Kelly Systems v. Fiore, L. v. OGP Architects ( 2018 )


Menu:
  • J-A13043-18
    
    2018 PA Super 293
    KELLY SYSTEMS, INC.                       :   IN THE SUPERIOR COURT OF
    :         PENNSYLVANIA
    :
    v.                           :
    :
    :
    LEONARD S. FIORE, INC.                    :
    :
    :
    v.                           :
    :
    :
    OGP ARCHITECTS, LLP,                      :
    :
    Appellant              :        No. 1714 WDA 2017
    Appeal from the Order October 25, 2017
    in the Court of Common Pleas of Blair County,
    Civil Division at No(s): No. 2017-GN-115
    BEFORE: OLSON, J., DUBOW, J., and MUSMANNO, J.
    OPINION BY MUSMANNO, J.:                            Filed: October 31, 2018
    OGP Architects, LLP (“OGP”), appeals from the Order granting the
    “Motion for Determination as to Necessity of Certificate of Merit” filed by
    Leonard S. Fiore, Inc. (“Fiore”), and declaring that Fiore was not required to
    file a Pa.R.C.P. 1042.3 Certificate of Merit in support of its Pa.R.C.P. 2252
    Complaint (the “Joinder Complaint”) to join OGP as an additional defendant.
    We affirm.
    Fiore, a general contractor, was hired to build the “core and shell” of a
    building in State College, Pennsylvania (the “Project”). Fiore entered into a
    contract (the “Kelly Subcontract”) with Kelly Systems, Inc. (“Kelly”), to install
    exterior wall panels on the building. Fiore entered into a separate contract
    J-A13043-18
    (the “OGP Subcontract”) with OGP to provide architectural designs for the
    Project. Kelly used the OGP drawings to calculate its bid for the Project and
    to complete construction.
    On October 4, 2016, Kelly requested a change order with Fiore, pursuant
    to the terms of the Kelly Subcontract,1 allegedly due to OGP’s architectural
    drawings calling for an “impossible to construct” mounting system.              Kelly
    advised Fiore that its proposed solution would cost $225,126.18 more than
    the original contract price.           Fiore rejected the change order.         Kelly
    subsequently submitted a letter to Fiore, requesting that Fiore reconsider the
    rejection, and advising that Kelly intended to proceed with its proposed
    solution. Fiore never accepted the change order, and Kelly continued to work
    on the Project, including implementing its proposed solution to the allegedly
    defective designs.
    On January 12, 2017, Kelly filed a Complaint (“Kelly’s Complaint”)
    against Fiore, seeking, inter alia, payment of $225,000.00 for the additional
    ____________________________________________
    1   Paragraph 9 of the Kelly Subcontract provides, in relevant part, as follows:
    Before proceeding with any [w]ork involving possible claims by
    [Kelly] for extra compensation above the [original contract price],
    [Kelly] shall submit in writing to [Fiore] a detailed estimate of the
    price for such extra [w]ork and materials and shall secure from
    [Fiore] a written order describing such work and fixing [Kelly’s]
    compensation. … Any change order work performed without
    [Fiore’s] prior written authorization pursuant to the foregoing
    procedures shall be at [Kelly’s] risk without right of payment or
    reimbursement under contract, quantum meruit or otherwise.
    Kelly Subcontract, 7/20/15, at ¶ 9 (italicization added).
    -2-
    J-A13043-18
    costs caused by the allegedly defective design. Fiore filed an Answer, in which
    it argued, inter alia, that it is not responsible for the additional costs allegedly
    incurred by Kelly. Fiore subsequently filed the Joinder Complaint, joining OGP
    as an additional defendant, and incorporating, without admitting, the
    allegations made in the Complaint.        Fiore additionally alleged that “OGP’s
    design documents and information provided under the [OGP S]ubcontract
    deviate from the acceptable professional standards … [and] to the extent any
    of Kelly’s alleged damages, in whole or in part, result from OGP’s acts or
    omissions … OGP is responsible and liable for Kelly’s damages.”             Joinder
    Complaint, 3/17/17, at ¶¶ 17-18.
    OGP filed a Pa.R.C.P. 1042.6 Notice of intent to enter judgment of non
    pros against Fiore, for Fiore’s failure to file a certificate of merit with the
    Joinder Complaint. Subsequently, Fiore filed a Motion seeking a determination
    by the trial court as to whether Fiore was required to file a certificate of merit.
