Lawndale Construction v. 1840 S. Camac ( 2016 )


Menu:
  • J. S44013/16
    NON-PRECEDENTIAL DECISION – SEE SUPERIOR COURT I.O.P. 65.37
    LAWNDALE CONSTRUCTION                        :    IN THE SUPERIOR COURT OF
    MANAGEMENT, LLC,                             :          PENNSYLVANIA
    :
    Appellant           :
    :
    v.                        :
    :         No. 3395 EDA 2015
    1840 S. CAMAC ST. PARTNERS GP,               :
    LLC                                          :
    Appeal from the Order, October 2, 2015,
    in the Court of Common Pleas of Philadelphia County
    Civil Division at No. June Term 2015 M0017
    BEFORE: FORD ELLIOTT, P.J.E., STABILE AND MUSMANNO, JJ.
    MEMORANDUM BY FORD ELLIOTT, P.J.E.:                       FILED JULY 11, 2016
    Lawndale Construction Management, LLC (“appellant”), appeals the
    order of the Court of Common Pleas of Philadelphia County that sustained
    the preliminary objections of 1840 S. Camac St. Partners GP LLC
    (“appellee”) and struck appellant’s mechanics’ lien.
    On June 19, 2015, appellant commenced an action by filing a
    mechanics’ lien which alleged that appellant began work on property located
    at 1840 South Camac Street, Philadelphia, Pennsylvania (“Property”), on or
    about September 2014 and which continued until at least June 15, 2015.
    Appellant further alleged that it performed the work for appellee pursuant to
    an   agreement   to     construct    a   seven-unit   planned   unit   development
    residential building on the Property. Appellant also alleged that it “provided
    J. S44013/16
    substantial materials and services to construct the building . . . including
    engineering, excavation, foundation, plumbing, masonry, carpentry, roofing,
    windows, doors and other construction materials and services for which
    [appellant] has been paid partially but not completely.”        (Claim of Lien --
    49 P.S. § 1503, 6/19/15 (“Lien”) at 2 ¶5.) Appellant alleged that it was due
    to be paid $161,000.
    On September 2, 2015, appellee preliminarily objected and asserted
    that it was not the record owner of the Property and that the record owner
    was 1840 S. Camac St. Partners, LP (“Partners, LP”). Appellee alleged that
    Partners LP entered into a residential construction contract with appellant
    where appellant was to serve as general contractor for the construction
    project at the Property. Appellee alleged that appellant agreed to a waiver
    of liens in the contract which was attached as an exhibit to the preliminary
    objections. Appellee moved to strike the mechanics’ lien claim because of
    the waiver of liens.
    On   September      23,   2015,   appellant    answered       the   preliminary
    objections and denied that the contract attached to the preliminary
    objections was the agreement to perform work at the Property and denied
    that appellant executed the agreement. Appellant also asserted that it did
    not execute the lien waiver. Appellant’s counsel submitted a declaration that
    the   purported    lien    waiver   did    not      contain   the     signature    of
    Thomas Niedermayer (“Niedermayer”), president and sole member of
    -2-
    J. S44013/16
    appellant.    Niedermayer included a declaration that he did not sign the
    contract and lien waiver and did not authorize anyone to sign on his behalf.
    By order dated September 30, 2015 and filed October 2, 2015, the
    trial court sustained the preliminary objections and struck the mechanics’
    lien claim:
    In the instant case, this court sustained
    Appellee’s Objections and struck the lien for the
    following reasons. Appellant’s claim did not state
    whether the “agreement” was a written or oral
    contract, and thus this court could not discern
    whether Appellant’s failure to attach the claim was
    due to the nature of the contract or Appellant’s own
    failure to attach said contract. While it is not always
    necessary that a claimant attach a contract, for
    example, where the specification of the size, weight
    and price of material, with averments of the kind to
    be furnished, the amount due, the manner in which
    such amount is made up and the date when the last
    material was furnished was sufficient compliance
    with the act, in the instant case, Appellant provided
    nothing that would allow this court to verify the
    legitimacy of its claims. Additionally, the claim did
    not identify the type of contract nor provide an
    agreed-upon sum pursuant to 49 P.S. § 1503(5), nor
    did it provide a detailed statement of the kind and
    character of the labor or materials furnished and the
    prices charged for each thereof.
