Jack Frost Construction v. Bertothy, J. ( 2023 )


Menu:
  • J-A02017-23
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT O.P. 65.37
    JACK FROST CONSTRUCTION, INC.              :   IN THE SUPERIOR COURT OF
    :        PENNSYLVANIA
    :
    v.                             :
    :
    :
    JASON T. BERTOTHY AND DANA A.              :
    BERTOTHY                                   :
    :   No. 208 WDA 2022
    Appellants              :
    Appeal from the Judgment Entered February 8, 2022
    In the Court of Common Pleas of Clearfield County Civil Division at
    No(s): 2019-541-CD
    BEFORE:      BOWES, J., MURRAY, J., and PELLEGRINI, J.*
    MEMORANDUM BY BOWES, J.:                           FILED: October 6, 2023
    Jason T. Bertothy and his wife, Dana A. Bertothy (collectively “the
    Bertothys”), appeal from the $40,5564.26 judgment entered on the verdict in
    favor of Jack Frost Construction, Inc. (“Jack Frost”). We vacate the judgment
    and remand for further proceedings.
    I.      Facts and Procedural History
    The certified record supports the following history of this case as
    outlined in the findings of fact enumerated in the trial court opinion and order
    entered on August 25, 2021. In November 2017, the Bertothys contracted
    with Jack Frost for the construction of a single-family residence (“the
    Contract”). The Contract, which was negotiated between the Bertothys and
    ____________________________________________
    *    Retired Senior Judge assigned to the Superior Court.
    J-A02017-23
    Jack Frost’s owner, Billy Joe Sallurday, specifically referenced, but did not
    incorporate, a September 12, 2017 estimate (“the Estimate”) that outlined a
    flat fee for materials, plans and labor totaling $480,107.00.1 The Contract
    provided that payments were due within ten days of the submission of an
    invoice and that Jack Frost retained the right to cease work if payments were
    not timely received.       In this vein, the contract included a provision that
    calculated interest at a rate of 1.5% per month or 18% per year. Neither the
    Contract nor the Estimate stated a completion date, but a proviso in the
    Estimate advised that the arrangement was “contingent upon . . . delays
    beyond [the contractor’s] control.” Estimate, 9/12/17, at 2.
    Over the ensuing year, construction was plagued by delays associated
    with winter weather, an abnormal amount of rainfall, and the failure of a sub-
    contractor, namely the Bertothys’ son, Trent, to excavate the site, grade the
    driveway, and dig the trenches for housing electrical and water supply lines.
    The various delays prompted an ongoing dispute between the parties over the
    pace of construction and the use and storage of construction materials at the
    site.
    Between the start of the project in November 2017 and July 2018, the
    Bertothys satisfied all four of the periodic invoices that Jack Frost submitted
    totaling $122,357.00. However, the Bertothys withheld payment on the fifth
    ____________________________________________
    1 While the Contract states the incorrect date of the Estimate, the parties do
    not dispute that they agreed to the Estimate provided on September 12, 2017.
    -2-
    J-A02017-23
    pay application (“Pay Application No. 5”) for $63,060.26 due to what they
    claimed were unresolved construction defects that they believed Jack Frost
    had failed to remedy, and because that application requested payment for
    work that had not been completed. While the trial court ultimately determined
    that Jack Frost continued to work on the project despite the non-payment of
    Pay Application of No.5, the parties dispute the amount and pace of
    construction after July 2018.
    On October 4, 2018, the Bertothys’ counsel mailed Jack Frost a cease-
    and-desist letter. Prior to receiving the letter, Jack Frost had partially framed
    the structure, sheathed the roof, and completed the deck footer, footer,
    foundation, and plumbing slab. The concrete work was approved by Pennsafe
    Building Inspection Services, LLC. Within six days of issuing the letter, the
    Bertothys had the property inspected by David Connelly, a structural engineer,
    who observed extensive moisture near the foundation, slab, framing, exterior
    walls, and roof trusses. See N.T., 11/5/19, at 102-11, 114-17, 118-19, 120-
    26, 130-31. Specifically, Mr. Connelly identified, inter alia, a wet slab and
    interior foundation, weather-compromised lumber used in framing and
    sheathing, and the accumulation of mold and mildew on the floor joists and
    roof trusses.   Id. at 108-09, 114-26, 130-31.       Overall, he described the
    prolonged moisture exposure as,
    A lot of wet construction, in a nutshell. Everything seemed to be
    pretty-well soaked, even the interior.       Yes, there was roof
    sheathing on the structure. There was still water coming through
    . . . that allowed a lot of water into the interior structure. . . .
