In re Block Island Power Company Petition for Declaratory Judgment ( 2023 )


Menu:
  •                                                     Supreme Court
    No. 2020-115-M.P.
    (Docket No. 4688)
    In re Block Island Power Company     :
    Petition for Declaratory Judgment.
    NOTICE: This opinion is subject to formal revision
    before publication in the Rhode Island Reporter. Readers
    are requested to notify the Opinion Analyst, Supreme
    Court of Rhode Island, 250 Benefit Street, Providence,
    Rhode Island 02903, at Telephone (401) 222-3258 or
    Email opinionanalyst@courts.ri.gov, of any typographical
    or other formal errors in order that corrections may be
    made before the opinion is published.
    Supreme Court
    No. 2020-115-M.P.
    (Docket No. 4688)
    In re Block Island Power Company       :
    Petition for Declaratory Judgment.
    Present: Suttell, C.J., Goldberg, Robinson, Lynch Prata, Long, JJ.
    OPINION
    Chief Justice Suttell, for the Court. This Court issued a writ of certiorari to
    review a decision and judgment of the Public Utilities Commission (the PUC)
    regarding the Town of New Shoreham Project, enacted by G.L. 1956 § 39-26.1-7.
    The petitioner, Block Island Utility District d/b/a Block Island Power Company
    (BIPCo), requests a reversal of the PUC’s decision to deny BIPCo’s petition for a
    declaratory judgment. BIPCo sought a declaratory judgment declaring that the
    enabling act, specifically § 39-26.1-7(f), requires the costs for BIPCo’s
    interconnection facilities and backup transformer to be socialized across all electric
    ratepayers in Rhode Island, not just those in the Town of New Shoreham (Block
    Island or the town).1 As an intervening party, Narragansett Electric Company d/b/a
    National Grid (National Grid) argued before the PUC that § 39-26.1-7(f) does not
    1
    This opinion will use the terms Block Island, the Town of New Shoreham, and the
    town, interchangeably.
    -1-
    encompass BIPCo’s interconnection facilities or backup transformer and, therefore,
    BIPCo and its ratepayers are solely responsible for those costs. The PUC issued a
    decision and judgment against BIPCo. For the reasons stated herein, we affirm the
    decision of the PUC.
    I
    Facts and Travel
    We glean the facts in this case from the PUC’s decision and judgment, the
    transcripts of both open meetings held before the PUC, and the submissions of the
    parties.
    The Town of New Shoreham Project
    In 2009, the Legislature enacted § 39-26.1-7 (the enabling act), which
    authorized the Town of New Shoreham Project (the project). The enabling act
    greenlit the construction of a five-turbine wind farm off the coast of Block Island,
    which is twelve miles south of Rhode Island’s mainland. Specifically, the enabling
    act declared that the project would “facilitate the construction of a small-scale
    offshore wind [farm] * * * including an undersea transmission cable that
    interconnects Block Island to the mainland[.]” Section 39-26.1-7(a).2 Within the
    2
    The Block Island wind farm was completed in 2016 and BIPCo interconnected to
    it in May 2017. There is no dispute among the parties that the interconnection exists
    and operates today. The matter before this Court concerns the allocation of certain
    costs between BIPCo and National Grid, according to the terms of the enabling act.
    -2-
    statute, the Legislature described its vision for this small-scale wind farm to be a
    “demonstration project[.]” Section 39-26.1-7(a). As the first of its kind in the nation,
    the Block Island wind farm was meant to symbolize Rhode Island’s unique role
    pioneering solutions for renewable energy across the United States.
    Section (a) of the enabling act enumerated four public-policy goals driving
    the project; namely, to (1) “position the state to take advantage of the economic
    development benefits of the emerging offshore wind industry”; (2) “promote the
    development of renewable energy sources that increase the nation’s energy
    independence from foreign sources of fossil fuels”; (3) “reduce the adverse
    environmental and health impacts of traditional fossil fuel energy sources”; and (4)
    “provide the town of New Shoreham with an electrical connection to the mainland.”
    Section 39-26.1-7(a).
