South Carolina Energy Users Committee v. South Carolina Electric & Gas , 410 S.C. 348 ( 2014 )


Menu:
  •         THE STATE OF SOUTH CAROLINA
    In The Supreme Court
    South Carolina Energy Users Committee,
    Appellant/Respondent,
    v.
    South Carolina Electric and Gas, South Carolina Office
    of Regulatory Staff and Pamela Greenlaw, Respondents,
    and Sierra Club, is Respondent/Appellant.
    Appellate Case No. 2013-000529
    Appeal From The Public Service Commission
    Opinion No. 27456
    Heard April 16, 2014 – Filed October 22, 2014
    AFFIRMED
    Scott Elliott, of Elliott & Elliott, P.A., of Columbia, for
    Appellant/Respondent.
    Robert Guild, of Columbia, for Respondent/Appellant.
    Belton Townsend Zeigler, of Pope Zeigler, LLC, and
    James B. Richardson, Jr., both of Columbia, K. Chad
    Burgess and Matthew W. Gissendanner, of Cayce,
    Florence P. Belser, Nanette S. Edwards, Jeffrey M.
    Nelson, and Shannon Bowyer Hudson, all of Columbia,
    for Respondents.
    CHIEF JUSTICE TOAL:             The South Carolina Energy Users Committee (the
    SCEUC) and the Sierra Club (collectively, Appellants) appeal orders of the Public
    Service Commission (the Commission) approving Respondent South Carolina
    Electric & Gas's (SCE&G) application for updated capital cost and construction
    schedules, pursuant to the Base Load Review Act, S.C. Ann. §§ 58-33-210 to -298
    (Supp. 2013) (the BLRA).1 In essence, this appeal presents the questions of
    whether the Commission applied the correct section of the BLRA, and whether the
    Commission must also consider the prudence of project completion at the update
    stage. We affirm.
    FACTS/PROCEDURAL BACKGROUND
    On March 2, 2009, SCE&G obtained an initial base load review order2
    authorizing it to complete a project involving the construction of two 1,117 net
    megawatt nuclear units in connection with the construction of a nuclear power
    plant at the V.C. Summer Nuclear Station located near Jenkinsville, South
    Carolina.
    On May 15, 2012, SCE&G petitioned the Commission for a base load
    review order approving updates to the capital cost and construction schedules for
    the project. SCE&G sought approximately $283 million in capital costs to be
    recouped from its customers in rates pursuant to the BLRA. The application
    comprised the following changes to the costs enumerated in the initial base load
    review order: (1) an Engineering, Procurement, and Construction Contract (EPC)
    change order resulting from a settlement agreement for schedule changes and
    additional costs related to the time frame in which the Combined Operating
    License was received from the Nuclear Regulatory Commission, the redesign and
    construction of certain components, and certain Unit 2 site conditions ($137.5
    1
    The South Carolina Office of Regulatory Staff (ORS) is also a respondent, made
    party pursuant to section 58-4-10 of the South Carolina Code. See 
    S.C. Code Ann. § 58-4-10
     (Supp. 2013).
    2
    A base load review order is "an order issued by the [C]ommission pursuant to
    Section 58-33-270 establishing that if a plant is constructed in accordance with an
    approved construction schedule, approved capital costs estimates, and approved
    projections of in-service expenses, as defined herein, the plant is considered to be
    used and useful for utility purposes such that its capital costs are prudent utility
    costs and are properly included in rates." 
    S.C. Code Ann. § 58-33-220
    (4).
    million); (2) owner's costs ($131.6 million); (3) transmission costs ($7.9 million);
    and (4) additional EPC change orders for cyber security ($5.9 million), healthcare
    costs ($139,573), and wastewater piping ($8,250). With respect to updates to the
    construction schedules, SCE&G sought to delay the completion date of Unit 2 by
    eleven months, which would advance the date for completion of the entire project
    by seven and one-half months.
    The Commission received timely notices to intervene by the Sierra Club,3
    the SCEUC, an organization consisting of industrial customers of SCE&G, and
    Pamela Greenlaw, a residential customer.4
    A hearing was convened before the Commission to assess the application on
    October 2–3, 2012. By order dated November 15, 2012, the Commission approved
    $278.05 million of the $283 million in cost increases to the previously approved
    capital cost budget and approved the updated construction schedule, finding the
    cost increases resulted from "the normal evolution and refinement of construction
    plans and budgets for the Units and not the result of imprudence on the part of
    SCE&G."
    Appellants filed petitions for reconsideration. In their petitions, along with
    specific errors, Appellants averred that the Commission erred generally in
    permitting the modifications after SCE&G did not anticipate the cost adjustments
    when it originally filed for an initial base load review order; that SCE&G was
    required to present a full evaluation of the prudence of the decision to continue to
    construct the nuclear units; and that the evidence in the Record was insufficient to
    meet that burden. By order dated February 14, 2013, the Commission denied
    Appellants' petitions for rehearing, finding they lacked merit. This appeal of the
    Commission's base load review order and decision to deny the petitions for
    reconsideration followed.
    3
    The Sierra Club is a non-profit organization dedicated to "protect[ing] the wild
    places of the earth" and to "promot[ing] the responsible use of the earth's
    ecosystems and resources." The Sierra Club's South Carolina Chapter consists of
    nine local groups and more than 5,000 members, some of whom are ratepayers of
    SCE&G and neighbors to the site of the proposed nuclear plant.
    4
    Pamela Greenlaw is not party to this appeal.
    ISSUES
    I. 	    Whether the Commission erred by applying the wrong section,
    and therefore the wrong standard, of the BLRA?
    II. 	   Whether the Commission erred in holding that a prudency
    evaluation of the need for the continued construction of the
    units is not required under the BLRA?
    III. 	 Whether the evidence supports the Commission's finding that
    the additional capital costs were prudent under the BLRA?
    STANDARD OF REVIEW
    "This Court employs a deferential standard of review when reviewing a
    decision from the Commission and will affirm the Commission's decision if it is
    supported by substantial evidence." S.C. Energy Users Comm. v. Pub. Serv.
    Comm'n of S.C., 
    388 S.C. 486
    , 490, 
    697 S.E.2d 587
    , 589–90 (2010) (citing Duke
    Power Co. v. Pub. Serv. Comm'n of S.C., 
    343 S.C. 554
    , 558, 
    541 S.E.2d 250
    , 252
    (2001)). "The Commission is considered the expert designated by the legislature to
    make policy determinations regarding utility rates." Id. at 490, 
    697 S.E.2d at
    590
    (citing Kiawah Prop. Owners Grp. v. Pub. Serv. Comm'n of S.C., 
    359 S.C. 105
    ,
    109, 
    597 S.E.2d 145
    , 147 (2004)); see also Hamm v. Pub. Serv. Comm'n of S.C.,
    