    -3-
    J-A02017-23
    [T]he exterior sheathing, really seemed to [have] taken on a lot
    of water.
    Id. at 102. The visual inspection was performed approximately six days after
    Mr. Sallurday was last on the job site and claimed that he observed no
    moisture-related damage when he left. Id. at 138; N.T., 11/4/20, at 48, 70-
    71.
    On April 1, 2019, Jack Frost sued the Bertothys for breach of contract
    due to their alleged failure to satisfy Pay Application No. 5 in accordance with
    the Contract. It also sought $13,006.27 for windows that had been purchased
    in anticipation of installation. The Bertothys’ answer and new matter included
    several counterclaims including breach of contract based upon Jack Frost’s
    alleged failure to perform in a timely and workmanlike manner. The Bertothys
    also pled violations of the Pennsylvania Unfair Trade Practices and Consumer
    Protection Law (“UTPCPL”) sections 201-2(4)(vii), (xiv), and (xxi), which
    relate to a business’s representation of goods and services, compliance with
    written warranties, and fraudulent or deceptive conduct, respectively.2
    Following a bench trial over three days between November 2020 and
    March 2021, and review of the parties’ proposed findings of fact and
    conclusions of law, the trial court found in favor of Jack Frost and awarded it
    ____________________________________________
    2 The Bertothys’ counterclaims also included alternative counts of unjust
    enrichment and negligence. As the Bertothys do not challenge the trial court’s
    rejection of these counts, we do not discuss them herein.
    -4-
    J-A02017-23
    $40,560.26, plus the contractual interest rate, for the unpaid materials and
    labor costs outlined in Pay Application No. 5.3
    As to the Bertothys’ counterclaims, the court rejected all of the requests
    for relief, holding:    (1) the issue concerning Jack Frost’s alleged failure to
    perform in a timely and workmanlike manner was not ripe because the
    Bertothys had not permitted the contractor to fix the potential defects
    associated with the incomplete performance prior to issuing the cease-and-
    desist letter and taking possession of the worksite; (2) all of the completed
    work had been performed in a workmanlike manner; and (3) Jack Frost did
    not engage in any of the alleged conduct that purportedly violated the UTPCPL.
    This timely appeal followed the denial of the Bertothys’ post-trial
    motions and the entry of judgment on the verdict. Both the Bertothys and
    the trial court complied with Pa.R.A.P. 1925.
    The Bertothys present seven questions for our review, which we re-
    ordered for ease of disposition:
    1. Whether, under relevant law, the trial court erred in permitting
    an expert witness to testify at trial who [Jack Frost] failed to
    disclose or identify during discovery.
    2. Whether, under relevant law, the trial court erred in finding
    [Jack Frost] is entitled to $40,560.26 for labor and materials,
    ____________________________________________
    3 While Jack Frost requested $63,060.26 in damages, plus $13,006.27 for the
    new windows, the court concluded that it only established $40,560,26 of that
    amount. See Trial Court Opinion and Order, 8/25/21, at 7 (holding, Jack Frost
    did not establish $13,006.27 damages for windows or $22,500.00 in damages
    for plumbing materials and HVAC equipment that was not used on the project.
    -5-
    J-A02017-23
    without any documentary evidence or business records to
    substantiate the amount claimed.
    3. Whether, under relevant law, the trial court erred in making
    findings contrary to the evidence presented at trial.
    4. Whether, under relevant law, the trial court erred in refusing to
    consider [the Bertothys’] counterclaim, because the claim was
    “not ripe.”
    5. Whether, under relevant law, the trial court erred in finding the
    implied warranty of reasonable workmanship is limited to latent
    defects.
    6. Whether, under relevant law, the trial court erred in finding the
    work [Jack Frost] completed was performed in a workmanlike
    manner, despite also finding the existence of non-latent
    construction defects.
    7. Whether, under relevant law, the trial court erred in failing to
    rule on undisputed facts that assertedly constitute violations of
    the Pennsylvania [UTPCPL].
    Appellant’s brief at 3-4.
    The following tenets inform our review.
    Our standard of review in non-jury trials is to assess
    whether the findings of facts by the trial court are supported by
    the record and whether the trial court erred in applying the law.
