Independent Enterprises v. JD Fields ( 2015 )


Menu:
  • J-A07041-15
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
    INDEPENDENT ENTERPRISES, INC.                   IN THE SUPERIOR COURT OF
    PENNSYLVANIA
    Appellee
    v.
    JD FIELDS & CO., INC.
    Appellant                No. 1421 WDA 2014
    Appeal from the Judgment Entered August 4, 2014
    In the Court of Common Pleas of Allegheny County
    Civil Division at No(s): GD-12-013078
    BEFORE: BENDER, P.J.E., LAZARUS, J., and MUNDY, J.
    MEMORANDUM BY MUNDY, J.:                            FILED MARCH 26, 2015
    Appellant, JD Fields & Co., Inc. (JD Fields), appeals from the August 4,
    2014 judgment of $38,601.66 entered, after a jury trial, in favor of Appellee,
    Independent Enterprises, Inc. (Independent).        After careful review, we
    affirm.
    The trial court summarized the relevant factual and procedural history
    of this case as follows.
    [Independent] is a construction company
    specializing in utility contracting involving water and
    sewer line work. [JD Fields] is a supplier of sheet
    piling products.      [Independent] purchased sheet
    piling material from [JD Fields] … to build a
    cofferdam in its efforts to complete a construction
    project. Sheet piling consists of long, flat sheets of
    steel that slide together to form a solid wall. These
    temporary cofferdams are used to keep water out of
    a work area.
    J-A07041-15
    [On July 27, 2012 Independent] filed this
    action against [JD Fields] asserting that said sheet
    piling supplied by [JD Fields] was defective, causing
    [Independent] to incur additional labor and
    equipment costs to install and remove the defective
    material.
    In February of 2012, [Independent] first
    contacted [JD Fields] to obtain information about its
    interlocking sheet piling products. [Independent]
    maintains that at said time the purpose of their
    project was explained to [JD Fields]; and based on
    [Independent]’s needs, [JD Fields] suggested the
    use of a specific product, Hoesch 1205k interlocking
    sheet piling. The marketing materials distributed by
    [JD Fields] represented that the product, among
    other things, shall have adequate free play so that
    the piles can be fitted into each other.
    On February 28, 2012, [Independent] issued
    Purchase Order 51359 (hereinafter “PO”).       Said
    order was a request for 143,985 pounds of Hoesch
    1205k sheet piling to be delivered on site in
    Pittsburgh for the price of $98,629.73. On March 8,
    2012, [JD Fields] delivered 143,985 pounds of said
    material to said site.
    [Independent] maintains that as installation of
    the sheet piling began, its employees immediately
    experienced a defect in the interlocking mechanism.
    Specifically, the interlocking mechanism did not
    contain adequate free play to allow the sheet pilings
    to be easily joined together. [Independent] further
    maintained that its employees had substantial
    experience and training with sheet piling as the
    installers were members of the local Millwrights and
    Pile Drivers Union. [Independent] asserted that the
    contractors had never experienced sheet piling that
    fit together so poorly. [Independent never paid the
    invoice for the purchase price of the sheet piling.]
    [Independent] claimed that the failure of the
    sheet piling to conform to the requirements or to [JD
    Fields’] published specifications constituted a breach
    -2-
    J-A07041-15
    of contract. [Independent] further claimed that the
    sheet pilings[’] failure to conform to the assertions
    made in the publication provided by [JD Fields], i.e.
    the product could be easily joined, constituted a
    breach of an express warranty.
    …
    This matter was initiated by a [c]omplaint filed
    by [Independent] on July 27, 2012. Following a brief
    round of preliminary objections challenging both the
    venue and facts, [JD Fields] filed an [a]nswer, [n]ew
    [m]atter and [c]ounterclaim on December 19, 2012
    [for $104,547.51, the total amount of the purchase
    price for the sheet piling it provided]. The case was
    then listed for trial.
    The parties were before [the trial court] in late
    March of 2014, and after argument on [m]otions in
    [l]imine were held, a three (3) day jury trial took
    place. At the conclusion of said trial, a [v]erdict was
    rendered in favor of [Independent] and against [JD
    Fields] in the amount of $90,875.42 and a verdict
    was entered in favor of [JD Fields] in its counter
    claim [sic] in the amount of $52,273.76.[1] The
    verdict was later molded by the [trial c]ourt to reflect
    an award in favor of [Independent] in the amount of
    $38,601.66.
    [JD Fields] timely filed a [m]otion for [p]ost-
    [t]rial [r]elief. Following argument on said [m]otion
    for [p]ost-[t]rial [r]elief, [the trial court] entered an
    [o]rder on July 1, 2014 denying [the] same.
