Clean Harbors Environmental Services, Inc. v.96-108 Pine Street LLC v. J.R. Vinagro Corporation J.R. Vinagro Corporation v. 96-108 Pine Street LLC ( 2023 )


Menu:
  • January 5, 2023
    Supreme Court
    Clean Harbors Environmental Services, :
    Inc.
    v.                    :           No. 2019-164-Appeal.
    (PM 12-1322)
    96-108 Pine Street LLC            :
    v.                    :
    J.R. Vinagro Corporation.          :
    J.R. Vinagro Corporation           :          No. 2019-165 Appeal.
    (PM 12-1719)
    v.                    :
    96-108 Pine Street LLC.           :
    NOTICE: This opinion is subject to formal revision
    before publication in the Rhode Island Reporter. Readers
    are requested to notify the Opinion Analyst, Supreme
    Court of Rhode Island, 250 Benefit Street, Providence,
    Rhode Island 02903, at Telephone 222-3258 or Email
    opinionanalyst@courts.ri.gov of any typographical or
    other formal errors in order that corrections may be made
    before the opinion is published.
    Supreme Court
    Clean Harbors Environmental Services, :
    Inc.
    v.                     :          No. 2019-164-Appeal.
    (PM 12-1322)
    96-108 Pine Street LLC            :
    v.                     :
    J.R. Vinagro Corporation.          :
    J.R. Vinagro Corporation           :
    No. 2019-165-Appeal.
    v.                     :          (PM 12-1719)
    96-108 Pine Street LLC.           :
    Present: Suttell, C.J., Goldberg, Robinson, Lynch Prata, and Long, JJ.
    OPINION
    Justice Lynch Prata, for the Court.       In these consolidated cases, the
    plaintiff/third-party defendant, J.R. Vinagro Corporation (Vinagro), appeals from
    a final judgment of the Superior Court following a nonjury trial, denying
    Vinagro’s motion for attorneys’ fees and costs against the defendant/third-party
    -1-
    plaintiff, 96-108 Pine Street LLC (Pine Street).1 Vinagro argues that the trial justice
    abused his discretion by not awarding Vinagro attorneys’ fees and costs under the
    parties’ demolition contract based on the trial justice’s determination that neither
    Vinagro nor Pine Street was the prevailing party. For the reasons stated herein,
    we vacate the judgment of the Superior Court.
    Facts and Travel
    On July 7, 2011, Vinagro and Pine Street executed a demolition contract for
    a fixed fee of $297,000 (the contract). The contract required Vinagro to demolish a
    parking garage owned by Pine Street located at 100 Pine Street in Providence (the
    garage); to conduct dewatering operations, as necessary; and to apply for, obtain,
    and pay for all permits as necessary for the completion of the work. The contract
    also contained a time-is-of-the-essence clause requiring Vinagro to complete the
    project within eight weeks. After commencing the demolition work, however,
    Vinagro observed six feet of oil-contaminated water in the basement of the garage.
    Consequently, Vinagro consulted and hired plaintiff Clean Harbors Environmental
    Services, Inc. (Clean Harbors), to remediate the contamination. Work, however,
    was disrupted, and litigation ensued.
    1
    Pine Street also filed a motion for attorneys’ fees and costs that was similarly
    denied.
    -2-
    The parties, including Clean Harbors, filed three separate cases in Providence
    County Superior Court, which were subsequently consolidated on July 27, 2012.2
    Thereafter, summary judgment was granted in favor of Clean Harbors on its breach-
    of-contract and bond claims, leaving the following claims for trial: (1) Vinagro’s
    direct claims against Pine Street for breach of contract and unjust enrichment; (2)
    Pine Street’s amended third-party complaint against Vinagro for breach of contract;
    and (3) Vinagro’s third-party counterclaim against Pine Street for breach of contract
    and unjust enrichment.
