Gavco Materials v. Brayman Construction ( 2016 )


Menu:
  • J-A07018-16
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
    GAVCO MATERIALS, INC.                            IN THE SUPERIOR COURT OF
    PENNSYLVANIA
    Appellee
    v.
    BRAYMAN CONSTRUCTION
    CORPORATION
    Appellant                 No. 697 WDA 2015
    Appeal from the Order Entered April 9, 2015
    In the Court of Common Pleas of Fayette County
    Civil Division at No(s): 173 of 2015 GD
    BEFORE: BOWES, J., MUNDY, J., and JENKINS, J.
    MEMORANDUM BY MUNDY, J.:                               FILED JUNE 21, 2016
    Appellant, Brayman Construction Corporation (Brayman), appeals from
    the April 9, 2015 order denying its motion to compel arbitration. 1      After
    careful review, we reverse and remand.
    The trial court summarized the facts and procedural history of this
    case as follows.
    On February 4, 2015, Gavco Materials Inc.
    (hereinafter “Gavco”) filed a complaint for breach of
    contract against Brayman alleging failure to furnish
    ____________________________________________
    1
    An order denying a motion to compel arbitration filed pursuant to Section
    7304 of the Pennsylvania Uniform Arbitration Act, 42 Pa.C.S.A. §§ 7301-
    7362, is immediately appealable as of right. See 42 Pa.C.S.A. § 7320
    (providing that an appeal may be taken from an order denying an
    application to compel arbitration under Section 7304); Pa.R.A.P. 311(a)(8)
    (stating that an appeal may be taken as of right from an order that is made
    appealable by statute).
    J-A07018-16
    payment for several deliveries of concrete supplied
    by Gavco. Brayman was the prime contractor on a
    Pennsylvania      Department     of    Transportation
    (hereinafter     [“]PENNDOT”)     project   involving
    construction of the Masontown Bridge carrying PA
    Route 21 over the Monongahela River (hereinafter
    “the Project”) in Fayette County, Pennsylvania.
    In November of 2011, Gavco delivered pricing
    information to Brayman for various mixes of redi-mix
    concrete that would be needed for the Project, and
    Brayman used that information when submitting its
    bid to PENNDOT.         Brayman was selected by
    PENNDOT as the Prime Contractor on the Project,
    and Brayman ordered concrete for the Project from
    Gavco beginning in 2012. In January 2012, Gavco
    and Brayman signed a purchase order, hereafter
    [sic] “Brayman PO”, which included the agreed-upon
    prices for the material expected to be supplied by
    Gavco.      The parties intentionally omitted the
    quantity of materials supplied and agreed that the
    quantity of the materials supplied would be defined
    on a rolling basis pursuant to each delivery.
    Upon delivery of the concrete, a representative
    of Brayman would sign a Delivery Ticket containing
    the Terms and Conditions of the sale and providing
    acknowledgement of the receipt of the concrete.
    Gavco would then prepare and deliver invoices for
    each concrete delivery to Brayman, who paid these
    invoices for a short time.      From July 16, 2013
    through December 30, 2013, a group of invoices
    totaling $77,212.82 were not paid by Brayman.
    When     Gavco     demanded     payment,     Brayman
    communicated that payment was being withheld
    based on problems Brayman had experienced with
    concrete installed at “Pier 5” of the Project. Upon
    Brayman’s suspension of payment, Gavco suspended
    deliveries of the concrete.