    Upon appellate review[,] the appellate court must consider the
    evidence in the light most favorable to the verdict winner and
    reverse the trial court only where the findings are not supported
    by the evidence of record or are based on an error of law. Our
    scope of review regarding questions of law is plenary.
    Woullard v. Sanner Concrete & Supply,, 
    241 A.3d 1200
    , 1207 (Pa.Super.
    2020) (quoting Century Indem. Co. v. OneBeacon Ins. Co., 
    173 A.3d 784
    ,
    802 (Pa.Super. 2017)).
    II.   Jack Frost’s Breach-of-Contract Claim
    -6-
    J-A02017-23
    We begin our review by addressing whether the Bertothys are entitled
    to a new trial in defending Jack Frost’s breach-of-contract claim implicating
    Pay Application No. 5.
    A.     Expert Testimony
    The Bertothys’ first challenge relates to the trial court’s decision to
    permit the contractor to present expert opinion testimony that was not
    disclosed during discovery. We review the trial court’s determination for an
    abuse of discretion. See Pledger by Pledger v. Janssen Pharm., Inc., 
    198 A.3d 1126
    , 1138 (Pa.Super. 2018) (“The admission of expert testimony is a
    matter within the sound discretion of the trial court, whose rulings thereon
    will not be disturbed absent a manifest abuse of discretion.” (citation
    omitted)).
    The following facts are relevant to our determination. Prior to trial, the
    Bertothys filed a motion in limine seeking to bar Jack Frost from presenting
    its construction expert, Philip J. Bosak, because Jack Frost failed to disclose
    or identify Mr. Bosak during discovery and neglected to claim that any
    extenuating circumstances caused the nondisclosure.
    Pursuant to Pa.R.C.P. 4003.5:
    An expert witness whose identity is not disclosed in compliance
    with subdivision (a)(1) of this rule shall not be permitted to testify
    on behalf of the defaulting party at the trial of the action.
    However, if the failure to disclose the identity of the witness is the
    result of extenuating circumstances beyond the control of the
    defaulting party, the court may grant a continuance or other
    appropriate relief.
    -7-
    J-A02017-23
    Pa.R.C.P. 4003.5(b).
    The purpose of Rule 4003.5(b) is to promote fairness and allow opposing
    parties to adequately prepare for trial. See Clark v. Hoerner, 
    525 A.2d 377
    ,
    383 (Pa.Super. 1987). In this vein, our Supreme Court has endorsed a four-
    part test to determine the propriety of admitting previously-undisclosed
    expert testimony: (1) the prejudice or surprise in fact of the party against
    whom the excluded witnesses would have testified; (2) the ability of that party
    to cure the prejudice; (3) the extent to which waiver of the rule against calling
    unlisted witnesses would disrupt the orderly and efficient trial of the case or
    other cases in the court; and (4) bad faith or willfulness in failing to comply
    with a pre-trial order limiting witnesses to be called to those named prior to
    trial. See Feingold v. SEPTA, 
    517 A.2d 1270
     (Pa. 1986); see also Gill v.
    McGraw Electric Co., 
    399 A.2d 1095
    , 1102 (Pa.Super. 1979) (en banc)
    (citing the same four factors for consideration when deciding whether a
    witness should be precluded for failing to comply with pre-trial orders).
    Furthermore, we have defined prejudice as “any substantial diminution of a
    party’s ability to properly present its case at trial,” not simply damage to the
    opponent’s case. Florig v. Estate of O'Hara, 
    912 A.2d 318
    , 325 (Pa.Super.
    2006).
    Instantly, Jack Frost failed to timely disclose or identify Mr. Bosak as an
    expert witness in direct contravention of Rule 4003.5. Indeed, although Jack
    Frost retained Mr. Bosak to inspect the property in 2019, it waited until one
    -8-
    J-A02017-23
    month before trial to disclose him as a witness, expert or otherwise.
    Moreover, Jack Frost did not provide Mr. Bosak’s expert report to the
    Bertothys until October 20, 2020, two weeks before trial. In addition, Jack
    Frost neglected to allege any extenuating circumstances that prevented it
    from disclosing Mr. Bosak’s identity during discovery.
    Nevertheless, finding that the delay in revealing the expert was not
    prejudicial to the Bertothys, the trial court denied the motion in limine and
    ultimately permitted Mr. Bosak to testify as a rebuttal witness. The trial court
    explained its rationale as follows:
    [Jack Frost] provided notice of the intention to call Mr. Bosak
    as an expert to [the Bertothys] over a month before the trial
    began, and his report was provided to [the Bertothys] two weeks
    before trial. Additionally, [the Bertothys] were permitted to confer
    with their own experts prior to cross-examining Mr. Bosak.
