The Spriggs Group v. Slivka ( 2013 )


Menu:
  • THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE
    CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING
    EXCEPT AS PROVIDED BY RULE 268(d)(2), SCACR.
    THE STATE OF SOUTH CAROLINA
    In The Court of Appeals
    The Spriggs Group, P.C., Respondent,
    v.
    Gene R. Slivka, Appellant.
    Appellate Case No. 2011-204366
    Appeal From Colleton County
    William H. Seals, Jr., Circuit Court Judge
    Unpublished Opinion No. 2013-UP-497
    Heard January 10, 2013 – Filed February 6, 2013
    AFFIRMED IN PART, REVERSED IN PART, AND
    REMANDED
    Robert T. Lyles, Jr., of Lyles & Lyles, LLC, of
    Charleston, for Appellant.
    A. Bright Ariail and James Atkinson Bruorton, IV, both
    of Rosen Rosen & Hagood, LLC, of Charleston, for
    Respondent.
    LOCKEMY, J.: In this action for foreclosure of a mechanic's lien and breach of
    contract, Gene Slivka argues the circuit court erred in (1) submitting a question
    involving the interpretation of section 29-5-10(a) of the South Carolina Code
    (2007) to the jury; (2) failing to direct a verdict; and (3) awarding The Spriggs
    Group, P.C. (Spriggs) attorney's fees, costs, and interest. We affirm in part,
    reverse in part, and remand.
    FACTS/PROCEDURAL BACKGROUND
    This case arises from a dispute between Slivka and Spriggs regarding Spriggs'
    provision of architectural services for Slivka's home. Spriggs designed all of the
    buildings on Slivka's Colleton County plantation (the property), including the main
    house, two detached garages with apartments, potting shed, conservatory, stable,
    and grotto. Pursuant to a November 17, 2006 written proposal (the Agreement),
    Spriggs was to receive a fixed fee of $161,500 for its architectural and engineering
    design services, and hourly fees for any additional services. The fixed fee was
    subsequently reduced to $152,402. Slivka paid half of the fee at the start of the
    design process and agreed to pay the remainder upon completion of the project.
    According to Slivka, he terminated Spriggs on December 12, 2008. Slivka
    contends he picked up the remaining drawings from Spriggs' office and told
    Spriggs he did not want any more drawings. Spriggs, however, continued to
    perform its services under the Agreement. According to Ken Spriggs, principal of
    Spriggs, he was unaware Slivka had allegedly terminated Spriggs. In February
    2009, Spriggs submitted four invoices totaling $198,834.53 to Slivka for payment
    in accordance with the terms of the Agreement. Slivka admitted he owed Spriggs
    $76,201, the balance of the Agreement price, but disputed the additional charges
    and refused to pay Spriggs. Spriggs provided services to Slivka pursuant to the
    Agreement through May 2009.
    As a result of Slivka's failure to pay Spriggs in accordance with the terms of the
    Agreement, Spriggs filed a mechanic's lien against the property on April 13, 2009.
    Slivka continued to refuse to pay Spriggs and posted a $265,112.71 cash bond to
    remove the lien from the property. Thereafter, on July 8, 2009, Spriggs
    commenced a foreclosure action on the lien. In an amended complaint filed in
    May 2010, Spriggs asserted claims for foreclosure of mechanic's lien, breach of
    contract, breach of contract accompanied by a fraudulent act, quantum meruit, and
    failure to comply with section 27-1-15 of the South Carolina Code (2007). Slivka
    counterclaimed for slander of title, violation of the Frivolous Claims Sanctions
    Act, tortious interference with contractual relationships with third parties
    dependent upon performance by Spriggs, and tortious interference with contractual
    relationships with third parties resulting from defective notice of mechanic's lien.
