Beaumont Condominium Assoc. v. Brown, J. ( 2017 )


Menu:
  • J-A13012-17
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
    BEAUMONT CONDOMINIUM                       IN THE SUPERIOR COURT OF
    ASSOCIATION                                      PENNSYLVANIA
    Appellee
    v.
    JEFFREY M. BROWN ASSOCIATES, INC.,
    CARSON CONCRETE, CORP., BEAUMONT
    CORP., MONTIVUE CONSTRUCTION AND
    PENNONI ASSOC., INC.
    APPEAL OF: JEFFREY M. BROWN
    ASSOCIATES, INC.
    No. 2177 EDA 2016
    Appeal from the Judgment Entered September 9, 2016
    In the Court of Common Pleas of Philadelphia County
    Civil Division at No(s): 1896, January Term, 2014
    *****
    JEFFREY M. BROWN ASSOCIATES, INC.          IN THE SUPERIOR COURT OF
    PENNSYLVANIA
    Appellant
    v.
    CARSON CONCRETE CORPORATION
    Appellee                 No. 2181 EDA 2016
    Appeal from the Order Entered June 7, 2016
    In the Court of Common Pleas of Philadelphia County
    Civil Division at No(s): 02440, December Term, 2013
    J-A13012-17
    BEFORE: LAZARUS, J., OTT, J., and FITZGERALD, J.*
    MEMORANDUM BY LAZARUS, J.:                              FILED NOVEMBER 03, 2017
    In these consolidated1 appeals (2177 EDA 20162 and 2181 EDA 20163)
    Jeffrey M. Brown Associates, Inc. (JMB) appeals from the trial court’s order
    granting in part and denying in part its motion for post-trial relief, granting
    Appellee Carson Concrete Corporation’s (Carson) post-trial motion, and
    striking an award of $62,510.73 in favor of JMB, and from the court’s final
    judgment entered in favor of Carson and against JMB. After careful review,
    we are constrained to affirm.
    Beaumont Corporation         (Owner) and        Montvue   Construction,   Inc.
    (Builder)4 hired JMB as a construction manager for a project (the “Project”)
    at    Beaumont     Condominiums,        a   13-story    condominium   complex     (the
    “Building”) located on South Front Street in Philadelphia.              Accordingly,
    Builder executed a “Standard Form of Agreement Between Owner and
    Construction Manager” on June 30, 2003.                On March 22, 2004, JMB hired
    ____________________________________________
    *Former Justice specially assigned to the Superior Court.
    1 On January 17, 2017, our Court entered an order granting JMB’s
    application to consolidate the two cases, 2177 EDA 2016 and 2181 EDA
    2016, as they involve related issues and parties. See Pa.R.A.P. 512.
    2   Beaumont Condominium Association lawsuit (“Association Action”).
    3   Referred to as “JMB lawsuit.”
    4 Owner hired Montvue to erect the Building and appurtenances on the
    subject property. See Beaumont Condominium Association’s Complaint,
    2/3/14, at ¶ 8.
    -2-
    J-A13012-17
    Carson,5 for $1.8 million, as a subcontractor6 to design and build the entire
    concrete superstructure for the Project using a structural system known as
    “post-tension” concrete. With this type of tension system, structural support
    ____________________________________________
    5The parties entered into a “Design Build Subcontract” to memorialize this
    agreement.
    6 In Turner Construction, Inc. v. American States Ins. Co., 
    579 A.2d 915
    (Pa. Super. 1990), our Court explained the nature of this type of
    relationship:
    Typically when major construction is involved an owner has
    neither the desire nor the ability to negotiate with and supervise
    the multitude of trades and skills required to complete a project.
    Consequently an owner will engage a general contractor. The
    general contractor will retain, coordinate and supervise
    subcontractors. The owner looks to the general contractor, not
    the subcontractors, both for performance of the total
    construction project and for any damages or other relief if there
    is a default in performance. Performance and the payment of
    damages are normally assured by the bond of a surety on which
    the general contractor is principal and the owner is the obligee.