    Following a hearing and submission of briefs, the trial court entered an Order
    declaring that Fiore was not required to file a certificate of merit, because
    Fiore’s negligence claim is related to the claims raised in Kelly’s Complaint.
    OGP thereafter filed the instant appeal.
    OGP’s issue on appeal is as follows:
    Whether the trial court erred in finding that [Kelly] pled a
    negligence claim against Fiore in submitting defective design
    specifications and/or in rejecting a change order as a result[,] and
    that    therefore[,]   Fiore’s   claims   for   contribution     and
    indemnification against OGP by incorporation of [Kelly’s] “bogus”
    averments[,] without verifying the truth thereof in the [J]oinder
    -3-
    J-A13043-18
    [C]omplaint[,] related to the “acts of negligence” set forth in
    [Kelly’s] [C]omplaint, which then did not require Fiore to file a
    certificate of merit under [Pa.R.C.P.] 1042.3(C)(2)[?]
    Brief for Appellant at 6.
    Prior to addressing OGP’s claim, we must determine whether this Court
    has jurisdiction to entertain the instant appeal.2 See Pennsy Supply, Inc.
    v. Mumma, 
    921 A.2d 1184
    , 1198 n.10 (Pa. Super. 2007) (stating that “[t]his
    Court may raise matters regarding its jurisdiction sua sponte.”). This Court
    “has jurisdiction to entertain appeals taken (1) as of right from a final order,
    … (2) from interlocutory orders by permission, … (3) from certain interlocutory
    orders    as   of   right,   …    and    (4)   from   certain   collateral   orders....”
    Redevelopment Auth. v. Int'l Ins. Co., 
    685 A.2d 581
    , 585 (Pa. Super.
    1996) (citations omitted).
    OGP alleges that its appeal is from a collateral order pursuant to
    Pa.R.A.P. 313. See Brief for Appellant at 2. OGP argues that the trial court’s
    Order can be addressed without analyzing the underlying central issue of the
    case, i.e., Fiore’s entitlement to damages, because whether Fiore must file a
    certificate of merit is a “procedural mechanism that does not resolve any
    substantive aspect of the claims.” 
    Id.
     According to OGP, resolving this issue
    is of great importance, because the rule regarding certificates of merit
    ____________________________________________
    2 On January 2, 2018, this Court issued a Rule to Show Cause why OGP’s
    appeal should not be quashed as an interlocutory appeal. On January 19,
    2018, following a Response from OGP, the Rule was discharged, but the issue
    was deferred for review by this panel.
    -4-
    J-A13043-18
    “minimize[s] the time and expense that may be incurred” by the parties to
    the litigation.    
    Id.
       OGP asserts that if its claim is not reviewed now, the
    protection granted by the certificate of merit rule – avoiding litigation of
    baseless claims – will be irreparably lost. Id. at 2-3.
    The collateral order doctrine
    permits a party to take an immediate appeal as of right from an
    otherwise unappealable interlocutory order if the order meets
    three requirements: (1) the order must be separable from, and
    collateral to, the main cause of action; (2) the right involved must
    be too important to be denied review; and (3) the question
    presented must be such that if review is postponed until after final
    judgment, the claim will be irreparably lost.
    Commonwealth v. Harris, 
    32 A.3d 243
    , 248 (Pa. 2011) (citing Pa.R.A.P.
    313(b)).
    Rule 313 must be interpreted narrowly, and the requirements for
    an appealable collateral order remain stringent in order to prevent
    undue corrosion of the final order rule. To that end, each prong
    of the collateral order doctrine must be clearly present before an
    order may be considered collateral.
    Melvin v. Doe, 
    836 A.2d 42
    , 46–47 (Pa. 2003) (citation omitted).              “In
    adopting    a     narrow   construction,   we   endeavor   to   avoid   piecemeal
    determinations and the consequent protraction of litigation. Such piecemeal
    litigation imposes a substantial burden on the orderly administration of
    justice.” Rae v. Pa. Funeral Dirs. Ass’n, 
    977 A.2d 1121
    , 1129 (Pa. 2009)
    (citations and quotation marks omitted).
    Here, the resolution of whether Fiore must file a certificate of merit
    requires no analysis of the merits of Fiore’s underlying claim. See K.C. v.
