Charter Homes at Mill Creek v. Charlan Group ( 2019 )


Menu:
  • J-A02009-19
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
    CHARTER HOMES AT MILL CREEK,            :   IN THE SUPERIOR COURT OF
    INC.                                    :        PENNSYLVANIA
    :
    :
    v.                         :
    :
    :
    CHARLAN GROUP, L.P.                     :
    :   No. 1113 MDA 2018
    Appellant             :
    :
    :
    :
    :
    v.                         :
    :
    :
    CHARTER HOMES BUILDING                  :
    COMPANY                                 :
    Appeal from the Judgment Entered June 11, 2018
    In the Court of Common Pleas of Lancaster County Civil Division at
    No(s): CI-15-01375
    BEFORE: LAZARUS, J., DUBOW, J., and NICHOLS, J.
    MEMORANDUM BY LAZARUS, J.:                           FILED APRIL 26, 2019
    Charlan Group, L.P. (“Charlan”), appeals from the judgment entered in
    favor of defendant Charter Homes at Mill Creek, Inc., and additional defendant
    Charter Homes Building Company (collectively, “Charter Building”), following
    a bench trial, the Honorable Leonard G. Brown, III, presiding. The underlying
    dispute between Charlan, a real estate developer, and Charter Building, a
    residential builder, arises out of a Lot Purchase Agreement (“Agreement”) and
    the parties’ subsequent oral modifications. Following trial, the court entered
    J-A02009-19
    judgment in favor of Charter Building in the amount of $1,054,033.95.
    Charlan filed this appeal, raising three issues:
    1.    Did the trial court commit an error of law in failing to follow
    the requirements set out in [Fine v. Checcio,] 
    870 A.2d 850
    (Pa.
    2005),[1] when it determined an applicable statute of limitations
    was tolled?
    2.    Did the trial court abuse its discretion in inferring an
    affirmative act of misrepresentation justifying a tolling of the
    statute of limitations?
    3.    Did the trial court commit an error of law or abuse of
    discretion in not finding Charter Building was estopped from
    changing its acceptance that $8.6 million in Improvement Costs
    had been paid by Charlan?
    Appellant’s Brief, at 4. After our review of the parties’ briefs, the record and
    the relevant law, we affirm based on Judge Brown’s August 6, 2018 Pa.R.A.P.
    1925(a) order, which incorporates his comprehensive findings of fact and
    conclusions of law, filed on May 7, 2018.2
    We first note our limited scope of review following a non-jury trial:
    During a non-jury trial, the trial court acts as the finder of fact and has the
    authority to make credibility determinations and resolve conflicts in evidence.
    Ruthrauff, Inc. v. Ravin, Inc., 
    914 A.2d 880
    , 888 (Pa. Super. 2006). The
    court may believe all, part or none of the evidence. Id.
    ____________________________________________
    1In portions of its brief, Charlan refers to this case as “Checo v. Fine.” See
    Appellant’s Brief, at iv, 10.
    2We refer to the order and findings/conclusions as the court’s May 7, 2018
    opinion.
    -2-
    J-A02009-19
    Issues of credibility and conflicts in evidence are for the trial court
    to resolve; this Court is not permitted to reexamine the weight
    and credibility determinations or substitute our judgment for that
    of the factfinder. Furthermore, the findings of the judge in a non-
    jury trial are given the same weight and effect as a jury verdict
    such that the court’s findings will not be disturbed on appeal
    absent an abuse of discretion, error of law, or lack of support in
    the record. We will not disturb the court’s factual findings merely
    on the basis we would have reached a different conclusion; rather,
    our task is to determine whether there is competent evidence in
    the record that a judicial mind could reasonably have determined
    to support the finding.
    
    Id. at 887
    (citations and quotations omitted).
