The Belgravia Condo. Assn. v. 1811 Belgravia Assoc ( 2015 )


Menu:
  • J-A06009-15
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
    BELGRAVIA CONDOMINIUM                       IN THE SUPERIOR COURT OF
    ASSOCIATION,                                      PENNSYLVANIA
    Appellee
    v.
    1811 BELGRAVIA ASSOCIATES
    Appeal of: O’Donnell & Naccarato, Inc.           No. 385 EDA 2014
    Appeal from the Judgment entered November 27, 2013
    In the Court of Common Pleas of Philadelphia County
    Civil Division at No(s): May Term, 2010, No. 00946
    BELGRAVIA CONDOMINIUM                       IN THE SUPERIOR COURT OF
    ASSOCIATION,                                      PENNSYLVANIA
    Appellee
    v.
    1811 BELGRAVIA ASSOCIATES, L.P., ET
    AL.
    Appeal of: O’Donnell & Naccarato, Inc.           No. 446 EDA 2014
    Appeal from the Judgment entered November 27, 2013
    In the Court of Common Pleas of Philadelphia County
    Civil Division at No(s): May Term, 2010, No. 00946
    BEFORE: PANELLA, J., OTT, J., and JENKINS, J.
    MEMORANDUM BY JENKINS, J.                       FILED AUGUST 13, 2015
    J-A06009-15
    A jury entered a verdict of $350,000.00 against O’Donnell &
    Naccarato, Inc. (“Engineer”) in this civil action.   Following denial of post-
    verdict motions and entry of judgment, Engineer filed two appeals which this
    court has consolidated for purposes of disposition.1         For the reasons
    articulated below, we affirm the judgment at 385 EDA 2014 and quash the
    appeal at 446 EDA 2014.
    The Belgravia Building is a century-old building at 1811-19 Chestnut
    Street in Philadelphia. In 2006, a developer, 1811 Belgravia Associates, and
    other related parties2 started to convert the building into a condominium.
    Also in 2006, in order to comply with the Uniform Condominium Act
    (“UCA”),3 the Belgravia defendants hired Engineer to inspect the building
    and report its findings. Engineer is a professional engineering firm that is in
    the business of providing, among other things, structural engineering and
    design services.
    In 2010, Belgravia Condominium Association (“Association”) filed a
    civil action against Engineer and the Belgravia defendants.        Association
    alleged that Engineer was liable for professional negligence and breach of
    ____________________________________________
    1
    Order dated May 19, 2014 (consolidating Engineer’s two appeals sua
    sponte pursuant to Pa.R.A.P. 513).
    2
    We refer to all defendants other than Engineer as the “Belgravia
    defendants”.
    3
    68 Pa.C.S. § 3101 et seq.
    -2-
    J-A06009-15
    the UCA on the grounds that Engineer’s inspection and report fell below the
    standard of care for the engineering profession, and Engineer defrauded
    purchasers of condominium units by revising its draft report to conceal
    defects in the condition of the building.
    At the close of Association’s case-in-chief, Engineer moved for a
    compulsory nonsuit, arguing that its work was not negligent, and that it
    complied with the UCA by identifying all visible defects.4 The trial court did
    not formally deny Engineer’s motion on the record, but it is implicit from the
    record that the court denied the motion because Engineer went on to
    present its own witnesses. Engineer did not move for a directed verdict at
    the close of evidence.
    The verdict slip directed the jury to answer whether Engineer
    “breached the standard of care applicable to professional engineers”, and
    whether “[Engineer’s] breach of the standard of care caused Association
    harm?”5 The jury answered “yes” to both questions and awarded $350,000
    in compensatory damages to Association.6
    ____________________________________________
    4
    N.T., 6/14/13, at 22-31.
    5
    N.T. 6/19/13, at 12-13 (questions 1 and 2 on page 2 of verdict slip).
    6
    