    When the Legislature passed the enabling act, Block Island was not at all
    connected to Rhode Island’s mainland electrical grid. For many years, without a
    hookup to mainland power, Block Island sourced its electricity exclusively from
    diesel-powered generators. These generators were operated by Block Island’s sole
    electric utility provider, BIPCo.3 One of the imperatives for the enabling act was to,
    at last, provide Block Island with an alternative power source that would render its
    polluting diesel generators obsolete.
    3
    At the time the enabling act was passed, BIPCo was a privately owned company.
    -3-
    The vehicle for this new power source—and the subject at the heart of this
    case—is an underwater transmission cable. See § 39-26.1-7(f). This cable is but one
    piece of the multifaceted project, which includes the five-turbine wind farm, an
    underwater transmission cable connecting the wind farm to a National Grid-owned
    and -operated substation on Block Island, the substation, and an underwater
    transmission cable connecting the substation to the mainland grid in the Town of
    Narragansett. Of the two transmission cables involved in the project, the one
    relevant to this case is the second—the cable that runs from National Grid’s
    substation on Block Island to the mainland. See § 39-26.1-7(a) (contemplating “an
    undersea transmission cable that interconnects Block Island to the mainland”).
    This system operates by transmitting wind-generated power from the turbines
    to the National Grid substation via the first transmission cable, at which point it
    diverts energy from the substation to BIPCo’s local distribution system and then
    transfers the remaining power, unused by BIPCo’s customers, to the mainland grid
    via the second transmission cable. Thus, the substation serves as the juncture—or
    interconnection—between BIPCo’s distribution system and National Grid’s network
    accessing the mainland.
    The two pieces of infrastructure at issue in this case are (1) BIPCo’s
    interconnection facilities and (2) the backup transformer. BIPCo’s interconnection
    facilities include the “wooden poles, overhead lines, a switch, and circuit breaker”
    -4-
    required to connect its local distribution system to the National Grid substation
    where it receives power from the wind farm. The backup transformer would, as the
    name suggests, act as a backup for the principal transformer that powers BIPCo’s
    interconnection to the substation.4          BIPCo argues that both units—the
    interconnection facilities and backup transformer—are covered in the cost allocation
    scheme laid out in section (f) of the enabling act.
    Section (f) of the enabling act governs the construction, ownership, and cost
    allocation associated with the transmission cable project. Section 39-26.1-7(f). In
    relevant part, section (f) provides that “the [Division of Public Utilities and Carriers]
    shall support transmission rates and conditions that allow for the costs related to the
    transmission cable and related facilities to be charged in transmission rates in a
    manner that socializes the costs throughout Rhode Island.” Id. (emphasis added).
    This portion of section (f) provides the basis for BIPCo’s claim that its
    4
    Typically, utility servicers retain spare or backup transformers because weather and
    manufacturing defects commonly cause outages. Here, however, the transformer
    powering BIPCo’s electricity supply to the island requires a special voltage due to
    the unique nature of the wind-powered project. As such, an additional transformer
    for this project is inordinately expensive and threatens extensive delays to build and
    obtain. BIPCo claimed that it could take as long as six months to procure a
    replacement transformer if necessary, which would force BIPCo to resort to its diesel
    generators to provide the island with power. At the time BIPCo petitioned the PUC
    for a declaratory judgment, BIPCo had not yet procured a backup transformer from
    National Grid, but discussions between the two entities concerning the cost and
    specifications for the transformer had taken place.
    -5-
    interconnection expenses should be socialized to all Rhode Island ratepayers
    because, arguably, those expenses qualify as “related facilities” costs.5
    Section (f) also granted National Grid the option to own and operate the
    transmission cable project by purchasing “the transmission cable and related
    facilities” from the developer. Section 39-26.1-7(f) (“The electric distribution
    company, at its option, may elect to own, operate, or otherwise participate in such
    transmission cable project. * * * The electric distribution company may elect to
    purchase the transmission cable and related facilities from the developer or an
    affiliate of the developer, pursuant to the terms of a transmission facility’s purchase
    agreement[.]”). On January 15, 2015, National Grid exercised that option and
    purchased the transmission cable project from the wind farm developer, Deepwater
    Wind Block Island, LLC (Deepwater), including the “engineering, permits, property
    rights, and other development work[.]” Deepwater subsequently constructed and
    installed the wind turbines, while National Grid built the Block Island substation and
    the underwater transmission cables connecting the wind farm, the island, and the
    mainland.
