 2020.          Thereafter, on
    January 24, 2020, Appellant filed a petition to transfer the petition to vacate
    from Montgomery County to Philadelphia County.
    The Montgomery County trial court did not rule on the transfer petition;
    instead, on February 6, 2020, the Montgomery County trial court denied and
    dismissed the petition to vacate because Appellant had filed the petition in the
    improper venue. In a footnote to its order, the court stated: “Pursuant to 42
    Pa.C.S.A. § 7321.28, [Appellant] may move for judicial relief in the court of
    - 11 -
    J-S36016-21
    the county where the arbitration was held.”8 (Order of Montgomery County
    Court of Common Pleas, 2/6/20, at 1 n.1; R.R. at 157a). Within 30 days of
    that order, on March 5, 2020, Appellant filed the instant petition to vacate in
    Philadelphia County.
    Under Section 5103(a), the Montgomery County trial court should have
    granted Appellant’s petition to transfer and transferred the first petition to
    vacate to the Philadelphia County Court of Common Pleas, where it would
    have been considered as timely filed. See 42 Pa.C.S.A. § 5103(a); Mulnix,
    supra. Based on the language in the footnote of the Montgomery County trial
    court’s order, Appellant reasonably filed a second petition to vacate in
    Philadelphia County within thirty days of that order.                Under these
    circumstances, we decline to construe Appellant’s current petition to vacate
    as a legal nullity, and we will reach the merits of the petition to vacate filed in
    Philadelphia County.9
    ____________________________________________
    8 The Montgomery County trial court cited to Section 7321.28, which is a post-
    amendment provision. Similar to Section 7319, Section 7321.28 requires that
    a motion relating to an application for judicial relief be made in the court of
    the county in which the arbitration hearing was held. See 42 Pa.C.S.A. §
    7321.28. Thus, under the pre or post-amendment statute, the law directed
    Appellant to file the petition to vacate in Philadelphia County, where the
    arbitration proceedings were held.
    9 Appellee has filed a petition to strike in this Court based on Appellant’s failure
    to ensure that all of the pertinent proceedings that took place in Montgomery
    County are part of the certified record in this appeal. Alternatively, Appellee
    asks this Court to remand so that Appellant can supplement the record with
    those filings. Our review of the record confirms that most of the filings that
    (Footnote Continued Next Page)
    - 12 -
    J-S36016-21
    In its issues combined, Appellant acknowledges that the arbitration
    clause contained in the parties’ contract stated that the parties would be
    bound by the arbitrator’s decision, where the contract states: “The parties
    specifically waive any rights under state law to move to set the arbitration
    decision aside and/or appeal, thus the arbitration decision shall be final and
    binding.”    (Appellant’s Brief at 13) (citing R.R. 35a).            Appellant argues,
    however, that it is not precluded from challenging irregularities in the
    arbitration process, which Appellant insists resulted in the rendition of an
    “unfair, inequitable, or unconscionable award.”             (Appellant’s Brief at 12).
    Appellant claims the arbitrator violated the AAA’s Construction Industry
    Arbitration Rules in various ways including, inter alia, the failure to make
    findings of fact and conclusions of law; the failure to permit Appellant to
    respond to Appellee’s post-hearing submission following arbitration; and the
    failure to apply Pennsylvania law to the proceedings.
    Specifically,   regarding     the    arbitrator’s   alleged   failure   to   apply
    Pennsylvania law to the proceedings, Appellant argues that the arbitrator
    applied her own “notion” of “construction law” by directing the parties to brief
    the applicability of the “Leading Edge Doctrine,” when no such doctrine exists
    ____________________________________________
    took place in Montgomery County are attached as exhibits to various filings in
    the certified record before us. Although the transcript of the January 22, 2020
    hearing in Montgomery County is not part of the record, the court’s order
    denying and dismissing the petition to vacate makes clear the court did so on
    procedural grounds based on improper venue. Because our review of the
    record is not impaired here, we deny Appellee’s application to strike.
    - 13 -
    J-S36016-21
    in Pennsylvania.     Appellant concedes that the arbitrator subsequently
    amended her request once the parties informed her that they were unaware
    of the “Leading Edge Doctrine,” and she clarified that she meant she wanted
    the parties to “brief the effect of verbal directions in the field without written
    change orders—even if there is language in the contract stating that all change
    orders must be in writing.” (Id. at 17) (citing R.R. at 72a). Appellant submits
    that the arbitrator’s amended direction demonstrates an ignorance of
    Pennsylvania law, which requires that when the words of a written contract
    are plain and unambiguous, the intent of the parties is to be ascertained from
    the plain language of the contract and courts are not permitted to alter the
    meaning of the contract under the guise of contractual interpretation.