    The general contractor, in turn, who is responsible for the
    performance of the subcontractors, has a right of action against
    any subcontractor which defaults. Performance and payment of
    damages by a subcontractor are normally assured by the bond of
    a surety on which the subcontractor is principal and the general
    contractor is the obligee.
    Thus the typical owner is insulated from the subcontractors both
    during the course of construction and during the pursuit of
    remedies in the event of a default. Conversely, the
    subcontractors are insulated from the owner. The owner deals
    with and, if necessary, sues the general contractor, and the
    general contractor deals with and, if necessary, sues the
    subcontractor.
    
    Id. at 918
    n.2, citing Pierce Associates, Inc. v. Neumours Foundation,
    
    865 F.2d 530
    , 535-36 (3rd Cir.1989).
    -3-
    J-A13012-17
    for the building is provided by reinforced concrete, with unstressed steel
    cables embedded within the concrete floor slabs, which are then tensioned
    after the concrete is poured. With post-tensioning, the cables are generally
    pulled or tensioned a few days after the concrete is poured. The design for
    Carson’s post-tension system included, in part, the use of certain U-shaped
    pieces of steel rebar called “hairpins” to reinforce and confine the cables in
    locations where the cables had to bend, or “sweep,” within the concrete.
    In April 2004, Owner hired an engineering firm, Pennoni Associates
    (“Pennoni”),   to   perform   testing   and   inspection   services   during   the
    construction process.   On July 6, 2004, Pennoni inspected the reinforcing
    steel and post-tensioning for the 10th floor of the condominium complex and
    reported that “[h]airpins were placed @ sweeps as designed.” Def.’s Ex. 4.
    Shortly thereafter, the concrete for the 10th floor was poured. The Project
    was completed in 2005.
    Around New Year’s Day 2013, a post-tensioned cable in the concrete
    floor of the 10th floor unit of the condominium complex lost its tension and
    ripped out of the concrete floor, causing damage to the unit owned by the
    Bergamo Trust (“the Trust”) as well as compromising the structural integrity
    of the Building. Specifically, the blowout dislodged hardwood flooring and a
    toilet in the 10th floor unit. JMB was immediately notified of the incident; it
    sent personnel to investigate the damage.
    At trial, JBM presented an expert who testified that a number of
    hairpins, which were included in the original Project drawings, were missing
    -4-
    J-A13012-17
    at the location where the blowout occurred. The expert further opined that
    “the lack of hairpins in this section of the tendon that was curving directly
    led to the failure of the concrete in this area[,] because the hairpins serve to
    restrain the tendons from moving the exact direction that they did[,]” and
    that had the hairpins been present the cables “would not have been able to
    pull out of the concrete and move in that direction.”      N.T. Non-Jury Trial,
    2/1/16, at 151-52. While JMB’s expert agreed with Carson’s expert that the
    68-mile per hour winds from Hurricane Sandy7 could have affected the
    structure, he did not think that the damage would have occurred if the
    hairpins had been in place. 
    Id. at 152
    (“[H]ad the hairpins been present,
    the failure would not have happened.”).
    The Beaumont Condominiums Association (Association), the unit
    owners’ association of the Beaumont Condominiums, engaged an expert
    from a post-tension firm to design and implement a remediation plan.
    Ultimately, the Association expended approximately $180,000 to investigate
    the blowout, repair the structural defect, and repair the physical damage to
    the Trust’s condominium unit.
    ____________________________________________
    7Hurricane Sandy became a Category 1 hurricane that made landfall in the
    Unites States about 8 p.m. EDT on October 29, 2014, near Atlantic City, NJ,
    with    winds   as    strong   as   80    miles   per    hour.         See
    www.livescience.com/24380-hurricane-sandy-status-data.html (last visited
    7/7/17).
