Marioncelli v. Westminster Lumber Co. , 8 R.I. Dec. 173 ( 1932 )


Menu:
  • BLODGETT, P. J.

    Heard without the intervention of a jury.

    Plaintiff brings action to recover for labor and materials furnished defendant.

    Defense is that the defendant corporation is not liable as the work was done under a contract with an individual.

    The Court is satisfied from the preponderance of the evidence that officers of the corporation sanctioned the work and delivery of material and received the benefit therefor.

    Decision for plaintiff for $232 and costs.

Document Info

Docket Number: No. 8671o

Citation Numbers: 8 R.I. Dec. 173

Judges: Blodgett

Filed Date: 1/11/1932

Precedential Status: Precedential

Modified Date: 11/14/2024