    5
    Before the PUC and in its briefs, BIPCo claimed that its facility interconnection
    costs summed to $263,700; grid interconnection costs were $1,836,000; and the
    spare transformer cost was $450,000. The total cost, $2,549,700, socialized among
    the roughly two thousand Block Island ratepayers would translate to a charge of
    $1,275 per customer. That amount would be collected from BIPCo’s ratepayers over
    a six-year amortization period. If the total cost were to be socialized across all Rhode
    Island ratepayers, the charge would come to about $5 per customer.
    -6-
    The Local Service Agreement
    The project is subject to the authority of ISO-New England Inc. (ISO-NE), a
    private, nonprofit entity that operates within the federal regulatory hierarchy headed
    by the Federal Energy Regulatory Commission (FERC).6 ISO-NE promulgates
    transmission rates, terms, and conditions for utility projects operating in New
    England through its ISO-NE Transmission, Markets and Services Tariff (the
    ISO-NE tariff), which ensures regional compliance with federal standards.
    As required by federal regulation, four agreements were filed with FERC in
    connection with the project, including a Local Service Agreement (LSA) executed
    between BIPCo (the Transmission Customer), New England Power Company (NEP)
    (the Transmission Owner), and ISO-NE (the Regional Transmission Organization).
    The LSA between BIPCo, NEP, and ISO-NE incorporated all terms of the ISO-NE
    tariff. The original LSA was submitted, uncontested, before FERC, allowing the
    commission to simply approve the agreement as presented without imposing its own
    determination.
    6
    ISO-NE serves as one of the many independent system operators or regional
    transmission organizations in the nation created by FERC in the late 1990s. See
    Regional Transmission Organizations, 
    89 FERC ¶ 61,285
     (Dec. 20, 1999); see also
    
    18 C.F.R. § 35.34
    . ISO-NE manages the power companies that own the transmission
    lines in New England, in this case New England Power Company—a wholly owned
    subsidiary of National Grid—under a set of rates, terms, and conditions contained in
    the ISO-NE Transmission, Markets and Services Tariff (ISO-NE tariff).
    -7-
    In a letter to FERC dated April 7, 2015, NEP and ISO-NE jointly sought to
    amend the original LSA because the Division of Public Utilities and Carriers (the
    division) determined that the original LSA did not comply with the enabling act.
    Specifically, the division informed NEP and ISO-NE that the LSA improperly
    calculated the transmission cable surcharge because it did not assess a higher rate to
    Block Island ratepayers, as section (f) directs.7 To rectify the error and bring the
    LSA—and by extension the tariff—in compliance with section (f), the LSA was
    amended to adjust the rate calculation such that Block Island ratepayers would never
    pay less than 120 percent of the rate charged to typical National Grid customers.
    7
    Section (f) provides that the transmission rates for the cable shall be calculated in
    the following manner:
    “The allocation of the costs related to the transmission
    cable through transmission rates or otherwise shall be
    structured so that the estimated impact on the typical
    residential customer bill for transmission costs for
    customers in the town of New Shoreham shall be higher
    than the estimated impact on the typical residential
    customer bill for customers on the mainland of the electric
    distribution company. This higher charge for the
    customers in the town of New Shoreham shall be
    developed by allocating the actual cable costs based on the
    annual peak demands of [BIPCo] and the electric
    distribution company, and these resultant costs recovered
    in the per-KWh charges of each company. * * * [T]he
    difference in the individual charge per KWh or per
    customer/month shall not exceed the ratio of average
    demand to peak demand for [BIPCo], relative to the
    electric distribution company, currently at 1.8 to 1.0
    respectively.” Section 39-26.1-7(f) (emphasis added).
    -8-
    FERC tariffs, including the ISO-NE tariff, typically contain “Direct
    Assignment Facility” (DAF) charges that an interconnecting customer must pay to
    the electric distribution company as reimbursement for the cost of connecting the
    new customer to the existing grid. BIPCo’s LSA contained a rate schedule, Schedule
    21, which listed the DAF charges BIPCo owed to National Grid for the cost of
    connecting to the grid. The DAF charges included under Schedule 21 were as
    follows: “Interconnection facilities and associated equipment: [one ]34.5kV breaker,
    [one ]34.5/4.16kV/2.4kV transformer, [and a] 5kV insulated line to customer
    substation and associated equipment.” Schedule 21, however, by its own terms,
    operated “in accordance with the rates, terms and conditions of Schedule 21-NEP[,]”
    which came from the ISO-NE tariff and was incorporated by reference into the LSA.