    Id. The jury
    also held the Belgravia defendants liable for $3,800,000 in
    compensatory damages and $900,000 in punitive damages. The Belgravia
    defendants later settled with Association, leaving Engineer as the only
    appellant in these appeals.
    -3-
    J-A06009-15
    Engineer filed timely post-verdict motions seeking judgment n.o.v.,
    which the court denied, followed by a praecipe for entry of judgment against
    itself.     Engineer then filed two appeals, which we have consolidated.
    Without ordering Engineer to file a Pa.R.A.P. 1925(b) statement, the trial
    court filed a Pa.R.A.P. 1925(a) opinion.
    Before turning to Engineer’s arguments, we explain why we quash its
    second appeal.        On December 12, 2013, Engineer filed its first notice of
    appeal following entry of judgment against itself but before entry of a final
    order relating to the Belgravia defendants. On January 2, 2014, the court
    entered an order marking Association’s action against the Belgravia
    defendants settled, discontinued and ended.             This order disposed of all
    remaining claims and parties and made Engineer’s first appeal ripe for
    disposition.       Pa.R.A.P. 905(a)(5) (“a notice of appeal filed after the
    announcement of a determination but before the entry of an appealable
    order shall be treated as filed after such entry and on the day thereof”).
    On January 30, 2014, Engineer filed a second notice of appeal.        It
    appears that Engineer filed this appeal as a protective measure because it
    was uncertain whether its first appeal was timely. Because Engineer’s first
    appeal is ripe for disposition under Pa.R.A.P. 905, we quash its second
    appeal as technically unnecessary.          Pa.R.A.P. 1972(7) (appeal subject to
    quashal for “any … reason appearing on the record”).
    Engineer raises three issues in its first appeal:
    -4-
    J-A06009-15
    The trial judge erred by not applying the economic
    loss doctrine to bar claims for what are solely
    economic losses.
    The trial judge erred in denying [Engineer’s] posttrial
    motion for jnov in a case where: [Association’s]
    experts could not state what defects existed at the
    time of the inspection; recommendations made by
    the inspecting engineer were not followed by the
    owners; and no analysis was offered on how the
    allegedly improper inspection caused any damages.
    [Engineer] did not waive its right to appeal the
    denial of a post-trial motion seeking jnov.
    Brief For Appellant, pp. 13, 14, 25.
    In its first argument, Engineer contends that it is entitled to judgment
    n.o.v. because the economic loss doctrine precludes Association’s claims of
    monetary damage.      The economic loss doctrine provides that no cause of
    action exists for negligence that results solely in economic damages
    unaccompanied by physical injury or property damage. Adams v. Copper
    Beach     Townhome       Communities,        L.P.,   
    816 A.2d 301
    ,   305
    (Pa.Super.2003).   Engineer waived this argument by failing to move for a
    compulsory nonsuit or directed verdict on this issue during trial.
    A motion for judgment n.o.v. is a post-trial motion which requests the
    trial court to enter judgment in favor of the moving party. There are two
    bases on which the court can grant judgment n.o.v.:
    [O]ne, the movant is entitled to judgment as a
    matter of law and/or two, the evidence is such that
    no two reasonable minds could disagree that the
    outcome should have been rendered in favor of the
    movant. With the first, the court reviews the record
    -5-
    J-A06009-15
    and concludes that even with all factual inferences
    decided adverse to the movant the law nonetheless
    requires a verdict in his favor, whereas with the
    second, the court reviews the evidentiary record and
    concludes that the evidence was such that a verdict
    for the movant was beyond peradventure.
    Polett   v.        Public    Communications,         Inc.,    
    83 A.3d 205
    ,     212
    (Pa.Super.2013).          In an appeal from the trial court’s decision to deny
    judgment n.o.v.,
    we must consider the evidence, together with all
    favorable inferences drawn therefrom, in a light most
    favorable to the verdict winner. Our standard of
    review when considering motions for a directed
    verdict and judgment notwithstanding the verdict are
    identical. We will reverse a trial court’s grant or
    denial of a judgment notwithstanding the verdict
    only when we find an abuse of discretion or an error
    of law that controlled the outcome of the case.
    Further, the standard of review for an appellate court
    is the same as that for a trial court.
    