    Finally, Appellant’s claim did not state when
    the work had been completed and, in fact did not
    indicate that the work was completed: the claim
    stated only that the work has “continued until at
    least June 15, 2015.”
    Appellant did not apply for leave of court to
    amend the Lien.
    Consequently, the Mechanics Lien was facially
    insufficient and properly stricken.
    -3-
    J. S44013/16
    Trial court opinion, 1/5/16 at 4-5 (citation omitted; emphasis in original).
    Appellant raises the following issue for this court’s review:
    Did the court below err as a matter of law in striking
    Appellant’s mechanics lien claim as facially deficient
    when the claim set forth the existence of the
    construction     agreement,   provided    a   general
    description of the labor and materials furnished, set
    forth the amount due and owing under the contract,
    and averred that claimant’s work continued at least
    until a specified date that was within six months of
    the filing of the lien claim?
    Appellant’s brief at 2.
    In determining whether the trial court
    properly       sustained    preliminary
    objections, the appellate court must
    examine the averments in the complaint,
    together with the documents and
    exhibits attached thereto, Witmer v.
    Exxon Corp., 260 Pa.Super. 537, 
    394 A.2d 1276
    (1978), affirmed, 
    495 Pa. 540
    , 
    434 A.2d 1232
    (1981), in order to
    evaluate the sufficiency of the facts
    averred. Mar Ray, Inc. v. Schroeder,
    242 Pa.Super. 14, 
    363 A.2d 1136
                       (1976).      See Lisk Plumbing and
    Heating Co., Inc. v. Schons, 283
    Pa.Super. 344, 
    423 A.2d 1288
    (1981)
    (agreements accompanying complaint
    are part of record).
    Our     inquiry    goes    only  to
    determining the legal sufficiency
    of appellant’s complaint and we
    may      only     decide    whether
    sufficient facts have been pleaded
    which would permit recovery, if
    ultimately proven.       Gordon v.
    Lancaster Osteopathic Hosp.
    Ass’n., 340 Pa.Super. 253, 489
    -4-
    J. S44013/16
    A.2d 1364 (1985). We must be
    able to state with certainty that
    upon the facts averred, the law
    will not permit recovery by the
    plaintiff.’ Berger v. Ackerman,
    293 Pa.Super. 457, 459, 
    439 A.2d 200
    , 201 (1981).
    Fizz v. Kurtz, Dowd & Nuss, Inc., 360
    Pa.Super. 151, 153, 
    519 A.2d 1037
    ,
    1038 (1987). See also Valley Forge
    Towers South Condominium v. Ron-
    Ike Foam Insulators, Inc., 393
    Pa.Super. 339, 345, 
    574 A.2d 641
    , 644
    (1990), affirmed, 
    529 Pa. 512
    , 
    605 A.2d 798
    (1992).
    Guistro Development Co., Inc. v. Lee, 428
    Pa.Super. 394, 399, 
    631 A.2d 199
    , 201-202 (1993).
    This Court will reverse the trial court’s decision only
    where there has been an error of law or abuse of
    discretion.     Bocchicchio v. General Public
    Utilities Corp., 456 Pa.Super. 23, 26, 
    689 A.2d 305
    , 307 (1997). Further, “when the sustaining of
    preliminary objections results in the denial of a claim
    or the dismissal of a suit in a mechanics’ lien
    proceeding, preliminary objections should be
    sustained only where the case is clear and
    doubtless.”     Guistro Development Co., 
    Inc., supra
    . 
    Id. at 400,
    631 A.2d at 202 (citing Castle
    Pre-Cast Superior Walls of Delaware, Inc. v.
    Strauss-Hammer, 416 Pa.Super. 53, 56, 
    610 A.2d 503
    , 504 (1992); Valley Forge Towers South
    Condominium v. Ron-Ike Foam Insulators, 
    Inc., supra
    ).
    Denlinger, Inc. v. Agresta, 
    714 A.2d 1048
    , 1050-1051 (Pa.Super 1998).
    “To effectuate a valid lien claim, the contractor/subcontractor must be
    in strict compliance with the notice requirements of the Mechanics’ Lien
    Law.” 
    Id. at 1052.