    On February 16, 2018, following a nonjury trial, the trial justice issued a
    written decision in favor of Vinagro on its breach-of-contract and unjust-enrichment
    claims, and in favor of Pine Street on its breach-of-contract claim.3 As a result of
    these findings, the trial justice awarded Vinagro $145,500 on the base contract and
    $284,245.92 for the extracontractual work, plus prejudgment interest from May 12,
    2012. 4 The trial justice also awarded Pine Street $62,000 in liquidated damages,
    2
    The three actions are J.R. Vinagro Corporation v. 96-108 Pine Street LLC (PM 12-
    1719); Clean Harbors Environmental Services, Inc. v. 96-108 Pine Street LLC v.
    J.R. Vinagro Corporation (PM 12-1322); and Clean Harbors Environmental
    Services, Inc. v. J.R. Vinagro Corporation et al. (PC 12-2141).
    3
    Throughout this litigation, Vinagro’s unjust-enrichment claim has been referred to
    as quantum meruit by both the parties and the trial justice. For purposes of clarity
    and consistency, we will refer to this claim as unjust enrichment.
    4
    The parties stipulated at trial that Vinagro was entitled to $145,500 on the base
    contract.
    -3-
    plus prejudgment interest from November 1, 2012. The trial justice reserved
    decision on the issue of attorneys’ fees.
    Subsequently, Vinagro and Pine Street each moved for attorneys’ fees and
    costs based on Section 10 of the contract, which provides:
    “If any party to this Contract brings a cause of action
    against the other party arising from or relating to the
    Contract, the prevailing party in such proceeding shall be
    entitled to recover its reasonable attorney fees and court
    costs.”
    In ruling on the parties’ cross-motions for attorneys’ fees, the trial justice
    concluded: (1) that Vinagro’s unjust-enrichment claim did not fall within the
    contract’s fee-shifting provision because it was an equitable claim that did not arise
    out of the contract; and (2) that “this was a split decision” in which “both sides won
    and both sides lost” because each party had prevailed on certain aspects of the
    underlying case. Significantly, the trial justice declined to consider the monetary
    awards for each cause of action, explaining that he was not interested in
    mathematical calculations because, “[w]hile the award of money is an important
    factor to consider * * * it is not the sole focus of the inquiry.”
    Additionally, the trial justice noted a lack of precedent in this jurisdiction
    concerning discretion to award attorneys’ fees in split decisions where a contractual
    fee-shifting provision is present. Because of this, he relied on caselaw from other
    jurisdictions supporting the proposition that, where the trial court finds that both
    -4-
    parties prevailed on significant issues, the trial justice has discretion to determine
    that no party prevailed in the litigation and may decline to award attorneys’
    fees under a prevailing-party provision. See Empire Development Co. v. Johnson,
    
    770 P.2d 525
    , 530 (Mont. 1989) (explaining that, although the “award of money is
    an important factor to consider * * * it is not the sole focus of the inquiry * * * where
    the parties have mutually breached the same contract,” and thus, holding that the
    lower court did not err by refusing to grant either party attorneys’ fees); Anderson &
    Karrenberg v. Warnick, 
    289 P.3d 600
    , 604 (Utah Ct. App. 2012) (finding that trial
    court did not exceed its discretion by concluding that neither party was entitled to an
    award of attorneys’ fees because there was no prevailing party); Browning-Ferris
    Industries, Inc. v. Casella Waste Management of Massachusetts, Inc., 
    945 N.E.2d 964
    , 975-76 (Mass. App. Ct. 2011) (affirming trial judge’s finding that, because
    neither party was a “prevailing party” within the meaning of the contract, the
    litigation produced a split decision, and holding that such a “divided outcome
    precludes either side from the usual status of ‘prevailing party’”); Brevard County
    Fair Association, Inc. v. Cocoa Expo, Inc., 
    832 So. 2d 147
    , 151 (Fla. Dist. Ct. App.
    2002) (explaining that in instances where the trial court finds that both parties
    prevailed on significant issues, “the trial judge has discretion to determine no party
    prevailed in the litigation and it is proper to deny an award of attorney’s fees under
    a prevailing party contract or statute”). Based on this caselaw, the trial justice
    -5-
    declined to award either party attorneys’ fees and costs and directed Vinagro and
    Pine Street to each bear its own expenses incurred as a result of the litigation.
