Haddad, D. v. Zawilla, G. ( 2016 )


Menu:
  • J-A10033-16
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
    DEBORAH HADDAD                                IN THE SUPERIOR COURT OF
    PENNSYLVANIA
    Appellee
    v.
    GEORGE ZAWILLA AND BONNIE
    ZAWILLA, HIS WIFE, D/B/A GORILLA
    GENERAL CONTRACTOR AND GORILLA
    CONTRACTING
    Appellants                 No. 885 WDA 2015
    Appeal from the Judgment Entered May 6, 2015
    In the Court of Common Pleas of Allegheny County
    Civil Division at No(s): GD 12-024665
    BEFORE: GANTMAN, P.J., BENDER, P.J.E., and PANELLA, J.
    MEMORANDUM BY GANTMAN, P.J.:                 FILED SEPTEMBER 14, 2016
    Appellants, George Zawilla and Bonnie Zawilla, his wife, d/b/a Gorilla
    General Contractor and Gorilla Contracting, appeal from the judgment
    entered in the Allegheny County Court of Common Pleas, in favor of
    Appellee, Deborah Haddad, in this breach of contract action. We affirm.
    The relevant facts and procedural history of this case are as follows.
    On January 3, 2011, Appellee entered into a home improvement contract
    with Appellants for the construction of an addition at Appellee’s home. The
    January 3, 2011 contract listed the price of the addition as $367,200.00.
    Despite the listed contract price, Appellee paid Appellants approximately
    $455,000.00 for Appellants’ work on the project. In April 2012, a dispute
    J-A10033-16
    arose between the parties over money owed.           As a result, both parties
    signed a letter dated May 7, 2012, which stated Appellee would pay
    Appellants   an   additional   $40,000.00   if    Appellants   finished   certain
    construction tasks.     Per the letter, Appellee was to pay Appellants
    $20,000.00 up front and $20,000.00 upon completion of the tasks listed in
    the letter. Appellee paid the initial $20,000.00; however, Appellee refused
    to pay the additional $20,000.00, despite Appellants’ claim that they had
    completed the tasks listed in the May 7, 2012 letter.
    On December 31, 2012, Appellee filed a complaint against Appellant
    George Zawilla.     The complaint alleged Appellant George Zawilla had
    breached the January 3, 2011 home improvement contract and violated the
    Unfair Trade Practices and Consumer Protection Law (UTPCPL).          Appellant
    George Zawilla filed an answer, new matter and counterclaim against
    Appellee on February 23, 2013.       The counterclaim alleged Appellee had
    violated the terms of the May 7, 2012 “substituted contract” when she
    refused to pay the additional $20,000.00.        On March 17, 2014, with the
    court’s permission, Appellee amended the complaint to add Appellant Bonnie
    Zawilla as a defendant.        Appellants filed an answer, new matter and
    counterclaim on July 25, 2014.     The counterclaim once again alleged that
    Appellee had violated the terms of the May 7, 2012 “substituted contract.”
    The parties proceeded to a bench trial, where the court heard
    testimony on November 25, 2014 and January 12, 2015.            On February 4,
    -2-
    J-A10033-16
    2015, the court ruled in favor of Appellee on both her breach of contract
    claim and Appellants’ counterclaim; however, the court ruled in favor of
    Appellants on Appellee’s UTPCPL claim. On February 13, 2015, Appellants
    filed a post-trial motion in which they asked the court to enter judgment
    notwithstanding the verdict or grant a new trial. After argument on April 28,
    2015, the court denied Appellants’ post-trial motion on April 29, 2015. On
    May 6, 2015, the court entered judgment on the verdict in favor of Appellee.
    Appellants timely filed a notice of appeal on June 5, 2015.     On June 10,
    2015, the court ordered Appellants to file a concise statement of errors
    complained of on appeal pursuant to Pa.R.A.P. 1925(b), and Appellants
    timely complied on June 26, 2015.