    The underlying facts are as follows: Charlan purchased undeveloped
    property in Lampeter Township, Lancaster County for $1.3 million, intending
    to develop it into a residential neighborhood. Charlan, which had a business
    relationship with Charter Building, entered into the Agreement with Charter
    Building pertaining to the development of the property, known as Mill Creek.
    The Agreement, dated September 19, 2002, contemplated that Charlan would
    complete the land improvements,3 estimated at $8.6 million, and then sell the
    237 lots to Charter Building.4
    ____________________________________________
    3  The improvements included, inter alia, installation of streets, sidewalks,
    walking paths, storm water management systems, site grading and street
    lighting. See infra, at n. 3.
    4Mill Creek originally had five phases, but Phase 4 was eliminated because
    Charlan sold the land to Charter Building for $670,000.00. Charlan, therefore,
    was relieved of its obligation to complete the improvements associated with
    Phase 4.
    -3-
    J-A02009-19
    Thereafter, disputes arose as to the duties and obligations of the parties
    under the Agreement. Charlan contended it was required to complete
    improvements up to $8.6 million, and that any additional required
    improvements would be the responsibility of Charter Building.            Charter
    Building contended that if improvements cost less than $8.6 million, Charlan
    was required to remit one-half the savings to Charter Building, and if
    improvements cost more than $8.6 million, Charter Building and Charlan
    would evenly share the additional costs. Charter Building would pay its 50%
    share of the additional costs in 237 installments, as it purchased lots from
    Charlan.5
    Further, according to Charter Building, the Agreement provided that,
    depending upon which pricing method was used (aggregate-sum pricing or
    fixed-price method), Charter Building might be obligated to pay an additional
    amount for the purchase of each lot if the improvements totaled more than
    $8.6 million. In other words, Charter Building would be required to reimburse
    Charlan for one-half of the “excess” improvement costs if the aggregate-sum
    pricing method were used. If the fixed-price method were used, then Charter
    Building would have no obligation to reimburse Charlan for any portion of the
    improvement costs overruns. At trial, Charlan’s representative testified that
    Charter Building was responsible for 100% of the costs in excess of $8.6
    million, regardless of which method was used.
    ____________________________________________
    5As stated above, the development was to consist of 237 lots. 
    See supra
    ,
    at p. 2.
    -4-
    J-A02009-19
    In 2006, Charlan informed Charter Building that it had spent $8.6 million
    on improvement costs and thereafter claimed that it had exceed the Adjusted
    Improvement Costs Budget (AICB).6 Trial Court Opinion, supra at 10, citing
    N.T. Bench Trial, 1/4/18, at 90-92; N.T. Bench Trial, 1/5/18, at 183-84, 237.
    At the beginning of the 2008 housing crisis, sales of lots and homes in Mill
    Creek essentially ground to a halt, and Charlan, which had a mortgage on the
    undeveloped property, was concerned about foreclosure.               Charlan was no
    longer in a position to continue paying for improvements in accordance with
    the Agreement. Thus, Charter Building agreed to pay for improvements with
    the understanding that, once the economy improved and sales picked up,
    Charlan would reimburse Charter Building for one-half the costs in excess of
    the AICB.
    Between 2008 and 2010, the height of the housing crisis, only a few lots
    sold; zero lots sold in 2009 and only two lots sold in 2010. In 2012, as the
    economy began to improve, lot sales began to pick up.
    As of October 31, 2012, Charter Building provided an accounting to
    Charlan, showing that Charlan’s share of the excess improvement costs
    beyond the AICB was $592,122. Charter Building indicated to Charlan that it
    would accept $325,000 in settlement of $592,122 amount. Charlan, in a May
    15, 2013 email to Charter Building, agreed to “reimburse” Charter $325,000.
    Charter     presented    Charlan     with      an   Amendment   to   the   Agreement,
    ____________________________________________
    6The cost of Phase 4 improvements that Charlan was not required to complete
    was $605,576.24; $8.6 million less that amount is the AICB - $7,994,423.76.