    Id. at 211.
    To preserve a motion for judgment n.o.v. for appeal, the appellant
    must either move for a compulsory nonsuit or a directed verdict during trial.
    The most comprehensive discussion of this point is in Haan v. Wells, 
    103 A.3d 60
    (Pa.Super.2014), where this Court held that the Haans waived their
    challenge     to    the   sufficiency   of   the   evidence   underlying   the    Wells’
    counterclaim by failing to move for a compulsory nonsuit or directed verdict
    during trial. We reasoned:
    Regarding the Haans’ sufficiency challenge, our
    review of the record demonstrates that the Haans
    did not raise such a claim by oral or written motion
    -6-
    J-A06009-15
    with the trial court either for a nonsuit or a directed
    verdict. In Bennyhoff v. Pappert, 
    790 A.2d 313
              (Pa.Super.2001), we set forth the following with
    regard to preserving a sufficiency claim:
    Pursuant to Pa.R.C.P. 230.1(c), a trial
    court may enter a nonsuit in favor of any
    or all [ ] defendants, if, at the close of
    the plaintiff’s case against all defendants,
    the plaintiff has failed to establish a right
    to relief. ‘A motion for compulsory
    nonsuit allows a defendant to test the
    sufficiency of a plaintiff’s evidence.’
    Harnish       v.   School     District     of
    Philadelphia, [] 
    732 A.2d 596
    , 598
    (Pa.1999). A sufficiency of the evidence
    claim may also be raised through a
    motion for a directed verdict. Lear, Inc.
    v. Eddy, 
    749 A.2d 971
    (Pa.Super.2000).
    
    Bennyhoff, 790 A.2d at 317
    (citation modified).
    Because the appellant in Bennyhoff failed to
    request either a nonsuit or a directed verdict, we
    concluded that the appellant’s sufficiency challenge
    was waived. 
    Id. In Estate
    of Hicks v. Dana Companies, LLC, 
    984 A.2d 943
    (Pa.Super.2009) (en banc), an en banc
    panel of this Court noted that the appellants in an
    asbestos case had preserved a challenge to the
    sufficiency of the evidence by making an oral motion
    for a directed verdict at the close of the evidence.
    
    Id. at 951
    n. 3 (citing Hayes v. Donohue Designer
    Kitchen Inc., 
    818 A.2d 1287
    , 1291 n. 4
    (Pa.Super.2003)) (stating ‘cases indicate that in
    order to preserve the right to request a JNOV post-
    trial[,] a litigant must first request a binding charge
    to the jury or move for a directed verdict at trial’).
    Finally, our Commonwealth Court has recognized,
    and adopted, this Court’s adherence to the principle
    that sufficiency challenges must first be raised before
    the trial court by a motion for a directed verdict. In
    Com. Dept. of Gen. Servs. v. U.S. Mineral Prods.
    Co.,    
    927 A.2d 717
      (Pa.Cmwlth.2007),      the
    -7-
    J-A06009-15
    Commonwealth Court, citing Bennyhoff and
    Thomas Jefferson Univ. v. Wapner, 
    903 A.2d 565
    , 570 (Pa.Super.2006), explained that ‘our
    Superior Court requires a motion for directed verdict
    during trial as a prerequisite to a post-trial motion
    for JNOV based on the state of the evidence.’ U.S.
    Mineral     
    Prods., 927 A.2d at 725
    .   The
    Commonwealth      Court    adopted    our   approach
    ‘[b]ecause this approach has the salutary effect of
    submitting the issue to the trial judge for initial
    evaluation during trial, when the proofs are still
    fresh, and is consistent with past practice and with
    the current rule governing post-trial practice.’ 
    Id. Consequently, the
    Commonwealth Court limited its
    appellate review in that case to the appellants’
    challenge to the weight of the evidence, and found
    any challenges to the sufficiency of the evidence to
    be waived. 
    Id. Hence, it
    is clear that, in order to preserve a
    challenge to the sufficiency of the evidence, the
    Haans first were required in this non-jury trial to
    move either for a nonsuit or a directed verdict.
    See Youst v. Keck’s Food Serv., Inc., 
    94 A.3d 1057
    , 1071 (Pa.Super.2014). The Haans did not do
    so. Consequently, any of the Haans’ challenges
    purporting to challenge the sufficiency of the
    evidence offered to prove the Wells’ ownership of
    Parcel No. 2 are waived.
    