    -5-
    J-A13043-18
    L.A., 
    128 A.3d 774
    , 778 (Pa. 2015) (stating that “an order is separable from
    the main cause of action if it is entirely distinct from the underlying issue in
    the case and if it can be resolved without an analysis of the merits of the
    underlying dispute.” (quotation marks omitted)).
    Additionally, there is a strong public interest in deterring frivolous
    negligence claims. See Geniviva v. Frisk, 
    725 A.2d 1209
    , 1214 (Pa. 1999)
    (stating that “[o]nly those claims that involve interests deeply rooted in public
    policy can be considered too important to [be] denied review.” (quotation
    marks and citation omitted)); see also Warren v. Folk, 
    886 A.2d 305
    , 307
    (Pa. Super. 2005) (stating that “[t]he goal of the certificate of merit is to weed
    out clearly nonmeritorious lawsuits early in the litigation process.”).
    Finally, OGP’s claim that Fiore must file a certificate of merit would be
    irreparably lost if the matter proceeded to trial. Accordingly, OGP’s appeal is
    from a collateral order, and we will review its claim on the merits.
    “[T]he interpretation and application of a Pennsylvania Rule of Civil
    Procedure presents a question of law.       …   Accordingly, … our standard of
    review is de novo, and our scope of review is plenary.” Barrick v. Holy Spirit
    Hosp. of the Sisters of Christian Charity, 
    32 A.3d 800
    , 808 (Pa. Super.
    2011) (citations and quotation marks omitted).
    OGP contends that the trial court erred in finding that Kelly pled a
    negligence claim against Fiore, which allowed Fiore to not file a certificate of
    merit for its negligence claim against OGP. Brief for Appellant at 16, 19. OGP
    argues that Kelly’s claims against Fiore are contract-based, whereas Fiore’s
    -6-
    J-A13043-18
    claims against OGP are tort-based. Id. at 19-21. OGP claims that Kelly did
    not allege any acts of negligence against Fiore, but instead, all of the
    averments in Kelly’s Complaint revolve exclusively around the denial of Kelly’s
    change order, which process is defined in the Kelly Subcontract. Id. at 20.
    OGP further alleges that the trial court failed to consider that Kelly’s claims
    are based on the implied duty of good faith and fair dealing, which “arises
    under the law of contracts, not under the law of torts.” Id. at 21 (citations
    omitted). Lastly, OGP alleges that it would be contrary to the spirit of the
    certificate of merit requirement for this Court to allow Fiore to pursue a
    professional negligence claim solely by “incorporation of [the] bogus
    averments” set forth in Kelly’s Complaint, “without admitting the truth
    thereof.” Id. (quotation marks omitted).
    In its Opinion, the trial court addressed OGP’s claim as follows:
    Specific rules of civil procedure apply for an action in
    professional liability by a patient or client of a licensed professional
    or a partnership, unincorporated association, corporation, or other
    entity responsible for a licensed professional who deviated from
    the professional standard. Pa.R.C.P. 1042.1[]. The rule lists
    professions covered by the rules, including architects. Pa.R.C.P.
    1042.1(iii). An action in professional negligence is different from
    an action in ordinary negligence[,] as a complaint in professional
    liability concerns negligence which breaches a professional
    standard. See Merlini ex rel. Martini v. Gallitzin Water Auth.,
    
    980 A.2d 502
    , 507 (Pa. 2009). When a party alleges a deviation
    from the professional standard, the party is required to file a
    [c]ertificate of [m]erit either with the complaint or within sixty
    (60) days of filing the complaint. Pa.R.C.P. 1042.3(a). The
    [c]ertificate of [m]erit must state either:
    (1) an appropriate licensed professional has supplied
    a written statement that there exists a reasonable
    -7-
    J-A13043-18
    probability that the care, skill or knowledge exercised
    or exhibited in the treatment, practice or work that is
    the subject of the complaint, fell outside acceptable
    professional standards and that such conduct was a
    cause in bringing about the harm, or
    (2) the claim that the defendant deviated from an
    acceptable professional standard is based solely on
    allegations that other licensed professionals for whom
    this defendant is responsible deviated from an
    acceptable professional standard, or
    (3) expert testimony of an appropriate licensed
    professional is unnecessary for prosecution of the
    claim.