    On January 9, 2015 Brayman filed a Demand
    for Arbitration with the American Arbitration
    Association seeking $3,000,000.00 plus ongoing
    damages as a result of Gavco’s alleged delivery of
    -2-
    J-A07018-16
    non-conforming      concrete.      Gavco     answered
    Brayman’s Demand for Arbitration on February 6,
    2015, after filing the underlying complaint with [the
    trial court] on February 4, 2015. In its complaint
    Gavco is alleging breach of contract by Brayman,
    and is requesting relief in the amount [of]
    $77,212.82 plus twelve percent (12%) per annum
    and reasonable costs and attorneys’ fees incurred by
    Gavco. Gavco’s answer to Brayman’s Demand for
    Arbitration denies the existence of a valid arbitration
    agreement. On March 4, 2015, Brayman filed a
    Motion to Compel Arbitration and Stay Judicial
    Proceedings.     Gavco subsequently filed a cross-
    motion to Stay Arbitration and Compel Judicial
    Proceedings on March 12, 2015. [The trial court]
    heard oral arguments in this matter on March 13,
    2015 and denied Brayman’s motion [on April 9,
    2015].      Brayman thereafter filed this timely
    [2]
    appeal.
    Trial Court Opinion, 6/26/15, at 1-3.
    On appeal, Brayman presents the following question for our review.
    1. Whether the trial court erred in denying
    Brayman’s motion to compel arbitration and stay
    the litigation pursuant to the Pennsylvania
    Arbitration Act, and granting Gavco’s motion to
    stay arbitration because the contract applicable to
    Gavco’s concrete deliveries for the project
    contains an enforceable arbitration agreement,
    and Gavco’s breach of contract claim fails [sic]
    within the scope of the arbitration agreement[?]
    Brayman’s Brief at 5.
    Our scope and standard of review are as follows.
    ____________________________________________
    2
    Brayman and the trial court have complied with Pennsylvania Rule of
    Appellate Procedure 1925.
    -3-
    J-A07018-16
    [A]rbitration is a matter of contract and, as such, it
    is for the court to determine whether an express
    agreement between the parties to arbitrate exists.
    Because the construction and interpretation of
    contracts is a question of law, the trial court’s
    conclusion as to whether the parties have agreed to
    arbitrate is reviewable by this Court. Our review is
    plenary, as it is with any review of questions of law.
    Midomo Co., Inc. v. Presbyterian Housing Dev. Co., 
    739 A.2d 180
    , 187
    (Pa. Super. 1999).
    We review a trial court’s denial of a motion to compel
    arbitration for an abuse of discretion and to
    determine whether the trial court’s findings are
    supported by substantial evidence. In doing so, we
    employ a two-part test to determine whether the
    trial court should have compelled arbitration. The
    first determination is whether a valid agreement to
    arbitrate exists.     The second determination is
    whether the dispute is within the scope of the
    agreement.
    Burkett v. St. Francis Country House, 
    133 A.2d 22
    , 27 (Pa. Super. 2016)
    (citation omitted).
    Accordingly, we first address whether an agreement to arbitrate exists.
    See 
    id.
       Brayman contends that a valid purchase order (PO) governs the
    contractual relationship of the parties, and it contains an arbitration
    provision. Brayman’s Brief at 23-24. In particular, the PO contains a page
    of terms and conditions, including the following arbitration provision.
    9. … At Buyer’s option, if Buyer so elects in its sole
    discretion with regard to any particular dispute, any
    dispute arising in connection with this Purchase
    Order shall be resolved by arbitration in Butler, PA in
    accordance with the rules of the American Arbitration
    Association; and all disputes shall otherwise be
    -4-
    J-A07018-16
    resolved in and only in the Court of Common Pleas of
    Butler County, PA as the exclusive judicial forum and
    in accordance with the substantive laws of the
    Commonwealth of Pennsylvania without giving effect
    to Pennsylvania’s choice of law principles. SUPPLIER
    WAIVES ITS RIGHT TO A JURY TRIAL REGARDING
    ANY DISPUTE OF THIS PURCHASE ORDER.
    Brayman PO, 12/5/11, at Terms and Conditions, ¶ 9 (capitalization in
    original). Brayman argues that the trial court erred in denying its motion to
    compel arbitration based on the trial court’s finding that the purchase order
    was not a valid and enforceable contract and did not control the parties’
    relationship. Id. at 21, 24-25.