    Schedule 21-NEP included pro forma language providing:
    “[I]nterconnection facilities and additional facilities shall
    be the financial responsibility of the Transmission
    Customer, to the extent consistent with Commission
    policy.”
    BIPCo did not dispute any of the LSA terms quoted above, but rather argued
    before the PUC that the enabling act language controls. BIPCo submitted that the
    division’s previous amendment to bring the LSA in conformity with section (f)
    established that the enabling act trumps the tariff. National Grid disputed BIPCo’s
    argument, cautioning the PUC that a ruling in favor of BIPCo would challenge the
    -9-
    tariff’s authority, flout FERC’s plenary jurisdiction over the wholesale energy
    market, and potentially create federal preemption issues.
    The PUC Decision
    On January 31, 2017, BIPCo filed a petition for declaratory judgment before
    the PUC. BIPCo contended that it should not be solely responsible for shouldering
    the costs of (1) the interconnection facilities required to hook up to National Grid’s
    substation and (2) the backup transformer because these are “related facilities” with
    respect to the transmission cable that should be socialized to all Rhode Island
    ratepayers per § 39-26.1-7(f). BIPCo averred that FERC precedent, which requires
    interconnecting customers to pay for interconnections to the main grid, does not
    apply to BIPCo because § 39-26.1-7(f) is a “specific provision that overrides the
    general interconnection tariff.” Additionally, BIPCo maintained that the backup
    transformer is not a proper DAF charge under the LSA because the LSA refers to
    only one transformer, not a second, backup transformer.
    On February 25, 2017, National Grid intervened and filed an objection to
    BIPCo’s petition. National Grid advanced two key arguments, first that categorizing
    BIPCo’s interconnection expenses as socialized costs would contradict FERC
    precedent; and second that § 39-26.1-7(f) unambiguously excludes the costs for
    which BIPCo seeks reimbursement because the statute makes no reference to
    BIPCo’s interconnection or its transformer.
    - 10 -
    In March 2017, the division filed a memorandum in support of National Grid’s
    objection. The division argued that the socialization for “related facilities” should
    be limited solely to those costs incurred by National Grid, not BIPCo. The division
    also concurred with National Grid’s claim that BIPCo’s interconnection is entirely
    separate from the socialization scheme the Legislature established in section (f).
    On May 30, 2017, the PUC held an open meeting to hear oral arguments from
    BIPCo, National Grid, and the division. At the meeting, BIPCo argued that the PUC
    should construe “related facilities” to include its interconnection facilities and
    backup transformer because such a reading would (1) be consistent with the
    legislative intent of the statute; and (2) properly regard the statute, not the ISO-NE
    tariff, as the prevailing authority for the cable cost calculations.
    National Grid countered BIPCo’s claims with several arguments, asserting
    that (1) the Legislature never intended all costs to be socialized, only those incurred
    by National Grid for the assets it bought from Deepwater; (2) the enabling act does
    not override the ISO-NE tariff; (3) BIPCo’s interconnection facilities and backup
    transformer are “sole-use”—or facilities that benefit only the customer—which
    FERC precedent requires the customer to cover; and (4) deciding for BIPCo would
    open the door for other similarly situated customers to seek recovery for
    interconnecting costs.
    - 11 -
    In an open meeting held on July 27, 2017, the PUC issued its decision with
    two votes in favor of National Grid and one vote against.            The majority of
    commissioners were convinced that FERC precedent and the ISO-NE tariff
    contemplate BIPCo as an ordinary, voluntary interconnecting customer solely
    responsible for the costs of interconnection. Chairwoman Curran discussed “how
    interconnections are dealt with in the wholesale market” and stated that, typically,
    “the interconnection to something like the cable * * * is the responsibility of the
    customer.” Commissioner Gold also added that § 39-26.1-7 does not technically
    require BIPCo to interconnect to the project at all and that “the legislative goal” of
    “moving the state and the region off fossil fuels * * * can be met even if Block Island
    were to continue to use their diesel generators.”