    Pa.R.C.P. 1042.3(a)(1)-(3). However, the filing of a [c]ertificate
    of [m]erit is not always required in certain instances relating to
    joinder or cross-claims. …
    [] A defendant or an additional defendant who has
    joined a licensed professional as an additional
    defendant or asserted a cross-claim against a licensed
    professional need not file a certificate of merit unless
    the joinder or cross-claim is based on acts of
    negligence that are unrelated to the acts of negligence
    that are the basis for the claim against the joining or
    cross-claiming party.
    Pa.R.C.P. 1042.3(c)(2).
    ….
    Fiore contends that it is not required to file a [c]ertificate of
    [m]erit, by and large, on the fact that it incorporated Kelly’s
    [C]omplaint into their [Joinder] [C]omplaint and therefore[,] the
    “acts of negligence” are related to the “acts of negligence” in
    [Kelly’s C]omplaint.    OGP argues that Kelly’s claims are in
    contract[,] and by incorporating Kelly’s [C]omplaint, Fiore only
    alleges a contract claim on a contract where OGP is not a party,
    [thereby] making Rule 1042.3(c)(2) inapplicable. Because Rule
    1042.3(c)(2) turns on whether the negligence alleged in the
    [J]oinder [C]omplaint is unrelated to the negligence [alleged in]
    [Kelly’s Complaint], the [c]ourt must determine whether [Kelly’s
    -8-
    J-A13043-18
    C]omplaint sounds in either contract or negligence. If the claims
    in [Kelly’s C]omplaint are contract claims, then any negligence
    alleged in Fiore’s [Joinder] [C]omplaint is new negligence,
    unrelated to the claims in [Kelly’s C]omplaint, and would force
    Fiore to file a [c]ertificate of [m]erit to assert any professional
    liability claims on OGP. If the claims in [Kelly’s C]omplaint are in
    negligence, then the [c]ourt must analyze the claims to see if the
    claims are related[, thereby qualifying] Fiore’s [Joinder]
    [C]omplaint [] under the rule.
    To determine whether a complaint sounds a claim in
    contract or in negligence, courts in Pennsylvania have used an
    evolving doctrine known as the “gist of the action” doctrine. See
    Bruno v. Erie Ins. Co., 
    106 A.3d 48
    , 61-62 (Pa. 2014); Zell v.
    Arnold, 
    2 Pen. & W. 292
     (Pa. 1830); Homey v. Nixon, 
    61 A. 1088
     (Pa. 1905); Bash v. Bell Tel., 
    601 A.2d 825
     (Pa. Super.
    1992); eToll Inc. v. Elias/Savion Adver., 
    811 A.2d 10
     (Pa.
    Super. 2002). In Bruno, the Supreme Court articulated the legal
    principles a court must use to determine the gist of the action
    doctrine, stating that a court must make a duty-based inquiry to
    determine whether the claim is in tort or contract:
    The substance of the allegations comprising a claim in
    a plaintiff’s complaint are of paramount importance,
    and, thus, the mere labeling by the plaintiff of a claim
    as being in tort, e.g., for negligence, is not controlling.
    If the facts of a particular claim establish that the duty
    breached is one created by the parties by the terms
    of their contract—i.e., a specific promise to do
    something that a party would not ordinarily have been
    obligated to do but for the existence of the contract—
    then the claim is to be viewed as one for breach of
    contract. If, however, the facts establish that the
    claim involves the defendant’s violation of a broader
    social duty owed to all individuals, which is imposed
    by the law of torts and, hence, exists regardless of the
    contract, then it must be regarded as a tort.
    Bruno, 106 A.3d at 68. Thus, if the claim offered is for a breach
    of a specific promise in the contract, then the claim will lie in
    contract[,] as the duty of the parties are purely contractual.
    However, if the claim is not based on the specific contractual
    promise, but rather on a duty that is owed independent of any
    -9-
    J-A13043-18
    contractual promises, then the claim will lie in tort, even if the
    parties’ relationship originates from the contract.