    -5-
    J-A13012-17
    Despite the Association’s demands to be reimbursed for the repair
    costs, Carson refused to resolve the matter. As a result, in December 2013
    JMB instituted a lawsuit (“JMB lawsuit”), sounding in breach of contract,
    negligence, and contractual indemnification, against Carson.       In January
    2014, the Association (“Association Action”) commenced an action against
    various defendants, pursuant to the Pennsylvania Uniform Condominium Act
    (PUCA),8 including JMB, Carson, the original condominium sponsors, and
    Pennoni seeking reimbursement of the costs incurred as a result of the
    blowout. The Trust later intervened as a plaintiff in the Association Action,9
    seeking rental income for the time it was unable to use the 10 th floor unit as
    a result of the blowout. In the Association Action, the Association and the
    Trust asserted claims against JMB for breach of implied warranty, negligence
    and strict liability in tort; JMB asserted a cross-claim for contractual
    indemnification, common law contribution and indemnity, breach of contract,
    and negligence against Carson. JMB ultimately settled with the Association
    for $140,000 and with the Trust for $36,000.10
    ____________________________________________
    8   See 68 Pa.C.S. §§ 3101-3414.
    9 The trial court granted the Trust’s petition to intervene on October 24,
    2014.
    10 Pennoni participated in the settlement, contributing $35,999 to the
    settlement with the Association and $9,000 to the settlement with the Trust.
    Pennoni is not a party to this appeal.
    -6-
    J-A13012-17
    Following settlement, JMB continued to pursue its claims against
    Carson in both cases.     In March 2015, JMB filed a motion for summary
    judgment against Carson, arguing that the undisputed facts of record left no
    doubt that Carson’s negligence caused the blowout and, therefore, that JMB
    was entitled to $210,154.88, representing the amount it paid in its
    settlement with the Association and the Trust, as well as engineering fees
    and legal fees paid in the matter.      The trial court denied JMB’s motion,
    finding that JMB had not established that its settlement with the Association
    and the Trust was reasonable, and, therefore, that an issue of material fact
    still remained in the case.
    On February 1, 2016, the court granted Carson’s motion to consolidate
    the two cases for trial. See Pa.R.C.P. 213(c). In February 2016, the trial
    court held a three-day bench trial before the Honorable Patricia A.
    McInerney. At the conclusion of trial, the court found the following facts:
       Hairpins were missing;
       Carson did not put the hairpins in the area of the blowout;
       The hairpins were not there when the concrete was poured; and
       The blowout would not have occurred but for the absence of the
    hairpins.
    Based upon these facts, the court made the following legal conclusions:
       Carson, as subcontractor, was negligent and breached its subcontract
    with JMB “in failing to place hairpins at the sweep at issue in this
    case;”
    -7-
    J-A13012-17
       Pennoni, as the inspector for the original owner and developer, was
    negligent “in failing to detect the absence of the hairpins at issue. . .
    upon its inspection of the 10th Floor before the concrete was poured.”
       Liability was apportioned as follows: Carson 60%/Pennoni 40%; and
       JMB’s claims against Carson for breach of contract and negligence
    failed where it did not prove that it had the inability to know Carson
    failed to place the hairpins despite the exercise of reasonable diligence
    where JMB “had representatives on the job site daily with ample
    opportunity to inspect the construction prior to the pour.”
       JMB was entitled to indemnification against Carson on the Trust’s
    underlying claim for breach of the implied warranty of habitability;
       The Association had no valid claim for breach of implied warranty of
    habitability against JMB because it was not a “first purchaser” in privity
    with the developer.
    On February 11, 2016, the court entered an order awarding JMB
    $62,510.7311 on its contractual indemnification claim against Carson and in
    favor of Carson on all other claims. On February 26, 2016, JMB filed post-
    trial motions.     Subsequently, Carson filed post-trial motions.       After oral
    argument on the motions, the trial court granted in part and denied in part
    JMB’s post-trial motion and granted Carson’s post-trial motion on June 7,
    2016.      Specifically, the court found that the missing hairpins were not
    reasonably discoverable by JMB.                However, because JMB only suffered
    economic damages as result of its settlement of the underlying Plaintiffs’
    claims, the court concluded it could not recover on its breach of contract and
    ____________________________________________
    11This figure represents the amount JMB paid to settle its claims with the
    Trust for lost rent ($36,000), reasonable attorneys’ fees ($13,488.23) and
    engineering costs incurred ($13,022.50).