    On June 30, 2011, Slivka offered to settle the case for $100,000, but Spriggs did
    not accept the offer. Prior to trial, Spriggs filed a motion to strike Slivka's
    affirmative defenses and counterclaims. Thereafter, Slivka filed a motion for
    summary judgment as to all of Spriggs' causes of action. Spriggs countered with
    its own motion for summary judgment. At the motions hearing, Slivka agreed to
    withdraw certain counterclaims, and the circuit court denied both motions for
    summary judgment.
    The parties proceeded to trial on all of Spriggs' causes of action and on Slivka's
    counterclaims for slander of title, tortious interference with contractual
    relationships with third parties dependent upon performance by Spriggs, and
    tortious interference with contractual relationships with third parties resulting from
    defective notice of mechanic's lien. At trial, Spriggs asserted the additional
    charges in its invoices were a result of Slivka's demands and changes, and they
    were billed pursuant to the Agreement. Slivka maintained the additional charges
    were not contemplated when the Agreement was made and Spriggs had a duty to
    advise him before performing and charging for additional work.
    At the conclusion of Spriggs' case, the circuit court denied Slivka's directed verdict
    motions as to Spriggs' causes of action for foreclosure of mechanic's lien, breach of
    contract, and failure to comply with section 27-1-15. The circuit court also denied
    Spriggs' motion for a directed verdict as to the section 27-1-15 claim. Spriggs
    withdrew its claims for breach of contract accompanied by a fraudulent act and
    quantum meruit. Following Slivka's case, the circuit court denied Spriggs' motion
    for a directed verdict as to Slivka's slander of title claim. Slivka also renewed his
    directed verdict motions as to Spriggs' causes of action for foreclosure of
    mechanic's lien and failure to comply with section 27-1-15. The circuit court ruled
    both causes of action would be submitted to the jury.
    Spriggs' foreclosure of mechanic's lien, breach of contract, and failure to comply
    with section 27-1-15 claims were submitted to the jury, along with Slivka's slander
    of title claim.1 Following deliberations, the jury returned a verdict in favor of
    Spriggs on all three of its causes of action and on Slivka's slander of title cause of
    action. The jury awarded Spriggs $173,990.53 in actual damages. Slivka made a
    post-trial motion seeking a judgment notwithstanding the verdict (JNOV) and/or a
    new trial on Spriggs' foreclosure of mechanic's lien and failure to comply with
    1
    Slivka withdrew both of his tortious interference with contractual relationships
    claims.
    section 27-1-15 claims.2 The circuit court denied Slivka's JNOV motion and his
    subsequent Rule 59(e), SCRCP, motion to alter or amend. Spriggs made a post-
    trial motion seeking attorney's fees, costs, and interest. The circuit court granted
    the motion and awarded Spriggs $235,030.31 in attorney's fees and costs and
    $37,413.92 in prejudgment interest. Thereafter, the circuit court denied Slivka's
    Rule 59(e) motion to alter or amend. This appeal followed.
    LAW/ANALYSIS
    I.       Statutory Interpretation
    Slivka argues the circuit court erred in submitting the question of whether the
    services provided by Spriggs in January 2009 fell within the definition of "labor"
    contained in section 29-5-10(a) of the South Carolina Code (2007) to the jury. We
    agree but find no reversible error.
    Pursuant to section 29-5-90 of the South Carolina Code (2007), a mechanic's lien
    shall be dissolved unless the person desiring to avail
    himself thereof, within ninety days after he ceases to
    labor on or furnish labor or materials for such building or
    structure, serves upon the owner . . . a statement of a just
    and true account of the amount due him, with all just
    credits given, together with a description of the property
    intended to be covered by the lien. . . .
    Section 29-5-10(a) states:
    [L]abor performed or furnished in the erection, alteration,
    or repair of any building or structure upon any real estate
    includes the preparation of plans, specifications, and
    design drawings and the work of making the real estate
    suitable as a site for the building or structure. The work is
    considered to include, but not be limited to, the grading,
    bulldozing, leveling, excavating, and filling of land
    (including the furnishing of fill soil), the grading and
    paving of curbs and sidewalks and all asphalt paving, the
    construction of ditches and other drainage facilities, and
    2
    Slivka did not appeal the jury's verdict on Spriggs' breach of contract claim.
    the laying of pipes and conduits for water, gas, electric,
    sewage, and drainage purposes, and the disposal of any
    construction and demolition debris, as defined in Section
    44-96-40(6), including final disposal by a construction
    and demolition landfill. Any private security guard
    services provided by any person at the site of the building
    or structure during its erection, alteration, or repair is
    considered to be labor performed or furnished within the
    meaning of this section. . . .
