Drago Custom Interiors, LLC v. Carlisle Building Systems, Inc. , 2012 R.I. LEXIS 162 ( 2012 )


Menu:
  •                                                              Supreme Court
    No. 2011-280-Appeal.
    (PC 05-3715)
    Drago Custom Interiors, LLC            :
    v.                      :
    Carlisle Building Systems, Inc., et al.   :
    NOTICE: This opinion is subject to formal revision before
    publication in the Rhode Island Reporter. Readers are requested to
    notify the Opinion Analyst, Supreme Court of Rhode Island,
    250 Benefit Street, Providence, Rhode Island 02903, at Telephone
    222-3258 of any typographical or other formal errors in order that
    corrections may be made before the opinion is published.
    Supreme Court
    No. 2011-280-Appeal.
    (PC 05-3715)
    Drago Custom Interiors, LLC             :
    v.                        :
    Carlisle Building Systems, Inc., et al.     :
    Present: Suttell, C.J., Goldberg, Flaherty, Robinson, and Indeglia, JJ.
    OPINION
    Justice Goldberg, for the Court.            This case came before the Supreme Court on
    October 25, 2012, pursuant to an order directing the parties to appear and show cause why the
    issues raised in this appeal should not summarily be decided. The defendant, International
    Fidelity Insurance Company (IFIC or defendant), appeals from a Superior Court judgment in
    favor of the plaintiff, Drago Custom Interiors, LLC (Drago or plaintiff). The defendant contends
    that the Superior Court was without authority either to remand the case back to the arbitrator for
    clarification of the record or to modify the arbitration award. After considering the memoranda
    submitted by the parties and the arguments of counsel, we are satisfied that cause has not been
    shown and that the appeal may be decided at this time. We affirm the judgment.
    In April 2003, Carlisle Building Systems, Inc. (Carlisle), the general contractor for a
    construction project (project) at the Charlestown Fire Station at Routes 2 and 112, contracted
    with Drago to perform carpentry work for the project. In accordance with the contract between
    Carlisle and the Charlestown Fire District (fire district), a Labor and Material Payment Bond
    (bond) was issued for the project; Carlisle was principal on the bond, and IFIC was the surety.
    Drago alleges that the bond guaranteed payment, from either Carlisle or IFIC, to any entity
    -1-
    supplying labor or material to the project and that Drago performed work on the project for
    which it had not been paid. Accordingly, on July 20, 2005, Drago filed suit against Carlisle and
    IFIC, seeking to recover payment for the work that it had performed.
    In its answer, IFIC admitted that it was the surety on the bond. However, because the
    project fell under the purview of the Public Works Arbitration Act (PWAA or act), G.L. 1956
    chapter 16 of title 37, and the contract between Carlisle and the fire district contained an
    arbitration provision, IFIC and Carlisle moved to stay the Superior Court proceedings pending
    arbitration of Drago‟s claims. See §§ 37-16-4 and 37-16-5. Notwithstanding Drago‟s objection,
    the case began a long sojourn through arbitration.
    After two days of hearings, the arbitrator issued his first award on March 26, 2008,
    finding Carlisle liable to Drago for $43,543.02, plus interest. However, because there was no
    evidence introduced that IFIC issued any bonds relative to the project or was responsible for any
    damages claimed by Drago, the arbitrator determined that IFIC was not liable to Drago. Because
    Drago was unaware that IFIC was contesting its responsibility for Carlisle‟s liability to Drago for
    payment—IFIC having admitted in its answer that it was the surety—it requested that the
    arbitrator reopen the proceedings so that the bond could be received into evidence.
    Instead, the arbitrator issued two amended awards. The arbitrator first amended his
    findings of fact by repeating his earlier finding that no evidence had been presented that IFIC had
    issued any bonds relative to the project, but adding that “[t]he issue of IFIC‟s liability was not
    asserted or denied during the arbitration hearings.” Nonetheless, the arbitrator concluded that
    IFIC was not liable to Drago but that the arbitration award was “without prejudice to any rights
    of Drago as asserted in any pending litigation involving Drago and IFIC.”             In his second
    amended award, the arbitrator deleted the finding that the issue of IFIC‟s liability was neither
    -2-
    asserted nor denied during the arbitration hearings, but once again declared that his finding that
    IFIC was not liable to Drago was “without prejudice to any rights of Drago as asserted in any
    pending litigation involving Drago and IFIC.”
    Drago then returned to Superior Court and moved to confirm the second amended award
    concerning Carlisle‟s liability and to modify it as to IFIC so that IFIC would be liable if Carlisle
    did not pay.1 IFIC objected to the proposed modification, contending that none of the statutory
    grounds for modification of an arbitration award applied in this case. IFIC also moved to
    confirm the original award, asserting that the arbitrator had no authority to issue amended
    awards.
    A hearing eventually was held on the parties‟ competing motions on February 11, 2011.
    The trial justice determined that, because IFIC failed to file a pre-arbitration statement and, in its
    answer to Drago‟s complaint, had admitted that it was on the bond, the issue of whether IFIC
    ever had disputed liability under the bond was “unclear.” The trial justice found that the
    arbitration hearings focused entirely on Carlisle‟s liability to Drago and that there was nothing to
    suggest that IFIC disputed its liability under the bond during the arbitration proceedings. The
    trial justice also pointed to two features of the arbitration awards that caused further uncertainty:
    (1) in his first amended award, the arbitrator had stated that the issue of IFIC‟s liability was
    neither asserted nor denied during the proceedings, only to delete that finding in his second
    amended award; and (2) despite changing that finding in the second amended award, the
    arbitrator‟s order declared that the award was “without prejudice to any rights of Drago as
    asserted in any pending litigation involving Drago and IFIC.” Confronted with the uncertainty
    of whether IFIC ever had disputed that it was on the bond, the trial justice, relying on our
    1
    Apparently, Carlisle was unable to satisfy the award.
    -3-
    decision in Pier House Inn, Inc. v. 421 Corp., 
    812 A.2d 799
     (R.I. 2002), concluded that the
    Superior Court possessed the inherent authority to remand the case back to the arbitrator for
    clarification. In accordance with this inherent authority, the trial justice remanded the matter
    back to the arbitrator yet again for determination of whether the issue of IFIC‟s liability under
    the bond was raised in the arbitration and for clarification of the phrase “without prejudice to any
    rights of Drago as asserted in any pending litigation involving Drago and IFIC.”
    Upon remand, the arbitrator issued a new award in which he found that, although there
    was no evidence presented at the initial arbitration hearings that IFIC issued a bond for the
    project, the issue of IFIC‟s liability was not raised in the initial proceedings and IFIC did not
    dispute either the existence of the bond or that it covered Drago‟s claims.2 The arbitrator
    concluded that both Carlisle and IFIC were liable to Drago for $43,543.02, plus interest, and the
    post-remand award reflected this conclusion.
    Drago then moved to confirm the arbitrator‟s latest award. IFIC objected and moved to
    vacate that award and to confirm the original award. The trial justice expressed her concerns that
    IFIC contributed to this case‟s tortured travel, having admitted that it was the surety in its
    answer―thereby inducing Drago to refrain from introducing the bond at the arbitration
    proceedings―and then attempting to capitalize on this omission after the proceedings were
    closed.     The trial justice accordingly granted Drago‟s motion to confirm the post-remand
    arbitration award. Additionally, the trial justice noted that, even if she was without authority to
    order the remand, she would have granted Drago‟s motion to modify the second amended award
    because IFIC never had disputed the existence of the bond or its liability thereunder. Before this
    Court, IFIC contends that the trial justice was without authority to remand this case back to
    2
    The arbitrator did find, however, that IFIC denied that it was liable to Drago based on Carlisle‟s
    defenses to Drago‟s claims.
    -4-
    arbitration or to modify the second amended award as requested by Drago. Nine years after
    commencement of the project, this dispute is before us.
    It is well settled that, in the typical case, the judiciary‟s role in the arbitration process is
    limited. Metropolitan Property & Casualty Insurance Co. v. Barry, 
    892 A.2d 915
    , 918 (R.I.
    2006) (citing Aponik v. Lauricella, 
    844 A.2d 698
    , 703 (R.I. 2004)); State v. Rhode Island
    Employment Security Alliance, Local 401, SEIU, AFL-CIO, 
    840 A.2d 1093
    , 1096 (R.I. 2003).
    When, as here, an arbitration provision is contained in a “contract for the construction, alteration,
    repair, painting, or demolition of any public building * * * one party to which is the state, a city,
    a town, or an authority, a board, a public corporation, or any similar body created by statute or
    ordinance * * *,” § 37-16-2(b)(1), the PWAA defines the contours of the judiciary‟s role.
    Specifically, the act directs that upon timely motion for an order confirming an arbitration award,
    “the court must grant the order unless the award is vacated, modified, or corrected, as prescribed
    in §§ 37-16-18 and 37-16-19 or unless the award is unenforceable under the provisions of § 37-
    16-13.” Section 37-16-17.
    Before this Court, IFIC contends that the PWAA delimits the universe of options
    available to a trial justice; the arbitration award can be affirmed, vacated, modified or corrected,
    but nothing more. The trial justice disagreed, reading our opinion in Pier House Inn as vesting
    her with the inherent authority to remand an arbitration case for clarification of the record. We
    disagree with the trial justice‟s reading of Pier House Inn.
    In Pier House Inn, an arbitrator awarded approximately $4,000 in “compensatory
    damages” and $150,000 in what the arbitrator termed “punitive damages” on a commercial
    lessee‟s counterclaim for breach of contract. Pier House Inn, 
    812 A.2d at 801
    . The Superior
    Court vacated the punitive damages award and remanded the matter back to arbitration “to
    -5-
    determine whether that [portion of the award awarding punitive damages] was in whole or in part
    intended to be compensatory.” 
    Id. at 804
    . On appeal, this Court affirmed the trial justice‟s
    decision to vacate the punitive damages award, 
    id. at 803
    , and then tackled the thorny issue of
    the Superior Court‟s authority to remand. See 
    id. at 804-07
    .
    Despite holding that the trial justice erred in relying on G.L. 1956 § 10-3-13 as authority
    to remand the case back to the arbitrator, we upheld the remand on other grounds. Pier House
    Inn, 
    812 A.2d at 805
    . This Court explained that the “blatant discrepancy” in the award—
    awarding punitive damages to the lessee while, at the same time, finding that the lessee breached
    the lease, compounded by an award of attorneys‟ fees to the lessor—“clearly exemplifies the
    type of award that § 10-3-14 authorizes a judge to modify or correct, in the interest of
    effectuating the intent of the award and promoting justice between the parties.” Pier House Inn,
    