    Appellants raise the following issues for our review:
    WHETHER THE [TRIAL COURT] ERRED IN FAILING TO
    ENTER JUDGMENT NOTWITHSTANDING THE VERDICT OR
    ORDER A NEW TRIAL BECAUSE APPELLEE FAILED TO
    INTRODUCE ANY EVIDENCE OF A CONTRACT BETWEEN
    APPELLEE AND APPELLANT BONNIE ZAWILLA?
    WHETHER THE [TRIAL COURT] ERRED IN FAILING              TO
    ENTER JUDGMENT NOTWITHSTANDING THE VERDICT              OR
    ORDER A NEW TRIAL BECAUSE APPELLEE FAILED               TO
    OFFER ANY EVIDENCE OF THE EXISTENCE OF                   A
    CONTRACT BETWEEN APPELLEE AND ANY PERSON                OR
    ENTITY OTHER THAN GORILLA CONSTRUCTION, INC.?
    WHETHER THE [TRIAL COURT] ERRED IN FAILING TO
    ENTER JUDGMENT NOTWITHSTANDING THE VERDICT OR
    ORDER A NEW TRIAL BECAUSE THE MAY 2012
    SUBSTITUTED CONTRACT EXTINGUISHED ALL CLAIMS
    EXISTING UNDER THE ORIGINAL CONTRACT?
    (Appellants’ Brief at 2).
    -3-
    J-A10033-16
    Our standard of review for the denial of a motion for JNOV is:
    [Whether], when reading the record in the light most
    favorable to the verdict winner and granting that party
    every favorable inference therefrom, there was sufficient
    competent evidence to sustain the verdict. Questions of
    credibility and conflicts in the evidence are for the trial
    court to resolve and the reviewing court should not
    reweigh the evidence. Absent an abuse of discretion, the
    trial court’s determination will not be disturbed.
    Holt v. Navarro, 
    932 A.2d 915
    , 919 (Pa.Super. 2007), appeal denied, 
    597 Pa. 717
    , 
    951 A.2d 1164
     (2008). Further:
    There are two bases upon which a [JNOV] can be entered:
    one, the movant is entitled to judgment as a matter of
    law, and/or two, the evidence was such that no two
    reasonable minds could disagree that the outcome should
    have been rendered in favor of the movant. With the first,
    a court reviews the record and concludes that even with all
    factual inferences decided adverse to the movant the law
    nonetheless requires a verdict in his favor, whereas with
    the second, the court reviews the evidentiary record and
    concludes that the evidence was such that a verdict for the
    movant was beyond peradventure.
    
    Id.
     “When reviewing a trial court’s denial of a motion for JNOV, we must
    consider all of the evidence admitted to decide if there was sufficient
    competent evidence to sustain the verdict….     Concerning any questions of
    law, our scope of review is plenary. Concerning questions of credibility and
    weight accorded the evidence at trial, we will not substitute our judgment for
    that of the finder of fact…. A JNOV should be entered only in a clear case.”
    
    Id.
    Section 517.7 of the Home Improvement Consumer Protection Act
    (“HICPA”) provides in relevant part:
    -4-
    J-A10033-16
    § 517.7. Home improvement contracts
    (a) Requirements.—No home improvement contract
    shall be valid or enforceable against an owner unless it:
    (1) Is in writing and legible and contains the home
    improvement contractor registration number of the
    performing contractor.
    (2) Is signed by all of the following:
    (i) The owner, his agent or other contracted
    party.
    (ii) The contractor or a salesperson on behalf of
    a contractor.
    (3) Contains the entire agreement between the
    owner and the contractor, including attached copies
    of all required notices.
    (4) Contains the date of the transaction.
    (5) Contains the name, address and telephone
    number of the contractor. For the purposes of this
    paragraph, a post office box number alone shall not
    be considered an address.
    (6) Contains the approximate starting date and
    completion date.
    (7) Includes a description of the work to be
    performed, the materials to be used and a set of
    specifications that cannot be changed without a
    written change order signed by the owner and the
    contractor.
    (8) Includes the total sales price due under the
    contract or includes a time and materials provision
    wherein the contractor and owner agree in writing to
    the performance of the home improvement by the
    contractor and payment for the home improvement
    by the owner, based on time and materials.