    Judgment on the [v]erdict was entered on August 4,
    2014, in the amount of $38,601.66. [JD Fields] filed
    ____________________________________________
    1
    The jury’s award of $90,875.42 in favor of Independent was based on the
    invoices it submitted regarding the extra equipment, labor, and two
    subcontractor costs associated with the sheet piling provided by JD Fields.
    As we explain infra, $52,273.76 was 50% of the JD Fields’ invoice, rounded
    upward to the nearest penny.
    -3-
    J-A07041-15
    a [timely n]otice of [a]ppeal to [this Court] on
    August 28, 2014.[2]
    On September 3, 2014, [the trial c]ourt
    directed … JD Fields to file a [c]oncise [s]tatement of
    matters [c]omplained of on [a]ppeal pursuant to
    Pennsylvania Rule of Appellate Procedure … 1925(b).
    Said statement was timely filed on September 24,
    2014, placing this matter properly before [this Court.
    The trial court filed its Rule 1925(a) opinion on
    October 29, 2014].
    Trial Court Opinion, 10/29/14, at 1-4 (internal quotation marks omitted).
    On appeal, JD Fields presents the following five issues for our review.
    1.     Whether expert testimony on the performance
    and characteristics of steel construction
    material known as sheet piling and the time it
    should take to install such sheet piling, the
    knowledge of which requires special skill and
    training, was necessary to prove a construction
    delay claim based on an alleged defect?
    2.     Whether the trial court erred in admitting
    opinion testimony about the existence of a
    “defect” in the sheet piling and the amount of
    time that would “normally” be required to
    install sheet piling where such testimony was
    provided by fact witnesses who had not been
    qualified or offered as expert witnesses?
    3.     Whether the evidence admitted at trial would
    not allow any reasonable jury to determine
    that [JD Fields] breached a contract for the
    sale of sheet piling to [Independent] in its
    provision of the sheet piling or that
    [Independent] established any damages with
    reasonable certainty?
    ____________________________________________
    2
    Independent has not filed a cross-appeal.
    -4-
    J-A07041-15
    4.     Whether, as a matter of law and upon
    consideration of the evidence at trial, it was
    error for the trial court to deny JD Fields’
    motion to set aside the verdict and grant
    additur to the verdict in its favor because, in
    the absence of any evidence disputing the
    amount of JD Fields’ damages, no two
    reasonable minds could disagree that the
    outcome should have been in favor of JD Fields
    for the amount of its invoice and JD Fields
    established with reasonable certainty that it
    had suffered damages in a sum certain amount
    of $104,547.51?
    5.     Whether the trial court erred in failing to grant
    remittitur because the damages award to
    [Independent], granting it in essence more
    than its damages claim, was neither fair nor
    reasonable and instead was excessive,
    arbitrary, and not supported by the evidence,
    and shocked the conscience so as to suggest a
    mistake?
    JD Fields’ Brief at 5-6.
    We begin by noting our standards of review regarding judgment
    notwithstanding the verdict (JNOV) and the awarding of a new trial.
    In reviewing a trial court’s decision whether or
    not to grant judgment in favor of one of the parties,
    we must consider the evidence, together with all
    favorable inferences drawn therefrom, in a light most
    favorable to the verdict winner. Our standard[s] of
    review when considering motions for a directed
    verdict and judgment notwithstanding the verdict are
    identical. We will reverse a trial court’s grant or
    denial of a judgment notwithstanding the verdict
    only when we find an abuse of discretion or an error
    of law that controlled the outcome of the case.
    Further, the standard of review for an appellate court
    is the same as that for a trial court.
    -5-
    J-A07041-15
    There are two bases upon which a judgment
    N.O.V. can be entered; one, the movant is entitled to
    judgment as a matter of law and/or two, the
    evidence is such that no two reasonable minds could
    disagree that the outcome should have been
    rendered in favor of the movant. With the first, the
    court reviews the record and concludes that, even
    with all factual inferences decided adverse to the
    movant, the law nonetheless requires a verdict in his
    favor. Whereas with the second, the court reviews
    the evidentiary record and concludes that the
    evidence was such that a verdict for the movant was
    beyond peradventure.
    Reott v. Asia Trend, Inc., 
    7 A.3d 830
    , 835 (Pa. Super. 2010) (citation
    omitted), affirmed, 
    55 A.3d 1088
    (Pa. 2012).