    Thereafter, final judgment entered on January 11, 2019, in the consolidated matters,
    and Vinagro timely appealed the denial of its attorneys’ fees and costs in both PM
    12-1322 and PM 12-1719.
    Standard of Review
    “We have repeatedly stated that, in conducting a review of a trial justice’s
    award of attorneys’ fees, ‘the issue of whether there exists a basis for
    awarding attorneys’ fees generally is legal in nature, and therefore our review of
    such a ruling is de novo.’” America Condominium Association, Inc. v. Mardo, 
    140 A.3d 106
    , 115 (R.I. 2016) (brackets omitted) (quoting Dauray v. Mee, 
    109 A.3d 832
    ,
    845 (R.I. 2015)). “Accordingly, we have further stated that ‘only if it is determined
    that there is such a legal basis, then this Court will review a motion justice’s
    actual award of attorneys’ fees for an abuse of discretion.’” 
    Id.
     (brackets omitted)
    (quoting Dauray, 
    109 A.3d at 845
    ).         “This Court has long adhered to the
    ‘American rule’ that ‘requires each litigant to pay its own attorney’s fees
    absent statutory authority or contractual liability.’” 
    Id.
     (quoting Moore v. Ballard,
    
    914 A.2d 487
    , 489 (R.I. 2007)).
    -6-
    Discussion
    On appeal, Vinagro contends that the trial justice erred in denying Vinagro’s
    motion for attorneys’ fees and costs, arguing that while discretion may be exercised
    by the trial justice in determining whether a particular party prevailed in a given
    matter, the trial justice is “divested of discretion when it comes to determining the
    prevailing party’s contractual entitlement to attorneys’ fee[s] and costs” when
    faced with a fee-shifting provision.            More specifically, Vinagro asserts
    that the “phrases ‘shall be entitled’ and ‘shall be awarded’ in the context of
    a contractual fee-shifting provision are indistinguishable and mandate that
    attorneys’ fees be awarded to the prevailing party as a matter of right.” Moreover,
    Vinagro avers that not only is Vinagro the prevailing party in this matter but that it
    is entitled to an attorneys’ fees award as a matter of right pursuant to the clear and
    unambiguous terms of the contract’s fee-shifting provision and that, therefore,
    the trial justice’s refusal to award such fees constitutes reversible error.
    Additionally, Vinagro argues that public policy favors enforcing the
    contract’s fee-shifting provision as written because two sophisticated parties—here,
    Vinagro and Pine Street—specifically bargained for such a provision. According to
    Vinagro, the contract’s fee-shifting provision clearly demonstrates that the parties
    “wished to ensure that a prevailing party in any ensuing litigation would be
    reimbursed for its attorneys’ fees.” Consequently, construing this provision in such
    -7-
    a way as to afford the trial court discretion to award attorneys’ fees to the prevailing
    party “would render the clear terms of the agreement a mere nullity” and would
    “incentivize the frivolous lawsuits which attorneys’ fee-shifting provisions are
    intended to discourage[.]”     Thus, Vinagro maintains that public policy favors
    enforcing the attorneys’-fee provision in the contract as written, and that the trial
    justice abused his discretion in determining that Vinagro was not a prevailing party
    and by declining to award Vinagro attorneys’ fees and costs.
    In response, Pine Street argues that the trial justice did not abuse his discretion
    in declining to award Vinagro attorneys’ fees because an award of attorneys’ fees is
    mandatory only if there is a prevailing party on the contractual claims. As such, an
    award of fees is not appropriate in this case because, according to Pine Street,
    Vinagro did not prevail on the significant issues related to its breach-of-contract
    claim, as the trial justice determined. Moreover, Pine Street maintains that this Court
    should afford the trial justice discretion in determining who is the prevailing party.
    Thus, Pine Street urges this Court to deny and dismiss Vinagro’s appeal and hold
    that the trial justice did not abuse his discretion in declining to award Vinagro
    attorneys’ fees and costs.