    Appellant further complains that the arbitrator’s failure to make findings
    of fact and conclusions of law is particularly problematic where there is no
    transcript of the arbitration proceeding. Under these circumstances, Appellant
    maintains “one can only reasonably conclude that the arbitrator rendered her
    decision based on neither the facts nor on Pennsylvania law, but merely on
    her personal predilections and unfounded ‘notions’ of ‘construction law.’”
    (Appellant’s Brief at 18-19).    Appellant insists the arbitrator impermissibly
    exceeded the scope of her authority under the arbitration agreement, which
    required the arbitrator to apply Pennsylvania law, by applying her personal
    “notion” of non-state-specific “construction law.” Appellant concludes it did
    not waive judicial review of these types of procedural irregularities in the
    - 14 -
    J-S36016-21
    proceedings, and this Court should reverse the orders denying its petition to
    vacate and granting Appellee’s petition to confirm, or vacate and remand for
    further proceedings. We disagree.
    Our standard and scope of review in this case are as follows:
    Judicial review of a common law arbitration award is
    severely limited as otherwise arbitration would be an
    unnecessary stage of litigation, causing only delay and
    expense without settling the dispute. The arbitrators are
    the final judges of both law and fact, and an arbitration
    award is not subject to a reversal for a mistake of either.
    Neither we nor the trial court may retry the issues addressed
    in arbitration or review the tribunal’s disposition of the
    merits of the case. Rather, we must confine our review to
    whether the appellant was deprived of a hearing or whether
    fraud, misconduct, corruption or other irregularity tainted
    the award. The appellant bears the burden to establish both
    the underlying irregularity and the resulting inequity by
    clear, precise, and indubitable evidence. In this context,
    irregularity refers to the process employed in reaching the
    result of the arbitration, not to the result itself.
    Civan v. Windermere Farms, Inc., 
    180 A.3d 489
    , 493 (Pa.Super. 2018)
    (quoting U.S. Spaces, Inc. v. Berkshire Hathaway Home Servs., Fox &
    Roach, 
    165 A.3d 931
    , 934 (Pa.Super. 2017)).            “[A] trial court order
    confirming a common law arbitration award will be reversed only for an abuse
    of discretion or an error of law.” Gargano v. Terminix Intern. Co., L.P.,
    
    784 A.2d 188
    , 193 (Pa.Super. 2001).
    “A cognizable irregularity may appear in the conduct of either the
    arbitrators or the parties.   [T]he phrase ‘other irregularity’ in the process
    employed imports such bad faith, ignorance of the law and indifference to the
    justice of the result as would cause a court to vacate an arbitration award.”
    - 15 -
    J-S36016-21
    F.J. Busse Co., Inc. v. Sheila Zipporah, L.P., 
    879 A.2d 809
    , 811 (Pa.Super.
    2005), appeal denied, 
    587 Pa. 694
    , 
    897 A.2d 457
     (2006) (internal citations
    and some internal quotation marks omitted). “[A] common law arbitration
    award is not reviewable for an error of law. Therefore, regardless of whether
    the arbitrators committed an error of law, the arbitrator’s award cannot be
    vacated on this basis.” 
    Id. at 812
    . “In most cases where an irregularity is
    alleged, our appellate courts have denied relief.” Chervenak, Keane & Co.,
    Inc. (CKC Associates) v. Hotel Rittenhouse Associates, Inc., 
    477 A.2d 482
    , 485 (Pa.Super. 1984) (collecting cases).
    [T]his Court has found irregularities rising to the level of the
    denial of a fair hearing where the arbitrators: exceeded the
    scope of the arbitration agreement, Ginther v. U.S. Fid. &
    Guar. Co., … 
    632 A.2d 333
    , 335 (Pa.Super. 1993); made
    an award for claims that were never raised, Mellon v.
    Travelers Inc. Co., … 
    406 A.2d 759
    , 762 (Pa.Super. 1979),
    or for claims that were not raised against the party against
    whom they were awarded, Alaia v. Merrill Lynch, Pierce,
    Fenner & Smith Inc., 
    928 A.2d 273
    , 277 (Pa.Super.
    2007); and had an undisclosed, ongoing business
    relationship with one of the parties, James D. Morrisey,
    Inc. v. Gross Const. Co., … 
    443 A.2d 344
    , 349 (Pa.Super.
    1982).
    However, this Court has held that no irregularity warranting
    modification occurred where the allegations were that the
    arbitrators: applied the wrong state’s law, Racicot v. Erie
    Ins. Exch., 
    837 A.2d 496
    , 500 (Pa.Super. 2003); failed to
    award fees as provided by a relevant statute, [F.J. Busse
    Co., supra]; made an award contrary to a policy exclusion,
    Hain v. Keystone Ins. Co., … 
    326 A.2d 526
    , 528
    (Pa.Super. 1974); and made an incorrect determination
    whether a person was an insured under a contract.