    The Pennsylvania Uniform Commercial Code, Article 2, Sales, 13
    Pa.C.S.A. §§ 2101-2725 (UCC), applies in this case because the purchase
    order involved sales of concrete, which are transactions in goods.3         13
    Pa.C.S.A. § 2102. Section 2204 of the UCC provides that “[a] contract for
    sale of goods may be made in any manner sufficient to show agreement,
    including conduct by both parties which recognizes the existence of such a
    contract.” Id. § 2204(a).
    Under Section 2204(a), the PO is a valid written contract because the
    parties agreed to the essential terms for the sale of concrete.       The PO is
    dated December 5, 2011 and numbered 11-0005-18.                 Brayman PO,
    12/5/11, at 1. It contains the agreed upon pricing and delivery fees for a
    ____________________________________________
    3
    The parties agree that the UCC applies in this case. Gavco’s Brief at 13;
    Trial Court Opinion, 6/26/15, at 4.
    -5-
    J-A07018-16
    list of materials. Id. It further provides that the prices are valid through
    June 1, 2014, that the material will meet PennDOT specifications, and that
    payment is due within 30 days from the date of the invoice.        Id.   Gavco,
    through its representative, signed and dated a signature line indicating that
    it accepted the purchase order. Id. Brayman’s representative also signed
    it. Id. Further, the PO is valid because after Gavco and Brayman signed it,
    the parties performed over 100 sales according to its terms, which evidences
    their recognition of the contract. 13 Pa.C.S.A. § 2204(a).
    The PO, however, does not specify the quantity of the materials that
    Brayman was ordering; instead, it lists the quantity as “TBD.” Id. On this
    basis, the trial court concluded that “[b]ecause the quantity term was
    omitted from the Brayman PO, and only included after communication
    between agents of each party, the Brayman PO is illusory as it does not
    obligate Brayman to procure materials from Gavco.”       Trial Court Opinion,
    6/26/15, at 7. Gavco agrees with the trial court that the failure to specify
    the quantity renders the agreement illusory.       Gavco’s Brief at 23-26.
    Brayman asserts that the contract is valid because a contract may leave
    some terms open under the UCC. Brayman’s Brief at 22.
    Section 2306 of the UCC permits “requirements contracts” that contain
    “[a] term which measures the quantity by the output of the seller or the
    requirements of the buyer[.]”    13 Pa.C.S.A. 2306(a).       Moreover, Section
    2204 of the UCC provides “[e]ven though one or more terms are left open[,]
    -6-
    J-A07018-16
    a contract for sale does not fail for indefiniteness if the parties have intended
    to make a contract and there is a reasonably certain basis for giving an
    appropriate remedy.”     13 Pa.C.S.A. 2204(c).     Here, the parties’ intent to
    enter into a contract is clear from their performance pursuant to the PO by
    ordering and delivering concrete, and the “TBD” quantity of concrete was
    determined by Brayman’s requirements.          Accordingly, the PO is a valid
    requirements contract under the UCC and it not illusory for failure to specify
    the precise quantity of concrete to be supplied.
    The trial court also concluded that the contract was illusory because it
    contained a clause permitting Brayman to terminate the PO at any time, so
    “it does not obligate Brayman to procure materials from Gavco.” Trial Court
    Opinion, 6/26/15, at 7.     Paragraph 12 of the PO provides that “[b]uyer
    [Brayman] in its sole discretion and without cause, may terminate this
    Purchase Order, in whole or in part, at any time[.]” Brayman PO, 12/5/11,
    at Terms and Conditions, ¶ 12.           Under Section 2309 of the UCC,
    “[t]ermination of a contract by one party except on the happening of an
    agreed event requires that reasonable notification be received by the other
    party.” 13 Pa.C.S.A. § 2309. Accordingly, Section 2309 of the UCC permits
    one party to unilaterally terminate a contract, but requires the party provide
    reasonable notice of termination. Id. Based on this provision allowing for
    unilateral termination, and the fact that Brayman never attempted to
    actually terminate the PO and so was not required to provide any notice of
    -7-
    J-A07018-16
    termination, the PO is not illusory due to the clause in paragraph 12 of the
    PO permitting unilateral termination. See id.
