Americo Construction v. Four Ten ( 2020 )


Menu:
  • J-S62015-19
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
    AMERICO CONSTRUCTION COMPANY               :   IN THE SUPERIOR COURT OF
    :        PENNSYLVANIA
    Appellant               :
    :
    :
    v.                             :
    :
    :
    FOUR TEN, LLC AND FORD                     :   No. 596 WDA 2019
    INVESTMENT GROUP                           :
    Appeal from the Order Entered March 26, 2019
    In the Court of Common Pleas of Washington County
    Civil Division at No(s): 2018-2992
    BEFORE: PANELLA, P.J., KUNSELMAN, J., and FORD ELLIOTT, P.J.E.
    MEMORANDUM BY PANELLA, P.J.:                        FILED FEBRUARY 14, 2020
    Americo Construction Company (“Americo”) appeals the March 26, 2019
    order1 sustaining the preliminary objections of Four Ten, LLC, (“Four Ten”)
    and Ford Investment Group in the Court of Common Pleas of Washington
    County. The trial court found that Americo failed to comply with the service
    requirements set forth in section 1502(c) of the Mechanics’ Lien Law of 1963
    (“Mechanics’ Lien Law” or “Law”). See 49 P.S. §§ 1101-1902. After review,
    we affirm.2
    ____________________________________________
    1 The order was signed and filed on March 25, 2019. However, the docket
    indicates that notice of entry of the order was sent on March 26, 2019. See
    Pa.R.A.P. 108(b).
    2 Americo does not challenge the trial court’s sustaining of preliminary
    objections as to Ford Investment Group. See Appellant’s Brief, at 8, ¶ 24.
    J-S62015-19
    Americo alleges that it is owed approximately $26,000 from work that
    it contractually performed on a building owned by Four Ten, a Pennsylvania
    company. After nonpayment, Americo sought a mechanics’ lien on that
    building. Americo timely filed its mechanics’ lien claim on June 21, 2018.
    Thereafter, on June 26, 2018, Americo directed the Washington County
    Sheriff’s Office to personally serve Four Ten. In the event personal service
    proved to be unsuccessful, Americo instructed the Sheriff’s Office to post the
    property by July 21, 2018, within the required thirty-days under the
    Mechanics’ Lien Law.
    As reflected on the docket for this case, the Sheriff’s Office was
    unsuccessful in personally serving anyone affiliated with Four Ten. The
    Sheriff’s Office attempted service on July 11, 2018, and the return of that
    attempt was filed to the docket on July 17, 2018. The filing did not mention
    whether posting of the property had been effected.
    Several weeks later, Americo received the Sheriff’s return by mail on
    August 8, 2018. Although the mailed return also stated that service was
    unable to be made on that July attempt, it, too, did not mention any posting
    of the property.
    Upon receiving this return and after further consultation Americo
    ____________________________________________
    Therefore, this memorandum only focuses whether service was properly
    effectuated on Four Ten.
    -2-
    J-S62015-19
    consulted with the Sheriff, who subsequently posted notice on the property
    on August 15, 2018. On September 5, 2018, Americo filed an affidavit of
    service, which set forth the date and manner of service.
    Four Ten filed preliminary objections contending that Americo ran afoul
    of the thirty-day service requirement contained in the Mechanics’ Lien Law. In
    strictly construing that Law, the trial court, while acknowledging that the
    Sheriff “neglected to post the property as requested,” Trial Court Opinion, filed
    3/25/19, at 3, sustained Four Ten’s preliminary objections and dismissed
    Americo’s claim with prejudice. After the trial court denied Americo’s motion
    for reconsideration, Americo filed a timely notice of appeal.
    Americo presents one question for our review:
    1) Did the trial court commit an error of law when it determined
    that late service of a notice of filing of a mechanics’ lien cannot
    be relieved due to a breakdown in the judicial system?
    See Appellant’s Brief, at 2.
    Our review of an order sustaining preliminary objections employs the
    following considerations:
    [t]his Court will reverse the trial court's decision regarding
    preliminary objections only where there has been an error of law
    or abuse of discretion. When sustaining the trial court's ruling will
    result in the denial of [a mechanics' lien] claim or a dismissal of
    suit, preliminary objections will be sustained only where the case
    is free and clear of doubt.
    Regency Investments, Inc. v. Inlander Ltd., 
    855 A.2d 75
    , 77 (Pa. Super.
    2004) (internal quotation marks and citation omitted).
    “Mechanics’ liens were unknown at common law and are entirely a
    -3-
    J-S62015-19
    creature of statute.” Schell v. Murphy, 
    153 A.3d 379
    , 381 (Pa. Super. 2016)
    (citation omitted). Accordingly, mechanics’ liens are “only available if the
    conditions of the legislature are strictly followed. Where the words of the
    statute are clear, the courts should not be requested to go beyond the
    requirements of the act.” 
    Id. (citation omitted).
    In other words, our
    “interpretation [of the Mechanics’ Lien Law] shall be resolved in favor of strict,
    narrow construction.” Wyatt Inc. v. Citizens Bank of Pennsylvania, 
    976 A.2d 557
    , 564 (Pa. Super. 2009) (citation omitted).
    Section 1502 of the Mechanics’ Lien Law provides the process to perfect
    such a lien. Stated succinctly, to generate a valid mechanics’ lien, a claimant
    must: 1) file its claim within six months of the date it completed its work; 2)
    serve the owner with written notice of the claim within one month after it filed
    its claim either in person or, if personal service is unsuccessful, by posting the
    property; and 3) file either an affidavit of service of notice or the acceptance
    of service within twenty days after service. See 49 P.S. § 1502.
    The statute directs that service must, in the first instance, be completed
    in the same manner as a writ of summons in assumpsit. See 49 P.S. §
    1502(c). We have interpreted this directive as being procedurally the same as
    the initiation of a civil action. See Clemleddy Construction, Inc. v.
    Yorston, 
    810 A.2d 693
    , 697       (Pa. Super. 2002).      Therefore, under
    Pennsylvania Rule of Civil Procedure 400(a), other than a few exceptions that
    are not relevant here, notice of the filing of a claim in a mechanics’ lien case
    -4-
    J-S62015-19
    must be served by a sheriff. See 
    id. In the
    instant case, both parties agree that, at first, a sheriff needed to
    attempt personal service on Four Ten. See Appellant’s Brief, at 11; Appellee’s
    Brief, at 6. Nevertheless, the two parties diverge from one another on the
    rigidity of the Mechanics’ Lien Law’s service requirements. Specifically,
    Americo and Four Ten contest whether a mechanics’ lien claimant is required
    to personally post the property if the sheriff fails to do so in a timely manner
    and notification of that failure comes outside of the Law’s thirty-day period for
    service.
    Initially, we note that a mechanics’ lien claim is a statutory protection
    afforded to those who supply labor or materials to improve property. See
    