    The relevant portions of [Kelly’s C]omplaint … relate to a
    claim of monetary damages due to the defective specifications[,
    and state as follows]:
    ***
    6. Additionally, the architectural details regarding the
    mental [sic] panels were defective, in that they
    specified a system which was not possible to
    construct, as a result of which Kelly incurred extra
    costs exceeding $225,000.00. Kelly promptly and
    timely notified Fiore of the defects in the architectural
    details and of the fact that Kelly was incurring
    additional costs as a result thereof, and provided Fiore
    with an estimate of the extra costs together with a
    written request for a change order, on October 4,
    2016. A true and correct copy of the aforesaid written
    request for a change order is hereto attached marked
    as Exhibit B.
    7. Fiore, on or about November 14, 2016, rejected
    Kelly’s request for a change order for extra costs
    resulting from the defective specifications.        On
    December 1, 2016, Kelly, through counsel, requested
    in writing that Fiore reconsider its rejection. A true
    and correct copy of the written request for
    reconsideration is hereto attached marked as Exhibit
    C. Fiore has refused to reconsider its rejection of
    Kelly’s request.
    II. COUNT TWO - ACTION FOR DAMAGES RESULTING
    FROM DEFECTIVE SPECIFICATIONS
    …
    12. As a result of the defective specifications as
    outlines [sic] in Exhibits B and C hereto, and at the
    direction of Fiore and the architect on the Project,
    Kelly was forced to expend in excess of $225,000 in
    additional costs in order to complete the metal panel
    portion of the Project.
    - 10 -
    J-A13043-18
    13. Despite Kelly’s demand for a change order to
    recover those extra costs, Fiore has failed and refused
    same.
    (Kelly[’s] Complaint, ¶¶ 6-7, 12-13).         Attached to [Kelly’s
    C]omplaint are Exhibits B (a letter by Kelly to Fiore detailing their
    request for a change order and their estimates, totaling upwards
    of $225,000) and C (a letter from Kelly’s counsel to Fiore, stating
    that the architectural details were inconsistent and impossible to
    construct[,] and that attempts at resolution were rejected by the
    architect, which forced Kelly to take more time and spend more
    money to finish their portion of the project).
    Kelly’s claim of monetary damages due to defective
    specifications is opaque on the issue of whether their claim is
    contractual in nature or sounds in negligence, whether the
    damages resulting to Kelly were because of the design defects, or
    whether the claim is that Fiore did not approve the change order
    due to the design defects, and thus, would be a contractual claim
    (as OGP argues). Paragraph 12 appears to claim negligence[,]
    stating that, as of a result of defective specifications, and at the
    direction of Fiore and the architect (OGP), Kelly was damaged in
    the amount of $225,000, spent by Kelly to finish the project.
    Paragraph 13, however, indicates that Kelly attempted to recover
    those costs through the [Kelly Sub]contract, but Fiore has refused
    to reimburse Kelly. In paragraph 6, Kelly claims that it timely
    notified Fiore of the change order[,] which is required [by] the
    [Kelly Sub]contract. Fiore, in its Answer, denied that Kelly was
    timely in its request, which would be dependent upon the [terms
    of the Kelly Sub]contract. Fiore also defends against Kelly’s claims
    by arguing that Kelly has executed partial lien waivers and
    releases and that the extra work uncured by Kelly was not outside
    the scope of work for the project. Thus, there is merit to OGP’s
    argument that Kelly’s claim is a contract claim.
    Count 1 is a claim by Kelly to recover the balance of the
    subcontract price that it believes will not be collected from Fiore.
    Facially, this is a claim that Fiore will not perform under the
    contract for finished work, and is a clear claim in contract.
    However, the basis of the claim in Count 2 was that the Kelly was
    provided with defective specifications, which they could not
    complete as specified, and sought a change order for those
    additional costs to complete their portion of the project, which
    - 11 -
    J-A13043-18
    were denied by Fiore. In order to prove that the change order
    was justified and should have been accepted by Fiore, Kelly will
    have to use expert testimony to demonstrate [] that the design
    specifications were defective.      As the change orders were
    premised on the alleged design defects, if the designs were not
    defective, Kelly cannot claim that Fiore improperly refused to
    grant the change order. Furthermore, Exhibit B, the proposed
    change order, indicates that Kelly believed the local code differed
    from the specifications that were used in Kelly’s contract bid.
    Exhibit C, a letter from Kelly’s counsel to Fiore, indicates their
    belief that the “architectural details on the project specified a
    system which was impossible to construct,” and that
    “inconsistencies permeate the architectural details.” The letter
    concludes, “[o]therwise, if we do not hear from you, Kelly reserves
    all rights to proceed with litigation to recover the extra costs
    incurred because of the defective drawings.” Thus, the crux of the
    issue with the change orders will be whether designs relied upon
    by Kelly were defective.