    -8-
    J-A13012-17
    negligence claims against Carson.          The trial court also reversed its finding
    that the Trust was the first purchaser of the 10th floor unit for purposes of
    establishing the third parties’ underlying claims for breach of an implied
    warranty of habitability.         Accordingly, the court struck its $62,510.73
    damage award in favor of JMB and against Carson on JMB’s indemnification
    claim.
    JMB filed timely notices of appeal from the court’s post-trial motion
    order and the final judgment, as well as a timely court-ordered Pa.R.A.P.
    1925(b) concise statement of errors complained of on appeal. On appeal, 12
    JMB raises the following issues for our consideration:
    (1)    Did the trial court err as a matter of law by failing to apply
    the appropriate measure of damages for Carson’s breach
    of contract, where Pennsylvania law unambiguously holds
    that a general contractor who receives deficient
    performance from a subcontractor is entitled to the benefit
    of its bargain, as measured by the cost of repairing the
    defective work?
    (2)    Did the trial court err as a matter of law in rejecting JMB’s
    indemnification claim against Carson, where its settlement
    of the underlying Plaintiffs’ negligence claims was
    reasonable under all of the circumstances presented at the
    time?
    (3)    Did the trial court err as a matter of law by holding that
    the Beaumont Condominium Association’s underlying claim
    against JMB for breach of implied warranty of habitability
    was invalid, and, therefore, rejecting JMB’s indemnification
    ____________________________________________
    12JMB filed two identical briefs raising the same “Questions Presented.” We
    have only listed the issues once to avoid redundancy.
    -9-
    J-A13012-17
    claim against the culpable subcontractor for the cost of
    that settlement?
    (4)    Was the trial court’s finding that JMB failed to prove that
    the Bergamo Trust . . . was the first purchaser of the
    damaged condominium unit unsupported by competent
    evidence, where the Trustee testified at trial that he had
    represented the Trust since the condominium was formed?
    Breach of Contract (JMB-Carson)
    In its first issue on appeal, JMB asserts that the trial court incorrectly
    determined that it did not prove actual damages on its breach of contract
    claim13 against Carson. Specifically, JMB claims that it is entitled to cost-of-
    repair damages as a recipient of a defective construction project where it
    was damaged by losing the benefit of its bargain.
    Pursuant to the Restatement (Second) of Contracts, § 348:
    (1) If a breach delays the use of property and the loss in value
    to the injured party is not proved with reasonable certainty, he
    may recover damages based on the rental value of the property
    or on interest on the value of the property.
    (2) If a breach results in defective or unfinished
    construction and the loss in value to the injured party is
    not proved with sufficient certainty, he may recover
    damages based on
    (a) the diminution in the market price of the
    property caused by the breach, or
    (b) the reasonable cost of completing performance
    or of remedying the defects if that cost is not clearly
    disproportionate to the probable loss in value to him.
    ____________________________________________
    13There is a six-year statute of limitations on this breach of contract action.
    See 42 Pa.C.S. § 5527. Instantly, the statute of limitations began to run at
    the time JMB was aware of the defects in Carson’s concrete work, which
    would have been when the accident occurred in January 2013.
    - 10 -
    J-A13012-17
    (3) If a breach is of a promise conditioned on a fortuitous event
    and it is uncertain whether the event would have occurred had
    there been no breach, the injured party may recover damages
    based on the value of the conditional right at the time of breach.
    Restatement (Second) of Contracts, § 348 (emphasis added).
    Carson contends that JMB is not entitled to cost-of-repair damages
    because it presented no evidence of diminution in value of the building. In
    fact, JMB suffered no loss in value to the unit. Rather, it was the Trust that
    suffered the loss in value. Moreover, JMB was not affected by any change in
    market price of the unit. Here, it was the Association that paid to remedy
    the damage to the unit and repair any structural defects in the Building as a
    result of the blowout. While JMB reimbursed the Association for those costs,
    it was not contractually obligated to do so. Thus, under section 348 of the
    Restatement, JMB is not the intended “injured party” that is entitled to the
    reasonable cost to remedy the defects.
    JMB relies on Douglass v. Liccardi Constr. Co., 
    562 A.2d 913
    (Pa.