    Haan, 103 A.3d at 67-68
    (footnotes omitted) (emphasis added).
    Here, Engineer did not move for a directed verdict at the close of
    evidence.   And while it moved for a compulsory nonsuit at the close of
    Association’s case, it neglected to raise any economic loss doctrine argument
    -8-
    J-A06009-15
    at that time.7      Consequently, Engineer has waived its right to raise the
    economic loss doctrine in this appeal. 
    Haan, supra
    .
    Engineer claims incorrectly that it preserved its motion for judgment
    n.o.v. on the economic loss doctrine by raising it in preliminary objections
    and then again in post-verdict motions.          Under Haan, however, Engineer
    was required to move for a compulsory nonsuit or directed verdict to give
    the trial court the opportunity to decide whether the trial evidence was
    sufficient to go to the jury.           The fact that Engineer filed preliminary
    objections on the economic loss doctrine is of no moment, because
    preliminary objections only test whether the complaint states a valid cause
    of action, not whether the trial evidence is sufficient to go to the jury.
    Meeting House Lane, Ltd. v. Melso, 
    628 A.2d 854
    (Pa.Super.1993),
    the decision Engineer cites for the proposition that it preserved the economic
    loss argument for appeal, is not on point. The trial court in Melso held that
    the appellant waived all issues in his post-trial motion because the motion
    failed to specify where he had raised the issues prior to verdict. This Court
    held a mere defect in form in post-verdict motions did not result in waiver
    because the appellant raised all issues in pretrial proceedings or during trial.
    