    Additionally, the [Kelly Sub]contract does not guarantee
    that a change order will take place. Paragraph 9 of the [Kelly
    Subcontract] states, in relevant part:
    Before proceeding with any work involving possible
    claims by Kelly for extra compensation above the price
    set forth in paragraph 1, Kelly shall submit in writing
    to Fiore a detailed estimate of the price for such extra
    work and materials and shall secure from Fiore a
    written order describing such work and fixing Kelly’s
    compensation ...[.] Agreement on any change order
    shall constitute a final settlement of all items covered
    therein, subject to performance thereof and payment
    therefore as provided in this agreement. If Fiore and
    Kelly fail to agree as to the amount of the adjustment,
    the work shall proceed as directed in writing by Fiore
    while the adjustment is being determined.            Any
    change order work performed without Fiore’s prior
    written authorization pursuant to the foregoing
    procedures shall be at Kelly’s risk without right of
    payment or reimbursement under contract quantum
    meruit or otherwise.
    [(Kelly Subcontract at 7).] This section does not contain any
    executory promises on behalf of Fiore to approve change orders
    - 12 -
    J-A13043-18
    for Kelly, and work not authorized by Fiore will be at Kelly’s risk.
    It does not appear that the damages claimed by Kelly flow from
    the contract, as Fiore is under no obligation under the contract to
    approve the change orders. However, the alleged damages come
    from why the change order was required and why the change
    order was not approved. Nowhere in the contract did Fiore
    promise to provide Kelly with designs that were without defects.
    Thus, the claim [regarding] the defective design is not based on
    the contract, but is rather based on whether Fiore was negligent
    in providing designs which contain alleged defects[,] or negligent
    in refusing the change order. Therefore, the [c]ourt believes that
    Count 2 of [Kelly’s C]omplaint sounds as an action in negligence
    and not contract.
    Thus, Fiore may still be covered under Rule 1042.3(c)(2),
    but the [c]ourt must [] determine if the negligence in the Fiore
    [Joinder] [C]omplaint is related to the negligence in [Kelly’s
    C]omplaint. Fiore, in its [Joinder C]omplaint, incorporates the
    claims in [Kelly’s C]omplaint without admitting to those claims,
    and argues that OGP is either solely liable for Kelly’s damages or
    that OGP is liable to or with Fiore for Kelly’s damages. Kelly’s
    claim is that the defective design specifications caused Kelly to
    expend money, which Fiore refused to cover. Fiore then argues
    that if Kelly was damaged, then OGP, as design subcontractor and
    as administrator and evaluator of the change order requests, was
    liable for Kelly’s damages and deviated from professional
    standards. In order for Fiore to prove that OGP was negligent,
    the same expert testimony and same evidence will be used to
    show whether the design specifications were defective and
    whether a change order should be granted in this instance. Fiore’s
    [Joinder] [C]omplaint, through the incorporation of [Kelly’s
    C]omplaint …, adequately puts OGP on notice of the claims against
    it[,] and allows OGP to make a defense. Thus, the [c]ourt finds
    that the negligence alleged in the Fiore [Joinder] [C]omplaint is
    related to [the negligence alleged in Kelly’s C]omplaint.
    OGP makes an additional argument about the pleading in
    the Fiore [Joinder] [C]omplaint: by incorporating, but not
    admitting, [] Kelly’s [C]omplaint, Fiore’s [Joinder] [C]omplaint
    goes against the purpose behind the Rules of Civil Procedure
    concerning professional liability actions, which is to weed out non-
    meritorious actions by requiring the filing of a [c]ertificate of
    [m]erit[,] and allows Fiore to pursue a professional liability action
    without having to file a [c]ertificate of [m]erit.
    - 13 -
    J-A13043-18
    In its research, the [c]ourt has found few actions where Rule
    1042.3(c)(2) was at issue. However, in Supervalu Inc., v.
