Moats Construction v. Sanders ( 2016 )


Menu:
  • THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE
    CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING
    EXCEPT AS PROVIDED BY RULE 268(d)(2), SCACR.
    THE STATE OF SOUTH CAROLINA
    In The Court of Appeals
    Moats Construction Services, LLC, Appellant,
    v.
    Bobby D. Sanders, Jr.; Staci Y. Sanders; Premier
    Southern Homes, LLC; Elite Mechanical Services, Inc.;
    Level Construction, LLC; Love Heating & Air, LLC;
    Solid Rock Construction Services, LLC; All Carolina
    Exteriors, LLC; American Concrete and Precast, Inc.;
    and Harbin Lumber Co., Inc., Defendants,
    Of whom Bobby Sanders is the Respondent.
    Bobby Sanders, Jr., and Staci Y. Sanders, Third Party
    Plaintiffs,
    Of whom Bobby Sanders, Jr., is the Respondent,
    v.
    Henry Beal, Third Party Defendant.
    Appellate Case No. 2013-002176
    Appeal From Anderson County
    Alexander S. Macaulay, Circuit Court Judge
    Unpublished Opinion No. 2016-UP-046
    Heard September 9, 2015 – Filed January 27, 2016
    AFFIRMED
    Ronald G. Tate, Jr., and Robert Batten Farrar, of
    Gallivan, White & Boyd, PA, of Greenville, for
    Appellant.
    Donald Ryan McCabe, Jr., and Stephanie Carol Trotter,
    of McCabe, Trotter & Beverly, P.C., of Columbia, for
    Respondent.
    PER CURIAM: Moats Construction Services (Moats) appeals the trial court's
    denial of its mechanic's lien action against Bobby Sanders. We affirm.
    1. We disagree with Moats' argument that the trial court erred in holding Moats failed
    to establish a valid mechanic's lien under section 29-5-10 of the South Carolina
    Code (2007). See Ferguson Fire & Fabrication, Inc. v. Preferred Fire Prot.,
    L.L.C., 
    409 S.C. 331
    , 340, 
    762 S.E.2d 561
    , 566 (2014) (providing under section
    29-5-10 liens are created when direct contractual relationship exists with the
    owner); § 29-5-10 (providing consent by the owner is a requirement to a lien
    placed by a laborer); Guignard Brick Works v. Gantt, 
    251 S.C. 29
    , 32, 
    159 S.E.2d 850
    , 851 (1968) (holding the word consent "implies something more than mere
    acquiescence in a state of things already in existence. It implies an agreement to
    that which, but for the consent, could not exist, and in which the party consenting
    has a right to forbid"); Ringer v. Graham, 
    286 S.C. 14
    , 17 n.2, 
    331 S.E.2d 373
    , 375
    n.2 (Ct. App. 1985) ("Code Section 29-5-10 gives a mechanic's lien to persons who
    by agreement or with the consent of the owner perform labor upon or furnish
    materials in the erection of a structure."). We find the trial court's determination
    that Moats failed to establish a direct contractual relationship with Sanders
    supported its holding there was no valid mechanic's lien established by Moats
    under section 29-5-10.
    2. We disagree with Moats' argument that the trial court erred in applying improper
    offsets against the amount Sanders owed. See Action Concrete Contractors, Inc. v.
    Chappelear, 
    404 S.C. 312
    , 319, 
    745 S.E.2d 77
    , 80 (2013) ("Where a general
    contractor abandons the job before work is complete . . ., the owner is entitled to
    credit for damages, if any, incurred by the owner to finish the general contractor's
    work. . . . [T]he owner may be entitled to offset moneys spent to repair that work
    against the lienholder's recovery."); 
    S.C. Code Ann. § 29-5-40
     (2007) (stating "in
    no event shall the aggregate amount of liens set up hereby exceed the amount due
    by the owner on the contract price of the improvement made"). We find the trial
    court was correct in applying offsets against the remaining escrowed construction
    funds and denying Moats' mechanic's lien.
    3. We disagree with Moats' argument that the trial court erred in failing to hold Moats
    had a valid mechanic's lien under section 29-5-20(A). Even though Moats did not
    meet the notice requirements under section 29-5-20(B), Moats may have met the
    notice requirements under section 29-5-40. The lien, however, failed on other
    grounds because the amount of liens exceeded the amount the owner owed on the
    contract price. See Taylor, Cotton & Ridley, Inc. v. Okatie Hotel Grp., LLC, 
    372 S.C. 89
    , 96, 
    641 S.E.2d 459
    , 462 (Ct. App. 2007) ("The main purposes of sections
    29-5-20 and 29-5-40 are (1) the protection through a lien of a party, who furnished
    labor or material but was not a party to a contract with the owner and (2) the
    protection of the owner by preventing his liability on the liens from exceeding the
    amount owner owes on the contract price."); Stoudenmire Heating & Air
    Conditioning Co. v. Craig Bldg. P'ship, 
    308 S.C. 298
    , 302, 
    417 S.E.2d 634
    , 637
    (Ct. App. 1992) (stating a letter to the owner and contractor provided sufficient
    written notice to the owner to meet the requirements of section 29-5-40); § 29-5-40
    (requiring notice to the owner of the furnishing of labor).
    4. In light of our previous findings, we decline to address whether Sanders was
    unjustly enriched in this case. See Futch v. McAllister Towing of Georgetown,
    Inc., 
    335 S.C. 598
    , 613, 
    518 S.E.2d 591
    , 598 (1999) (holding an appellate court
    need not address remaining issues on appeal when its determination of a prior issue
    is dispositive).
    AFFIRMED.
    HUFF, WILLIAMS, and THOMAS, JJ., concur.
    

Document Info

Docket Number: 2016-UP-046

Filed Date: 1/27/2016

Precedential Status: Non-Precedential

Modified Date: 10/22/2024