    Id., 628 A.2d
    at 857. The present case involves a fundamental trial error by
    counsel for Engineer, not a mere technical defect in the form of post-verdict
    ____________________________________________
    7
    N.T., 6/14/13, at 22-31.
    -9-
    J-A06009-15
    motions: counsel neglected to argue during trial that the trial evidence was
    insufficient as a matter of law under the economic loss doctrine. Counsel’s
    omission results in waiver under Haan.
    In its second argument on appeal, Engineer contends that the trial
    court erred in denying judgment n.o.v. for four reasons: (1) Association
    made no showing that the defects in the building were visible; (2)
    Association’s experts did not testify with the requisite degree of engineering
    certainty; (3) there was no proof tying the relationship between Engineer’s
    conduct and the amount of money damages caused to Association; and (4)
    Engineer’s conduct in 2006 was too remote in time to constitute the
    proximate cause of the damages, and there were other intervening causes of
    harm, such as other inspections conducted after Engineer’s failure to
    uncover defects, and Association’s failure to perform proper maintenance
    after 2006.8
    Subpart I is a claim that Association failed to prove that Engineer
    breached the applicable standard of care. Engineer contends that the proper
    standard of care is a duty to discover visible defects that is embodied in
    section 4-106 of the UCA, codified at 68 Pa.C.S. § 3404. Brief For Appellant,
    p. 15.   This argument is unconvincing for two reasons: the UCA does not
    ____________________________________________
    8
    Because Engineer has grouped these four issues under one heading in its
    brief, we will refer to them as “Subpart I”, “Subpart II”, “Subpart III” and
    “Subpart IV”.
    - 10 -
    J-A06009-15
    provide the applicable standard of care for Engineer, and even if the UCA
    provides the correct standard, the evidence demonstrates that Engineer
    breached it.
    68 Pa.C.S. § 3404 provides in relevant part:
    (a)   The   public   offering  statement   of    a
    condominium containing a conversion building
    must contain …
    (1) A statement by the declarant, based on a
    report prepared by an independent registered
    architect or professional engineer:
    (i) describing the age and present condition
    and, if known or reasonably ascertainable, the
    dates of construction, installation and major
    repairs of all structural components and
    mechanical     and    electrical   installations,
    including, but not limited to, roofs, plumbing,
    heating, air conditioning and elevators,
    material to the use and enjoyment of the
    condominium; and
    (ii) describing the results of the inspection of
    the units and common elements required
    pursuant to section 3411(c) (relating to
    warranty against structural defects) for visible
    conditions that adversely affect the health or
    safety of residential occupants. The statement
    should also state the extent to which the
    report by the architect or professional engineer
    is based upon a visual inspection of the units
    as well as the common elements.
    68 Pa.C.S. § 3404 (emphasis added).             The UCA defines “declarant” as
    follows:
    - 11 -
    J-A06009-15
    (1) If the condominium has been created,
    ‘declarant’ means:
    (i) any person who has executed a declaration,
    or an amendment to a declaration to add
    additional real estate, other than persons
    holding interests in the real estate solely as
    security for an obligation, persons whose
    interests in the real estate will not be conveyed
    to unit owners, or, in the case of a leasehold
    condominium, a lessor who possesses no
    special declarant rights and who is not an
    affiliate of a declarant who possesses special
    declarant rights; or
    (ii) any person who succeeds under section
    3304 (relating to transfer of special declarant
    rights) to any special declarant rights.
    (2) If the condominium has not yet been
    created, ‘declarant’ means any person who
    offers to dispose of or disposes of his interest
    in a unit to be created and not previously
    disposed of.
    (3) If a declaration is executed by a trustee of
    a land trust, ‘declarant’ means the beneficiary
    of the trust.
    68 Pa.C.S. § 3103.       A “declaration” is a document that creates the
    condominium and defines its basic elements, such as the number of units,
    boundaries, common elements, etc. 68 Pa.C.S. § 3205 (contents of
    declaration).
    The standards prescribed in section 3404 only apply to declarants, i.e.,
    signers of the declaration.   Engineer is not itself a “declarant”; it merely
    provides a report to the declarant about the condition of the condominium.
    Thus, the standards prescribed under section 3404, including the duty to
    - 12 -
    J-A06009-15
    report “visible conditions that adversely affect the health or safety of
    residential occupants,” does not apply to Engineer.
    Assuming arguendo that the “visible condition” standard applies to
    engineers, Association presented evidence that Engineer overlooked visible
    defects in the building and failed to mention these defects in its 2006 report.
    Patrick McCoy, one of Association’s experts, testified that Engineer (1) failed
    to have a licensed engineer perform a sufficient visual assessment and write
    the report,9 (2) failed to investigate cracks in the mortar joints which were
    visible in 2006 and would have led to discovery of distress in the facade,10
    (3) failed to observe visibly corroded iron cast balconies on top of terra
    cotta, missing mortar joints and severe deterioration in the mortar,11 (4)
    failed to comply with the UCA by not reviewing public records of the
    building,12 (5) failed to identify issues with rainwater conductors that existed
    in 2006 and which caused severe water damage and corrosion,13 and (6)
    deleted or altered portions of its draft report to cover up these defects.14
    ____________________________________________
    9
    N.T., 6/12/13 (PM), at 31-32, 42-43.
    10
    
    Id. at 41-42.
    11
    
    Id. at 31-32.
    12
    
    Id. at 44-45.
    13
    
    Id. at 33-35.
    14
    
    Id. at 63-64.
    (Footnote Continued Next Page)
    - 13 -
    J-A06009-15
    McCoy testified that Engineer overlooked visible safety hazards during
    its 2006 inspection and neglected to mention them in its report.     According
    to McCoy, (1) Engineer failed to notice that rain water conductors were
    failing and causing corrosion on the steel deck15; (2) Engineer did not notice
    “severe deterioration” to the balconettes that “was the same then [in 2006]
    as when [McCoy] did [his] inspection in 2011, and … some of those joints
    were opened up and … there was already cracking and mortar that was
    missing”16; (3) Engineer failed to note the lack of maintenance in any
    facades or windows from 1983 to 2006, even though the trim around the
    windows was “completely rotten”17; and (4) Engineer ignored severe
    corrosion on the portico in front of the building in 2011.18
    Thus, even if the “visible condition” standard was the proper test,
    Association presented sufficient evidence to satisfy it.19
    _______________________
    (Footnote Continued)
    15
    
    Id. at 34-35.
    McCoy testified that he “believe[d]” that a licensed
    professional engineer would have observed this defect and included it in its
    report.    
    Id. at 35.
       The verb “believe” did not make his testimony
    insufficient, because he later testified that all of his opinions were within a
    reasonable degree of engineering certainty. 
    Id. at 70-71.
    16
    