    -5-
    J-A02009-19
    memorializing this agreement, but Charlan never signed it. See Trial Court
    Opinion, supra at 9, 25; N.T. Bench Trial, 1/4/18, at 72-73.
    In July 2013, Charlan instructed its Comptroller, Julie Landis, to shred
    the last seven (7) years of invoices relating to Mill Creek, thus destroying
    documentation of what Charlan allegedly spent on improvements in 2005 and
    earlier. See Order, 6/11/18 (amending findings of fact). In a September 4,
    2013 email from Charlan to Charter Building, Charlan stated that it was
    obvious the parties “can’t work this out. You have our last offer so do what
    you feel you need to.” Email from Doug Desmond [of Charlan] to Rob Bowman
    [of Charter Building], 9/4/13, Charlan’s Exhibit 29.
    On February 13, 2015, Charter Building filed suit against Charlan,
    alleging breach of contract and related claims, and seeking to recover
    improvement costs pursuant to the Agreement. Charter Building filed an
    amended complaint on April 10, 2017, based on post-complaint discovery,
    that Charlan had not actually reached the AICB amount (of $7,994,423.76).
    In its complaint, Charter Building alleged that after the Agreement was
    signed, “Charlan did not have the funds to pay for all of the Improvements
    and requested that [Charter Building] pay for the Improvements.” Complaint,
    2/13/15, at ¶ 20. Charter Building also alleged that Charlan assured it “that
    it would reimburse [Charter Building] for the amount it had to spend to
    complete the Improvements up to the $8.6 million threshold[, and o]nce the
    costs exceeded $8.6 million, Charlan would reimburse [Charter Building] for
    half the amount spent by [Charter Building] thereafter.” 
    Id. at ¶
    21. See
    -6-
    J-A02009-19
    also 
    id. at ¶
    33. In reliance on Charlan’s promise, Charter Building averred
    that it incurred costs in the amount of $1,246,891.00. 
    Id. at 22.
    Charter Building claimed that it had agreed to use its own funds for
    improvements, “based on its expectation and the understanding between [the
    parties] that Charlan would reimburse [Charter Building] for one hundred
    percent of the amount it spent up to the $8.6 million specified in the
    Agreement, and fifty percent of the amount spent by [Charter Building] above
    and beyond the $8.6 million threshold specified in the Agreement.” 
    Id. at ¶
    29. Further, Charter Building averred that “Charlan failed to pay for the first
    $8.6 million in Improvements Costs and [Charter Building] was required to
    pay for some of the Improvements that were clearly Charlan’s responsibility.”
    
    Id. at 34.
    Robert P. Bowman, President of Charter Building, testified why it was
    Charter Building’s position that Charlan had not paid the threshold $8.6 million
    in improvement costs:
    [W]hen we asked for information, backup, this detailed report was
    provided, say, I think a handful of invoices. There is no – primarily
    no backup to this document. All we really have are these
    headings, what we assume are costs are under those headings
    that were spent at Mill Creek. But if I were just to take out the
    ones that are not improvement costs, the number falls
    dramatically from totals that are here to an amount that we
    believe were paid for improvement costs. So those are two
    reasons I believe that they didn’t hit that. One, I don’t have any
    verification of whether there were Mill Creek invoices or not. The
    second point is that the typical improvement costs which are
    contemplated under the [A]greement, there are a lot of costs on
    this list that aren’t considered improvement costs.
    -7-
    J-A02009-19
    N.T. Bench Trial, 1/4/18, at 91. Additionally, Bowman testified that he first
    came to the conclusion that Charlan had not paid $8.6 million in improvement
    costs “[a]fter we got this detailed summary,” which was in response to a
    discovery request, after the original complaint had been filed in 2015. 
    Id. at 92-93.
    He clarified that between 2007 and 2015, he had no reason to doubt
    that Charlan had paid $8.6 million in improvement costs, because George
    Desmond, general partner of Charlan, with whom he had had a business
    relationship since 1999, had told him so. 