    Our review of the trial court’s denial of a new
    trial is limited to determining whether the trial court
    acted capriciously, abused its discretion, or
    committed an error of law that controlled the
    outcome of the case. In making this determination,
    we must consider whether, viewing the evidence in
    the light most favorable to the verdict winner, a new
    trial     would    produce     a    different   verdict.
    Consequently, if there is any support in the record
    for the trial court’s decision to deny a new trial, that
    decision must be affirmed.
    Joseph v. Scranton Times, L.P., 
    89 A.3d 251
    , 260 (Pa. Super. 2014)
    (citations omitted).
    We elect to address JD Fields’ third issue first, as a ruling in its favor
    on this issue would entitle it to judgment. In its third issue, JD Fields avers
    that it is entitled to JNOV because “the evidence was, as a matter of law,
    insufficient to create an issue of fact for the jury, and JD Fields was entitled
    to a verdict in its favor.” JD Fields’ Brief at 34. Specifically, JD Fields argues
    -6-
    J-A07041-15
    that the evidence is insufficient to establish that it breached its contract with
    Independent and that Independent established its damages with reasonable
    certainty. 
    Id. at 34-35.
    Generally, “[t]o successfully maintain a cause of action for breach of
    contract the plaintiff must establish: (1) the existence of a contract,
    including its essential terms, (2) a breach of a duty imposed by the contract,
    and (3) resultant damages.” Albert v. Erie Ins. Exch., 
    65 A.3d 923
    , 928
    (Pa. Super. 2013) (citation omitted). Furthermore, with regard to damages,
    our Supreme Court has noted the following.
    Where one party to a contract without any legal
    justification, breaches the contract, the other party is
    entitled to recover, unless the contract provided
    otherwise, whatever damages he suffered, provided
    (1) they were such as would naturally and ordinarily
    result from the breach, or (2) they were reasonably
    foreseeable and within the contemplation of the
    parties at the time they made the contract, and (3)
    they can be proved with reasonable certainty.
    Helpin v. Trustees of Univ. of Pa., 
    10 A.3d 267
    , 270 (Pa. 2010).
    Additionally, “Pennsylvania law has never required proof of such damages to
    a mathematical certainty.      This Court has long held that the evidence
    necessary to establish damages is no more than ‘the best evidence
    available.’” Hatwood v. Hosp. of the Univ. of Pa., 
    55 A.3d 1229
    , 1237
    (Pa. Super. 2012) (internal citations omitted), appeal denied, 
    65 A.3d 414
    (Pa. 2013).    As an appellate court, “[i]f the verdict bears a reasonable
    resemblance to the damages proven, we will not upset it merely because we
    -7-
    J-A07041-15
    might have awarded different damages.”                    Newman Dev. Grp. of
    Pottstown, LLC v. Genuardi’s Family Mkt., Inc., 
    98 A.3d 645
    , 659-660
    (Pa. Super. 2014) (en banc) (citation omitted).
    As the trial court notes, “[t]his cause of action was merely to
    determine     whether      the   product       supplied   by   [JD   Fields]    met   the
    representations made by [JD Fields], i.e., that the sheet piling supplied by
    [JD Fields] allowed for adequate ‘free play’ as promised.”3                    Trial Court
    Opinion, 10/29/14, at 7-8. In this case, Independent elicited testimony on
    direct examination from Jack Cargoni, an operating engineer and owner of
    Independent, that the bulk of the sheet piling had “free play” issues after
    delivery.
    Q:     You heard [other witnesses] describe the
    problems that they experienced with the sheet
    piling?
    A:     That’s correct.
    Q:     And did you observe them taking these steps
    to try to fit the sheet piling together?
    A:     I was involved with it. 100 percent throughout
    the whole ordeal.
    …
    Q:     What did you do once those problems started?
    ____________________________________________
    3
    Independent refers to this as an “express warranty” regarding the sheet
    piling.  Independent’s Brief at 12.    JD Fields does not challenge this
    characterization. See generally JD Fields’ Reply Brief at 2 n.1.
    -8-
    J-A07041-15
    A:    Whenever -- as soon as we started having
    problems, big problems as far as the sheets
    not going in at all, we had minor problems to
    start with and then we started having major
    problems, and that’s when I got ahold of the
    office to get ahold of Geno Shore to get ahold
    of JD Fields and have a representative sent out
    immediately.
    Q:    Now, we said there are 85 pairs. Did every
    one of these 85 pairs not fit together?
    A:    No. There was some that mated up.             Some
    that mated up.
    Q:    Slid together?
    A:    Slid together. And there was some that just
    didn’t slide together at all.
    Q:    As a percentage of the whole, how many of
    them did you have -- how many sheets did you
    have problems with?
    A:    75 percent of them.