    Moreover, the [November 2020] trial was extended through March
    2021, giving [the Bertothys] an additional four months to prepare
    any supplementary experts and/or witnesses necessary, or
    request other relief. [Despite] stating [they] were prejudiced,
    there has been no showing of actual prejudice suffered by [the
    Bertothys].
    Trial Court Opinion, 12/28/21, at 9.
    Considering the several opportunities that the Bertothys had to prepare
    for their cross-examination of Mr. Bosak, most significantly the extended four-
    month-delay between the close of the Bertothys’ case-in-chief in November
    2020 and the witness’s eventual rebuttal testimony during March 2021, we do
    not discern an abuse of discretion in this case. As the preceding discussion
    illustrates, rigid adherence to deadlines in these circumstances is in tension
    -9-
    J-A02017-23
    with our rules and prevailing decisional law.4 While trial courts may preclude
    an expert from testifying based upon violation of discovery order or deadline,
    the trial court’s decision to permit the testimony in the case was a reasonable
    exercise of discretion.
    B. Weight of the Evidence
    The Bertothys’ next two issues relate to the trial court’s findings of fact
    concerning Jack Frost’s damages of $40,560.26 in labor and materials, the
    start date, Mr. Sallurday’s representations about the anticipated duration of
    construction, the end date, and the weather problems that hampered
    construction. While the Bertothys frame these issues as allegations of trial
    court error in ignoring what they characterize as uncontroverted facts, their
    arguments effectively assert that the trial court’s findings are against the
    weight of the evidence. Critically, the Bertothys do not contend that Jack
    Frost failed to present evidence of its damages or its representations about
    the anticipated start, duration, and completion of the project. Instead, they
    assail the evidence that Jack Frost adduced as inferior to the evidence that
    they presented to the trial court. Hence, they challenge the greater weight of
    the evidence.
    ____________________________________________
    4  See, e.g., Pa.R.C.P. 126 (“The rules shall be liberally construed to secure
    the just, speedy and inexpensive determination of every action or proceeding
    to which they are applicable. The court at every stage of any such action or
    proceeding may disregard any error or defect of procedure which does not
    affect the substantial rights of the parties.”).
    - 10 -
    J-A02017-23
    In such cases, our review is exceptionally limited:
    Appellate review of a weight claim is a review of the exercise of
    discretion, not of the underlying question of whether the verdict
    is against the weight of the evidence. Because the trial judge has
    had the opportunity to hear and see the evidence presented, an
    appellate court will give the gravest consideration to the findings
    and reasons advanced by the trial judge when reviewing a trial
    court’s determination that the verdict is against the weight of the
    evidence. One of the least assailable reasons for granting or
    denying a new trial is the lower court’s conviction that the verdict
    was or was not against the weight of the evidence and that a new
    trial should be granted in the interest of justice.
    It is not the role of an appellate court to pass on the credibility of
    witnesses; hence we will not substitute our judgment for that of
    the factfinder. Thus, the test we apply is not whether we would
    have reached the same result on the evidence presented, but
    rather, after due consideration of the evidence which the trial
    court found credible, whether the trial court could have reasonably
    reached its conclusion.
    Fazio v. Guardian Life Ins. Co. of Am., 
    62 A.3d 396
    , 413 (Pa.Super. 2012)
    (cleaned up).   “We will respect a trial court’s findings with regard to the
    credibility and weight of the evidence unless the appellant can show that the
    court’s determination was manifestly erroneous, arbitrary and capricious[,] or
    flagrantly contrary to the evidence.”    J.J. Deluca Co., Inc. v. Toll Naval
    Associates, 
    56 A.3d 402
    , 410 (Pa.Super. 2012) (quoting Ecksel v. Orleans
    Const. Co., 
    519 A.2d 1021
    , 1028 (Pa.Super. 1987)).
    In addressing the Bertothys’ weight claim, the trial court reasoned as
    follows:
    The findings stated within-this court’s opinion and order
    were based on a full review of the testimony and evidence
    presented by the parties during the three[-]day trial. . . . No new
    evidence has been presented which would cause this court to find
    - 11 -
    J-A02017-23
    the previous testimony and evidence is no longer credible. Only
    when a verdict is shocking should judgment be entered in favor of
    the moving party or a new trial granted. . . . Therefore, this court
    does not find that the verdict is so shocking as to require relief,
    and in the interests of justice, [the Bertothys’] post-trial motion
    must be denied.