    However, while the notice and other requirements under
    -5-
    J. S44013/16
    the Law are to be strictly construed, Pennsylvania courts apply the doctrine
    of substantial compliance such that if enough appears on the face of the
    statement to lead to successful inquiry, the claim may go forward.        
    Id. at 1052-1053.
    Appellant contends that the claim of lien provided the information
    required by the Mechanics’ Lien Law of 1963 (“Law”).1 Appellant argues that
    its claim of lien identified the contract, described the scope of work, set forth
    the amount then due under the contract, and identified the time frame of
    the work with sufficient specificity to demonstrate that the lien was timely
    filed.
    Section 503 of the Law, 49 P.S. § 1503, provides:
    The claim shall state:
    (1)   the name of the party claimant, and whether
    he files as contractor or subcontractor;
    (2)   the name and address of the owner or reputed
    owner;
    (3)   the date of completion of the claimant’s work;
    (4)   if filed by a subcontractor, the name of the
    person with whom he contracted, and the
    dates on which preliminary notice, if required,
    and of formal notice of intention to file a claim
    was given;
    (5)   if filed by a contractor under a contract or
    contracts for an agreed sum, an identification
    of the contract and a general statement of the
    1
    Act of August 24, 1963, P.L. 1175, as amended, 49 P.S. §§ 1101-1902.
    -6-
    J. S44013/16
    kind and character of the labor or materials
    furnished;
    (6)   in all other cases than that set forth in
    clause (5) of this section, a detailed statement
    of the kind and character of the labor or
    materials furnished, or both, and the prices
    charged for each thereof;
    (7)   the amount or sum claimed to be due; and
    (8)   such description of the improvement and of the
    property claimed to be subject to the lien as
    may be reasonably necessary to identify them.
    49 P.S. § 1503.
    The claim of lien stated that appellant performed work pursuant to an
    “agreement” to construct a seven-unit planned unit development residential
    building.   As a result of this agreement, the claim of lien states that
    appellant provided substantial material and services including “engineering,
    excavation, foundation, plumbing, masonry, carpentry, roofing, windows,
    doors and other construction materials and services.” (Lien, at 2 ¶5.)
    The trial court found that appellant did not indicate whether the
    “agreement” or contract was written or oral and could not discern whether
    appellant’s failure to attach the contract was because the contract was oral
    or because appellant simply neglected to do so.
    Although not found in the Law, Pa.R.C.P. No. 1019(h) requires that
    when a claim is based upon an agreement, the pleading shall state if the
    agreement is oral or written, and if written, the agreement should be
    attached.   Appellant did not indicate in the claim of lien whether the
    -7-
    J. S44013/16
    agreement was oral or written.         However, as appellant points out, in
    Denlinger, this court held that where the lien claimant does not indicate in
    the pleading whether the agreement is oral or written, it is presumed to be
    oral.   As a result, this court finds that the fact that a contract was not
    included with the claim of lien does not necessarily mean that the claim of
    lien should be stricken.
    Section 503(5) of the Law, 49 P.S. § 1503(5), also provides that if the
    contract is for an agreed sum, a general statement of the kind and character
    of the labor or materials furnished is required. The trial court determined
    that appellant failed to provide an agreed upon sum. A review of the claim
    of lien confirms that. Although the claim of lien states that the amount of
    $161,000 is due to be paid from the owner of the property for work
    performed, the claim of lien does not indicate whether this was an agreed
    upon amount in the contract. As a result, the claim of lien does not meet
    the requirements of Section 503(5) of the Law.
    Section 503(6) of the Law, 49 P.S. § 1503(6), provides that if there is
    not a contract for an agreed upon sum, then “a detailed statement of the
    kind and character of the labor or materials furnished, or both, and the
    prices charged for each thereof” must be included on the statement of lien.
    As the trial court noted, the claim of lien does not include this important
    information.    While this court is cognizant of the doctrine of substantial
    compliance, the absence of this basic information does not indicate
    -8-
    J. S44013/16
    substantial compliance with the Law.    Additionally, the trial court reported
    that appellant did not ask for leave of court to amend the claim of lien. The
    trial court did not err when it sustained the preliminary objections on the
    basis that the claim of lien did not contain the information required under
    the Law.
    Order affirmed.
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 7/11/2016
    -9-