    Prudential Prop. & Cas. Ins. Co. [
    683 A.2d 683
    , 684
    (Pa.Super. 1996)].
    - 16 -
    J-S36016-21
    In sum, “only claims which assert some impropriety in the
    arbitration process may be the subject [of] an appeal—to
    the exclusion of appeals which seek review of the merits.”
    [Snyder, 
    supra at 1201
    ]. “[N]either we nor the trial court
    may retry the issues addressed in an arbitration proceeding
    or review the tribunal’s disposition of the merits of the
    case.” F.J. Busse Co., [supra] at 811.
    D’Amelia v. Toll Bros., Inc., 
    235 A.3d 321
    , 329-30 (Pa.Super. 2020).
    Instantly, in evaluating the merits of Appellant’s current petition to
    vacate, the trial court reasoned:
    In 2020, Appellee filed a Petition to Confirm the 2019
    Arbitration Award. Subsequent to oral argument, the trial
    court: (1) found that the 2016 Construction Contract was
    valid; (2) found that the 2016 Construction Contract was
    duly signed by both parties; and, (3) found that Appellant
    had waived the right to appeal the 2019 Arbitration Award
    [based on the contract language]. Furthermore, Appellant
    has provided no evidence, pursuant to 42 Pa.C.S. § 7341,
    to show that Appellant was “denied a hearing or that fraud,
    misconduct, corruption or other irregularity” caused the
    2019 Arbitration Award. Therefore, the trial court properly
    granted Appellee’s Petition to Confirm and properly denied
    Appellant’s Section Petition to Vacate.
    (Trial Court Opinion at 5). We see no reason to disrupt the court’s decision.
    Here, Appellant claimed the arbitrator violated the AAA’s Construction
    Industry Arbitration Rules. Regarding the arbitrator’s improper reference to
    the “Leading Edge Doctrine,” upon questioning from the parties, the arbitrator
    explained that she had used that phrase in the colloquial sense “from a
    construction law perspective” and wanted the parties to brief the “effect of
    verbal directions in the field without written change orders—even if there is
    language in the contract stating that all change orders must be in writing.”
    - 17 -
    J-S36016-21
    The arbitrator gave the parties another opportunity to brief this issue. (See
    Arbitrator’s E-mail to Parties, 7/23/19, at 1; R.R. at 72a).            Even if the
    arbitrator misapplied Pennsylvania law, that is not grounds for upsetting the
    arbitration award. See Civan, supra; F.J. Busse Co., supra.
    Additionally, Appellant’s claims of the arbitrator’s alleged violations of
    the AAA’s Construction Industry Arbitration Rules do not rise to the level of
    those procedural irregularities where modification of the arbitration award was
    required.    See D’Amelia, supra.              The record simply does not show that
    Appellant was deprived of a hearing or that fraud, misconduct, corruption, bad
    faith, ignorance of the law, or indifference to the justice of the result occurred
    such that the arbitration award should be vacated. See Civan, supra; F.J.
    Busse Co., supra. In light of our very narrow scope of review which favors
    the public policy of finality in arbitration proceedings, we cannot say the trial
    court abused its discretion in denying Appellant’s petition to vacate and
    granting Appellee’s petition to confirm the arbitration award.10 See Gargano,
    ____________________________________________
    10 Appellee requests that we award damages, attorney’s fees, and interest
    under Pa.R.A.P. 2744 (explaining that appellate court may award counsel fees
    and other damages when it determines that appeal is frivolous or taken solely
    for delay or that conduct of participant against whom costs are to be imposed
    is dilatory, obdurate or vexatious). Appellee’s request is based, at least in
    part, on its belief that Appellant’s current petition to vacate was untimely filed
    in Philadelphia County. Nevertheless, we have already decided that the timely
    Montgomery County filing should have been transferred to Philadelphia
    County. Further, while Appellant’s issues on appeal do not merit any relief,
    we decline to hold that this appeal is frivolous or was taken solely for the
    purpose of delay. See id.; U.S. Claims, 
    supra at 878
     (stating: “In
    (Footnote Continued Next Page)
    - 18 -
    J-S36016-21
    supra; Civan, supra. Accordingly, we affirm.
    Orders affirmed.
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 2/23/2022
    ____________________________________________
    determining the propriety of such an award, we are ever guided by the
    principle that an appeal is not frivolous simply because it lacks merit; rather,
    it must be found that the appeal has no basis in law or fact”).
    - 19 -