    In its written decision, the PUC majority engaged with the statutory
    interpretation issue in greater detail and reasoned that “the transmission cable and
    related facilities are treated [in the statute] as a package of items.” The conjunctive
    phrase “transmission cable and related facilities” deliberately “isolate[d] the
    equipment and infrastructure as items that National Grid * * * elect[ed] to purchase
    from the developer[,]” according to the PUC. (Emphasis added.) This infrastructure
    included everything National Grid received from Deepwater, but not the
    interconnection facilities, which pertain exclusively to BIPCo and were never owned
    by Deepwater.     The PUC decided that, because BIPCo’s facilities were not
    - 12 -
    “necessary to serve the developer’s project,” they are not “related facilities” to the
    transmission cable under § 39-26.1-7(f) and that the costs thereof were not subject
    to be socialized.
    Commissioner DeSimone did not pen a written dissent, but he did articulate
    his reasons for opposing the majority’s decision at the July meeting. He stressed
    that, when viewing the statute in its entirety, it became clear to him that failing to
    socialize the costs of BIPCo’s interconnection would frustrate a fundamental
    legislative purpose of § 39-26.1-7: to connect the Town of New Shoreham to the
    mainland. Commissioner DeSimone further dismissed National Grid’s concerns
    that a decision in favor of BIPCo would lead to a slippery slope because the statute
    is single purpose, necessarily limiting any ruling from the PUC to this case and this
    project. Finally, Commissioner DeSimone rejected National Grid’s claim that
    BIPCo is a voluntary interconnecting customer, instead perceiving BIPCo as an
    entity composed of ratepayers—the citizens and businesses of Block Island—who
    had no choice whether to interconnect. This made the interconnection cost an
    “involuntary assessment” to Block Island ratepayers, according to Commissioner
    DeSimone.
    The PUC filed a decision and judgment in favor of National Grid on May 6,
    2020. On May 12, 2020, BIPCo filed a petition for writ of certiorari, seeking review
    of the PUC’s order, which we granted.
    - 13 -
    II
    Standard of Review
    The General Assembly has prescribed the standard of review for decisions by
    the PUC brought before this Court, under G.L. 1956 § 39-5-3:
    “The findings of the commission on questions of fact shall
    be held to be prima facie true and as found by the
    commission, and the [S]upreme [C]ourt shall not exercise
    its independent judgment nor weigh conflicting evidence.
    An order or judgment of the commission made in the
    exercise of administrative discretion shall not be reversed
    unless the commission exceeded its authority or acted
    illegally, arbitrarily, or unreasonably.”
    “[T]his Court reviews judgments and orders of the PUC solely to determine whether
    the PUC’s findings are lawful and reasonable, fairly and substantially supported by
    legal evidence, and sufficiently specific to enable us to ascertain if the evidence upon
    which the PUC based its findings reasonably supports the result.” In re A & R Marine
    Corp., 
    199 A.3d 533
    , 537 (R.I. 2019) (brackets omitted) (quoting Narragansett
    Electric Co. v. Public Utilities Commission, 
    773 A.2d 237
    , 240 (R.I. 2001)).
    “[P]ure questions of law, including statutory interpretations, decided by the
    [PUC] are reviewed de novo by this Court.” In re Proposed Town of New Shoreham
    Project, 
    25 A.3d 482
    , 504 (R.I. 2011). “It is well settled that when the statutory
    language is clear and unambiguous, we give the words their plain and ordinary
    meaning.” In re Estate of Cardiff, 
    266 A.3d 1217
    , 1219 (R.I. 2022) (quoting Butler
    v. Gavek, 
    245 A.3d 750
    , 754 (R.I. 2021)). “It is only when confronted with an
    - 14 -
    unclear or ambiguous statutory provision that this Court will examine the statute in
    its entirety to discern the legislative intent and purpose behind the provision.”
    Liberty Mutual Insurance Company v. Kaya, 
    947 A.2d 869
    , 872 (R.I. 2008) (quoting
    State v. LaRoche, 
    925 A.2d 885
    , 887 (R.I. 2007)).