    Id. at 92
    (“George told me $8.6
    million and I believed him.”). At trial, Charlan admitted that the Agreement
    stated that it was required to complete all improvements shown on the
    development plans.7
    ____________________________________________
    7   The Agreement provides, as follows:
    5. RESPONSIBILITIES OF SELLER AND BUYER
    Seller [Charlan] shall be responsible for completion of all
    improvements required in connection with the Land Use Plan,
    recorded Subdivision Plan or Plans, and other plans submitted to
    and approved by all governmental entities having jurisdiction
    thereof (hereinafter collectively referred to as the “Development
    Plans”), in accordance with all requirements of all governmental
    entities having jurisdiction thereof, including all grading, streets,
    curbs, storm water system (excluding individual Lot storm water
    detention facilities, if any), common facilities including (but not
    limited to) the neighborhood center, recreational facilities, walking
    path, street lighting, common area landscaping, and public water
    and sanitary sewer lines, underground electric, telephone and
    other required utilities.
    -8-
    J-A02009-19
    Following trial, the court issued findings of fact and conclusions of law.
    In particular, the court found as follows:
    1. Charlan spent a total of $7,052,519.88 on Improvements;
    2. Charter Building incurred costs of $1,166,164.02 for Improvements;
    3. The total Charlan and Charter Building spent on Improvement Costs
    is $8,218,683.90;
    4. Charlan was solely responsible for paying the Adjusted Improvement
    Costs Budget of $7,994,423.76;
    5. The difference between the $8,218,683.90 and the Adjusted
    Improvement Costs Budget of $7,994,423.76, is $224,260.14;
    ____________________________________________
    Lot Purchase Agreement, 9/19/02, at § 5. The Agreement also provided that
    in the event the improvements totaled less than $8.6 million, Charlan would
    pay half of the difference/savings to Charter Building:
    6. COSTS OF SELLER RESPONSBILITIES                     AND BUYER
    CREDIT
    Seller’s [Charlan’s] direct costs for the responsibilities of Seller as
    forth in Section 6 of this Agreement, including the development of
    all phases of Mill Creek, are estimated to total Eight Million Six
    Hundred Thousand and no/100 Dollars ($8,600,000.00)
    (“Improvement Costs”). . . . Upon the completion of the
    responsibilities of [Charlan] as set forth in Section 5 of this
    Agreement, if the Improvement costs shall be less than Eight
    Million    Six   Hundred      Thousand      and    no/100      Dollars
    ($8,600,000.00), [Charlan] shall pay to [Charter Building] one
    half of the difference between the final Improvement Costs and
    Eight Million six Hundred Thousand and no/100 Dollars
    ($8,6000,000.00).
    
    Id. at ¶
    6.
    -9-
    J-A02009-19
    6. Under section 3(a)(ii) of the Lot Purchase Agreement, Charter
    Building had to pay 50% of the Improvement Costs in excess of the
    budget to Charlan.8 This amounted to $112,130.07; [and]
    7. Since Charter Building had paid $1,166,164.02 for Improvements in
    place of Charlan, when it was only supposed to have paid
    $112,130.07, Charlan owed Charter Building the difference, which
    amounted to $1,054,033.95.
    Trial Court Opinion, 5/7/18, at 12, 22-23. As noted above, the court entered
    judgment in favor of Charter Building for $1,054,033.95. Charlan filed a post-
    trial motion on May 17, 2018 and this timely appeal followed.
    ____________________________________________
    8   Section 3(a)(ii) of the Agreement provides:
    a. For all Lots, [Charter Building] shall pay to [Charlan] as the
    Purchase price for each Lot[:]
    ii.    The aggregate sum of:
    (1)    Twenty Three percent (23%) of the Base Price
    of each home and Lot sold by [Charter Building]
    as Builder to a Homebuyer; and
    (2)    Fifty percent (50%) of the Lot Premium, if any,
    paid by the Homebuyer; and
    (3)    Fifteen percent (15%) of the price of Options
    incorporated into the home sold by [Charter
    Building] as Builder to the Homebuyer, and
    (4)    In the event that Improvement Costs (as
    defined in Section 6 of this Agreement exceed
    the sum of $8,600,000, one two hundred thirty
    sevenths (1/237) of fifty percent of the
    difference between the total Improvement costs
    and $8,600,000.