    N.T., 3/25/14, at 172-173. JD Fields’ own witness, Dan Abbondanza, who
    was    called    to   the   site   after   Independent   reported    the    problems,
    acknowledged that 25% of the sheet piling had this issue. 
    Id. at 266.
    As to damages, Cargnoni testified that he drew up an invoice for the
    extra costs associated with the sheet piling provided by JD Fields, including
    additional labor costs. N.T., 3/25/14, at 184. Cargnoni divided such costs
    into   four   distinct   categories,   equipment,   labor,   and    two    contractor-
    subcontractor categories. 
    Id. at 185.
    Cargnoni explained to the jury how
    each line was calculated in detail.          
    Id. at 185-189.
      Cargnoni sent the
    -9-
    J-A07041-15
    invoice to JD Fields, but it did not pay said invoice. 
    Id. at 189.
    Cargnoni
    later adjusted the labor costs downward in a second invoice.                 
    Id. at 191-
    192. These invoices were admitted without objection. 
    Id. at 184,
    235.
    Although      JD   Fields   points    out     inconsistencies   in   Independent’s
    witnesses’ testimony regarding damages, these inconsistencies do not
    render Independent’s evidence insufficient. See DeArmitt v. N.Y. Life Ins.
    Co., 
    73 A.3d 578
    , 593 (Pa. Super. 2013) (stating with regard to calculation
    of damages, “[a]lthough the factfinder may not render a verdict based on
    sheer conjecture or guesswork, it may use a measure of speculation in
    estimating damages[]”) (citation omitted); Epstein v. Saul Ewing, LLP, 
    7 A.3d 303
    , 314 (Pa. Super. 2010) (stating, “[w]here the evidence of damages
    presented by the plaintiff is contested by the defendant, the jury in a civil
    action does not have to accept the plaintiff’s measure of damages because
    the jury is free to accept all, part, or none of the evidence[]”) (citation
    omitted), appeal denied, 
    20 A.3d 1212
    (Pa. 2011).                      Based on these
    considerations, we conclude there is evidence in the record for the jury to
    conclude that Independent proved breach and damages by a preponderance
    of the evidence. See 
    Reott, supra
    . As a result, JD Fields is not entitled to
    relief on this issue.
    We next address JD Fields’ first and second issues together, as they
    are interrelated.    In its first issue, JD Fields argues that Independent was
    required to provide expert testimony to establish “the purported cause of
    - 10 -
    J-A07041-15
    any installation issues with the [s]heet [p]iling.” JD Fields’ Brief at 25. JD
    Fields further avers that Independent failed to “present expert testimony to
    allow the jury to conclude that any such installation issues caused [it] to
    suffer a delay, and thus damages, on the River Crossing Project.” 
    Id. In its
    second issue, JD Fields argues that Independent’s witnesses who testified to
    the subject matters of “the performance and characteristics of sheet piling,
    [the] installation time for sheet piling, and whether the [s]heet [p]iling had
    adequate free play[]”offered only inadmissible lay opinion evidence. 
    Id. at 30.
    Our standard of review with regard to evidentiary issues at trial is well
    settled.
    When we review a trial court ruling on
    admission of evidence, we must acknowledge that
    decisions on admissibility are within the sound
    discretion of the trial court and will not be
    overturned absent an abuse of discretion or
    misapplication of law. In addition, for a ruling on
    evidence to constitute reversible error, it must have
    been harmful or prejudicial to the complaining party.
    An abuse of discretion is not merely an error of
    judgment, but if in reaching a conclusion the law is
    overridden or misapplied, or the judgment exercised
    is manifestly unreasonable, or the result of partiality,
    prejudice, bias or ill-will, as shown by the evidence
    or the record, discretion is abused.
    Phillips v. Lock, 
    86 A.3d 906
    , 920 (Pa. Super. 2014) (citation omitted).
    Pennsylvania Rules of Evidence 701 and 702 describe the interplay
    between lay witnesses and expert witnesses.
    Rule 701. Opinion Testimony by Lay Witnesses
    - 11 -
    J-A07041-15
    If a witness is not testifying as an expert, testimony
    in the form of an opinion is limited to one that is:
    (a) rationally based on the witness’s perception;
    (b) helpful to clearly understanding the witness’s
    testimony or to determining a fact in issue; and
    (c) not based on scientific, technical, or other
    specialized knowledge within the scope of Rule 702.