    The PUC decision and judgment at issue here is one of statutory
    interpretation; we, therefore, proceed with our review de novo.
    III
    Discussion
    This is not the first time that the Block Island wind project has reached this
    Court. In 2011, in In re Proposed Town of New Shoreham Project, we dealt with a
    dispute concerning the power purchase agreement (PPA) between the electric
    distribution company, National Grid, and the wind farm developer, Deepwater. In re
    Proposed Town of New Shoreham Project, 
    25 A.3d at 485-86
    . Our decision in that
    case also recounted a thorough history of the project, its inception in the General
    Assembly, and its previous proceedings before the PUC. 
    Id. at 486-504
    .8
    Our discussion here pertains only to the narrow question on which BIPCo
    seeks review: Does the phrase “related facilities,” under § 39-26.1-7(f), cover
    BIPCo’s interconnection facilities and backup transformer such that those costs must
    8
    We encourage the curious reader to review the In re Proposed Town of New
    Shoreham Project, 
    25 A.3d 482
     (R.I. 2011), opinion for a more exhaustive
    background on the project.
    - 15 -
    be socialized across all Rhode Island ratepayers? This is a question of statutory
    interpretation.
    The parties advocate for two opposing interpretations of “related facilities”
    under § 39-26.1-7(f), National Grid advancing a narrower definition and BIPCo a
    broader one. The PUC decided in favor of National Grid, ruling that “related
    facilities” must be narrowly construed to encompass only the equipment and assets
    National Grid had the option to purchase from the developer—Deepwater—as part
    of the transmission cable project. See § 39-26.1-7(f). On the contrary, BIPCo
    implores this Court to read the statute as a whole and hold that, as a matter of law,
    “related facilities” must include its interconnection facilities and backup
    transformer.
    “It is well settled that when the statutory language is clear and unambiguous,
    we give the words their plain and ordinary meaning.” Butler, 245 A.3d at 754
    (quoting Bayview Loan Servicing, LLC v. Providence Business Loan Fund, Inc., 
    200 A.3d 153
    , 157 (R.I. 2019)). Further, “when we examine an unambiguous statute,
    there is no room for statutory construction and we must apply the statute as written.”
    Morel v. Napolitano, 
    64 A.3d 1176
    , 1179 (R.I. 2013) (quoting Mutual Development
    Corp. v. Ward Fisher & Co., LLP, 
    47 A.3d 319
    , 328 (R.I. 2012)).
    The Legislature does not define or itemize “related facilities” in section (f),
    nor does the term possess any existing meaning in our caselaw to guide this Court’s
    - 16 -
    understanding of its plain and ordinary meaning. Section 39-26.1-7(f); see Jerome
    v. Probate Court of Town of Barrington, 
    922 A.2d 119
    , 123 (R.I. 2007) (holding that
    the terms “encumbrance” and “lien” were not ambiguous because, even though
    undefined in the statute, these terms “have a particular meaning in our law”).
    However, even though the Legislature did not define the term “related facilities,” it
    did qualify it in a way that extinguishes any ambiguity. See Freepoint Solar LLC v.
    Richmond Zoning Board of Review, 
    274 A.3d 1
    , 6 (R.I. 2022) (reasoning that “where
    the Legislature has not defined or qualified the words used within the statute” it is
    “particularly true” that we must give clear and unambiguous language its plain and
    ordinary meaning) (emphasis added) (quoting Drs. Pass and Bertherman, Inc. v.
    Neighborhood Health Plan of Rhode Island, 
    31 A.3d 1263
    , 1269 (R.I. 2011)).
    “Related facilities” is mentioned three times in § 39-26.1-7(f), each time in
    conjunction with the transmission cable.
    First: “The electric distribution company may elect to purchase the
    transmission cable and related facilities from the developer or an affiliate of the
    developer, pursuant to the terms of a transmission facility’s purchase agreement[.]”
    Section 39-26.1-7(f) (emphasis added).
    Second: “Once written consent is provided, the electric distribution company
    and its transmission affiliate are authorized to make a filing with the Federal Energy
    Regulatory Commission to put into effect transmission rates to recover all of the
    - 17 -
    costs associated with the purchase of the transmission cable and related facilities
    and the annual operation and maintenance.” Section 39-26.1-7(f) (emphasis added).
