Vincent C. Carter v. Eagles Landing Restaurants ( 2022 )


Menu:
  • THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE
    CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING
    EXCEPT AS PROVIDED BY RULE 268(d)(2), SCACR.
    THE STATE OF SOUTH CAROLINA
    In The Court of Appeals
    Vincent C. Carter d/b/a Elite Construction Co.,
    Respondent,
    v.
    Eagles Landing Restaurants, LLC, Appellant.
    Appellate Case No. 2019-001062
    Appeal From Florence County
    Eugene Preston Warr, Jr., Special Referee
    Unpublished Opinion No. 2022-UP-347
    Heard April 12, 2022 – Filed August 24, 2022
    AFFIRMED AS MODIFIED
    Brooks Roberts Fudenberg, of Law Office of Brooks R.
    Fudenberg, LLC, of Charleston, for Appellant.
    Gary Ivan Finklea and Patrick Buel Ford, both of Finklea
    Law Firm of Florence, for Respondent.
    PER CURIAM: In this breach of contract and quantum meruit action between
    Vincent Carter d/b/a Elite Construction Co. and Eagles Landing Restaurants, LLC
    (Eagles Landing), Eagles Landing argues the special referee erred in (1) denying
    Eagles Landing a properly calculated setoff, (2) declining to award Eagles Landing
    damages for lost profits, and (3) applying an improper standard in reviewing the
    parties' Rule 59(e), SCRCP, motions. We affirm as modified.
    Facts and Procedural History
    Mohammed Makawi owns several IHOP restaurants and manages them through a
    limited liability company, Eagles Landing. In 2015, Makawi sought to open a new
    IHOP in Charleston. The building, a former Ruby Tuesday restaurant, had been
    vacant for ten to twelve years and required extensive renovations.
    Carter, a general contractor and friend of Makawi, submitted a bid to renovate the
    building for $624,354.00. The bid proposed a ninety-day construction schedule
    and included an itemized "bid breakdown" listing the costs for various aspects of
    the project. Carter and Makawi executed a lump sum contract (the Contract)
    providing, "The Owner shall pay the Contractor the Contract Sum in current funds
    for the Contractor's performance of the Contract. The Contract Sum shall be Six
    Hundred Twenty Four Thousand Three Hundred Fifty Four ($624,354.00), subject
    to additions and deductions as provided in the Contract Documents."
    The Contract required Eagles Landing to make progress payments to Carter, with
    final payment due after the City of Charleston issued a certificate of occupancy to
    the contractor, net 10 days, and specified:
    Contractor is to be paid $100,000 from this contract as a
    Project Management Fee. Payments to be made to
    contractor as progress of work begins. Payment and
    amount requested shall be at the discretion of contractor.
    Typically, payment draws to contractor for payment shall
    be made 1/3 after start net 2 weeks. Another 1/3 half
    way into project progress and final 1/3 at or near
    completion.
    After executing the Contract, Makawi had difficulty obtaining financing and was
    unable to get a traditional loan to finance the project. Ultimately, Eagles Landing
    borrowed approximately $500,000, and Makawi anticipated proceeds from the sale
    of North Carolina real estate would help fund the renovation.
    After demolition began, Carter discovered mold in the building and immediately
    halted work. Due to the additional work and cost of the mold remediation, Carter
    executed a change order. Carter recorded several additional change orders
    reflecting both Makawi's requests to amend the scope of the work and Carter's
    crediting of Eagle's Landing on certain cost savings.
    During the course of construction, Jimmy Free, Eagles Landing's former Chief
    Financial Officer, paid Carter when he requested a draw, until at some point,
    Makawi instructed Free not to pay Carter. Then, when Eagles Landing did pay, it
    did not cover the full draw—instead, Carter had to "prove" what he spent on labor
    and materials, and he was paid only enough to cover those costs. This placed
    Carter in the position of being unable to pay his subcontractors. Eagles Landing
    began paying subcontractors directly due to filed mechanic's liens. In all, Eagles
    Landing paid Carter only $229,900 on the $624,354.00 Contract.