    289 S.C. 22
    , 25, 
    344 S.E.2d 600
    , 601 (1986) (stating that because the Commission
    is an "expert" in utility rates, "the role of a court reviewing such decisions is very
    limited" (quoting Patton v. Pub. Serv. Comm'n of S.C., 
    280 S.C. 288
    , 291, 
    312 S.E.2d 257
    , 259 (1984))). "The construction of a statute by the agency charged
    with its administration will be accorded the most respectful consideration and will
    not be overruled absent compelling reasons." Dunton v. S.C. Bd. of Exam'rs in
    Optometry, 
    291 S.C. 221
    , 223, 
    353 S.E.2d 132
    , 133 (1987); see also Nucor Steel v.
    Pub. Serv. Comm'n of S.C., 
    310 S.C. 539
    , 543, 
    426 S.E.2d 319
    , 321 (1992)
    ("Where an agency is charged with the execution of a statute, the agency's
    interpretation should not be overruled without cogent reason."). Thus,
    [b]ecause the Commission's findings are presumptively correct, the
    party challenging the Commission's order bears the burden of
    convincingly proving the decision is clearly erroneous, or arbitrary or
    capricious, or an abuse of discretion, in view of the substantial
    evidence of the record as a whole.
    S.C. Energy Users Comm., 
    388 S.C. at 491
    , 
    697 S.E.2d at
    590 (citing Duke Power
    Co., 
    343 S.C. at 558
    , 
    541 S.E.2d at 252
    ); see also S.C. Code Ann § 1-23-380(A)(6)
    (Supp. 2013).
    ANALYSIS
    I. Statutory Construction
    Appellants argue that the Commission erred as matter of law by failing to
    apply the relevant legal standard in granting SCE&G's request because the
    additional capital costs could have been anticipated when SCE&G applied for an
    initial base load review order in 2008, and therefore, the additional costs were
    imprudent under the BLRA. In so arguing, they claim that the Commission erred
    by applying the prudence standard found in section 58-33-270(E) of the South
    Carolina Code, rather than the standard found in section 58-33-275(E). See 
    S.C. Code Ann. §§ 58-33-270
    (E), -275(E).
    The purpose of the BLRA "is to provide for the recovery of the prudently
    incurred costs associated with new base load plants . . . when constructed by
    investor-owned electrical utilities, while at the same time protecting customers of
    investor-owned electrical utilities from responsibility for imprudent financial
    obligations or costs." S.C. Energy Users Comm., 
    388 S.C. at
    494–95, 
    697 S.E.2d at
    592 (citing 
    S.C. Code Ann. § 58
    –33–210 (Supp. 2009) (Editor's Note)).
    Therefore, the objectives of the BLRA are:
    (1) to allow SCE&G to recover its "prudently incurred costs"
    associated with the nuclear facility; and (2) to protect customers "from
    responsibility for imprudent financial obligations or costs."
    