    Third: “The division shall support transmission rates and conditions that allow
    for the costs related to the transmission cable and related facilities to be charged in
    transmission rates in a manner that socializes the costs throughout Rhode Island.”
    Section 39-26.1-7(f) (emphasis added).
    Observing these three uses of “related facilities,” National Grid insists that the
    phrase is clear and unambiguous. Looking to the first use, National Grid argues that
    “related facilities” refers to the transmission cable project exclusively as National
    Grid acquired the project from the developer. Moreover, because the developer
    never owned BIPCo’s interconnection facilities, National Grid contends, those
    facilities cannot possibly be related to the transmission cable project optioned from
    Deepwater.
    As to the second use, National Grid contends that “related facilities” covers
    only the infrastructure for which “the electric distribution company and its
    transmission affiliate” would seek reimbursement through transmission rates filed
    with FERC. Section 39-26.1-7(f). National Grid also emphasizes that section (f)
    never mentions the words interconnection facilities or transformer. Such glaring
    omissions must, National Grid argues, signal that the Legislature never intended for
    BIPCo’s interconnection to be socialized.
    - 18 -
    And finally, as to the third use, National Grid simply asserts that if the
    Legislature had intended to socialize all costs associated with the project, including
    those for BIPCo’s interconnection, it would have written that into the statute.
    BIPCo, meanwhile, grounds its argument in a more holistic reading of the
    statute. BIPCo maintains that, because a topline priority of the enabling act is to
    “provide the town of New Shoreham with an electrical connection to the mainland,”
    any infrastructure facilitating that connection must be, at minimum, “related” to the
    transmission cable. Section 39-26.1-7(a). Removing the interconnection and backup
    transformer from the “related facilities” costs socialized to all Rhode Islanders
    defeats and frustrates the fundamental purpose of the act, according to BIPCo.
    Considering these arguments, the PUC based its final decision on National
    Grid’s first argument, concurring that “related facilities” encompasses only the
    facilities necessary to complete the wind farm as acquired from Deepwater. The
    PUC ruled, “[I]t is clear from the text of the statute that the ‘related facilities’
    associated with the ‘transmission cable’ that National Grid was permitted to
    purchase from the ‘developer or affiliate of the developer’ includes only those
    facilities necessary to serve the developer’s project, the Block Island Wind Farm.”
    Having reviewed the matter de novo, we agree with the PUC’s decision. See
    In re Narragansett Electric Company, 
    276 A.3d 363
    , 371 (R.I. 2022). Upon each
    use of the term “related facilities,” the Legislature coupled it with the conjunctive
    - 19 -
    connector “and” along with “the transmission cable.” See § 39-26.1-7(f). Reading
    section (f) according to this plain construction, “related facilities” clearly refers only
    to those facilities directly involved with the transmission cable project as National
    Grid purchased it from Deepwater. Purely as a matter of grammar, therefore, the
    language does not arouse any hint of ambiguity.
    We also acknowledge that this reading of section (f) aligns with this Court’s
    previous analysis of the enabling act in In re Proposed Town of New Shoreham
    Project. In re Proposed Town of New Shoreham Project, 
    25 A.3d at 509
    . In that
    case, we drew a distinction between the Town of New Shoreham Project, generally,
    and the transmission cable project, specifically. See 
    id.
     (noting that § 39-26.1-7(f)
    “refer[s] to National Grid’s optional participation in the ‘transmission cable project’”
    and that § 39-26.1-7(g) “distinguish[es] the ‘transmission cable project’ from ‘the
    Town of New Shoreham Project’”).9 We further opined that “the ‘Town of New
    9
    Section (g) of the enabling act reads, in relevant part:
    “Any charges incurred by [BIPCo] * * * in implementing
    this section * * * shall be recovered annually in rates
    through a fully reconciling rate adjustment, subject to
    approval by the commission. If the electric distribution
    company owns * * * the transmission cable project,
    pursuant to section (f) of this section, the provisions of
    § 39-26.1-4 shall not apply to the cable cost portion of the
    town of New Shoreham project.” Section 39-26.1-7(g).