    On October 23, 2015, the City issued a temporary certificate of occupancy; a
    permanent certificate of occupancy followed in late November. On February 10,
    2016, Carter notified Eagles Landing of the remaining amount due under the
    Contract, which Carter calculated to be $438,306.50. On March 17, 2016,
    electrical contractor Carolina Construction Solutions filed an action against both
    Carter and Eagles Landing seeking payment for its work on the project.
    Carter then filed this action for breach of contract and unjust enrichment/quantum
    meruit. Eagles Landing timely answered and counterclaimed for breach of
    contract, fraud, quantum meruit, negligence, and indemnification.
    Following a nonjury trial, the special referee found Eagles Landing breached the
    Contract with Carter. The special referee further held that even if certain change
    orders were not part of the Contract, Eagles Landing was unjustly enriched based
    on the labor and materials Carter furnished pursuant to the change orders. The
    special referee acknowledged the parties agreed Eagles Landing paid $390,888.33
    to third-party vendors and subcontractors for work related to the project. The order
    then broke down these payments into two itemized lists: one delineating Eagles
    Landing's $212,195.26 in third-party payments for work within the scope of the
    Contract, and another listing $97,607.74 in payments for work performed outside
    the scope of the Contract. After accounting for the previous payments to Carter,
    payments to third parties, and certain project-related credits, the special referee
    calculated Eagles Landing owed Carter $160,130.83.
    Eagles Landing and Carter filed motions to alter or amend the special referee's
    order. While these motions were pending, Eagles Landing reached a $50,000
    settlement with Carolina Construction Solutions. By supplemental order, the
    special referee denied the post-trial motions and increased the award to Carter
    "from $160,130.83, to 176,794.99, plus additional interest due" in light of Carter's
    own $16,664.16 confession of judgment to Carolina Construction Solutions.
    Law and Analysis
    I. Setoff for Carolina Construction Solutions Payments
    "An action for breach of contract seeking money damages is an action at law."
    McCall v. IKON, 
    380 S.C. 649
    , 658, 
    670 S.E.2d 695
    , 700 (Ct. App. 2008). "In an
    action at law tried without a jury, an appellate court's scope of review extends
    merely to the correction of errors of law. The Court will not disturb the trial court's
    findings unless they are found to be without evidence that reasonably supports
    those findings." Miller Constr. Co., LLC v. PC Constr. of Greenwood, Inc., 
    418 S.C. 186
    , 195, 
    791 S.E.2d 321
    , 326 (Ct. App. 2016) (quoting Temple v. Tec–Fab,
    Inc., 
    381 S.C. 597
    , 599–600, 
    675 S.E.2d 414
    , 415 (2009)). With respect to setoff
    requests, "South Carolina courts have consistently held 'there can be only one
    satisfaction for an injury or wrong.'" Stoneledge at Lake Keowee Owners' Ass'n,
    Inc. v. IMK Dev. Co., LLC, 
    435 S.C. 109
    , 133, 
    866 S.E.2d 542
    , 555 (2021)
    (quoting Smith v. Widener, 
    397 S.C. 468
    , 471, 
    724 S.E.2d 188
    , 190 (Ct. App.
    2012)).
    Eagles Landing first asserts the special referee erred in failing to credit it for
    payments made to Carolina Construction Solutions for additional electricians and
    in failing to recognize the purported savings achieved under the Contract through
    the use of these electricians. We disagree.
    Although Carter's bid estimated $92,780 for "Electrical Materials and Labor Site
    Work," this was a lump-sum contract requiring Eagles Landing to pay Carter a
    total of $624,354.00 at draw intervals "at the discretion of contractor." The
    Contract provided $100,000 of the contract sum was Carter's project management
    fee, and Carter testified he added a markup to certain estimates for the project to
    earn a profit.