    Trial Court Order and Opinion, 12/8/21/ at 8 (cleaned up).
    From this, we conclude that the trial court’s failure to find the verdict
    conscience-shocking was not an abuse of discretion. Thus, the weight claim
    fails.
    II.      Bertothys’ Counterclaims.
    Having found no reason to disturb the verdict in favor of Jack Frost, we
    turn to the Bertothys’ three issues relating to the trial court’s rejection of their
    counterclaims against Jack Frost. Essentially, the Bertothys assert that the
    court erred in concluding that (1) the breach of contract allegations were not
    ripe absent evidence that they provided the contractor reasonable opportunity
    to rectify any potential defects associated with incomplete performance; (2)
    the implied warranty of reasonable workmanship did not apply to obvious
    defects; and (3) the certified record did not support the trial court’s factual
    finding that Jack Frost performed the contract in a workman-like manner. We
    address these arguments seriatim.
    A. Opportunity to Cure
    First, contrary to the trial court’s legal conclusion, the Bertothys were
    not required to provide Jack Frost an opportunity to cure any construction
    defects. In Church v. Tantarelli, 
    953 A.2d 804
    , 807 (Pa.Super. 2008), we
    - 12 -
    J-A02017-23
    noted that there is no common law or statutory rights to cure construction
    defects in private residential construction projects. We further explained that
    the prevailing case of Hood v. Meininger, 
    105 A.2d 126
     (1954),
    does not stand for the proposition that a plaintiff must establish
    he gave a contractor a reasonable opportunity to rectify defects in
    order to establish a cause of action for breach of a construction
    contract, and no case of which we are aware cites Hood for this
    proposition. Frankly, we are unaware of any case which stands for
    this proposition. While cure and mitigation are unquestionably
    relevant to the issue of damages in a contract dispute as a general
    matter, there is simply no support in our caselaw for th[is]
    proposition[.]
    Church 
    supra at 807
    .
    Instantly, neither the Contract nor the Estimate included a right-to-cure
    clause that required the Bertothys to give Jack Frost notice of alleged defects
    prior to directing it to stop performance.         Hence, the trial court erred in
    rejecting, as premature, the Bertothys’ counterclaim seeking damages for
    those defects because they did not provide Jack Frost an opportunity to cure.
    Second, the court erred in concluding that the Bertothys’ breach-of-
    contract allegations necessarily would fail because the implied warranty of
    reasonable workmanship did not cover the visible defects that the Bertothys
    alleged.5 In reaching this conclusion, the trial court isolated the Bertothys’
    ____________________________________________
    5 Modern jurisprudence defines “workmanlike manner,” as “doing the work in
    an ordinarily skilled manner as a skilled workman should do it.” PHILIP L.
    BRUNER & PATRICK J. O’CONNOR, JR., BRUNER & O'CONNOR ON CONSTRUCTION LAW
    § 9:77 (2022). The warranty is predicated on the founding principle that
    (Footnote Continued Next Page)
    - 13 -
    J-A02017-23
    averment stating, “[t]he contract contained an implied warranty that the work
    would be performed in a reasonable, timely and workmanlike manner.”
    Answer, New Matter, and Counterclaim, 4/29/19, at ¶45.               Rather than
    accepting the statement at face value that the Bertothys expected the work
    to be performed as agreed, the court interpreted this averment as invoking
    the implied warranty of workmanlike performance, which it further reasoned
    applied only to latent defects. See Trial Court Opinion, 8/25/21, at 4. The
    court continued that, since the Bertothys’ cause of action alleged obvious,
    non-latent construction defects, the doctrine did not apply.           Id. at 6.
    However, as explained, infra, the trial court’s fixation with the Bertothys’
    reference to an implied warranty is misplaced.