    Rule 702. Testimony by Expert Witnesses
    A witness who is qualified as an expert by
    knowledge, skill, experience, training, or education
    may testify in the form of an opinion or otherwise if:
    (a) the expert’s scientific, technical, or other
    specialized knowledge is beyond that possessed by
    the average layperson;
    (b) the expert’s scientific, technical, or other
    specialized knowledge will help the trier of fact to
    understand the evidence or to determine a fact in
    issue; and
    (c) the expert’s methodology is generally accepted in
    the relevant field.
    Pa.R.E. 701, 702.
    JD Fields points to several cases in which the courts of this
    Commonwealth have held expert testimony was required to assist the trier
    of fact.   In Electron Energy Corp. v. Short, 
    597 A.2d 175
    (Pa. Super.
    1991), affirmed, 
    618 A.2d 395
    (Pa. 1993), this Court held that expert
    testimony was required in a breach of contract action in order to show that
    there was a breach of “a duty to design a [heating and cooling] system up to
    reasonable professional standards[.]” 
    Id. at 180.
    JD Fields also points to
    - 12 -
    J-A07041-15
    the Commonwealth Court’s decision in Tennis v. Fedorwicz, 
    592 A.2d 116
    (Pa. Cmwlth. 1991) in which it concluded that expert testimony was
    “indispensable for proving that the road was negligently designed.”4 
    Id. at 117.
    In   this   case,   Independent         presented   the   testimony   of   Arthur
    Klajnowski. Before Klajnowski began his testimony, the trial court cautioned
    counsel that Klajnowski was not to give any expert opinion, but rather “[h]e
    can only talk about facts, what he actually saw on the job.” N.T., 3/24/14,
    at 48. Klajnowski had been employed with the local pile drivers’ union for
    27 years.      
    Id. at 50.
          Klajnowski worked on this particular job with
    Independent and he explained the difficulties he faced working with this
    sheet piling on this specific job.
    Q:     Can you describe for the jury what the problem
    is that you experienced on this job?
    A:     The sheet piling would not go together. It
    would not run. Meaning -- by run, I mean
    when you drop it, it is supposed to go down to
    the bottom. It wasn’t doing that.
    Q:     When you drop it, describe for the jury when
    you drop it.
    ____________________________________________
    4
    We note that “[t]his Court is not bound by decisions of the Commonwealth
    Court. However, such decisions provide persuasive authority, and we may
    turn to our colleagues on the Commonwealth Court for guidance when
    appropriate.” Petow v. Warehime, 
    996 A.2d 1083
    , 1088 n.1 (Pa. Super.
    2010) (citations omitted), appeal denied, 
    12 A.3d 371
    (Pa. 2010).
    - 13 -
    J-A07041-15
    A:   With the crane. You have the crane and let
    them come down on it. They are supposed to
    slide together.
    …
    Q:   What did you have to do to deal with the
    difficulty in sliding these pieces together?
    A:   We actually had to get an air tugger and burn
    holes in the bottom of the sheet, hook them to
    the template and drag them down.
    Q:   What is an air tugger?
    A:   It is actually like a chain pull. It is a chain with
    hooks on either end powered by air that turns
    and pulls the sheet piling down.
    …
    Q:   Did you do anything else? Did you have to do
    anything else besides use an air tugger?
    A:   Yes. They actually greased the sheets first and
    then they decided to use soap on them to try
    to get them to slide.
    Q:   Did that help?
    A:   Not really.
    Q:   Did you try anything else other using an air
    tugger and greasing or soaping the channels?
    A:   We used a vibratory hammer that you’re
    supposed to use to drive the sheets down once
    they are in. We used -- looks like a hairpin.
    That’s what we call it. It is just weight to get
    on top of the sheet and try to push it with that.
    
    Id. at 55-59.
    - 14 -
    J-A07041-15
    Independent also called Michael Pape, its foreman on this project, to
    testify to the sheet piling and the problems that he encountered.
    Q:    Tell us what you understand sheet piling to be.
    A:    It is an interlocking system for whatever kind
    of work, shoring or dirt jobs, cofferdams or
    whatever need be.
    …
    Q:    Tell us very succinctly the problem with the
    sheet piling on this project.
    A:    The sheet piling wouldn’t go together.
    Q:    What solutions did you try to employ to solve
    that?
    A:    We cut the tips of the sheet piling that was
    already instituted in the river. We cut a notch
    out in the sheet piling that we are going to
    bring into the river, we do cut a notch out to
    try to get it going and it catch the notch where
    you already have a couple inches going in
    there and we would soap it up with a lubricant
    to try to get it to slide together.
    Q:    Are you on site when you removed the sheet
    piling in this case?
    A:    Yes.
    Q:    Were there any problems removing the sheet
    piling from the river?
    A:    Yes.
