Smith v. Spratt Machine Co. , 46 S.C. 511 ( 1896 )


Menu:
  • The opinion of the Court was delivered by

    Mr. Chief Justice McIver.

    The plaintiff brought this action to recover the amounts mentioned in two bills of exchange drawn by the “Tugaloo Iron Works” on the defendant company, in favor of the plaintiff and accepted by said company. By the terms of these bills of exchange the amounts mentioned were to be paid out of the money due the drawer by the acceptor, when the same became payable. The only defense which it is necessarjr to notice, under this appeal, was that no money ever became due the Tugaloo Iron Works by the Spratt Machine Company. It is a conceded fact that the Tugaloo Iron Works entered into a contract with the Spratt Machine Company to furnish certain iron work to be used by the defendant company in the construction of the court house at Yorkville. No time was specified in such contract for the completion of the same; but the defendant claimed that, as a matter of law, the contract should have been completed within a reasonable lime, and that, as a matter of fact, it was not completed within a reasonable time. It is admitted by counsel that: “At the hearing, testimony was introduced by the plaintiff tending to show the size of the plant of the Tugaloo Iron Works, and the number of operatives engaged at the time the said Tugaloo Iron Works were at work -upon the order of the *513Spratt Machine Company, and at the time the contract was awarded. Testimony was also introduced to show in what time, with the facilities on hand, the Tugaloo Iron Works could have completed the contract. Testimony was also introduced hy the Spratt Machine Company, defendant, tending to show that the said Spratt Machine Company was not aware of the size of the plant of the TugalooJron Works at the time the order was given by the Spratt Machine Company to the Tugaloo Iron Works; and that the Tugaloo Iron Works’ plant was a small and insignificant one, and, from the size of the plant and lack of facilities, they were unable to ever carry out the contract.”

    Under the charge of his Honor, Judge Aldrich, the jury found a verdict in favor of the. defendant, and judgment having been entered thereon, plaintiff appeals upon the several grounds set out in the record; all of which have been waived except the third, which reads as follows: “For not charging the jury, as requested by plaintiff in his eighth request to charge, the following: ‘No time having been specified in the contract between Spratt Machine Company and Tugaloo Iron Works, in which the contract was to be completed, the law fixes a reasonable time — that is, such time in which parties, similarly circumstanced as the Tugaloo Iron Works, could have completed the contract;’ and further erred in charging the jury as follows: ‘That in the main is correct; but I can not charge you that it means that a reasonable time is that in which a company, similarly circumstanced as the Tugaloo Iron Works were, could perform that contract. I charge you this: that the reasonable time in which to complete that contract, was a time in which a corporation or individuals engaged in furnishing these iron materials would have furnished them. That is a reasonable time.’ ”

    So that the only question presented by this appeal is, whether the Circuit Judge erred in instructing the jury as to- the test of what would be a reasonable time for the performance of this contract. It seems to us that in determin*514ing what would be a reasonable time for the performance of a given contract, regard should be had to the situation and circumstances of the parties; for a time which would be reasonable in one case would not be in another. Take this case as an illustration — if the defendant had entered into a similar contract with one of the largest and best equipped iron foundries in the country, the defendant might reasonably have expected that the contract could and would be performed in much less time than if entered into with a much smaller concern, not so well equipped. The defendant was under no obligation to let this contract to the Tugaloo Iron Works, which is represented to be a small concern, not. provided with such means and appliances as would enable it to complete the work required by the contract in as short a time as would be required by an iron foundry better supplied with means and appliances; and if the defendant chose to give the contract to the Tugaloo Iron Works, and omitted to specify any time for its performance, as it might have done, we do not see how the defendant could reasonably expect that the contract should be performed in a less time than it would be reasonable to expect that a concern similarly circumstanced, as the Tugaloo Iron Works were, would be able to complete the work called for by the contract. It seems to us that the true rule upon this subject is, that when two parties enter into a contract in the absence of any stipulations to the contrary, it must be assumed that the}r contracted in view of, and with reference to, the situations and surroundings; and to apply this rule to the present case, when the defendant entered into this contract with the Tugaloo Iron Works, and omitted to specify any time for the performance of the contract, it could not have been reasonably expected that the contract should be performed in a less time than would be reasonably required by a concern situated as the Tugaloo Iron Works were. If the defendant desired to avail itself of the testimony which it offered as above set forth, to the effect that the Tugaloo Iron Works, from the size of its plant and *515its lack of facilities, never could have completed the contract, it must be remembered that such testimony was in conflict with that offered by the plaintiff, tending to show within what time, with the facilities at hand, the Tugaloo Iron Works could have completed the contract; and hence, to render that testimony available, the defendant should have requested the Circuit Judge to instruct the jury, that if they believed, from the testimony, that the Tugaloo Iron Works never could have completed the contráct, then they should find for the defendant; for, if that was so, then, of course, the contract was not performed within a reasonable time, because it could not have been performed at all. But no such request was submitted, and this Court has no means of ascertaining what the jury believed as to this point. It seems to us that the Circuit Judge erred in furnishing the jury with an erroneous test, by which they were to determine what was a reasonable time for the performance of the contract in this case.

    The judgment of this Court is, that the judgment of the Circuit Court be reversed, and that the case be remanded to that Court for a new trial. ■

Document Info

Citation Numbers: 46 S.C. 511

Judges: McIver, Pope

Filed Date: 4/4/1896

Precedential Status: Precedential

Modified Date: 7/20/2022