    It is well settled that “the issue of whether there exists a basis for awarding
    attorneys’ fees generally is legal in nature,” and therefore such a ruling is reviewed
    de novo. America Condominium Association, Inc., 140 A.3d at 115 (brackets and
    -8-
    emphasis omitted) (quoting Dauray, 
    109 A.3d at 845
    ). This Court will review a trial
    justice’s actual award for attorneys’ fees for an abuse of discretion only if it is first
    determined that such a legal basis exists. 
    Id.
     Consequently, we begin our analysis
    by looking to the contract to determine whether a legal basis exists for Vinagro’s
    claim for attorneys’ fees and costs. See id. at 115-16.
    As noted, Section 10 of the contract provides that “[i]f any party to this
    Contract brings a cause of action against the other party arising from or relating to
    the Contract, the prevailing party * * * shall be entitled to recover its reasonable
    attorney fees and court costs.” (Emphasis added.) A plain reading of Section 10
    leads to the inescapable conclusion that the contract provides a legal basis for an
    award of attorneys’ fees and costs. See America Condominium Association, Inc., 140
    A.3d at 116; see also Rivera v. Gagnon, 
    847 A.2d 280
    , 284 (R.I. 2004) (stating that
    a contract “must be viewed in its entirety, and the contract terms must be assigned
    their plain and ordinary meanings”). The words “shall be” and “entitled to” mandate
    an award of attorneys’ fees and costs where a party prevails on a claim (or claims)
    arising from or relating to the contract. Section 10’s fee-shifting mandate, however,
    is predicated on the existence of: (1) a prevailing party; and (2) a claim or claims
    arising from or relating to the contract.
    Turning first to the question of who was the prevailing party, the trial justice
    declined to award either party attorneys’ fees and costs, reasoning that each
    -9-
    party prevailed on certain aspects of the underlying case and that, therefore,
    there was no one prevailing party.      On appeal, however, Vinagro argues that
    such a finding constitutes an abuse of discretion because “the fee-shifting
    provision * * * is an inviolable command that requires the trial justice to award the
    prevailing party * * * its reasonable fees and costs[.]” Vinagro maintains that “shall
    be entitled” is a clear mandate requiring the trial justice to identify the
    prevailing party in the instant litigation and award that party their reasonable
    attorneys’ fees and costs. Thus, according to Vinagro, by failing to adhere to the
    clear terms of the fee-shifting provision contained in the contract, the trial justice
    committed reversible error.
    In attempting to identify the prevailing party in this matter, the trial justice
    relied on the framework adopted by this Court in Keystone Elevator Company, Inc.
    v. Johnson & Wales University, 
    850 A.2d 912
     (R.I. 2004). In Keystone Elevator
    Company, Inc., we contemplated the meaning of the phrase “prevailing party” in the
    context of G.L. 1956 § 34-28-19, Rhode Island’s mechanics’ lien statute.
    Keystone Elevator Company, Inc., 
    850 A.2d at 917-18
    . In doing so, this Court
    embraced the significant-issues test endorsed by the Supreme Court of Florida,
    which provides that “the fairest test to determine who is the prevailing party is to
    allow the trial judge to determine from the record which party has in fact prevailed
    on the significant issues tried before the court.” 
    Id. at 918
     (quoting Prosperi v. Code,
    - 10 -
    Inc., 
    626 So. 2d 1360
    , 1363 (Fla. 1993)). Importantly, this Court made clear that
    “[s]uch a standard places the determination of which party is the ‘prevailing party’
    precisely where it ought to be, within the sound discretion of the trial justice.” Id. at
    919. As we have previously explained, “a trial justice is in the best position to assess
    the merit of each party’s claims or defenses, and to determine which party fairly may
    be said to have prevailed on the significant issues.” Id. Consequently, the question
    of which party is the prevailing party is a factual one that will be reviewed for an
    abuse of discretion. See id.