    Q:    What were the problems?
    A:    We couldn’t get them -- some of them would
    pull apart and we had trouble. You go to pull
    one out and you would be pulling three or four
    - 15 -
    J-A07041-15
    sheets at one time to get them out, so we got
    -- instead of trying to separate them and get
    them out, we would swing them off the river
    and lay them on the ground and try to pull
    them apart with an excavator so we could get
    them on the truck and load them up.
    Q:    Had you had to use excavators to pull them
    apart on a prior sheet piling project that you
    worked on?
    A:    No. We slid them apart.
    
    Id. at 72,
    89-90.
    Here, the trial court concluded that expert testimony was not required
    in this case based on the following.
    [The trial court] heard nothing prior to or
    during the trial to convince the [trial] court that the
    jury would need the assistance of an expert with the
    concept of two pieces of sheet metal not fitting
    together.     Nor did [the trial court] hear any
    testimony from either side that sounded too highly
    technical or beyond a layperson’s understanding.
    The case sub judice was not a professional
    malpractice action or complex products liability
    matter involving complex language or techniques
    necessitating opinions proffered by an expert, nor
    does the instant case involve a design defect of a
    technical nature. This cause of action was merely to
    determine whether the product supplied by [JD
    Fields] met the representations made by [JD Fields],
    i.e., that the sheet piling supplied by [JD Fields]
    allowed for adequate “free play” as promised.
    Trial Court Opinion, 10/29/14, at 7-8.
    After careful review, we agree with the trial court’s reasoning and
    conclusion.     Unlike Electron Energy Corp. and Tennis there was no
    - 16 -
    J-A07041-15
    requirement that the jury needed to find that JD Fields breached a duty of
    care or that the sheet piling had a design defect. As Independent argues, it
    does not matter why the sheet piling did not fit together as promised, just
    that it did not do so. Independent put forth factual evidence in the form of
    testimony from Klajnowski and Pape as to what occurred with this particular
    shipment of sheet piling on this specific construction job. This did not cross
    into the realm of impermissible expert opinion under Rule 702, nor was it
    improper lay opinion under Rule 701. Rather, Klajnowski and Pape testified
    to what they observed personally regarding this product on this job, as a
    matter of fact, not as a matter of opinion.5            Cargnoni testified that he
    expected to install 15 to 20 piles in an eight-hour shift, this answer was
    based on his experience, and was his estimate for this project.               See
    generally N.T., 3/24/14, at 162.               Klajnowski testified, based on his
    experience, that one could put 158 sheets in per day. 
    Id. at 63.
    Based on
    ____________________________________________
    5
    JD Fields highlights one instance where Klajnowski stated that the sheet
    piling was “supposed to fit together[.]” N.T., 3/24/14, at 55. However, the
    record reveals that JD Fields immediately objected, the trial court sustained
    JD Fields’ objection, and JD Fields requested no further relief from the trial
    court. 
    Id. at 56.
    As the trial court ruled in JD Fields’ favor on this specific
    instance, it cannot complain about it on appeal. See generally Coffey v.
    Minwax Co., Inc., 
    764 A.2d 616
    , 622 (Pa. Super. 2000). In its brief, JD
    Fields complains that Klajnowski gave expert testimony when he stated that
    other factors did not cause the problems they had with the sheet piling. JD
    Fields’ Brief at 32; N.T., 3/24/14, at 61. However, we note JD Fields did not
    object to this question, thus waiving the issue on appeal. See 
    id. - 17
    -
    J-A07041-15
    these considerations, we conclude the trial court did not abuse its discretion
    with regard to these issues. See 
    Phillips, supra
    .
    Finally, we elect to address JD Fields’ fourth and fifth issues together,
    as they pertain to the damage awards in this case. In its fourth issue, JD
    Fields    argues   that   the   jury   should    have   awarded   damages   on    its
    counterclaim in the amount of $104,547.51.              JD Fields’ Brief at 38.   It
    argues that because the parties stipulated to the existence of the contract,
    which contained a purchase price of $104,547.51, and Independent “offered
    no evidence to discount the amount of damages cause[d] to JD Fields by
    [Independent’s] refusal to pay the invoice[,]” JD Fields should have been
    awarded the invoice amount in full. 
    Id. at 38-39.
    JD Fields also argues that
    it is entitled to prejudgment interest at the rate of six-percent per annum
    beginning on April 8, 2012. 
    Id. at 41.
    Finally, in its fifth issue, JD Fields
    avers that it is entitled to remittitur because the jury’s $90,875.42 award to
    Independent on its claim “was neither fair nor reasonable.” JD Fields’ Brief
    at 42.     JD Fields further argues that Independent “was more than made
    whole for its purported and unsupported damages and put into a position
    better than if the contract between the parties had been performed.” 