    Super. 1988), to support its argument that it is entitled to section 348
    damages for Carson’s defective concrete work.       In Douglass, a builder
    breached its contract with owners of a home when it failed to construct the
    dwelling in accordance with the parties’ contract and also performed some of
    the construction work in a defective and unworkmanlike manner. The jury
    entered a verdict in favor of the owners, awarding them $15,000, which
    represented the cost to correct the defects and complete the construction.
    The court noted, “the [owners] had contracted for [certain] things . . . and
    - 11 -
    J-A13012-17
    they clearly had value to them. The jury was not compelled to accept the
    same or in reliance thereon conclude that the cost of repairing the defects in
    construction was disproportionate to the loss of value to [owners] because of
    such defects.” 
    Id. at 916.
    On appeal, the builder argued that the jury’s award was unsupported
    by the evidence.     In upholding the verdict, the court cited to section 348,
    stating that because it is often difficult to prove with certainty the loss in
    value to the injured party, “he or she may elect to calculate the loss in value
    in accordance with Section 348(2) of the Restatement (Second) of
    Contracts.”     
    Id. at 915.
    Notably, the court recognized that our courts have
    generally allowed damages for defective performance of a building contract
    to be measured by the cost of completing the work or correcting the defects
    by another contractor.
    Here, JMB was not in the same position as the owners in Douglass
    who were forced to correct the defective and non-compliant work performed
    by their builder. Rather, the Association paid the costs to repair the damage
    from the blowout and complete the work to fix structural issues from the
    accident.     JMB simply did not have any “cost to remedy the construction
    defects” which is the measure of damages under section 348.
    Indemnification Claims
    - 12 -
    J-A13012-17
    In its next three issues, JMB argues that its settlement of the
    underlying claims with the Association and the Trust was both reasonable
    and makes Carson subject to its indemnification14 obligation.
    ____________________________________________
    14  Instantly, the JMB-Carson                  subcontract   provides   the   following
    indemnification clause:
    Article 8 - Indemnification
    8.1 The Subcontractor agrees for ¡tself and its insure[d] to
    indemnify, defend and hold harmless Owner, Contractor,
    Architect, Engineer, and their parent, subsidiary and affiliated
    companies and their respective agents, officers, directors,
    employees and assigns from and against any and all
    liabilities, claims, losses, damages, penalties, costs or
    expenses (including but not limited to court costs and
    reasonable attorney's fees) for damage to property
    whatsoever kind or nature or injury to persons (including, but
    not limited to death) arising out of or due to or claimed to
    have arisen out of or been due to design, manufacture,
    delivery, installation, use, maintenance, repair, or operation of
    any part of all of the goods, material and equipment, if any,
    supplied by Subcontractor, or the performance of the Work
    by Subcontractor, its agents, Independent Contractors, Sub-
    Subcontractors, vendors, and each of their agents, officers or
    employees, or any other of their operations, no matter by
    whom performed for or on behalf of the Subcontractor.
    Subcontractor’s obligations under this indemnity shall not extend
    to property damage or personal injury caused by the sole
    negligence of indemnitee or its agents, officers, directors,
    employees and assigns.
    *       *    *
    8.3   The Subcontractor shall bear any expense of an
    indemnitee because of any claim or other matter
    indemnified against hereunder, including reasonable
    attorney’s fees and court costs in the defense of, or
    preparing for the defense of, or preparing for the defense
    against, any such claim; even if such claim or any lawsuit
    (Footnote Continued Next Page)
    - 13 -
    J-A13012-17
    It is well-settled in Pennsylvania that provisions to indemnify for
    another party's negligence are to be narrowly construed, requiring a clear
    and unequivocal agreement before a party may transfer its liability to
    another party. Integrated Project Servs. v. HMS Interiors, Inc., 
    931 A.2d 724
    , (Pa. Super. 2007).          Accordingly, indemnification provisions are
    given effect only when clearly and explicitly stated in the contract between
    two parties. Moreover,
    [I]n Pennsylvania . . . provisions to indemnify for another party's
    negligence are to be narrowly construed, requiring a clear and
    unequivocal agreement before a party may transfer its liability to
    another party. Ruzzi v. Butler Petroleum Co., [] 
    588 A.2d 1
    ,
    7 (Pa. 1991); Perry v. Payne, [] 66 A 553 (Pa. 1907).