    Lot Purchase Agreement, supra at 3(a)(ii).
    - 10 -
    J-A02009-19
    We address Charlan’s first two claims together.           Charlan argues the
    court erred in finding that the statute of limitations9 was tolled and in inferring
    that Charlan misrepresented that it had paid $8.6 million in improvement
    costs. Charlan argues that Charter Building’s cause of action accrued in 2006,
    when Charlan first told Charter Building that it had satisfied the relevant
    portion of the Agreement. See Trial Court Opinion, supra at 7, 10. Charlan
    claims that Charter Building’s 2015 lawsuit, amended in 2017, is time-barred
    as to the contract claim, and that the trial court erred in allowing the discovery
    rule to toll the statute, thereby improperly increasing Charter Building’s
    damages. Charlan relies on 
    Fine, supra
    , to support its argument.
    In Fine, the Court stated “the discovery rule applies to toll the statute
    of limitations in any case where a party neither knows nor reasonably should
    have known of his injury and its cause at the time his right to institute suit
    arises.” 
    Id. at 859.
    Charlan is not entitled to relief under Fine.
    The    trial   court   found    that    Charlan   told   Charter   Building   in
    “approximately 2006,” and “[i]n late 2007,” that it had spent $8.6 million
    improvement costs and thereafter consistently claimed it had exceeded the
    AICB. See 
    id. at 7,
    10.            Charlan produced a document entitled “Job
    Transaction Detail Report,” which listed costs Charlan purportedly incurred at
    Mill Creek; however, Charlan produced no invoices, bills, payments requests,
    checks or evidence to support its claims, contending all documentation from
    ____________________________________________
    9 Pennsylvania’s statute of limitations requires lawsuits upon a contract to
    commence within four years. See 42 Pa.C.S.A. § 5525(a).
    - 11 -
    J-A02009-19
    2005 and earlier was destroyed in 2013.         See Order, 6/11/18 (amending
    findings of fact).   Since Charlan destroyed its evidence, and presented no
    evidence in support of its claims, the trial court, sitting as finder of fact, found
    its witnesses not credible. The court found Charter Building credibly testified
    that it was never provided with detailed invoices for amounts it was charged
    by Charlan for improvements prior to 2008. See N.T. Bench Trial, 1/4/18, at
    91-93 (Testimony of Robert Bowman).
    Significantly, the court concluded that Charter Building’s cause of action
    against Charlan arose on September 4, 2013, when Charlan indicated it would
    not be paying the previously-agreed reimbursements (for improvements paid
    for by Charter Building during the height of the housing crisis).          Further,
    Charlan indicated that if Charter Building would not accept reimbursement in
    lots, Charlan essentially invited Charter Building to file suit, “[D]o what you
    feel you need to.” Charter Building then filed its suit on February 13, 2015,
    within the four-year statute of limitations.
    As the court reasoned, “it is not unusual for a party to agree to pay
    money on another’s behalf based on agreement that the debt will be repaid
    at an unspecified later time.” Trial Court Opinion, supra at 23. Here, the
    court concluded that Charlan’s “obligation to repay the debt” arose, based on
    the facts and circumstance here, “when the housing market rebounded.” 
    Id. at 23-24.
    In particular, it was not until after Charter Building filed suit and it
    obtained Charlan’s Job Transaction Detail Report, that Charter Building’s claim
    for the excess improvement costs accrued. The court determined that Charter
    - 12 -
    J-A02009-19
    was previously unaware that Charlan “did not actually incur costs up to the
    [AICB] as Charlan told Charter Building in 2006 that it had spent $8.6 million
    and thereafter consistently claimed that it had exceeded the [AICB]. 
