In the Matter of Joint Application of Duke Energy Carolinas, LLC ( 2016 )


Menu:
  • THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE
    CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING
    EXCEPT AS PROVIDED BY RULE 268(d)(2), SCACR.
    THE STATE OF SOUTH CAROLINA
    In The Court of Appeals
    In the Matter of Joint Application of Duke Energy
    Carolinas, LLC and North Carolina Electric Membership
    Corporation for a Certificate of Environmental
    Compatibility and Public Convenience and Necessity for
    the Construction and Operation of a 750MW Combined
    Generating Plant Near Anderson, SC.
    Appellate Case No. 2014-001514
    Appeal from the Public Service Commission
    Unpublished Opinion No. 2016-UP-054
    Heard January 14, 2016 – Filed February 10, 2016
    AFFIRMED
    James Blanding Holman, IV and Christopher Kaltman
    DeScherer, Southern Environmental Law Center, both of
    Charleston, and Gudrun E. Thompson, Southern
    Environmental Law Center, of Chapel Hill, North
    Carolina, for Appellants South Carolina Coastal
    Conservation League and Southern Alliance for Clean
    Energy.
    Frank Rogers Ellerbe, III, Robinson McFadden & Moore,
    PC, of Columbia, and Timika Shafeek-Horton, Duke
    Energy Carolinas, LLC, of Charlotte, North Carolina, for
    Respondent Duke Energy Carolinas, LLC.
    Shannon Bowyer Hudson, Nanette Solveig Edwards,
    Jeffrey M. Nelson, and Florence P. Belser, all of
    Columbia, for Respondent Office of Regulatory Staff.
    Len Sullivan Anthony, of North Myrtle Beach, for
    Respondent North Carolina Electric Membership
    Corporation.
    Jackquelyn Sue Dickman and Susan Annelle Lake, both
    of Columbia, for Respondent South Carolina Department
    of Health and Environmental Control.
    Richard Lee Whitt, Austin & Rogers, PA, of Columbia,
    for Respondent Invenergy Therman Development, LLC.
    PER CURIAM: The South Carolina Coastal Conservation League and the
    Southern Alliance for Clean Energy (the Alliance) appeal the Public Service
    Commission's decision to issue Duke Energy Carolinas, LLC and the North
    Carolina Electric Membership Corporation (NCEMC) a Certificate of
    Environmental Compatibility and Public Convenience and Necessity to build a 750
    megawatt combined cycle natural gas-fired generating facility near Anderson. The
    Coastal Conservation League and the Alliance argue the Commission erred in
    issuing the Certificate by (1) finding the proposed plant's environmental impact
    was justified and (2) not requiring Duke Energy and NCEMC to modify their
    application for the Certificate. We affirm and find (1) the Commission considered
    and understood the Coastal Conservation League and the Alliance's proposed solar
    component, (2) substantial evidence supports the Commission's issuance of the
    Certificate, and (3) there is no legal basis for requiring the Commission to
    condition the Certificate on Duke Energy soliciting bids for the proposed solar
    plant.
    "No person shall commence to construct a major utility facility without first having
    obtained a certificate1 issued with respect to such facility by the Commission."
    
    S.C. Code Ann. § 58-33-110
    (1) (2015). "An applicant for a certificate shall file an
    1
    "The term 'certificate' means a certificate of environmental compatibility and
    public convenience and necessity." 
    S.C. Code Ann. § 58-33-20
    (8) (2015).
    application with the commission, in such form as the commission may prescribe."
    
    S.C. Code Ann. § 58-33-120
    (1) (2015).
    The Commission shall render a decision upon the record
    either granting or denying the application as filed, or
    granting it upon such terms, conditions or modifications
    of the construction, operation or maintenance of the
    major utility facility as the Commission may deem
    appropriate; such conditions shall be as determined by
    the applicable State agency having jurisdiction or
    authority under statutes, rules, regulations or standards
    promulgated thereunder, and the conditions shall become
    a part of the certificate. The Commission may not grant
    a certificate for the construction, operation, and
    maintenance of a major utility facility, either as proposed
    or as modified by the Commission, unless it shall find
    and determine:
    (a)   The basis of the need for the facility.
    (b)   The nature of the probable environmental impact.
    (c)   That the impact of the facility upon the
    environment is justified, considering the state of
    available technology and the nature and economics
    of various alternatives and other pertinent
    considerations.
    (d)   That the facilities will serve the interests of the
    system economy and reliability.
    (e)   That there is reasonable assurance that the
    proposed facility will conform to applicable State
    and local laws and regulations issued thereunder,
    including any allowable variance provisions
    therein, except that the Commission may refuse to
    apply any local law or local regulation if it finds
    that, as applied to the proposed facility, such law
    or regulation is unreasonably restrictive in view of
    the existing technology, or of factors of cost or
    economics or of the needs of consumers whether
    located inside or outside of the directly affected
    government subdivisions.
    (f)   That public convenience and necessity require the
    construction of the facility.
    