    Applying the significant-issues test as adopted in Keystone Elevator
    Company, Inc., the trial justice explained that Vinagro prevailed in recovering
    $145,500 on the base contract and on Vinagro’s unjust-enrichment claim, and that
    Pine Street had prevailed on its liquidated-damages claim.            The trial justice
    determined, however, that Vinagro’s unjust-enrichment claim did not fall within the
    scope of Section 10 because the claim was equitable in nature and therefore did not
    arise out of the contract. The trial justice further explained that the two significant
    issues in this case were dewatering and the contaminated soils; Pine Street prevailed
    on the former and Vinagro prevailed on the latter. The trial justice also noted that,
    although the amounts recovered on these respective claims were different, he did not
    believe that a mathematical calculation was useful in determining which party
    prevailed on the significant issues of the case. For these reasons, the trial justice
    - 11 -
    determined that this case was a split decision and, thus, it was fair and equitable to
    require each side to bear its own attorneys’ fees and court costs.
    Although the trial justice’s reliance on Keystone Elevator Company, Inc. was
    understandable in attempting to identify the prevailing party, the trial justice’s
    subsequent finding that no party had prevailed, without a more fact-intensive, case-
    specific analysis, was erroneous. Keystone Elevator Company, Inc. involved an
    award of attorneys’ fees in the context of Rhode Island’s mechanics’ lien statute,
    which explicitly provides the trial court with discretion to award fees to the
    prevailing party. See Keystone Elevator Company, Inc., 
    850 A.2d at 917
    . Indeed,
    the statute expressly states that “[t]he court, in its discretion, may also allow
    for the award of attorneys’ fees to the prevailing party.” Section 34-28-19
    (emphasis added). In the instant case, however, the trial justice was faced with a
    contract containing a mandatory fee-shifting provision that required a determination
    of, among other things, a prevailing party. This Court “staunchly adheres to the
    American    rule   that   requires   each   litigant   to   pay its   own   attorney’s
    fees absent statutory authority or contractual liability.” Arnold v. Arnold, 
    187 A.3d 299
    , 315 (R.I. 2018) (emphasis added) (brackets omitted) (quoting Danforth v.
    More, 
    129 A.3d 63
    , 72 (R.I. 2016)). These two sophisticated parties freely and fairly
    bargained for Section 10’s fee-shifting mandate and intended for the prevailing party
    to any proceeding arising from or relating to the contract to be reimbursed for its
    - 12 -
    attorneys’ fees. Consequently, the trial justice was divested of discretion with
    respect to determining an entitlement to attorneys’ fees; the trial justice was required
    to resolve the question of which party was the prevailing party.
    The appropriate standard for determining who is the prevailing party in the
    context of a contract containing a mandatory fee-shifting provision, for which the
    contract provides no specific definition, is a matter of first impression for this Court.
    In breach-of-contract actions such as the present case, some courts have
    held that the trial justice must designate one party as the prevailing party.
    See, e.g., Green Companies, Inc. v. Kendall Racquetball Investment, Ltd., 
    658 So. 2d 1119
    , 1121 (Fla. Dist. Ct. App. 1995); Lucite Center, Inc. v. Mercede, 
    606 So. 2d 492
    , 493 (Fla. Dist. Ct. App. 1992) (“In a breach of contract action, one party must
    prevail.”); Reinhart v. Miller, 
    548 So. 2d 1176
    , 1177 (Fla. Dist. Ct. App. 1989).
    Others, however, have endorsed a more flexible approach that affords the trial justice
    greater discretion in determining who the prevailing party is when faced with a
    situation in which both or neither party may be considered to have prevailed.
    See, e.g., R.T. Nielson Company v. Cook, 
    40 P.3d 1119
    , 1127 (Utah 2002);
    Empire Development Co., 770 P.2d at 530; Skylink Jets, Inc. v. Klukan, 
    308 So. 3d 1048
    , 1052-54 (Fla. Dist. Ct. App. 2020); Anderson & Karrenberg, 289 P.3d at
    603-04; Browning-Ferris Industries, Inc., 945 N.E.2d at 976; Brevard County Fair
    Association, Inc., 
    832 So. 2d at 151
    .
    - 13 -
    For instance, in R.T. Nielson Company, the Utah Supreme Court was faced
    with a similar contractual fee-shifting provision which provided that “the prevailing
    party to any litigation brought to enforce any provision of this Agreement shall
    be awarded its costs and attorneys fees.” R.T. Nielson Company, 40 P.3d at 1122
    (brackets omitted). The Utah Supreme Court explained that determining which
    party is the prevailing party is an appropriate question for the trial court—one which
    depends largely on “the context of each case, and, therefore, it is appropriate to leave
    this determination to the sound discretion of the trial court.” Id. at 1126-27.