    Bernotas v. SuperFresh Food Mkts., Inc., 
    863 A.2d 478
    , 482-83 (Pa.
    2004). Finally,
    To establish the right to indemnification, the indemnitee must
    establish: the scope of the indemnification agreement; the
    nature of the underlying claim; its coverage by the
    indemnification agreement; the reasonableness of the alleged
    (Footnote Continued) _______________________
    arising therefore is groundless, false or fraudulent. If any such
    claims has not been settled or discharged when the Work is
    finished, final settlement between the Contractor and the
    Subcontractor and final payment of the Subcontract Price and
    the acceptance of the Work shall be deferred until any such
    claim is paid or settled or the Subcontractor provides a bond,
    acceptable to the Contractor, in its sole discretion, to satisfy
    such claim.
    Moreover, Carson assumed all the design responsibility for “converting the
    structure and foundations from structural steel and metal deck to post[-]
    tension reinforced concrete.” 
    Id. at 2.
    - 14 -
    J-A13012-17
    expenses; and, where the underlying action is settled
    rather than resolved by payment of a judgment, the
    validity of the underlying claim and the reasonableness of
    the settlement.
    Burlington Coat Factory of Pa., LLC v. Grace Constr. Mgmt. Co., LLC,
    
    126 A.3d 1010
    , 1022 (Pa. Super. 2015) (citing McClure v. Deerland Corp.,
    
    585 A.2d 19
    , 22 (Pa. Super. 1991) (emphasis added).                See Martinique
    Shoes, Inc. v. New York Progressive Wood Heel Co., 
    217 A.2d 781
    ,
    783 (1966) (to recover indemnity where there has been voluntary payment,
    party paying must himself be legally liable and show that he could have
    been compelled to satisfy claim).
    Thus, in order for Carson to be legally obligated to indemnify JMB for
    settling with the Association and the Trust, the question boils down to
    whether those parties had valid causes of action against JMB.15
    In speaking to that question, JMB claims that the trial court erred in
    concluding that its settlement with the Association and the Trust was not
    subject to Carson’s duty to indemnify.             Specifically, JMB asserts that it
    reasonably settled its claims with the Association, that the Trust was the
    first-purchaser of the damaged unit, and that the Association had a valid
    implied warranty of habitability in the common area where the accident
    occurred.
    ____________________________________________
    15 Notably, there was no contractual privity between the Association and JMB
    or the Trust and JMB. In fact, JMB had only contracted with Builder.
    - 15 -
    J-A13012-17
    Negligence
    Instantly, the Association sued JMB for negligence as the project
    manager.     Essentially, the Association alleged that JMB was liable for
    professional negligence where it did not ensure that its subcontractor,
    Carson, properly placed the hairpins in the post-tensioning system of the
    concrete superstructure for the Building.
    The trial court concluded that JMB could not recover on this negligence
    theory, however, because it:
    failed to establish any [direct harm or] damages in regard to . . .
    negligence as the only damages in this case related to the
    settlement of underlying plaintiffs’ causes of action and JMB’s
    claims for indemnification of the settlement payments that were
    made to those plaintiff[s] and for legal expenses and
    investigating and engineering expenses pursuant to a
    contractual indemnification clause.
    Post-Trial Trial Court Opinion, 9/12/16, at 11.      Specifically, the trial court
    found that JMB failed to demonstrate either the causal relationship between
    the breach and the resulting injury suffered by it, or the actual loss suffered
    by it, necessary to support a cause of action for negligence. 
    Id. at 23.
    While JMB suffered a monetary loss by paying the Association and the
    Trust for the expenses it incurred in remedying the physical damage to the
    units and Building and lost rent, the trial court is correct in concluding that it
    did not suffer any actual physical or property damage.           See Adams v.
    Copper Beach Townhome Communities, L.P., 
    816 A.2d 301
    (Pa. Super.