    812 A.2d at 805
    . We concluded that the award of punitive damages was an “evident material
    mistake” under § 10-3-14(a)(1). Pier House Inn, 
    812 A.2d at 805
    . This Court then determined
    that the remand was proper:
    “Although § 10-3-14 requires the reviewing court to modify the
    award as necessary and does not expressly limit the hearing
    justice‟s scope of review, under the circumstances of this case, the
    remand to the arbitrator was appropriate, given the insufficient
    evidence before the * * * hearing justice regarding the rationale for
    the punitive damages award.” Pier House Inn, 
    812 A.2d at 806
    .
    Elaborating on the paucity of evidence, we noted that there was neither a transcript of the
    arbitration proceeding, nor an explication of the arbitrator‟s reasoning. 
    Id.
     This Court thus
    declared that “[r]ather than rely on defendant‟s representations to modify the punitive damages
    award, the court properly sought a clarification from the arbitrator.” 
    Id.
    The precise holding of Pier House Inn, 
    812 A.2d at 805-06
    , although perhaps lacking
    pristine clarity, was that § 10-3-14 vested the trial justice with the authority to modify or correct
    -6-
    the award, but that the record before the trial justice was insufficient for him to exercise that
    authority. The uncertainty of whether the arbitrator intended the “punitive damages” award to be
    compensatory or punitive necessitated a remand to the arbitrator. Pier House Inn, 
    812 A.2d at 805-06
    . Our holding in Pier House Inn does not stand for the broader proposition that the
    Superior Court possesses the inherent authority, independent of an appropriate statutory basis, to
    remand an arbitration case back to the arbitrator to clarify the record.
    In Pier House Inn, we cited our decision in Lemoine v. Department of Mental Health,
    Retardation and Hospitals, 
    113 R.I. 285
    , 290, 
    320 A.2d 611
    , 614 (1974), wherein we held that a
    remand for clarification for the purpose of taking further evidence under the Administrative
    Procedures Act, G.L. 1956 chapter 35 of title 42 (APA), “was part of the reviewing court‟s
    „inherent power * * * to correct deficiencies in the record and thus afford the litigants a
    meaningful review.‟” Pier House Inn, 
    812 A.2d at 806
     (quoting Lemoine, 113 R.I. at 290, 
    320 A.2d at 614
    ). However, Lemoine, in contrast to Pier House Inn and this case, involved a remand
    of an agency proceeding in accordance with § 42-35-15(g) of the APA and not an arbitration
    case. See Lemoine, 113 R.I. at 286-87, 290, 
    320 A.2d at 612-14
     (affirming trial justice‟s remand
    of a personnel appeal board decision). Additionally, in Pier House Inn, we were careful to
    ground the trial justice‟s authority to remand within the provisions of § 10-3-14, noting that the
    decision “comports with the statutory mandate that the reviewing justice effectuate the intent of
    the award and „promote justice between the parties.‟ * * * But because of the minimal record, a
    remand was necessary to ascertain the arbitrator‟s intent.” Pier House Inn, 
    812 A.2d at 806
    (quoting § 10-3-14(b)).
    In the case before us, although we disagree with the trial justice‟s reading of Pier House
    Inn, we nonetheless affirm the decision on other grounds. See Pier House Inn, 
    812 A.2d at 805
    .
    -7-
    After carefully reviewing the record, we are convinced that the trial justice had clear grounds to
    vacate the second amended award. Once an award is vacated, the PWAA vests the Superior
    Court with discretion to order a rehearing before the original arbitrator(s) or before a new
    arbitrator or arbitrators. Section 37-16-19.3 We explain briefly.
    Section 37-16-18 sets forth three instances when the court must, upon motion by any
    party, vacate the award:
    “(1) When the award was procured by fraud.
    “(2) Where the arbitrator or arbitrators exceeded their powers, or