    The Utah Supreme Court stated that, in determining which party is the prevailing
    party, appropriate considerations for the trial court include, but are not limited to:
    “(1) contractual language, (2) the number of claims,
    counterclaims, cross-claims, etc., brought by the parties,
    (3) the importance of the claims relative to each other and
    their significance in the context of the lawsuit considered
    as a whole, and (4) the dollar amounts attached to and
    awarded in connection with the various claims.” Id. at
    1127.
    Importantly, the Utah Supreme Court explained that “[i]n most cases involving
    language similar to the contractual language before us here, there can generally be
    only one prevailing party.” Id. However, the court also noted that the above-
    mentioned standard may permit a case-by-case evaluation and affords the trial court
    flexibility to handle unique circumstances “where both, or neither, parties may be
    considered to have prevailed.” Id.
    - 14 -
    Similar to Utah, Florida has also endorsed a flexible approach to determining
    the prevailing party in the context of breach-of-contract cases to afford the trial
    justice greater discretion when faced with a situation in which both parties or neither
    party may be considered to have prevailed. See Skylink Jets, Inc., 308 So. 3d at 1052-
    54; Newton v. Tenney, 
    122 So. 3d 390
    , 392 (Fla. Dist. Ct. App. 2013); Hutchinson
    v. Hutchinson, 
    687 So. 2d 912
    , 913 (Fla. Dist. Ct. App. 1997). More specifically,
    Florida courts have recently stated that while there generally is only one prevailing
    party in a breach-of-contract action, “there may be compelling circumstances in
    which a trial court determines that neither party prevailed in a breach of contract
    action.” Newton, 
    122 So. 3d at 392
    ; see also Hutchinson, 
    687 So. 2d at 913
    .
    Although Florida courts have not expressly defined what constitutes compelling
    circumstances, a review of relevant Florida caselaw suggests that compelling
    circumstances may exist when the parties battle to a draw such that neither party
    prevailed in the litigation. See, e.g., M.A. Hajianpour, M.D., P.A. v. Khosrow Maleki,
    P.A., 
    975 So. 2d 1288
    , 1289-90 (Fla. Dist. Ct. App. 2008) (explaining that
    compelling circumstances existed for the trial justice to decline to award fees
    because neither party prevailed on the significant issues in the litigation); Newton,
    
    122 So. 3d at 392
     (reversing trial justice’s decision not to award fees because one
    party prevailed on the significant issue in the litigation, and, thus, no compelling
    - 15 -
    circumstances existed to justify a denial of attorneys’ fees); Skylink Jets, Inc., 308
    So. 3d at 1054.
    These prevailing-party tests endorsed by Utah and Florida are the approaches
    we deem most acceptable. As other courts have highlighted, utilizing a flexible and
    reasoned approach affords the trial court sufficient discretion and places it in the best
    position to properly ascertain which party prevailed, particularly in complicated
    cases involving multiple claims and parties. See R.T. Nielson Company, 40 P.3d at
    1127; Skylink Jets, Inc., 308 So. 3d at 1053-54 (noting that the Florida Supreme
    Court has emphasized a flexible approach that gives the trial courts broad discretion
    in determining which party is the prevailing party, including the discretion to make
    a determination that neither party has prevailed if compelling circumstances are
    present); KCIN, Inc. v. Canpro Investments, Ltd., 
    675 So. 2d 222
    , 223 (Fla. Dist. Ct.
    App. 1996). As one court explained:
    “Prevailing party attorney’s fees are just and proper
    in the majority of contract litigation. We are concerned,
    however, with contracts that fail as a result of
    fault by both contracting parties. A rule which requires
    an award of prevailing party attorney’s fees in all
    cases may result in an unjust reward to a party
    whose conduct caused the failure of the contract. The
    rule is especially inequitable in the ever increasing
    number of cases in which the attorney’s fees far
    exceed the claims for damages arising from the contract.”