    -5-
    J-A10033-16
    *    *    *
    (9) Includes the amount of any down payment plus
    any amount advanced for the purchase of special
    order materials. The amount of the down payment
    and the cost of the special order materials must be
    listed separately.
    (10) Includes the names, addresses and telephone
    numbers of all subcontractors on the project known
    at the date of signing the contract. For the purposes
    of this paragraph, a post office box number alone
    shall not be considered an address.
    (11) Except as provided in section 12, agrees to
    maintain liability insurance covering personal injury
    in an amount not less than $50,000 and insurance
    covering property damage caused by the work of a
    home improvement contractor in an amount not less
    than $50,000 and identifies the current amount of
    insurance coverage maintained at the time of signing
    the contract.
    (12) Includes the toll-free number under section
    3(b).
    (13) Includes a notice of right of rescission under
    subsection (b).
    (b) Right of rescission.—An individual signing a home
    improvement contract…shall be permitted to rescind the
    contract without penalty regardless of where the contract
    was signed, within three business days of the date of
    signing.
    *    *    *
    (g) Contractor’s recovery right.—Nothing in this
    section shall preclude a contractor who has complied with
    subsection (a) from the recovery of payment for work
    performed based on the reasonable value of services which
    were requested by the owner if a court determines that it
    would be inequitable to deny such recovery.
    -6-
    J-A10033-16
    73 P.S. §§ 517.7(a), (b), (g).
    After a thorough review of the record, the briefs of the parties, the
    applicable law, and the well-reasoned opinion of the Honorable Michael A.
    Della Vecchia, we conclude Appellants’ issues merit no relief. The trial court
    opinion comprehensively discusses and properly disposes of the questions
    presented. (See Trial Court Opinion, filed July 22, 2015, at 4-9) (finding:
    (issues    1-2)      evidence   at   trial    demonstrated   that   Appellee      paid
    approximately $455,000.00 to Appellant George Zawilla or one of his
    business entities during construction project on Appellee’s home; each of
    these payments was deposited into personal Dollar Bank account in name of
    Appellant George Zawilla, Appellant Bonnie Zawilla, and Gorilla Built despite
    whether checks were made out to “Gorilla” or “Gorilla Construction”;
    evidence also showed that Appellant Bonnie Zawilla held herself out as sole
    proprietor and owner of company called Gorilla Contracting in connection
    with credit application with supplier Carter Lumber in 2011; during same
    time period and throughout construction at Appellee’s home, Appellants
    represented themselves through trade or business as no less than seven
    separate business entities; when questioned about these distinct business
    entities   at   trial,   Appellant   George    Zawilla   admitted   “they   are    all
    intermingled” and “it all comes down to my last name”; Appellant George
    Zawilla further admitted in deposition in another case that Appellant Bonnie
    Zawilla is also owner of these various entities; neither original contract nor
    -7-
    J-A10033-16
    May 7, 2012 letter contain numerous terms required by HICPA for home
    improvement contracts; specifically, both original contract and May 7, 2012
    letter fail to include home improvement contractor registration number for
    performing contractor, required notices, estimated start and completion
    dates, toll free number, and Notice of Right of Rescission; Appellants also
    failed to identify any subcontractors used on project; further, Appellants did
    not execute any signed change orders for additional moneys paid over
    contract   price   of   $367,200.00;    Appellants’   actions   justified   piercing
    corporate veil under enterprise or “single entity” theory of liability; thus,
    court properly found Appellants personally liable; (issue 3) May 7, 2012
    letter failed to include numerous required terms under HICPA; missing terms
    include performing contractor’s home improvement contractor registration
    number, required notices, approximate start and completion dates for
    project, description of work to be performed, materials to be used, set of
    specifications which cannot be changed without written change order signed
    by homeowner and contractor, total sales price due under contract or time
    and   materials    provision,   names     and   contact    information      for   all
    subcontractors, toll free number, and Notice of Right of Rescission; because
    Appellants failed to follow requirements codified in HICPA, court properly
    refused to enforce May 7, 2012 letter against Appellee as substituted
    contract). Accordingly, we affirm on the basis of the trial court opinion.