    For its lien to be timely, Spriggs must have performed labor, within the definition
    contained in section 29-5-10(a), on or after January 13, 2009. According to Andy
    Bozeman, a Spriggs employee, Spriggs addressed a plumbing subcontractor's
    request to substitute the size of plumbing lines used on the project on January 13,
    2009. Bozeman also communicated with a mechanical engineer and answered
    questions regarding the plumbing line substitution.
    At trial, Slivka argued that while the timeliness of the lien was a question of fact
    for the jury to decide, whether the construction administration services performed
    by Spriggs on January 13, 2009, fell within the statutory definition of labor was a
    question of statutory interpretation for the court. In response, Spriggs argued the
    question before the jury was one of timeliness, and the services it provided on
    January 13, 2009, were clearly within the definition of labor. The circuit court
    decided,
    as to the mechanic's lien itself, I'm just going to submit it
    to the jury. I'm going to read them the statute. I'm going
    to give them the charge . . . . It's kind of long and
    redundant but y'all can argue whether that is service that
    falls within the mechanic's lien statute. And of course
    you can argue the timeliness and all of that kind of stuff.
    Slivka contends the question of whether Spriggs' work fell within the purview of
    the mechanic's lien statute was erroneously submitted to the jury. Spriggs
    maintains the jury was properly instructed to determine whether its lien was valid
    and timely. Spriggs also notes the circuit court ruled post-trial it was "implausible
    that construction administration services would be excluded from the description
    of labor performed or furnished in the erection, alteration, or repair of any
    building."
    We find the circuit court erred in submitting the question of whether Spriggs' work
    fell within the purview of the mechanic's lien statute to the jury. See Catawba
    Indian Tribe of S.C. v. State, 
    372 S.C. 519
    , 524, 
    642 S.E.2d 751
    , 753 (2007)
    (holding the issue of interpretation of a statute is a question of law for the court).
    However, this error was harmless because, as discussed below, we find the
    construction administration services proved by Spriggs fell within the definition of
    labor contained in 29-5-10(a).
    II.   Timeliness of the Lien
    Slivka argues the circuit court erred in denying his motion for directed verdict
    because Spriggs' lien was not timely. We disagree.
    "When reviewing the denial of a motion for directed verdict or JNOV, this Court
    must employ the same standard as the [circuit] court by viewing the evidence and
    all reasonable inferences in the light most favorable to the nonmoving party."
    Welch v. Epstein, 
    342 S.C. 279
    , 299, 
    536 S.E.2d 408
    , 418 (Ct. App. 2000). "The
    [circuit] court must deny the motions when the evidence yields more than one
    inference or its inference is in doubt." Id. at 300, 536 S.E.2d at 418. "This Court
    will reverse the [circuit] court only when there is no evidence to support the ruling
    below." Id. "When considering directed verdict and JNOV motions, neither the
    [circuit] court nor the appellate court has authority to decide credibility issues or to
    resolve conflicts in the testimony or evidence." Id. at 300, 536 S.E.2d at 419.
    First, Slivka contends the work performed by Spriggs on January 13, 2009, does
    not fall within the definition of labor contained in section 29-5-10(a) because none
    of Spriggs' work involved "the preparation of plans, specifications, and design
    drawings." Slivka maintains none of the work performed by Bozeman occurred on
    site, and the work only amounted to construction administration services. Slivka
    argues the circuit court erred in relying on Williamson v. Hotel Melrose, 
    110 S.C. 1
    , 
    96 S.E. 407
     (1918), in finding construction administration services are a type of
    labor for which a mechanic's lien may be filed under the mechanic's lien statute. In
    Williamson, our supreme court determined an architect who furnished plans and
    specifications and "superintended" the construction of a project had performed
    labor within the meaning of the mechanic's lien statute. 