    Id. at 41-42.
    17
    
    Id. at 49-51.
    18
    
    Id. at 55-56.
    19
    Engineer not only fails to convince us that section 3404 is the proper
    standard of care, but he also fails to identify the proper standard or analyze
    the evidence under the proper standard. Therefore, Engineer has waived
    (Footnote Continued Next Page)
    - 14 -
    J-A06009-15
    In Subpart II, Engineer claims that Association’s experts failed to
    testify with the requisite degree of engineering certainty. Engineer waived
    this argument by failing to make it at the compulsory nonsuit or directed
    verdict stages. 
    Haan, 103 A.3d at 67-68
    . Even if Engineer preserved this
    issue, two of Association’s experts testified that their opinions were within a
    reasonable degree of certainty in their respective fields.20
    Engineer argues in Subpart III that Association failed to prove any
    relationship between Engineer’s conduct and the amount of money damages
    caused to Association.          Engineer disregards McCoy’s testimony that the
    deletions and alterations to the draft report caused the following damages:
    $287,000 for elevator repairs, $41,448 for providing an adequate accessible
    entrance, $20,000 to repair steel platform and stairs, and $15,000 to repair
    corroded beams and cracked concrete in the basement.21             McCoy also
    observed that Association would incur $228,808.30 to repair the roof and
    $65,600 to repair structural defects in the building.22        Another expert,
    _______________________
    (Footnote Continued)
    the argument that the evidence fails to satisfy the correct standard of care.
    Owens v. Mazzei, 
    847 A.2d 700
    , 705-06 (Pa.Super.2004) (issues waived
    due to lack of argument in appellate brief).
    20
    N.T., 6/12/13 (PM), at 70-71 (McCoy), 82-83 (Nevel).
    21
    
    Id. at 67-70.
    22
    
    Id. at 27.
    - 15 -
    J-A06009-15
    William Payne, gave exhaustive testimony about the damage caused to the
    building,23 and testified that Association incurred $400,000 in hazard
    mitigation expenses and $900,000 for waterproofing and aesthetic repairs. 24
    In Subpart IV, Engineer contends that its conduct in 2006 was not the
    proximate cause of Association’s harm, because Engineer’s conduct was too
    remote in time, and there were other intervening causes of harm, such as
    other inspections conducted after Engineer’s failure to uncover defects, and
    Association’s failure to perform proper maintenance after 2006.             Engineer
    has waived this argument by making a different argument on appeal than it
    made below. Engineer’s lone causation argument at the nonsuit stage was
    that Association was contributorily negligent because it failed to review
    public documents (a Deed of Façade Easement and title report) that would
    have alerted Association to any problems.              Association, Engineer argued,
    “[was] on constructive or actual notice of the deed of façade easement,” but
    from 2006 onward, “nobody decided to follow the … mandates of the
    easement” with “constant inspections, constant vigilance.”25 In this Court,
    however,      Engineer       argues      that      Association   ignored   Engineer’s
    recommendations for repair work/maintenance, a separate and distinct
    ____________________________________________
    23
    N.T. 6/13/13, at 17-70.
    24
    N.T. 6/13/13, at 17.
    25
    N.T. 6/14/13, at 25, 26.
    - 16 -
    J-A06009-15
    matter from Assocation’s failure to follow the easement. Because Engineer
    failed to argue at the compulsory nonsuit stage that Association ignored its
    recommendations for repair work/maintenance, it waived this point on
    appeal. 
    Haan, 103 A.3d at 67-68
    .
    In its third and final argument on appeal, Engineer contends that it did
    not waive its right to appeal the denial of a post-trial motion seeking
    judgment n.o.v.      We have addressed this issue above in the foregoing
    discussion by identifying several issues that Engineer waived by failing to
    raise them at the compulsory nonsuit or directed verdict stages of trial.
    For these reasons, the trial court properly denied Engineer’s post-trial
    motions seeking judgment n.o.v.
    Judgment affirmed at 385 EDA 2014.        Appeal quashed at 446 EDA
    2014.
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 8/13/2015
    - 17 -