    2003) (explaining economic loss doctrine which provides that no cause of
    action exists for negligence that results solely in economic damages
    - 16 -
    J-A13012-17
    unaccompanied by physical injury or property damage). Thus, while there
    was actual property damage to the building as a result of Carson’s
    negligence, JMB did not suffer any actual property or physical injury
    recoverable under a negligence theory.
    Breach of Implied Warranty of Habitability
    The Association and the Trust also sued JMB under a theory of breach
    of an implied warranty of habitability.
    Pennsylvania   law   recognizes      implied   warranties   in   construction
    contracts where a builder sells a home to a residential purchaser. Conway
    v. Cutler Group, Inc., 
    99 A.3d 67
    , 69-70 (Pa. 2014), citing Elderkin v.
    Gaster, 
    288 A.2d 771
    (Pa. 1972).           “[T]he warranties of habitability and
    reasonable workmanship are not created by representations of a builder-
    vendor[,] but rather are implied in law and as such, exist independently of
    any representations of a builder-vendor.”         Tyus v. Resta, 
    476 A.2d 427
    ,
    433 (Pa. Super. 1984). An implied warranty may be waived by clear and
    unambiguous     contract   language;      however,   “such   language    must   be
    sufficiently particular to inform the home purchaser of the right he or she is
    waiving.”   Pontiere v. James Dinert, Inc., 
    627 A.2d 1204
    , 1206 (Pa.
    Super 1993) (quoting 
    Tyus, 476 A.2d at 432
    (Pa. Super. 1984)). “To supply
    proper notice, language of disclaimer must refer to its effect on specifically
    designated, potential latent defects.”          
    Tyus, 476 A.2d at 432
    .      Latent
    defects are those “which would not be apparent to an ordinary purchaser as
    a result of a reasonable inspection.” 
    Tyus, 476 A.2d at 433
    .
    - 17 -
    J-A13012-17
    In 1000 Grandview Assoc’n v. Mt. Washington Assoc’n, 
    434 A.2d 796
    (Pa. Super. 1981), our Court concluded that a condominium association
    did have standing under PUCA’s predecessor statute, the Unit Property Act, 16
    to assert such warranty claims, stating:
    [A]n association may have representational standing to assert
    the rights of its individual members, if it alleges an immediate,
    direct and substantial injury to any one of them. The allegations
    of the second count of the complaint, which are admitted for the
    purposes of the demurrer, . . . state that the appellees failed to
    comply with their implied and express warranties for the
    common areas resulting in, inter alia, cracked masonry, water
    leakage, a defective sewage pump, etc. Surely these are
    allegations of a direct injury to the interests of the
    association's members which permit the association to
    claim standing.
    
    Id. at 798
    (emphasis added).           Notably, the Grandview panel specifically
    stated that PUCA was not applicable to its case;
    In concluding the discussion on the standing issue, we note that
    since this appeal was taken, the Pennsylvania legislature has
    repealed the Unit Property Act and has adopted the Uniform
    Condominium Act [PUCA], 68 Pa.C.S. § 3101 et seq. (Adopted
    on July 2, 1980, effective in 120 days). The new act specifically
    states    that   the    condominium     association,    even      if
    unincorporated, may "[i]nstitute, defend or intervene in litigation
    . . . ." 68 Pa.C.S. § 3302(a)(4). Moreover, even if the unit
    owners' association was formed before the effective date of the
    act, the association would still have standing to sue under the
    new statute if the complained of injury occurred after the act's
    effective date. 68 Pa.C.S. § 3102(a). Of course, the Uniform
    Condominium Act is not applicable to [the] instant case.
    Id.
    ____________________________________________
    16   68 P.S. § 700.101, et seq.
    - 18 -
    J-A13012-17
    Here the Association’s complaint, filed pursuant to PUCA, alleges that:
    As a result of the blow-out and shifting of the tendons, the
    tendons lost their necessary and designed tensioning, and thus
    failed to provide the concrete with the necessary and designed
    support. As a result of the aforesaid failure and the undermined
    structural integrity of the concrete floor, the habitability of all
    Units in The Building was compromised and posed a serious risk
    of harm, including the risk of potential collapse of the entire 10th
    floor, with the consequent impact upon all other floors above and
    below.