    Pennsylvania is a fact pleading jurisdiction. Young v. Lippl, 
    251 A.3d 405
     (Pa. 2021).       Thus, so long as the Bertothys pled facts constituting a
    breach of contract, they were not required to plead a specific legal theory. As
    this Court has explained:
    Pennsylvania courts have long-held as a general principal
    that “plaintiffs should not be forced to elect a particular theory in
    pursuing a claim” and risk the “possibility that meritorious claims
    will fail because the wrong legal theory was chosen.” Schreiber
    v. Republic Intermodal Corp, 
    473 Pa. 614
    , 
    375 A.2d 1285
    ,
    1291 (1977) (citation omitted). “Although a plaintiff is not
    required to specify the legal theory underlying the complaint, the
    material facts which form the basis of a cause of action must be
    ____________________________________________
    “[a] contractor's failure to perform in a workmanlike manner could result in
    the rendering of work of little or no value to the contractee and, under the
    circumstances, no obligation to pay for such services would arise regardless
    of the parties’ failure to express this intention in their agreement.” 
    Id.
    - 14 -
    J-A02017-23
    alleged.” Lampus v. Lampus, 
    541 Pa. 67
    , 
    660 A.2d 1308
    , 1312
    n.2 (1995).
    Id. at 419.
    Instantly, the Bertothys pled, inter alia,
    32. [Jack Frost’s] work was not performed in a reasonable,
    timely and workmanlike manner, the evidence of which includes,
    but is not limited to:
    a.    [Jack Frost] sporadically and sparingly working on the
    [P]roject;
    b.       The improper installation and/or grading of the foundation;
    c.    Failing to construct portions of the Project as agreed to by
    the parties;
    d.   Failing to adequately protect the property from water and
    moisture damage, which includes the growth of significant mildew
    and mold;
    e.   Permitting and/or directing materials to be stored outside,
    unprotected and exposed to the weather, thereby substantially
    damaging and compromising said materials;
    f.   Installing substantially        damaged    and   compromised
    materials into the Project;
    g.       Improper installation of trusses;
    h.    Failing to construct the [p]roperty in accordance with
    industry standards, laws, and regulations and/or building codes;
    and
    f.    Otherwise failing to complete the [P]roject in a reasonable,
    timely and workmanlike manner.
    Answer,   New       Matter,   and   Counterclaim,   4/29/19,    at   ¶32    and
    ¶43 (incorporating averments into breach of contract claim). It is axiomatic
    that, to the extent that the Bertothys never accepted these obvious defects,
    - 15 -
    J-A02017-23
    they are not precluded from asserting them as bases for the breach-of contract
    claim.
    As is clear from the foregoing excerpt, the Bertothys pled material facts
    in support of their claim for a breach of contract based on Jack Frost’s allegedly
    substandard performance.      Specifically, the Bertothys contended that Jack
    Frost failed to perform as expected and as required by the Contract and
    Estimate that was attached to the complaint. Id. at ¶¶ 26-32, 43-39. In this
    regard, we also observe that the Estimate referenced in the Contract
    specifically warranted, “All Work to be completed in a professional manner
    according to standard practices.” Estimate, 9/12/17, at 2. Hence, insofar as
    the Bertothys were not required to invoke a specific legal theory as to their
    breach-of-contract claim, our review of the pleading bears out that they set
    forth sufficient material facts to form the basis of that cause of action,
    notwithstanding the reference to an “implied warranty” to highlight their
    expectation that the work would be performed satisfactorily. Thus, the trial
    court erred in ignoring the pleadings and applying law that purportedly limited
    the potential breach of performance to latent defects as an alternative basis
    to reject the Bertothys’ breach-of-contract claim.
    B. Non-latent Defects
    The Bertothys also assert that the trial court erred in making the
    contradictory findings of fact that Jack Frost performed in a workmanlike
    manner, while also recognizing the existence of non-latent defects. Bertothys’
    - 16 -
    J-A02017-23
    brief at 27. This assertion invokes the conditional language that the trial court
    used after stating its position that Jack Frost was precluded from fixing “any
    potential error or defects prior to [the Bertothys] taking possession of the
    house[.]”     Trial Court Opinion, 8/25/21, at 6.           After making that
    determination, the court continued, “[f]urther, many of the defects, such as
    water pooling on the basement slab, were not latent defects[.]” Id.
    Notwithstanding the Bertothys’ characterization of the trial court’s latter
    reference to “defects” as a genuine finding of fact, the reference actually
    related to the court’s observation of the obvious nature of some of the
    incomplete work that formed the bases of several of the Bertothys’ complaints.
    Hence, contrary the Bertothys’ protestations, the trial court’s findings are not
    in conflict. As the court clearly explained in the “Findings of Fact” section of
    its opinion: “The work that was complete, was done in a workmanlike manner,
    and any incomplete work could have been fixed of any defect prior to
    completion of the house.” Id. at 2. Accordingly, this assertion is unavailing.