    110 S.C. at 1
    , 
    96 S.E. at 411
    . At the time, the mechanic's lien statute did not include the definition of labor
    contained in the current statute. The statute at the time afforded a lien to "any
    person to whom a debt is due for labor performed or furnished." 
    Id.
    Slivka maintains Williamson is not applicable because the current version of the
    mechanic's lien statute, section 29-5-10(a), contains specific activities determined
    by the legislature to be "labor" and does not include construction administration
    services. Slivka argues the legislature could have included off-site construction
    administration services of a design professional in its definition of labor but it
    chose not to. Furthermore, Slivka maintains Spriggs was not on-site directing the
    work on the property like the architect in Williamson. Ken Spriggs testified he was
    not directing any work or supervising the construction.
    We find the construction administration services provided by Spriggs are labor
    pursuant to the definition of labor in section 29-5-10(a). While the statute provides
    labor "includes the preparation of plans, specifications, and design drawings," it
    also states labor includes "the work of making the real estate suitable as a site for
    the building or structure." Here, Spriggs' discussions with the plumber and
    engineer in January 2009 were part of its architectural services overseeing the
    proper construction of the property.
    Slivka also contends the circuit court erred in finding work performed by Spriggs
    in May 2009 supported the timeliness of the lien filed on April 13, 2009. At trial,
    Bozeman testified he provided design sketches for an appraisal of the property in
    May 2009. Slivka argues this work could not support the timeliness of Spriggs'
    lien because it was allegedly performed after the lien was filed. We find the circuit
    court did not err because the court's order does not explicitly say, as alleged by
    Slivka, that the May 2009 services were performed within ninety days of April 13,
    2009. While the circuit court order mentions the May 2009 services, it notes these
    services were performed after the lien was filed. The court also specifically notes
    the lien was filed within ninety days of January 13, 2009. Accordingly, we affirm
    the circuit court's denial of Slivka's motion for a directed verdict on Spriggs'
    mechanic's lien claim.
    III.   Attorney's Fees, Costs, and Interest
    "A party cannot recover attorney's fees unless authorized by contract or statute."
    Cullen v. McNeal, 
    390 S.C. 470
    , 491, 
    702 S.E.2d 378
    , 389 (Ct. App. 2010). Here,
    sections 27-1-5 and 29-5-10 of the South Carolina Code (2007) both authorize an
    award of attorney's fees to Spriggs. Pursuant to section 27-1-15,
    [w]henever a contractor, laborer, design professional, or
    materials supplier has expended labor, services, or
    materials under contract for the improvement of real
    property, and where due and just demand has been made
    by certified or registered mail for payment for the labor,
    services, or materials under the terms of any regulation,
    undertaking, or statute, it is the duty of the person upon
    whom the claim is made to make a reasonable and fair
    investigation of the merits of the claim and to pay it, or
    whatever portion of it is determined as valid, within
    forty-five days from the date of mailing the demand. If
    the person fails to make a fair investigation or otherwise
    unreasonably refuses to pay the claim or proper portion,
    he is liable for reasonable attorney's fees and interest at
    the judgment rate from the date of the demand.
    Additionally, pursuant to section 29-5-10(a), "[t]he costs which may arise in
    enforcing or defending against the lien. . . , including a reasonable attorney's fee,
    may be recovered by the prevailing party." "The fee must be determined by the
    court in which the action is brought but the fee and court costs may not exceed the
    amount of the lien." 
    Id.
    The following six factors should be considered when determining reasonable
    attorney's fees: "(1) the nature, extent, and difficulty of the case; (2) the time
    necessarily devoted to the case; (3) professional standing of counsel; (4)
    contingency of compensation; (5) beneficial results obtained; and (6) customary
    legal fees for similar services." Jackson v. Speed, 
    326 S.C. 289
    , 308, 
    486 S.E.2d 750
    , 760 (1997). "The decision to award or deny attorneys' fees under a state
    statute will not be disturbed on appeal absent an abuse of discretion." Kiriakides v.