    The defects in the construction of the post-tensioning system
    posed a substantial risk of harm and undetermined the structural
    integrity of the entire Building. The aforesaid structural defect
    and consequent blow-out of the post-tensioning cables seriously
    and dangerously compromised and negatively impacted the
    habitability of The Building and all of the Units therein.
    Association’s Complaint, 2/3/2014, at ¶¶ 20, 22, 41-42.          However, the
    Association stated in its complaint that pursuant to section 3302(a)(4) of
    PUCA, it was “acting in its own name[,] . . . independent of any right of any
    individual Unit owner, past or present,” and it did so “on a matter affecting
    the condominium.” Association’s Complaint, 2/3/2014, at ¶ 3. Cf. Valley
    Forge Towers South Condominium v. Ron-Ike Foam Insulators, Inc.,
    
    574 A.2d 641
    (Pa. Super. 1990) (condominium association, acting as legally
    authorized representative of unit owners under section 3302(4) of PUCA,
    sued roofing membrane manufacturer to honor its warranty; court reinstated
    association’s cause of action under Pennsylvania’s UTPCPL); see 68 Pa.C.S.
    § 3302(a)(4) of the Act, a condominium association may “[i]nstitute, defend
    or intervene in litigation . . . in its own name on behalf of itself or two or
    more unit owners on matters affecting the condominium.”).
    - 19 -
    J-A13012-17
    Thus, where the Association clearly chose not to assert the individual
    rights of any of the unit owners, but merely pursued its own interest in
    litigating the matter as explicitly stated under section 3302(4) of PUCA, we
    cannot apply the standing analysis announced in Grandview.               We also
    decline to extend the implied warranty to an association in its own right
    where the Association had the opportunity to sue on behalf of the unit
    residents as their legally authorized representative and chose not to.
    With regard to the Trust, we note that the implied warranty of
    habitability is not limited to first purchasers. See Spivack v. Berks Ridge
    Corp., 
    586 A.2d 402
    (Pa. Super. 1990). Rather, it is limited to first user-
    purchasers. Conway v. Cutler Group, Inc., 
    99 A.3d 67
    (Pa. 2014).
    To prove that it was the first purchaser of Unit 10, the damaged unit,
    David Rasner, Esquire, testified on behalf of the Trust. Rasner testified that
    he is the co-trustee of the Trust which was established by his co-trustee’s
    grandmother. He testified that the only asset that the Trust has is the 10 th
    floor unit at the Beaumont and that the unit was rented out to tenants.
    Rasner testified that he thought he had been the co-trustee of the Trust
    since the unit was established and that he was co-trustee at the time of the
    blowout. N.T. Waiver Trial, 2/1/2016, at 69. The tenants renting the unit at
    the time of the blowout vacated the premises in March 2013, concluding that
    “the unit was uninhabitable and that they were concerned for their safety.”
    
    Id. at 70-71.
    The Trust did not secure a new tenant until April 2014. 
    Id. at -
    20 -
    J-A13012-17
    71.   The Association paid the Trust approximately $19,000 to make the
    needed repairs to the damaged unit. 
    Id. at 73-73.
    Instantly, the Trust attached a copy of its agreement of sale for Unit
    10 to its petition to intervene in the underlying matter.     The agreement,
    entered into on March 9, 2007, indicates that The Bergamo Trust, c/o Laura
    Zarett,   is   purchasing   “Unit   1000”   at   Beaumont   Condominiums   for
    $1,725,000.00. The agreement lists the Beaumont Corporation as the seller
    of the unit.   However, as the trial court acknowledges, not only does that
    agreement purport to waive any implied warranty of habitability, 
    Pontiere, supra
    ; 
    Tyus, supra
    , the statute of limitations on an action to enforce any
    warranty within the agreement had run by the time the Association sued
    JMB and the Trust intervened.        Thus, we reluctantly agree with the trial
    court that neither the Association nor the Trust had a valid cause of action
    for breach of implied warranty against JMB.
    Judgment and order affirmed.
    Judge Ott joins this Memorandum.
    Justice Fitzgerald files a Concurring and Dissenting Memorandum.
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 11/3/2017
    - 21 -