    National Grid argues that any cost-recovery options available to BIPCo are
    contemplated in section (g), negating any claims it may seek under section (f). This
    argument does not impact our analysis as we find the language in section (f) to be
    - 20 -
    Shoreham Project’ was the umbrella project over which the contract for the purchase
    of renewable energy and the ‘transmission cable project’ were integral, but not
    necessarily simultaneous parts.” Id. at 491. We further stated that “the general policy
    goals for the Town of New Shoreham Project” do not “create an express mandate”
    for each of its composite parts, including the transmission cable project. Id. at 509-10
    (rejecting the notion that section (a)’s policy goals informed the requirements for the
    2010 PPA because “§ 39-26.1-7(a)’s policy intention * * * of interconnecting Block
    Island [was] directed at the ‘Town of New Shoreham project’ to ‘effectuate’”).
    BIPCo’s attempt to use the section (a) policy goals to graft new language onto
    section (f)—like “interconnection” and “transformer”—defies this Court’s explicit
    disaggregation of the Town of New Shoreham Project from the transmission cable
    project. Section (f) covers the transmission cable project only, which need not
    advance the general policy goals espoused in section (a). See In re Proposed Town
    of New Shoreham Project, 
    25 A.3d at 509
     (admonishing the petitioners for
    “cherrypick[ing] and then cobbl[ing] together the overarching policy goals for the
    Town of New Shoreham Project to form what they allege is a * * * mandate for the
    2010 PPA”). BIPCo misunderstands the framework of the enabling act with its
    contention that the project’s goal in section (a) to “provide the town of New
    unambiguous and exclusive of BIPCo’s interconnection costs, regardless of section
    (g).
    - 21 -
    Shoreham with an electrical connection to the mainland” must inform the meaning
    of “related facilities” as it appears in section (f). Sections 39-26.1-7(a), (f). That is
    not what this Court held in In re Proposed Town of New Shoreham Project and it is
    not what a plain and ordinary reading of the statutory language demands.
    Noting that “we accord great deference to the PUC[] * * * and [that] we will
    not disturb an order unless the PUC ‘clearly * * * acts illegally, arbitrarily, or
    unreasonably[,]’” we observe no grounds to overturn the PUC’s decision. In re Kent
    County Water Authority Change Rate Schedules, 
    996 A.2d 123
    , 128 (R.I. 2010)
    (quoting Narragansett Electric Co., 
    773 A.2d at 240
    ). We hold that “related
    facilities” clearly and unambiguously excludes the costs of BIPCo’s interconnection
    facilities and backup transformer. See In re A & R Marine Corp., 
    199 A.3d at 537
    .
    As such, we affirm the PUC’s decision in favor of National Grid.10
    IV
    Conclusion
    For the reasons stated herein, we affirm the decision and judgment of the PUC.
    We remand the record to the PUC with our decision endorsed thereon.
    10
    Given our affirmance of the PUC’s definition of “related facilities,” no conflict
    exists between section (f) of the enabling act and the terms of the ISO-NE tariff. The
    ISO-NE tariff, Schedule 21-NEP, incorporates BIPCo’s interconnection and backup
    transformer as DAF charges owed by BIPCo and its ratepayers. This scheme is not
    at odds with the cost allocation structure established in either section (f) or (g) of the
    enabling act. Absent any conflict, we need not reach the parties’ arguments as to the
    tariff or preemption of FERC’s plenary authority.
    - 22 -
    STATE OF RHODE ISLAND
    SUPREME COURT – CLERK’S OFFICE
    Licht Judicial Complex
    250 Benefit Street
    Providence, RI 02903
    OPINION COVER SHEET
    In re Block Island Power Company
    Title of Case
    Petition for Declaratory Judgment.
    No. 2020-115-M.P.
    Case Number
    (Docket No. 4688)
    Date Opinion Filed                       February 10, 2023
    Suttell, C.J., Goldberg, Robinson, Lynch Prata, Long,
    Justices
    JJ.
    Written By                               Chief Justice Paul A. Suttell
    Source of Appeal                         The Rhode Island Public Utilities Commission
    Judicial Officer from Lower Court        N/A
    For Petitioner:
    Leah J. Donaldson, Esq.
    Attorney(s) on Appeal                    For Respondent:
    Tiffany A. Parenteau, Esq.
    Christine E. Dieter, Esq.
    SU-CMS-02A (revised November 2022)