    Id.
    In an initial application for the approval of capital and construction costs
    pursuant to the BLRA, the Commission shall issue a base load review order
    approving rate recovery for capital costs if it determines, inter alia, that "the
    utility's decision to proceed with construction of the plant is prudent and
    reasonable considering the information available to the utility at the time." 
    S.C. Code Ann. § 58-33-270
    (A)(1). The Commission's order must establish:
    (1) the anticipated construction schedule for the plant including
    contingencies;
    (2) the anticipated components of capital costs and the anticipated
    schedule for incurring them, including specified contingencies;
    (3) the return on equity established in conformity with Section 58-33-
    220(16);
    (4) the choice of the specific type of unit or units and major
    components of the plant;
    (5) the qualification and selection of principal contractors and
    suppliers for construction of the plant; and
    (6) the inflation indices used by the utility for costs of plant
    construction, covering major cost components or groups of related
    cost components. Each utility shall provide its own indices, including:
    the source of the data for each index, if the source is external to the
    company, or the methodology for each index which is compiled from
    internal utility data, the method of computation of inflation from each
    index, a calculated overall weighted index for capital costs, and a five-
    year history of each index on an annual basis.
    
    Id.
     § 58-33-270(B)(1)–(6); see also Friends of the Earth v. Pub. Serv. Comm'n of
    S.C., 
    387 S.C. 360
    , 370, 
    692 S.E.2d 910
    , 915 (2010) (listing the necessary
    components of an initial base load review order).
    However,
    (E) As circumstances warrant, the utility may petition the
    commission, with notice to the [ORS], for an order modifying any of
    the schedules, estimates, findings, class allocation factors, rate
    designs, or conditions that form part of any base load review order
    issued under this section. The commission shall grant the relief
    requested if, after a hearing, the commission finds:
    (1) as to the changes in the schedules, estimates, findings,
    or conditions, that the evidence of record justifies a
    finding that the changes are not the result of imprudence
    on the part of the utility; and
    (2) as to the changes in the class allocation factors or rate
    designs, that the evidence of record indicates the
    proposed class allocation factors or rate designs are just
    and reasonable.
    
    S.C. Code Ann. § 58-33-270
    (E) (emphasis added).
    Appellants argue that the Commission erred in applying section 58-33-270
    to SCE&G's application. They argue that the proper legal standard in this case is
    found in section 58-33-275 of the BLRA, which provides:
    So long as the plant is constructed or being constructed in accordance
    with the approved schedules, estimates, and projections set forth in
    Section 58-33-270(B)(1) and 58-33-270(B)(2), as adjusted by the
    inflation indices set forth in Section 58-33-270(B)(5), the utility must
    be allowed to recover its capital costs related to the plant through
    revised rate filings or general rate proceedings.
    
    S.C. Code Ann. § 58-33-275
    (C). However,
    [i]n cases where a party proves by a preponderance of the evidence
    that there has been a material and adverse deviation from the
    approved schedules, estimates, and projections set forth in Section 58-
    33-270(B)(1) and 58-33-270(B)(2), as adjusted by the inflation
    indices set forth in Section 58-33-270(B)(5), the commission may
    disallow the additional capital costs that result from the deviation, but
    only to the extent that the failure by the utility to anticipate or avoid
    the deviation, or to minimize the resulting expense, was imprudent
    considering the information available at the time that the utility could
    have acted to avoid the deviation or minimize its effect.
    