    C. UTPCPL Claim
    Next, we confront whether “[t]he trial court erred in failing to rule on
    undisputed facts that assertedly constitute violations of the [UTPCPL].”
    Bertothys’ brief at 33. While the Bertothys’ counterclaim alleged that Jack
    Frost violated 201-2(4)(vii), (xiv), and (xxi), their current argument relates
    only to the Section 201-2(4) (xxi) “catchall provision which prescribes
    fraudulent or deceptive conduct which creates a likelihood of confusion or
    - 17 -
    J-A02017-23
    misunderstanding.” Id. at 34. Specifically, citing, inter alia, discrepancies in
    Pay Application No. 5 and alleging that Mr. Sallurday represented that
    construction would be complete in ten months, they contend that “undisputed
    evidence presented at trial” established that Jack Frost violated the UTPCPL
    by engaging in deceptive practices or misleading conduct that had a likelihood
    of confusion or misunderstanding. Id. at 34.
    In Gregg v. Ameriprise Financial, Inc., 
    245 A.3d 637
    , 649 (Pa.
    2021), our High Court recently recounted,
    the plain language of the current statute imposes liability on
    commercial vendors who engage in conduct that has the potential
    to deceive and which creates a likelihood of confusion or
    misunderstanding. That is all that is required. The legislature
    required neither carelessness nor intent when a cause of action is
    premised upon deceptive conduct.
    Thus, the Bertothys are correct insofar as they assert that liability under the
    catchall provision could arise if they established fraudulent or deceptive
    practices. However, as discussed infra, the certified record disproves their
    contention that Jack Frost engaged in deceptive or misleading conduct.
    In rejecting the Bertothys’ UTPCPL claim, the trial court held that they
    did not support their claim with sufficient evidence that Jack Frost specified a
    completion date or that they had any reason to disregard the clear language
    in the contract documents that completion was contingent upon delays beyond
    the contractor’s control. See Opinion and Order, 8/25/21, at 6. The court
    reasoned that it would be irrational for the Bertothys to believe that home
    construction that starts on the eve of winter would not experience weather-
    - 18 -
    J-A02017-23
    related delays. 
    Id.
       The court further noted that some of the delays were
    attributable to the Bertothys’ son, the excavation contractor, whom the
    Bertothys specifically requested perform work under the contract. Id. at 7.
    In its ensuing Rule 1925(a) opinion, the trial court expounded that the
    Bertothys also failed to establish that Jack Frost violated its warranty of
    reasonable workmanlike manner prior to receiving the cessation letter or that
    it misrepresented the quality of work that it would perform. Thus, the court
    found that the Bertothys failed to establish a violation of §201-2(4)(xxi)
    catchall provision. For the following reasons, we agree.
    First, as it relates to the Bertothys’ claim that Jack Frost billed them for
    work that it had not yet completed, the certified record reveals that Jack Frost
    purchased the plumbing and heating equipment identified in Pay Application
    No. 5, and immediately incurred liability to pay for it. N.T., 11/4/20, at 43.
    Thus, the cost of the equipment was properly billed to the Bertothys.
    However, after the Bertothys failed to satisfy Pay Application No. 5 and
    directed Jack Frost to stop construction at the site, the contractor was able to
    cancel the order and recoup that expenditure. Id. at 43-44. In light of this
    explanation, the record supports the trial court’s decision to reject the
    Bertothys’ claim that Jack Frost’s July invoice billed for incomplete work in
    contravention of the UTPCPL provision protecting consumers from a
    contractor’s deceptive or misleading conduct.
    - 19 -
    J-A02017-23
    Similarly, as noted earlier in this memorandum, despite allegations that
    Mr. Sallurday represented that the home would be completed within
    approximately ten months to one year, the record evinces that the parties
    never discussed a completion date beyond Ms. Bertothys’ initial desire to be
    completed by Christmas 2018. Id. at 27. However, at the preliminary stage
    when the contract was formed, it was impossible for Mr. Sallurday to
    guarantee a completion date. Id. More importantly, the Contract did not
    state a completion date and the September 12, 2017 Estimate, whose
    legitimacy is undisputed, anticipated possible weather delays beyond the
    contractor’s control, i.e. “All agreements contingent upon . . . delays beyond
    our control.” As the certified record will not sustain the Bertothys’ complaint
    that Jack Frost promised to complete the residence by a certain date, this
    alleged violation of the catchall provision fails.