    Construction Engineering Consultants, Inc., 
    65 Pa. D. & C. 4th 449
     (C.P. Allegheny, 2004), a similar though not entirely
    congruous situation to the present action, Judge R. Stanton
    Wettick of Allegheny County required a [c]ertificate of [m]erit to
    be filed by a defendant because the acts of negligence alleged in
    the defendant’s joinder complaint involved different activities and
    different expert testimony to establish professional negligence
    against an additional defendant. However, in a footnote, Judge
    Wettick noted that the defendant also included claims that were
    incorporated by the defendant in their joinder complaint, and
    determined those claims did not require a [c]ertificate of [m]erit:
    I recognize that in this case[,] [defendant]’s complaint
    also incorporates the allegations contained in
    plaintiff[’]s complaint. [Defendant,] even if it does
    not file a certificate of merit, may pursue these claims
    under the provision of Rule 1042.3(c)(2) that the
    joining party need not file a certificate of merit where
    the joinder is based on the same acts of negligence
    that are the basis of plaintiffs claim against the joining
    party. Thus, any judgment of non pros would not
    include the allegations in [defendant]’s complaint
    which expressly incorporate the allegations contained
    in plaintiff[’]s complaint.
    [Id. at 453 n.2.] Although the footnote does not state whether
    the defendant incorporated the claims of the plaintiff without
    admission, Judge Wettick understood Rule 1042.3(c)(2) to mean
    that if incorporated claims would result in the same negligence
    alleged, that negates the requirement of filing a [c]ertificate of
    [m]erit. [Id.] While OGP argues that this case is not binding on
    the [c]ourt, the [c]ourt notes that Judge Wettick’s opinion is well
    reasoned[,] and cites the case for its persuasive value.
    OGP does not offer any case law, statute, or rule for the
    proposition that, in a case where the defendant joins a
    professional who is covered under Rule 1042.3(c)(2), the
    defendant, by incorporating a plaintiff[’]s complaint in its
    complaint against an additional defendant, must admit to the
    claims [made] against it by the plaintiff. However, what is present
    in the instant case is the interplay between the [c]ertificate of
    [m]erit rules, the joinder rules, and specifically, Rule
    - 14 -
    J-A13043-18
    1042.3(c)(2). When joining an additional defendant under [Rule]
    2252(a)(1), the claim does not move from the plaintiff to the
    additional defendant, but rather is an assertion by the defendant
    that the plaintiff[’]s claim is actually against the additional
    defendant. Thus, the defendant is not asserting a claim against
    the additional defendant, but rather, through joining the
    additional defendant, is asserting that the cause of action should
    be against the additional defendant, and not itself.
    OGP may have an argument under [Rule] 2252(a)(4),
    where joinder is allowed if the additional defendant is liable to or
    with the defendant, and thereby being liable to Fiore may require
    Fiore to file a [c]ertificate of [m]erit. However, the plain language
    of [Rule] 1042.3(c)(2) does not make such a distinction; the rule
    only requires that the acts of negligence against the additional
    defendant are related to the acts of negligence alleged by the
    plaintiff against the defendant. This is the importance of the
    requirement in Rule 1042.3(c)(2) that the “acts of negligence” in
    the complaint and the [joinder] complaint must not be unrelated.
    If unrelated, then a defendant is asserting an additional claim
    against the additional defendant, and a [c]ertificate of [m]erit
    must be required as it is the defendant’s claim against the
    additional defendant. The [c]ourt sees nothing in the rules that
    requires a defendant to admit to the claims in a plaintiff[’]s
    complaint in order to join an additional defendant in sole liability
    based on Pa.R.C.P. 2252(a)(1) and (4), and Fiore need[] not file
    a [c]ertificate of [m]erit if that joinder is based on acts of
    negligence that are related to the acts of negligence claimed by
    the [p]laintiff.
    In conclusion, Fiore is not required to file a [c]ertificate of
    [m]erit in order to join [] OGP as [an] additional defendant
    pursuant to Pa.R.C.P. 2252(a)(1) and 2252(a)(4), as Fiore’s
    [Joinder] [C]omplaint raises a negligence claim that is related to
    the claims made in [Kelly’s C]omplaint.
    Trial Court Opinion, 10/23/17, at 8-17 (brackets, footnotes and some citations
    omitted; italicization and emphasis added). We agree with the trial court’s
    reasoning and determination, and therefore affirm on this basis. See 
    id.
    Order affirmed.
    - 15 -
    J-A13043-18
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 10/31/2018
    - 16 -