    Id.
     § 58-33-275(E) (emphasis added).
    In South Carolina Energy Users Committee v. SCE&G, we found that the
    Commission abused its discretion in allowing SCE&G to recoup contingency costs
    in an initial base load review order. 
    388 S.C. at 491
    , 
    697 S.E.2d at 590
    . In so
    finding, we said:
    [T]he enactment of section 58-33-270(E) of the South Carolina Code .
    . . reveals that the General Assembly anticipated that construction
    costs could increase during the life of the project. Under section 58-
    33-270(E), SCE&G may petition the Commission for an order
    modifying rate designs.
    Id. at 496, 
    697 S.E.2d at
    592–93. This is exactly the course that SCE&G followed
    here.
    Thus, we find the BLRA contemplates changes to an initial base load review
    order and provides the mechanism to accomplish such changes in section 58-33-
    270, not section 58-33-275, as Appellants argue. Cf. Friends of the Earth, 
    387 S.C. at 369
    , 
    692 S.E.2d at
    914–15 (stating that "section 58-33-270(E) . . . provides
    that once a final order by the Commission has been issued, a 'utility may petition
    the [C]omission . . . for an order modifying any of the schedules, estimates,
    findings, class allocation factors, rate designs, or conditions that form part of any
    base load review order issued under this section,'" and that "[c]learly the General
    Assembly did not contemplate the Commission's ability to prevent subsequent
    modification of its orders under the [BLRA], as subsection (E) expressly provides
    the utility that right"). On the other hand, section 58-33-275(E) applies only after a
    utility has already deviated from an existing base load review order and attempts to
    recoup costs from the deviation. In that situation, a party must demonstrate by a
    preponderance of the evidence that the utility has deviated from the original base
    load review order, and then the utility may only recoup costs that were not the
    result of imprudence. Thus, the Commission correctly rejected Appellants' attempt
    to convert the modification proceeding into a deviation proceeding, and because
    SCE&G sought to update the existing base load review order, section 58-33-270
    plainly applied. See Hodges v. Rainey, 
    341 S.C. 79
    , 85, 
    533 S.E.2d 578
    , 581
    (2000) ("[I]t is not the court's place to change the meaning of a clear and
    unambiguous statute."); see also Sloan v. S.C. Bd. of Physical Therapy Exam'rs,
    
    370 S.C. 452
    , 468, 
    636 S.E.2d 598
    , 606 (2006) ("A statute as a whole must receive
    practical, reasonable, and fair interpretation consonant with the purpose, design,
    and policy of lawmakers.").5
    5
    The titles of the sections lend further support to SCE&G's and ORS's positions as
    section 58-33-270 is entitled "Base load review orders; contents; petitions for
    modification; settlement agreements between [ORS] and applicant," whereas,
    section 58-33-275 is entitled "Base load review order; parameter; challenges;
    recovery of capital costs." (Emphasis added). See Beaufort Cnty. v. S.C. State
    Election Comm'n, 
    395 S.C. 366
    , 373 n.2, 
    718 S.E.2d 432
    , 436 n.2 (2011) ("This
    Court may, of course, consider the title or caption of an act in determining the
    intent of the Legislature." (citation omitted)).
    Therefore, we find the Commission did not err in applying section 58-33-
    270 to SCE&G's application for an additional base load review order to update the
    capital costs and construction schedules contained in the original base load review
    order.
    II. Continued Construction
    Relying on section 58-33-280(K) of the BLRA, Appellants next argue that
    the Commission should have conducted a prudency evaluation of the entire
    construction project "going forward" at the time of the modification request. We
    disagree.
    Section 58-33-280(K) provides:
    Where a plant is abandoned after a base load review order approving
    rate recovery has been issued, the capital costs and AFUDC[6] related
    to the plant shall nonetheless be recoverable under this article
    provided that the utility shall bear the burden of proving by a
    preponderance of the evidence that the decision to abandon
    construction of the plant was prudent. Without limiting the effect of
    Section 58-33-275(A), recovery of capital costs and the utility's cost
    of capital associated with them may be disallowed only to the extent
    that the failure by the utility to anticipate or avoid the allegedly
    imprudent costs, or to minimize the magnitude of the costs, was
    imprudent considering the information available at the time that the
    utility could have acted to avoid or minimize the costs. The
    commission shall order the amortization and recovery through rates of
    the investment in the abandoned plant as part of an order adjusting
    rates under this article.
    The mere fact that the BLRA provides for a course of action in the event of
    the abandonment of a construction project has no relevance under these
    circumstances. In fact, the express language of the BLRA contradicts Appellants'
    6
    "AFUDC" is "the allowance for funds used during construction of a plant
    calculated according to regulatory accounting principles." 
    S.C. Code Ann. § 58-33
    -
    220(1) (Supp. 2013).
    contention. Section 58-33-275(A) provides:
    A base load review order shall constitute a final and binding
    determination that a plant is used and useful for utility purposes, and
    that its capital costs are prudent utility costs and expenses and are
    properly included in rates so long as the plant is constructed or is
    being constructed within the parameters of:
    (1) the approved construction schedule including contingencies;
    and
    (2) the approved capital costs estimates including specified
    contingencies.
    