    Id. at 24,
    citing N.T., 1/4/18, at 90-92, N.T. 1/5/18, 183-84, 237.       Thus, the court
    concluded, Charter Buildings’ claim for Charlan’s share of the excess
    improvement costs was timely. 
    Id. at 24.
    We also find Charlan’s argument that the court erred in “inferring an
    affirmative act of misrepresentation” to justify tolling the statute of limitations,
    misplaced. The trial court based its conclusion on the discovery rule-- that
    the statute was tolled because Charter Building did not know, or could not
    reasonably have known, of its damages until (a) Charlan indicated it would
    not reimburse Charter, and (b) Charter Building received Charlan’s Job
    Transaction Detail Report after the original complaint was filed.        Charlan’s
    attempt to cast the trial court’s tolling of the statute as based on a “finding”
    of misrepresentation, is a red herring. Fraudulent concealment is a separate
    ground that may toll a statute of limitations. Charlan attempts to conflate the
    two, arguing that a showing of fraud is required in order for the court to apply
    the discovery rule to toll the statute. Fraud need not be shown in order for a
    party to invoke the discovery rule.       As we noted in Gustine Uniontown
    Assocs., Ltd. v. Anthony Crane Rental, Inc., 
    892 A.2d 830
    (Pa. Super.
    2006):
    The discovery rule is distinct from the issue of whether a party is
    equitably estopped from invoking the statute of limitations. Fine
    v. Checcio, 
    582 Pa. 253
    , 
    870 A.2d 850
    (2005). The discovery
    - 13 -
    J-A02009-19
    rule operates to toll the statute of limitations during the period the
    plaintiff’s injury or its cause was neither known nor reasonably
    knowable to the plaintiff. 
    Id. The separate
    doctrine of fraudulent
    concealment tolls the statute based on an estoppel theory and
    provides that a defendant may not invoke the statute of limitations
    if through either intentional or unintentional fraud or concealment,
    the defendant causes the plaintiff to relax his vigilance or deviate
    from his duty of inquiry into the facts. 
    Id. Thus, the
    former
    doctrine involves a plaintiff’s lack of knowledge and the latter
    doctrine pertains to a defendant’s conduct after the cause of
    action arose.
    
    Id. at 835.n.2.
    Here, the court did not make a finding of misrepresentation; it
    determined that the discovery rule applied. As the record supports the trial
    court’s findings, we find no error. See Gleason v. Borough of Moosic, 
    15 A.3d 479
    (Pa. 2011) (where complaining party is reasonably unaware that his
    or her injury has been caused by another party’s conduct, discovery rule
    suspends, or tolls, running of statute of limitations). See also Ruthrauff,
    supra at 888; John B. Conomos, Inc. v. Sun Co., Inc., 
    831 A.2d 696
    , 703
    (Pa. Super. 2003) (our task is to “determine whether there is competent
    evidence in the record that a judicial mind could reasonably have determined
    to support the finding.”).
    Charlan’s final claim, that the court erred in not finding Charter Building
    was estopped from changing its “acceptance that $8.6 million in Improvement
    Costs had been paid by Charlan,” is waived. Charlan did not raise this claim
    in its May 17, 2018 motion for post-trial relief. See Chalkey v. Roush, 
    805 A.2d 491
    , 496 (Pa. 2002); Pa.R.C.P. 227.1.
    - 14 -
    J-A02009-19
    We, therefore, affirm the judgment entered in favor of Charter Building,
    and we direct the parties to attach a copy of Judge Brown’s comprehensive
    opinion in the event of further proceedings in this matter.   See Pa.R.A.P.
    1925(a) Order, 8/6/18; Findings of Fact/Conclusions of Law, 5/7/18.
    Judgment affirmed.
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 4/26/2019
    - 15 -