    Judgment affirmed.
    -8-
    J-A10033-16
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 9/14/2016
    -9-
    Circulated 08/18/2016 09:56 AM
    IN THE COURT OF COMMON PLEAS OF ALLEGHENY COUNTY, PENNSYLVANIA
    CIVIL DIVISION
    DEBORAH HADDAD,                                             No. GD 12-024665
    Plaintiff,    885 WDA 2015
    vs.
    GEORGE ZAWILLA and BONNIE
    ZAWILLA, his wife, d/b/a GORILLA
    GENERAL CONTRACTOR and
    GORILLA CONTRACTING,
    Defendants.
    OPINION
    .   ..
    :
    Honorable Michael A. Della Vecchia
    71 O City-County Building
    414 Grant Street
    Pittsburgh, PA 15219
    ("')
    ~-.,,.296 A.2d 792
    , 794 (Pa. 1972), any court must
    start from the general rule that the corporate entity should be recognized and upheld,
    unless specific, unusual circumstances call for an exception .... care should be taken on
    all occasions to avoid making the entire theory of corporate entity useless (Advanced
    Telephone Systems v. Com-Net Professional Mobile Radio, LLC, 846 A.2d. 1264-78 (Pa.
    Super. 2004) citing, Zubrik v Zubrik, 
    384 F.2d 267
    , 273 (3d. Cir. 1967)). "The corporate
    form will be disregarded only when the entity is used to defeat public convenience, justify
    wrong, protect fraud or defend crime." (Good v Holstein, 
    787 A.2d 426
    , 430 (Pa.Super.
    2001 )). (quoting Kellytown Co. Williams, 
    426 A.2d 663
    , 668 (Pa.Super. 1981 )).
    The Pennsylvania Commonwealth Court has set out the factors to be considered
    in disregarding the corporate form as follows: undercapitalization, failure to adhere to
    corporate formalities, substantial intermingling of corporate and personal affairs and use
    of the corporate form to perpetuate a fraud (Department of Environmental Resources v.
    Peggs Run Coal Co., 
    423 A.2d 765
     (Pa.Cmlth. 1980)).
    5
    At trial, evidence established none of the purported contracts contain a home
    improvement contractor registration number for the performing contractor; that the
    agreements are deficient in scope, in respect to notices, start and completion dates;
    there is the absence of the toll free number required under Pennsylvania's Home
    Improvement Consumer Protection Act (HICPA); and further deficient as to a Notice of
    the Right of Rescission as required by the Act. Additionally, the Defendants failed to
    identify any subcontractors used on the project or to execute a single Change Order,
    signed by both owner and contractor, for the additional moneys paid over and above the
    contract price.
    This writer found the Defendants actions or inactions justified piercing the
    corporate veil under the enterprise, or single entity theory of liability, in which two or
    more corporations share common ownership and are, in reality, operating as a corporate
    combine (See, Miners Inc., v. Alpine Equipment, 
    722 A.2d 691
    , 694 (Pa.Super. 1998)).
    Following the testimony and evidence produced at trial, it was apparent to this
    writer that the Defendants be held personally liable. 'Where a corporation operates as a
    mere facade for the operations of a dominant shareholder, the dominating shareholder
    may be held liable for the corporation1s inequitable conduct perpetrated through the use
    of the corporate form's protections" (Newcrete Products v. City of Wilkes-Barre, 37 A.3d.
    7, 12 (Pa.Cmwlth. 2012). See also Bennett vs. A. T. Masterpiece, 
    40 A.3d 145
     (2012).
    The Defendants next raise in their third and fourth claims of error exception to this
    writer's finding that the contract was indeed breached by the Defendants. This Court
    was presented with two (2) days of credible evidence that more than convinced this
    writer that the contract was breached by the Defendants.