    Sch. Dist. of Greenville Cnty., 
    382 S.C. 8
    , 20, 
    675 S.E.2d 439
    , 445 (2009). "An
    abuse of discretion occurs when the conclusions of the [circuit] court are either
    controlled by an error of law or are based on unsupported factual conclusions." 
    Id.
    "Similarly, the specific amount of attorneys' fees awarded pursuant to a statute
    authorizing reasonable attorneys' fees is left to the discretion of the trial judge and
    will not be disturbed absent an abuse of discretion." 
    Id.
    A.    Section 27-1-15
    Slivka argues the circuit court erred in denying his motion for a directed verdict on
    Spriggs' failure to comply with the section 27-1-15 claim. We disagree.
    Slivka contends Spriggs failed to present any evidence Slivka did not perform a
    fair and reasonable investigation because at the time Spriggs made its demand
    under the statute the parties were involved in litigation initiated by Spriggs. We
    find whether a fair and reasonable investigation of Spriggs' claim has been made
    and whether a valid portion of the claim was paid in a timely manner are questions
    of fact for the jury. See Hardaway Concrete Co., Inc. v. Hall Contracting Corp.,
    
    374 S.C. 216
    , 229, 
    647 S.E.2d 488
    , 495 (Ct. App. 2007) (holding whether a party
    made a fair and reasonable investigation of the merits of a claim is a question of
    fact).
    Additionally, Slivka argues at the time the demand was made it was impossible to
    determine the "valid" amount due because of the parties' pending claims against
    each other for damages. Finally, Slivka maintains his failure to make a payment at
    the time of the demand was not unreasonable because he had already paid the court
    a cash bond exceeding the amount of Spriggs' claim. Slivka fails to cite any legal
    precedent to support these arguments. Accordingly, we find these arguments are
    abandoned on appeal. See Bennett v. Investors Title Ins. Co., 
    370 S.C. 578
    , 599,
    
    635 S.E.2d 649
    , 660 (Ct. App. 2006) (noting when an appellant fails to cite any
    supporting authority for his position and makes conclusory arguments, the
    appellant abandons the issue on appeal).
    B.    Amount of Attorney's Fees and Costs
    Slivka argues the circuit court erred in awarding Spriggs $235,030.31 in attorney's
    fees and costs. We agree.
    The circuit court determined Spriggs was entitled to $235,030.31 in attorney's fees
    and costs pursuant to sections 29-5-10 and 27-1-15. The court further found the
    fees and costs awarded were reasonable based upon the six criteria established by
    the supreme court. The circuit court noted, "[Spriggs] was required to expend
    considerably more time and effort on this case due to specific actions of [Slivka]
    who created unnecessary delays, filed meritless motions, and forced [Spriggs] to
    incur additional attorney's fees and costs above and beyond what would otherwise
    have been incurred."
    First, Slivka argues Spriggs was not entitled to recover $28,619.25 in staff member
    fees as part of its attorney's fees award. We find the circuit court did not abuse its
    discretion in including staff member fees in its award of attorney's fees. We note
    Slivka fails to cite any legal precedent to support this argument. Additionally, this
    court has upheld attorney's fees awards which included paralegal fees. See
    McElveen v. McElveen, 
    332 S.C. 583
    , 602, 
    506 S.E.2d 1
    , 11 (Ct. App. 1998);
    Charleston Lumber Co. v. Miller Housing Corp., 
    318 S.C. 471
    , 484, 
    458 S.E.2d 431
    , 439 (Ct. App. 1995).