    so imperfectly executed them, that a mutual, final, and definite
    award upon the subject matter submitted was not made.
    “(3) If there was no valid contract, and the objection has been
    raised under the conditions set forth in § 37-16-13.”
    In this case, a decision vacating the second amended award clearly was warranted. The
    trial justice properly determined that the arbitrator‟s findings with respect to the existence of the
    bond were indefinite and inconsistent. In his first award, the arbitrator found “that there was no
    evidence presented that IFIC issued any bonds relative to the [p]roject.”            Soon after, the
    arbitrator issued his first amended award, which added that “[t]he issue of IFIC‟s liability was
    not asserted or denied during the arbitration hearings.” Just days later, the arbitrator deleted this
    additional finding in his second amended award.
    3
    General Laws 1956 § 37-16-19 provides:
    “Where an award is vacated, the court in its discretion may direct a
    rehearing either before the same arbitrator or arbitrators or before a new arbitrator
    or arbitrators to be chosen in the manner provided in the contract for the selection
    of the original arbitrator or arbitrators or as provided for in § 37-16-7 and any
    provision limiting the time in which the arbitrator or arbitrators may make a
    decision shall be deemed applicable to the new arbitration and shall commence
    from the date of the court‟s order.”
    -8-
    Compounding this inconsistency was the arbitrator‟s treatment of IFIC‟s liability to
    Drago. In the original award, the arbitrator found, without qualification, that IFIC was “not
    liable to Drago for any claims or damages relative to the [p]roject.” This finding stands in stark
    contrast to the first and second amended awards, which provided that IFIC was not liable to
    Drago, but added that “[t]his Order is without prejudice to any rights of Drago as asserted in any
    pending litigation involving Drago and IFIC.” This language defeats the requirement that a
    “mutual, final, and definite award upon the subject matter” be made. Section 37-16-18(2).
    The grave uncertainties infecting the second amended award, especially with respect to
    the “without prejudice” language, compel our conclusion that the arbitrator so imperfectly
    executed his powers that a final and definite award with respect to IFIC‟s liability was not made.
    See § 37-16-18(2) (providing that the court must vacate an arbitration award “[w]here the
    arbitrator or arbitrators exceeded their powers, or so imperfectly executed them, that a mutual,
    final, and definite award upon the subject matter submitted was not made.” (Emphasis added.)).
    Additionally, § 37-16-27(a)4 commands that, in an arbitration involving a surety, “[t]he
    4
    Section 37-16-27 provides as follows:
    “(a) If a contractor principal on a bond furnished to guarantee performance
    or payment on a construction contract and the claimant are parties to a written
    contract with a provision to submit to arbitration any controversy thereafter
    arising under the contract, or subject to arbitration as provided in § 37-16-2(b),
    the arbitration provisions shall apply to the surety for all disputes involving
    questions of the claimant‟s right of recovery against the surety. Either the
    claimant, the contractor principal, or surety may demand arbitration in accordance
    with the written contract or as provided in § 37-16-2(b) if applicable in one
    arbitration proceeding, provided that the provisions of § 37-16-3 shall be
    applicable to any demand for arbitration. The arbitration award shall decide all
    controversies subject to arbitration between the claimant, on the one hand, and the
    contractor principal and surety on the other hand, including all questions
    involving liability of the contractor principal and surety on the bond, but a
    claimant must file suit for recovery against the surety within the time limits set
    -9-