    KCIN, Inc., 
    675 So. 2d at 223
    .
    - 16 -
    We agree. While most cases containing language similar to that found in
    Section 10 of the contract before us will result in the determination of one prevailing
    party, there may be compelling circumstances which justify a finding that both, or
    neither, of the parties may be considered to have prevailed. See Skylink Jets, Inc.,
    308 So. 3d at 1053; Newton, 
    122 So. 3d at 392
    ; Hutchinson, 
    687 So. 2d at 913
    (“In a breach of contract action, one party must prevail, absent compelling
    circumstances.”). Such a finding, however, shall be left for those instances in which,
    after considering the above-mentioned factors, it is clear to the trial justice that such
    compelling circumstances exist to warrant a refusal to award fees.
    Therefore, we hold that the trial justice erred in finding that neither
    party prevailed in the litigation despite the existence of a mandatory fee-shifting
    provision without a more comprehensive, fact-intensive, and case-specific analysis.
    Accordingly, we vacate the trial justice’s findings in this regard and
    remand the matter to the Superior Court for a determination of the prevailing
    party by considering: “(1) [the] contractual language[;] (2) the number of claims,
    counterclaims, cross-claims, etc., brought by the parties[;] (3) the importance of
    the claims relative to each other and their significance in the context of the
    lawsuit considered as a whole[;] and (4) the dollar amounts attached to and
    awarded in connection with the various claims[,]” as well as whether compelling
    - 17 -
    circumstances exist to justify a finding that both parties, or neither party may be
    considered to have prevailed. R.T. Nielson Company, 40 P.3d at 1127.
    Unjust Enrichment
    In addition to taking issue with the trial justice’s determination that there was
    no prevailing party, Vinagro also challenges the trial justice’s conclusion that its
    unjust-enrichment claim did “not fall within the language of Paragraph 10 because
    it’s an equitable remedy, and * * * not a cause of action that arises out of the
    contract.” Vinagro argues that the expansive scope of the contract’s fee-shifting
    provision entitles it to attorneys’ fees related to prosecuting both its breach-of-
    contract and unjust-enrichment claims. Vinagro points out that the contract’s fee-
    shifting provision specifically applies to causes of action “arising from or relating
    to the Contract,” which, according to Vinagro, evidences the parties’ intent that for
    claims arising from their obligations under the contract or relating to the work on the
    subject project, the prevailing party is entitled to recoup its attorneys’ fees and costs.
    According to Vinagro, its “extra costs and expenses incurred due to unforeseen work
    on the project [we]re certainly costs and expenses ‘arising from or relating to’ the
    [contract].” Thus, Vinagro avers that interpreting Section 10 as not encompassing
    its unjust-enrichment claim would render the foregoing language mere surplusage.
    Pine Street, however, argues that the trial justice correctly found that Vinagro’s
    unjust-enrichment claim does not come within the scope of Section 10 because
    - 18 -
    equitable claims such as unjust enrichment “only lie in the absence of a contractual
    relationship.” Therefore, Pine Street contends that a claim “relating to the Contract”
    is, by definition, not one that sounds in unjust enrichment, and thus, Vinagro may
    not be awarded fees on this quasi-contractual claim.
    In determining whether Vinagro’s unjust-enrichment claim falls within
    the scope of the contract’s fee-shifting provision, we deem it “appropriate
    to apply the laws of contract construction.” America Condominium Association,
    Inc., 140 A.3d at 113 (quoting Sisto v. America Condominium Association, Inc., 
    68 A.3d 603
    , 611 (R.I. 2013)). “The determination of whether a contract’s terms are
    ambiguous is a question of law to be decided by the court.” Botelho v. City of
    Pawtucket School Department, 
    130 A.3d 172
    , 176 (R.I. 2016) (quoting JPL
    Livery Services, Inc. v. Rhode Island Department of Administration, 
    88 A.3d 1134
    ,
    1142 (R.I. 2014)); see also Beacon Mutual Insurance Company v. Spino
    Brothers, Inc., 
    11 A.3d 645
    , 648 (R.I. 2011) (“[W]hether a contract is clear and
    unambiguous is a question of law.”) It is well settled that this Court reviews
    questions of law de novo. Botelho, 130 A.3d at 176.