    The trial court also concluded that “Gavco’s self-inclusive Terms and
    Conditions on the Delivery Ticket are indicia that Gavco desired to be bound
    by those terms, and those terms were assented to by Brayman upon signing
    the Delivery Ticket.” Trial Court Opinion, 6/26/15, at 7. However, the PO
    provides that it is the “entire contract” between the parties, as follows.
    1. The following terms and conditions, together with
    the terms set forth in the purchase order form
    incorporates by reference any plans, specifications,
    Prime Contract between Owner and General
    Contractor, contracts and subcontracts (“Contract
    Documents”) to the extent that those Contract
    Documents involve, relate to, or are affected by any
    and all goods, materials, products, software and/or
    services (“Supplies”) being supplied under this
    Purchase Order or other documents as are
    incorporated by reference, as amended in any
    subsequent authorized writing from Buyer, shall
    constitute the entire contract (“Purchase Order”)
    between Brayman [] (“Buyer”) and Supplier,
    Supplier shall assume as to Buyer all obligations of
    Buyer to Owner, and/or higher tier contractors under
    the Contract Documents. If this Purchase Order is
    construed as an offer, this offer expressly limits
    acceptance to the terms of this offer and notice of
    objection to any different, additional or prior terms is
    hereby given. If this Purchase Order is construed as
    an acceptance of an offer, this acceptance is
    expressly conditioned upon the offeror’s assent to
    any different or additional terms contained or
    referenced in this Purchase Order. If this Purchase
    Order is construed as a confirmation of an existing
    contract, the parties agree that this confirmation
    states the exclusive terms of any contract between
    the parties. This Purchase Order shall be deemed to
    have been accepted by the Supplier upon receipt by
    -8-
    J-A07018-16
    the Buyer of any writing, including a writing
    transmitted by fax or other means of electronic
    transmission, indicating acceptance or by the
    commencement of performance or shipment of any
    Supplies or any portion thereof.
    Brayman PO, 12/5/11, at Terms and Conditions, ¶ 1.            Based on this
    provision, and the parties’ performance under the PO of ordering and
    delivering concrete, the PO is the entire agreement between the parties and
    their agreement does not include any subsequent, additional terms in the
    delivery slips.
    Thus, the PO is not illusory and it governs the parties’ relationship.
    Because the PO is valid and enforceable, the arbitration clause contained
    therein is a valid agreement to arbitrate. See Midomo, 
    supra.
    We next address whether the parties’ dispute is within the scope of the
    arbitration clause. The arbitration clause provides that “any dispute arising
    in connection with this Purchase Order shall be resolved by arbitration[.]”
    Brayman PO, 12/5/11, at Terms and Conditions, ¶ 9.       Gavco’s complaint,
    sounding in breach of contract, indicates that it is seeking payment for a
    group of invoices totaling $77,212.82.    Gavco’s Complaint, 2/4/15, at 2.
    Gavco also noted that Brayman was withholding payment based on alleged
    problems Brayman experienced with some of the concrete.          
    Id.
       Those
    disputes arise in connection with the PO because the parties agreed that
    Gavco would supply material meeting PennDOT standards, and Brayman
    -9-
    J-A07018-16
    would submit payment for that concrete within 30 days of delivery.
    Brayman PO, 12/5/11, at 1. Therefore, the PO’s arbitration clause applies.
    For the foregoing reasons, we conclude that the trial court erred by
    denying Brayman’s motion to compel arbitration based on its finding that the
    PO was illusory. Accordingly, we reverse the trial court’s April 9, 2015 order
    and remand for further proceedings consistent with this memorandum.
    Order reversed. Case remanded. Jurisdiction relinquished.
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 6/21/2016
    - 10 -
    

Document Info

Docket Number: 697 WDA 2015

Filed Date: 6/21/2016

Precedential Status: Non-Precedential

Modified Date: 12/13/2024