    arbitration award shall decide all controversies subject to arbitration between the claimant, on the
    one hand, and the contractor principal and surety on the other hand, including all questions
    involving liability of the contractor principal and surety on the bond * * *.” (Emphases added.)
    The arbitrator‟s decision in this case falls far short of the statutory mandate; an award entered
    “without prejudice to any rights of [the claimant] as asserted in any pending litigation involving
    [the claimant] and [the surety]” cannot, under any interpretation of the language, be considered
    “final” or “definite.”5
    For these reasons, we are of the opinion that the second amended award should have been
    vacated under § 37-16-18(2) and that the trial justice was authorized, under § 37-16-19, to
    remand the case to the same arbitrator for a rehearing.         Because the remand in this case
    accomplished the same result that could have been accomplished under §§ 37-16-18 and
    forth in §§ 37-12-2 and 37-12-5. The arbitration shall be in accordance with this
    chapter and the court shall enter judgment thereon as provided therein.
    “(b) The arbitrator or arbitrators, if more than one, shall make findings of
    fact as to the compliance with the requirements for recovery against the surety,
    and those findings of fact shall be a part of the award binding on all parties to the
    arbitration.”
    5
    We pause briefly to stress the unenviable position in which the Superior Court justice found
    herself. IFIC strenuously argued that Drago‟s failure to introduce the bond into evidence at the
    arbitration proceedings compelled the arbitrator‟s conclusion that IFIC was not liable to Drago—
    a position IFIC maintains on appeal. The trial justice found this argument to be unpersuasive
    because it overlooked the undeniable fact that IFIC had admitted the existence of the bond in its
    answer to Drago‟s complaint and insisted that the matter proceed to arbitration, thereby
    removing the issue from contention. Faced with a mountain of uncertainty, the options available
    to the trial justice were few, and she concluded that a remand was the proper means of
    addressing this problem. Although we reject the trial justice‟s decision with respect to a court‟s
    inherent authority to remand an arbitration award, we similarly are hard pressed to fault Drago
    for failing to introduce the bond—and to permit IFIC to capitalize on this omission—when IFIC
    conceded that it was on the bond.
    - 10 -
    37-16-19, we affirm the judgment below, but do so on grounds other than those relied upon by
    the trial justice.6
    Conclusion
    For the reasons articulated above, we affirm the judgment below. The papers in this case
    may be remanded to the Superior Court.
    6
    Given our disposition of this appeal, we need not address the trial justice‟s alternative ground
    for her decision: that the award could be modified under § 37-16-20. We accordingly express no
    opinion on whether modification of the second amended award would have been proper.
    - 11 -
    RHODE ISLAND SUPREME COURT CLERK’S OFFICE
    Clerk’s Office Order/Opinion Cover Sheet
    TITLE OF CASE:        Drago Custom Interiors, LLC v. Carlisle Building Systems, Inc., et
    al.
    CASE NO:              No. 2011-280-Appeal.
    (PC 05-3715)
    COURT:                Supreme Court
    DATE OPINION FILED: December 19, 2012
    JUSTICES:             Suttell, C.J., Goldberg, Flaherty, Robinson, and Indeglia JJ.
    WRITTEN BY:           Associate Justice Maureen McKenna Goldberg
    SOURCE OF APPEAL:     Providence County Superior Court
    JUDGE FROM LOWER COURT:
    Associate Justice Judith C. Savage
    ATTORNEYS ON APPEAL:
    For Plaintiff: Joseph J. Reale, Jr., Esq.
    For Defendant: Peter L. Kennedy, Esq.
    

Document Info

Docket Number: 2011-280-Appeal

Citation Numbers: 57 A.3d 668, 2012 R.I. LEXIS 162, 2012 WL 6624914

Judges: Suttell, Goldberg, Flaherty, Robinson, Indeglia

Filed Date: 12/19/2012

Precedential Status: Precedential

Modified Date: 10/26/2024