    Id. As noted
    above, “[w]here an appellant’s claim arises from a challenge
    to the jury’s determination of damages, our review is highly circumspect.”
    Helpin, supra at 601 n.9.
    The duty of assessing damages is within the province
    of the fact-finder and should not be interfered with
    - 18 -
    J-A07041-15
    unless it clearly appears that the amount awarded
    resulted    from    partiality,  caprice,   prejudice,
    corruption or some other improper influence.
    Generally, a verdict will not be disturbed merely on
    account of the smallness of the damages awarded or
    because the reviewing court would have awarded
    more. To support the granting of a new trial for
    inadequacy, the injustice of the verdict should stand
    forth like a beacon. So long as the verdict bears a
    reasonable resemblance to the damages proved, it is
    not the function of the court to substitute its
    judgment for that of the jury.
    
    Epstein, supra
    (citation omitted).      In addition, we note our standard of
    review of a denial of remittitur is whether or not the trial court abused its
    discretion. Paliometros v. Loyola, 
    932 A.2d 128
    , 134 (Pa. Super. 2007)
    (internal citations omitted).
    In this case, the parties appear to agree that the purchase price for
    the sheet piling was $104,547.51. JD Fields’ Brief at 38; Independent’s Brief
    at 13.   As noted above, Independent’s witness testified that 75% of the
    sheet piling that was delivered did not fit together. N.T., 3/25/14, at 173.
    JD Fields’ witness, Abbondanza, testified that 25% of the sheet piling had
    this issue.     
    Id. at 266.
        The mean and median between these two
    percentages is 50%.        The jury awarded JD Fields $52,273.76 on its
    counterclaim, which is 50% of the purchase price agreed to by the parties,
    rounded upward to the nearest penny. See generally JD Fields’ Brief at 38;
    Independent’s Brief at 13.       As the trial court noted, “the jury simply
    reconciled the testimony to accept the fact that half of said sheets would not
    allow for adequate ‘free play’ and awarded their damage figure accordingly.”
    - 19 -
    J-A07041-15
    Trial Court Opinion, 10/29/14, at 8.           As there is a basis for the jury’s
    decision, as an appellate court, we will not substitute our judgment for the
    jury or grant additur because this Court might “have awarded more.”
    
    Epstein, supra
    .        In addition, we further conclude that remittitur is not
    warranted. The jury’s verdict in this case found that Independent was 50%
    liable for the purchase price of the sheet piling that Independent received.
    Therefore, Independent did not receive a windfall as JD Fields argues, and
    the jury’s verdict does not shock the conscience. We hence conclude that
    the trial court did not err or abuse its discretion when it denied additur or
    remittitur in this case. See id.; 
    Paliometros, supra
    .
    Turning to the prejudgment interest portion of its argument, JD Fields
    relies on Section 354 of the Restatement (Second) of Contracts in support of
    its argument.6 JD Fields argues that it is entitled as of right to prejudgment
    interest under Section 354(1) of the Restatement, as the issue in this case
    ____________________________________________
    6
    Independent argues that JD Fields waived this issue “by failing to raise the
    issue at trial, and by failing to request an instruction to the jury on the same
    during the charging conference.” Independent’s Brief at 14. However, this
    Court has held that “even if the issue of prejudgment interest was not
    submitted to the jury, the trial court may mold the verdict to include it.”
    Verner v. Shaffer, 
    500 A.2d 479
    , 482 (Pa. Super. 1984); see also
    McMahon v. Caravan Refrigerated Cargo, Inc., 
    594 A.2d 349
    , 352 (Pa.
    Super. 1991) (distinguishing Verner and concluding the prejudgment
    interest issue was waived because, unlike Verner, “the issue of pre-
    judgment interest was not raised in appellee’s post-trial motions[]”). JD
    Fields raised the issue of prejudgment interest in its post-trial motion. JD
    Fields’ Post-Trial Motion, 4/4/14, at ¶ 24. As a result, JD Fields has not
    waived this issue.
    - 20 -
    J-A07041-15
    was a sum certain.     JD Fields’ Brief at 41.     The restatement provides as
    follows.
    § 354 Interest as Damages
    (1) If the breach consists of a failure to pay a
    definite sum in money or to render a performance
    with fixed or ascertainable monetary value, interest
    is recoverable from the time for performance on the
    amount due less all deductions to which the party in
    breach is entitled.