    Next, Slivka contends Spriggs' total recovery is limited to the amount of the cash
    bond he posted with the clerk of court. Slivka argues that pursuant to section 29-5-
    110 of the South Carolina Code (2007), the total payment to Spriggs is limited to
    $266,012.71, the amount of the cash bond he paid to the clerk of court. Therefore,
    Slivka maintains because Spriggs' verdict was $173,990.53, any award of
    attorney's fees under the mechanic's lien statute is limited to a maximum of
    $92,022.18. We disagree. Section 29-5-110 relates to the amount of the judgment
    and makes no mention of attorney's fees. Attorney's fees are specifically addressed
    in section 29-5-10, which provides that the costs and fees incurred in enforcing or
    defending against the lien may be recoverable by the prevailing party up to the
    amount of the lien. See § 29-5-10(a).
    Finally, Slivka argues the attorney's fees awarded by the circuit court are not
    reasonable and the circuit court order fails to specify which fees were awarded
    pursuant to which statute. Although the amount of attorney's fees awarded in this
    case, compared to the jury award, may not shock the conscience of this court, the
    needle is definitely moving on the seismograph. The circuit court order is unclear
    as to which fees were awarded under which statutory authority. We note the
    court's award exceeds the amount permitted under the mechanic's lien statute.
    Further, although theoretically possible, it is improbable an attorney's fee of almost
    $250,000 would be awarded for a net recovery of approximately $75,000 above the
    $100,000 settlement offered by Slivka under section 27-1-15. The circuit court
    may have combined the two statutes to reach the figure, although the legality of
    that procedure is not addressed in this decision. Moreover, the trial court surely
    did not award fees for the two causes of action it dismissed or for the breach of
    contract claim. Thus, because we find the circuit court's order is unclear, we
    reverse the court's award of $235,030.31 in attorney's fees to Spriggs and remand
    the issue of attorney's fees to the circuit court for reconsideration. We order the
    circuit court to clearly identify the statutory authority for its award and the fees
    incurred under each statute.
    C.    Prejudgment Interest
    Slivka argues the circuit court's award of $37,413.92 in prejudgment interest to
    Spriggs was not supported by statute. We disagree.
    The law permits the award of prejudgment interest when a monetary obligation is a
    sum certain, or is capable of being reduced to certainty, accruing from the time
    payment may be demanded either by the agreement of the parties or the operation
    of law. Butler Contr., Inc. v. Court St., LLC, 
    369 S.C. 121
    , 133, 
    631 S.E.2d 252
    ,
    258 (2006). Generally, prejudgment interest may not be recovered on an
    unliquidated claim in the absence of agreement or statute. 
    Id.
     The fact that the
    amount due is disputed does not render the claim unliquidated for purposes of
    awarding prejudgment interest. 
    Id.
     Rather, the proper test is "whether or not the
    measure of recovery, not necessarily the amount of damages, is fixed by conditions
    existing at the time the claim arose." 
    Id.
     "The award of prejudgment interest will
    not be disturbed on appeal unless the [circuit] court committed an abuse of
    discretion." Historic Charleston Holdings, LLC v. Mallon, 
    381 S.C. 417
    , 435, 
    673 S.E.2d 448
    , 457-58 (2009).
    We find the circuit court did not err in awarding Spriggs prejudgment interest. We
    note the court's award of prejudgment interest was not limited to Spriggs' cause of
    action for failure to comply with section 27-1-15. The court also awarded interest
    on Spriggs' breach of contract claim, which was not appealed and is the law of the
    case. Accordingly, we affirm the circuit court's award of prejudgment interest.
    CONCLUSION
    We find the construction administration services provided by Spriggs fell within
    the definition of labor contained in section 29-5-10(a). Additionally, we affirm the
    circuit court's award of prejudgment interest and denial of Slivka's directed verdict
    motions as to Spriggs' section 27-1-15 and mechanic's lien claims. We reverse the
    circuit court's award of attorney's fees and remand for reconsideration.
    AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.
    SHORT and KONDUROS, JJ., concur.
    

Document Info

Docket Number: 2013-UP-497

Filed Date: 2/6/2013

Precedential Status: Non-Precedential

Modified Date: 10/22/2024