    S.C. Code Ann. § 58-33-160
    (1) (2015). "[T]his Court employs a deferential
    standard of review when reviewing a decision of the Public Service Commission
    and will affirm that decision when substantial evidence supports it." Friends of
    Earth v. Pub. Serv. Comm'n, 
    387 S.C. 360
    , 366, 
    692 S.E.2d 910
    , 913 (2010).
    First, we find the Commission considered and understood the Coastal Conservation
    League and the Alliance's solar proposal. The Commission made the findings
    required by South Carolina Code section 58-33-160. Specifically at issue in this
    appeal, the Commission made findings on "the nature of the probable
    environmental impact" of the proposed gas plant and determined the impact was
    "justified, considering the state of available technology and the nature and
    economics of various alternatives and other pertinent considerations." See § 58-
    33-160(1)(b)-(c).
    The Commission found Duke Energy and NCEMC had appropriately evaluated the
    environmental impacts of the proposed plant, and the Commission described those
    impacts. Specifically, the Commission found the proposed plant (1) had "critical
    infrastructure such as available land, water supply, and transmission facilities . . .
    already in place," due to its location—adjacent to an existing power plant; (2) had
    archeological clearance; (3) would have "minimal effects on the visual resources
    and scenic quality" of the area; (4) would feature "state of the art environmental
    control technology for natural gas combined cycle generation;" and (5) would
    include a cooling tower to minimize "both the intake and discharge impacts to the
    Saluda River." The Commission also noted the Office of Regulatory Staff's
    witness testified the proposed plant would not result in any significant impacts to
    the environment and the Department of Health and Environmental Control, the
    Department of Natural Resources, and the Department of Parks, Recreation and
    Tourism were all parties to the case and did not appear.
    Additionally, the Commission found the impact of the proposed plant was
    "justified, considering the state of available technology and the nature and
    economics of the various alternatives and other pertinent considerations." See §
    58-33-160(1)(c). The Commission considered the solar proposal and found there
    was no need for an additional 375 megawatt solar facility.2 The Commission
    found Duke Energy had "conducted a thorough review in determining" the
    proposed plant "is best to meet its future electricity generating needs," and
    "decline[d] to require [Duke Energy] to do further."3
    Second, we find substantial evidence supports the Commission's issuance of the
    Certificate. "[T]he [c]ourt may not substitute its judgment for the Commission's on
    questions about which there is room for a difference of intelligent opinion."
    Friends of Earth, 
    387 S.C. at 366
    , 
    692 S.E.2d at 913
    . "[T]he Commission's
    findings are presumptively correct, [and] the party challenging a Commission order
    bears the burden of convincingly proving the decision is clearly erroneous, or
    arbitrary or capricious, or an abuse of discretion, in view of the substantial
    evidence on the whole record." 
    Id.
    The Commission made specific findings based on testimony regarding the nature
    of the environmental impact of the proposed plant and whether it was justified.
    The Commission accurately described the solar proposal both in its order issuing
    the Certificate and its order denying the petition for rehearing. Additionally, Duke
    Energy's application and its witnesses4 described the proposed plant's projected
    impact on water quality, air quality, and cultural resources. For these reasons, the
    Commission's finding that the proposed plant was justified, without the solar plant,
    was supported by the evidence.
    Third, we find there is no legal basis for requiring the Commission to condition the
    Certificate on Duke Energy soliciting bids for the proposed solar plant. Section
    2
    The Coastal Conservation League and the Alliance argue the Commission
    misunderstood their solar proposal. However, the Coastal Conservation League
    and the Alliance made this same argument in a petition for rehearing on the
    Commission's order issuing the Certificate. The Commission denied the petition
    for rehearing and emphasized it understood the proposed solar plant was to be used
    to "offset gas generation when conditions exist for economic solar energy
    production."
    3
    The Commission also encouraged Duke Energy to voluntarily consider solar
    generation.
    4
    Interestingly, one of Duke Energy's witnesses testified the proposed solar plant
    would be the largest solar plant in the world and would require approximately
    2,625 acres of land.
    58-33-160 allows the Commission to grant an application for a certificate "upon
    such terms, conditions or modifications of the construction, operation or
    maintenance of the major utility facility as the Commission may deem
    appropriate." § 53-33-160(1). However, this section does not enable the
    Commission to grant an application but require more than a "modification" to the
    application. "Modification" is defined as a "small alteration, adjustment, or
    limitation." Modification, Webster's II New College Dictionary (Houghton Mifflin
    Co. ed., 1999). We hold requiring Duke Energy to build—or solicit bids for—the
    proposed solar plant would constitute more than a "modification" to its application.
    See 64 Am. Jur. 2d Public Utilities § 143 (2011) ("Public service commissions are
    administrative agencies whose power is derived from the legislature and whose
    functions are legislative functions."); Sloan v. S.C. Bd. of Physical Therapy
    Exam'rs, 
    370 S.C. 452
    , 468, 
    636 S.E.2d 598
    , 606 (2006) ("A statute as a whole
    must receive practical, reasonable, and fair interpretation consonant with the
    purpose, design, and policy of lawmakers.").
    We hold the Commission considered and understood the Coastal Conservation
    League and the Alliance's solar proposal, substantial evidence supports the
    Commission's issuance of the Certificate, and there is no legal basis for requiring
    the Commission to condition the Certificate on Duke Energy soliciting bids for the
    proposed solar plant. Accordingly, the Commission's issuance of a Certificate to
    Duke Energy and NCEMC is AFFIRMED.
    FEW, C.J., and KONDUROS and LOCKEMY, JJ., concur.
    

Document Info

Docket Number: 2016-UP-054

Filed Date: 2/10/2016

Precedential Status: Non-Precedential

Modified Date: 10/22/2024