    …
    Restatement (Second) of Contracts § 354(1) (1981).            Furthermore, our
    Supreme Court has explained the issue of prejudgment interest in the
    following terms.
    In adopting Section       354     [of   the   Restatement
    (Second)], we stated:
    For over a century it has been the law of this
    Commonwealth that the right to interest upon
    money owing upon contract is a legal right.
    That right to interest begins at the time
    payment is withheld after it has been the duty
    of the debtor to make such payment.
    Fernandez[v. Levin, 
    548 A.2d 1191
    , 1193 (Pa.
    1988)].
    With regard to prejudgment interest, we have
    explained, “[i]nterest has been defined ‘to be a
    compensation allowed to the creditor for delay of
    payment by the debtor,’ and is said to be impliedly
    due ‘whenever a liquidated sum of money is unjustly
    withheld.’” School Dist. of City of Carbondale v.
    Fidelity & Deposit Co. of Maryland, 
    346 Pa. 491
    ,
    492, 
    31 A.2d 279
    , 280 (1943) (citations omitted).
    However,    “as    prerequisites  to  running    of
    prejudgment interest, the debt must have been
    - 21 -
    J-A07041-15
    liquidated with some degree of certainty and the
    duty to pay it must have become fixed.” 
    Id. at 493,
               31 A.2d at 280; Restatement (Second) of Contracts
    § 354(1) (“If the breach consists of a failure to pay a
    definite sum of money or to render a performance
    with fixed or ascertainable monetary value, interest
    is recoverable.”). Thus, even where the terms of a
    contract do not expressly provide for the payment of
    interest, a nonbreaching party has a legal right to
    recover interest, as damages, on a definite sum
    owed under the contract.
    Furthermore, as is the case with an award of
    contractual interest, an award of prejudgment
    interest under Section 354(1) is not subject to a
    court’s discretion. See id.; Dox Planks[of Ne. Pa.
    v. Ohio Farmers Ins. Co., 
    621 A.2d 132
    , 136 (Pa.
    Super. 1993)] (citing Fernandez, and holding a
    successful plaintiff in a contract case is entitled to
    prejudgment interest at the statutory rate as a
    matter of right); Peterson v. Crown Fin. Corp.,
    
    661 F.2d 287
    , 293 (3rd Cir. 1981) (applying
    Pennsylvania law and holding that a “court is thus
    obligated to award ‘simple interest at the statutory
    legal rate’ only in those circumstances in which the
    plaintiff proves that the defendant breached a
    promise to pay ‘a definite sum of money’”).
    TruServ Corp. v. Morgan’s Tool & Supply Co., Inc., 
    39 A.3d 253
    , 263-
    264 (Pa. 2012) (emphasis in original; footnotes omitted).
    Independent counters that JD Fields’ reading of Section 354 is flawed
    and offers the following illustration from the comment to Section 354.
    9. A contracts to build a bungalow for B for $30,000.
    After completion but before B has paid the final
    $6,000, B occupies the bungalow but refuses to pay
    the balance because the workmanship and materials
    are unsatisfactory. A sues B and recovers only
    $4,000 on the ground that B’s claim entitles him to
    compensation in the amount of $2,000. The sum of
    $4,000 was not sufficiently definite to give A a right
    - 22 -
    J-A07041-15
    to interest on it. The allowance of interest is within
    the discretion of the court. The fact that A was
    himself in breach will be considered.
    Independent’s Brief at 15, quoting Restatement (Second) of Contracts
    § 354, cmt.
    In our view, this illustration is much like the instant case.    Here, JD
    Fields agreed to provide sheet piling to Independent for $104,547.51. After
    receiving said sheet metal, Independent refused to pay the invoice because
    it viewed the sheet metal as unsatisfactory. JD Fields filed a counterclaim
    against Independent seeking the amount due under the original contract. JD
    Fields was awarded 50% of their original contract or $52,273.76. Following
    the Restatement, we agree with Independent that this amount “was not
    sufficiently definite to give [JD Fields] a right to interest on it.” Restatement
    (Second) of Contracts § 354, cmt. As a result, JD Fields did not have a legal
    right to prejudgment interests under Section 354(1), as there was not a sum
    certain in this case. See id.; TruServ Corp., supra at 264 n.12. Based on
    these considerations, we conclude JD Fields is not entitled to relief on its
    fourth or fifth issues.
    Based on the foregoing, we conclude all of JD Fields’ issues on appeal
    are devoid of merit. Accordingly, the trial court’s August 4, 2014 judgment
    entered in favor of Independent is affirmed.
    Judgment affirmed.
    - 23 -
    J-A07041-15
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 3/26/2015
    - 24 -