    Schell, 153 A.3d at 381
    . “Mechanics’ liens accomplish this goal by giving
    lienholders security for their payment independent of contractual remedies.”
    
    Id. “The Mechanics’
    Lien statute provides an expeditious method to obtain
    a lien at very little cost to the claimant.” Regency 
    Investments, 855 A.2d at 80
    . Consequently, a court striking off a mechanics’ lien does not entirely
    deprive the claimant of a remedy at law; the claimant may still file suit seeking
    monetary damages for breach of contract. See 
    id. In exchange
    for an expedited lien, the act requires claimants to be
    vigilant in effecting service within the statutory timeframe. “It is the claimant’s
    principal responsibility to ensure timely service of the claim.” 
    Id. Strict -5-
    J-S62015-19
    compliance with the service and notice provisions is mandated because
    owners, purchasers, and other lien creditors should have a date by which they
    can be assured that no mechanics’ lien can be filed. See 
    Clemleddy, 810 A.2d at 697
    . As a result, a claimant can only invoke the doctrine of substantial
    compliance regarding issues with the form of notice. When the timeliness of
    service is at issue, strict compliance is enforced. See 
    Regency, 855 A.2d at 80
    .
    Here, Americo contends that it did everything it was required to do to
    serve Four Ten in a timely manner. We agree that Americo had the statutory
    right to instruct the sheriff to post the property. See, e.g., 
    Clemleddy, 810 A.2d at 698
    ; 
    Regency, 855 A.2d at 80
    . Moreover, Americo did everything it
    was required to do effect service under the statute and our case law. Indeed,
    we would find that Americo did everything it reasonably could do to ensure
    timely service.
    Nevertheless, it remains undisputed that Americo did not timely serve
    Four Ten under the Law despite all of Americo’s efforts. We cannot ignore the
    unanimous authorities providing that the Mechanics’ Lien Law must be strictly
    construed. Further, our authorities are unanimous in holding that a claimant
    cannot substantially comply with the timeliness requirements: either service
    was timely or it was not.
    To reiterate the timeline illuminated above, Americo filed its lien claim
    on June 21, 2018. On June 26, 2018, Americo mailed notice of the claim’s
    -6-
    J-S62015-19
    filing to Washington County’s Sheriff’s Office, directing that Office to
    personally serve Four Ten by July 21, 2018, which was thirty days after the
    claim’s filing. That same document requested the Sheriff’s Office to post the
    property in the event that personal service failed. The Sheriff’s Office
    attempted personal service on July 11, 2018, and filed to the docket evidence
    of the same on July 17, 2018. The Sheriff’s Office did not post the property.
    Americo received the Sheriff’s return on August 8, 2018, but that return
    contained no indicia whether the Sheriff had posted the property. Eventually,
    the Sheriff posted the property on August 15, 2018, and correspondingly, the
    Sheriff’s Office filed its return of service on August 17, 2018.
    We are constrained to conclude that since service was not timely made
    on Four Ten, Americo is not entitled to the enhanced benefits of the Mechanics’
    Lien Law. Strict compliance with the time limits in the act serve the purpose
    of providing a date certain for owners and third parties to be assured of the
    absence of such claims. Americo still retains a possible remedy at law, but in
    the absence of timely service, Americo’s mechanics’ lien claim was properly
    stricken.
    Accordingly, we affirm the trial court’s order sustaining Four Ten’s
    preliminary objections.
    Order affirmed.
    -7-
    J-S62015-19
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 2/14/2020
    -8-