    The Bertothys’ remaining assertions of confusion and deceit concern the
    start date and the composition of Jack Frost’s work force, respectively. As to
    the former, the Bertothys contend that Jack Frost started construction prior
    to executing the contract documents. However, the alleged “work” consisted
    entirely of a one-day site investigation, which the contractor performed with
    the Bertothys’ assistance.    Id. at 99, 101. During the trial, Mr. Sallurday
    explained:   “We met with Jason and Dana to locate the house, locate the
    septic, to find out where the utilities would come in.”      Id. at 99.   This
    preliminary investigation with the cooperation of the Bertothys is not
    - 20 -
    J-A02017-23
    tantamount to construction work and it does not establish a likelihood of
    confusion and misunderstanding under the UTPCPL.
    In relation to the latter contention concerning the composition of the
    Jack Frost work force, again, the record contradicts the Bertothys’ assertion
    that Jack Frost was not a legitimate construction company because it relied
    substantially on child labor. See Bertothys’ brief at 35. The three minors that
    this argument references, Mr. Sallurday’s teenaged nephew, grandson, and
    family friend, worked an aggregate total of 463 hours on the project in
    accordance with state regulations and under the supervision of a construction
    worker with approximately fifty-seven years of experience.          See N.T.,
    11/4/20, at 29, 115-16. Furthermore, due to the nature of carpentry and
    framing, the composition of the five-man work crew was typical for a project
    like the Bertothys’ home, which used prefabricated walls, because superfluous
    laborers would increase the cost of construction unnecessarily. Id. at 29-30.
    Moreover, as Mr. Sallurday explained in relation to the minors’ job-site
    activities, they “use nails . . . [a]nd screw guns, [which] they are allowed to
    use[.] Battery-operated tools, they're still allowed to use battery-operated
    tools, just not power tools.” Id. at 116. Hence, discounting the Bertothys’
    disingenuous inference that Jack Frost exploited child labor, the size and
    composition of the construction crew was in no way deceptive or misleading
    in violation of the UTPCPL.
    - 21 -
    J-A02017-23
    Overall, because there was sufficient evidence to support the trial court’s
    finding that the Bertothys failed to establish liability under the catchall section
    of the UTPCPL, this issue must fail.               Sufficient facts presented at trial
    demonstrated that Jack Frost did not make any misrepresentations to the
    Bertothys or act in a manner that would constitute deceptive or misleading
    conduct.      Insofar as the certified record supports the trial court’s
    determination that the claimed representations and conduct did not create a
    likelihood of confusion or misunderstanding, no relief is due.
    Thus, as it relates to the three issues concerning the denial of the
    Bertothys’ counterclaims, we conclude that the trial court erred in finding that
    the breach of contract claim was not ripe absent evidence that the Bertothys
    provided the contractor reasonable opportunity to rectify any potential defects
    associated with incomplete performance.               Accordingly, the Bertothys are
    entitled to have the trial court decide the merits of that counterclaim based
    upon the evidence presented at trial.6 Namely, the trial court must decide
    whether Jack Frost was in breach of contract and whether the Bertothys
    incurred any breach-related damages prior to October 4, 2018, the date that
    they ordered the contractor off the site.
    IV.    Conclusion
    ____________________________________________
    6 As both parties had a full and fair opportunity to present evidence to the trial
    court during the three-day hearing, a new trial is not warranted.
    - 22 -
    J-A02017-23
    In summary, we affirm the $40,560.26 verdict in favor of Jack Frost and
    do not disturb the trial court’s conclusion that the Bertothys failed to establish
    a claim for relief pursuant to the UTPCPL or its finding that the work Jack Frost
    completed prior to its dismissal was performed in a workmanlike manner.
    However, for the reasons discussed above, we vacate the judgment entered
    on the verdict and remand the matter for the court to address the Bertothys’
    breach-of-contract counterclaim based on the evidence presented at the trial.
    If the Bertothys ultimately prevail on this counterclaim, the trial court is
    directed to offset the relative verdicts and, upon praecipe of one of the parties,
    enter judgment in favor of the party with the net verdict.
    Judgment vacated.      Case remanded with instructions.         Jurisdiction
    relinquished.
    DATE: 10/6/2023
    - 23 -
    

Document Info

Docket Number: 208 WDA 2022

Judges: Bowes, J.

Filed Date: 10/6/2023

Precedential Status: Non-Precedential

Modified Date: 12/13/2024