    6
    Initially, the fact that the Plaintiff paid $455,000.00 for a job which she contracted
    to pay $367 ,200.00 (absent any signed Change Order by the Plaintiff) signaled to this
    writer that there may be a breach. When you combine that fact with the Plaintiff's
    incurred additional and remedial costs of $24,31 o.oo to reinstall the HVAC system; that
    the Plaintiff had paid $11,550.00 for contractors to buy, install and seal new tile flooring;
    additional and remedial electrical work totaling $8,000.00; additional and remedial
    plumbing work in the sum of $16,800.00; $3,231.00 in cleaning costs; additional and
    remedial painting costs in the amount of $24,000.00, this writer was convinced that
    Defendant was in breach of the contract. The Plaintiff credibly testified, which was
    supported by evidence, that she had previously paid and/or needs to pay a total of
    $158,850.00 to correct and complete the work that was contracted to be performed by
    the Defendants. (See Tr. 152-187). And when Patrick McGonigle, the president of
    Welte Roofing Company; James Ireland, an electrical contractor for over forty-nine (49)
    years; Nicholas Kowalecki, a mason; Joseph Pasquale, the owner of The Kitchen and
    Bath Store; and Bernie Swatchick, the plumbing operations manager from Tudi
    mechanical all credibly testified as to the deficiencies with the Defendants' work, this
    Court was more than convinced that the Defendants had breached the contract with the
    Plaintiff (See Tr. 4-79).
    To claim that it was~..Pco find that the Defendants breached their contract when
    faced with a mountain of evidence and testimony to the contrary is disingenuous at best
    and should not be given additional consideration by the Superior Court.
    o<
    The Defendants remaining claims ofv,(- concern this Court's failure to
    acknowledge the letter of May 17, 2012, as a substitute contract or accord and
    7
    satisfaction.   The Defendants assert that the parties to the original contract entered into a
    substituted contract in May of 2012. In April of 2012, a dispute arose between the
    parties as to an owed sum, purported by the Defendants to be $77,800.00.         The May
    2012 agreement is an offer from the Plaintiff to George Zawilla in which the Plaintiff
    proposes an itemized list of building products to be provided or installed for an additional
    amount of $40,000.00, to be paid in two $20,000.00 payments. The Plaintiff failed to pay
    the second installment payment under that agreement.
    Although the Defendants provide the courts with a primer on substituted contracts,
    the Defendants are silent as to why said contract does not have to comport with Home
    Improvement Consumer Protection Act. The Plaintiff has consistently argued that the
    letter of May 7, 2012 is unenforceable as it fails to comply with the Home Improvement
    Consumer Protection Act (hereinafter "HICPA"), codified at 73 P.S. §517.7, which
    includes numerous requirements that are absent in the May 2012 agreement, including:
    (a)(1) in writing and is legible and contains the Home Improvement
    Contractor Registration Number of the performing contractor.
    (a) (3) contains the entire agreement between the owner and the
    contractor, including attached copies of all required notices ..
    (a) (6) contains the approximate starting date and completion date.
    (a) (7) includes a description of the work to be performed, the materials to
    be used and a set of specifications that cannot be changed without a
    written change order signed by the by the owner and contractor.
    (a)(8) includes the total sales price due under the contract or includes a
    time and materials provision wherein contractor and owner agree in writing
    to the performance of the home improvement by the contract and payment
    for the home improvement by the owner, based o time and materials ...
    (a) (10) includes the names, addresses and telephone numbers of all
    subcontractors on the project known at the date of signing the contract.
    8
    (a)(12) includes the toll free telephone number under Section 3(b) ..
    (a)(13) includes a Notice of the Right of Rescission under Subsection (b).
    After assessing the testimony and evidence elicited at trial, it is apparent that the
    Defendants failed to follow any of the requirements codified in the HICPA. This writer is
    unwilling to hold the Plaintiff to a writing that is deficient as to all the requirements
    enacted in an effort to preclude the type of litigation sub judice.
    V. CONCLUSION
    For the above stated reasons, this writer respectfully requests the Superior
    Court of Pennsylvania to affirm this Court's Order dated April 24, 2015.
    9