    “We have often stated that, when we review a contract on appeal, the contract
    ‘must be viewed in its entirety, and the contract terms must be assigned their plain
    and ordinary meanings.’” America Condominium Association, Inc., 140 A.3d at 113
    (quoting Rivera, 
    847 A.2d at 284
    ). “Consequently, ‘if the contract terms are clear
    - 19 -
    and unambiguous, judicial construction is at an end for the terms will be applied as
    written.’” 
    Id.
     (brackets omitted) (quoting Rivera, 
    847 A.2d at 284
    ). The Court will
    “refrain from engaging in mental gymnastics or from stretching the imagination to
    read ambiguity into a contract where none is present.” 
    Id.
     (brackets omitted)
    (quoting Bliss Mine Road Condominium Association v. Nationwide Property and
    Casualty Insurance Co., 
    11 A.3d 1078
    , 1083 (R.I. 2010)). “A term in a contract is
    ambiguous when it is ‘reasonably and clearly susceptible to more than one rational
    interpretation.’” Botelho, 130 A.3d at 176 (quoting Miller v. Saunders, 
    80 A.3d 44
    ,
    49 (R.I. 2013)); see also America Condominium Association, Inc., 140 A.3d at 113
    (“A contract is ambiguous only if it is ‘reasonably and clearly susceptible of more
    than one interpretation.’”) (quoting Rivera, 
    847 A.2d at 284
    ).
    In the instant matter, viewing the contract, and in particular Section 10, in its
    entirety and giving the terms thereof their plain, ordinary, and usual meanings,
    Vinagro’s unjust-enrichment claim clearly and unambiguously falls within the scope
    of Section 10. While the trial justice was correct in concluding that equitable
    remedies are not causes of action that generally arise out of contract, the trial justice
    overlooked the words, “or relating to the Contract.” These words cannot be ignored.
    As Vinagro correctly notes, Vinagro’s extra costs and expenses incurred due to the
    unforeseen work on the project unquestionably relate to the contract for the obvious
    reason that but for the existence of the contract, Vinagro would not have been
    - 20 -
    obligated to perform the unforeseen work. Thus, while we agree with the trial justice
    that Vinagro’s unjust-enrichment claim does not arise from the contract,
    it nevertheless is inextricably related to the contract. Therefore, the trial justice erred
    in concluding that Vinagro’s unjust-enrichment claim does not fall within the scope
    of the contract’s fee-shifting provision, and, consequently, we reverse the trial
    justice’s determination in this regard.
    Conclusion
    For the foregoing reasons, we vacate the judgment of the Superior Court.
    This matter shall be remanded to the Superior Court for a determination of who is
    the prevailing party through application of the standard adopted herein on the basis
    of the existing record.
    - 21 -
    STATE OF RHODE ISLAND
    SUPREME COURT – CLERK’S OFFICE
    Licht Judicial Complex
    250 Benefit Street
    Providence, RI 02903
    OPINION COVER SHEET
    Clean Harbors Environmental Services, Inc. v. 96-
    108 Pine Street LLC v. J. R. Vinagro Corporation.
    Title of Case
    J.R. Vinagro Corporation v. 96-108 Pine Street LLC.
    No. 2019-164-Appeal.
    (PM 12-1322)
    Case Number
    No. 2019-165-Appeal.
    (PM 12-1719)
    Date Opinion Filed                       January 5, 2023
    Suttell, C.J., Goldberg, Robinson, Lynch Prata, and
    Justices
    Long, JJ.
    Written By                               Associate Justice Erin Lynch Prata
    Source of Appeal                         Providence County Superior Court
    Judicial Officer from Lower Court        Associate Justice Richard A. Licht
    For Plaintiff:
    Jackson C. Parmenter, Esq.
    Attorney(s) on Appeal
    For Defendant:
    Armando E. Batastini, Esq.
    SU-CMS-02A (revised November 2022)