    S.C. Code Ann. § 58-33-275
    (A). Moreover, "[d]eterminations under Section 58-
    33-275(A) may not be challenged or reopened in any subsequent proceeding,
    including proceedings under [s]ection 58-27-810 and other applicable provisions
    and [s]ection 58-33-280 and other applicable provisions of this article." 
    Id.
     § 58-
    33-275(B).
    Practically speaking, it would be nonsensical to include such a requirement
    at this stage. As the Commission aptly noted,
    [T]he BLRA was intended to cure a specific problem under the prior
    statutory and regulatory structure. Before adoption of the BLRA, a
    utility's decision to build a base load generating plant was subject to
    relitigation if parties brought prudency challenges after the utility had
    committed to major construction work on the plant. The possibility of
    prudency challenges while construction was underway increased the
    risks of these projects as well as the costs and difficulty of financing
    them. In response, the General Assembly sought to mitigate such
    uncertainty by providing for a comprehensive, fully litigated and
    binding prudency review before major construction of a base load
    generating facility begins. The BLRA order related to [the initial base
    load review order], is the result of such a process. It involved weeks
    of hearings, over 20 witnesses, a transcript that is more than a
    thousand pages long and rulings that have been the subject of two
    appeals to the South Carolina Supreme Court.
    The Commission found that the BLRA did not require it to reassess the
    prudency of the entire construction project at that base load order review stage, and
    we adopt its logic:
    Update proceedings are likely to be a routine part of administering
    BLRA projects going forward (including future projects proposed by
    other elective utilities), such that under the Sierra Club's argument, the
    prudence of the decision to build the plant will be open to repeated
    relitigation during the construction period if a utility seeks to preserve
    the benefits of the BLRA for its project. Reopening the initial
    prudency determinations each time a utility is required to make an
    update filing would create an outcome that the BLRA was intended to
    prevent and would defeat the principal legislative purpose in adopting
    the statute.[7]
    Therefore, we find Appellants' argument that the Commission should have
    conducted a prudency evaluation of the entire construction project at this
    modification stage unavailing.
    III. Sufficiency of the Evidence
    Next, Appellants argue that SCE&G failed to meet its burden to establish
    that the costs were prudent. We disagree.
    As pointed out in SCE&G's brief, Appellants do not argue that the decision
    is not supported by substantial evidence, but that the Commission should have
    7
    However, we agree with ORS that Appellants received the review they sought
    because the Commission addressed the prudency of the entire construction project
    anyway:
    In any event, although not required by the terms of the BLRA, the
    record in this proceeding has provided the Commission with the
    sufficient evidence on which to examine and evaluate the positions of
    SCE&G and the Sierra Club on the factual issue of whether
    continuing with the construction of the Units is prudent and whether
    the additional costs and schedule changes are prudent. Based on the
    evidence of the record before us, the Commission concludes that the
    construction of the Units should continue and that the additional costs
    and schedule changes are not the result of imprudence on the part of
    SCE&G . . . .
    decided the modification application differently.
    We agree that Appellants failed to demonstrate that the factual findings are
    unsupported by reliable, probative, and substantial evidence in the record. See
    Waters v. S.C. Land Res. Conservation Comm'n, 
    321 S.C. 219
    , 226, 
    467 S.E.2d 913
    , 917 (1996) ("Substantial evidence is not a mere scintilla of evidence nor
    evidence viewed blindly from one side, but is evidence which, when considering
    the record as a whole, would allow reasonable minds to reach the conclusion that
    the agency reached. The possibility of drawing two inconsistent conclusions from
    the evidence will not mean the agency's conclusion was unsupported by substantial
    evidence. Furthermore, the burden is on appellants to prove convincingly that the
    agency's decision is unsupported by the evidence." (internal citations and quotation
    marks omitted)). To the contrary, the Commission parsed all of the evidence
    presented during the hearing and provided a detailed summary of all of the
    testimony on which it based its very technical findings. Thus, there is no doubt
    that the Commission's findings are supported by substantial evidence in the
    Record. Therefore, we find that this issue lacks merit.
    CONCLUSION
    For the foregoing reasons, we affirm the Commission's orders.
    PLEICONES, BEATTY, KITTREDGE and HEARN, JJ., concur.