    During the course of the work, Makawi became frustrated by construction delays
    and demanded that Carter hire additional electricians. A June 12, 2015 change
    order noted:
    Carolina Construction Solutions aided in the completion
    of electrical services needed on the project. Mr. Makawi
    informed Mr. Carter to tell the original contracted
    electrician that their services were no longer needed. Mr.
    Makawi wanted as many electricians from Carolina
    Construction Solutions as were available for his project
    to work 7 days a week if necessary to complete all
    electrical as quickly as possible. Mr. Makawi was
    informed that this would be a change order which he
    approved. The original electricians, Turner Electric, had
    been working and were completing work as per plans and
    specifications, however Mr. Makawi decided he wanted
    to go with another contractor.
    The change order listed a cost of $37,397.45 to hire the additional electricians and
    specifically noted, "** All change orders shall be added to original contract price
    and be paid by owner upon completion of work, net 30. **" Makawi understood
    the change order would be costly; however, he claimed he did not know how much
    more the cost would be. In any event, Carter's bid of $92,780 for "Electrical
    Materials and Labor Site Work," did not contemplate hiring additional electricians
    to work 24/7 under Makawi's change order and demand to accelerate the
    construction process. Thus, we find the special referee properly declined to offset
    Eagles Landing's liability to Carter by either its payment to Carolina Construction
    Solutions or by any alleged savings under the Contract.
    II. Calculation and Crediting of Payments by Eagles Landing
    Eagles Landing next asserts the special referee's mathematical or clerical error in
    failing to account for a remaining $81,085.33 paid as either within or outside the
    scope of the contract resulted in an overstatement of the amount Eagles Landing
    owed Carter under the Contract. We disagree.
    The trial court is vested with considerable discretion over
    the amount of a damages award, and our review of the
    amount of damages is limited to the correction of errors
    of law. In reviewing a damages award, we do not weigh
    the evidence, but determine if any evidence supports the
    award.
    Oaks at Rivers Edge Prop. Owners Ass'n, Inc. v. Daniel Island Riverside Devs.,
    LLC, 
    420 S.C. 424
    , 446, 
    803 S.E.2d 475
    , 487 (Ct. App. 2017) (quoting Vortex
    Sports & Ent., Inc. v. Ware, 
    378 S.C. 197
    , 208, 
    662 S.E.2d 444
    , 450 (Ct. App.
    2008) (citation omitted)).
    Eagles Landing spent $620,788.33 in connection with the renovation. Of this,
    $229,990 was paid to Carter. The parties disagree as to whether the remaining
    $390,788.33 in payments went to third parties on Carter's behalf within the scope
    of work of the Contract—and thus should offset the balance Eagles Landing owed
    Carter—or were payments made outside the scope of the Contract for reasons
    related to Makawi's change orders and supplemental demands.
    The special referee found Eagles Landing made payments to twenty-nine vendors:
    $212,195.26 on Carter's behalf for work within the scope of the Contract and
    $97,607.74 to eleven other vendors for work outside the scope of the Contract.
    Thus, the special referee credited Eagles Landing with a line item $212,195.26
    offset towards the remaining balance it owed Carter.
    Eagles Landing correctly asserts that based on the order's itemized lists, it appears
    the special referee failed to account for $81,085.33 in payments by Eagles
    Landing. However, the special referee separately addressed additional transactions
    later in the order, crediting Eagles Landing with $11,285.00 paid to ARS Rescue
    Rooter for work within the scope of the Contract. The special referee's damages
    summary on the final page of the order notes this payment as a separate line item
    credited to Eagles Landing in addition to the $212,195.26 credit.
    Next, the special referee found Eagles Landing was not entitled to an offset credit
    or other award for two heating, ventilation, and air conditioning (HVAC) units
    because the parties agreed the HVAC system would not need to be replaced, and
    Carter issued a credit to Eagles Landing of $44,439.00. The evidence in the record
    shows Eagles Landing paid $58,392.96 for "monthly lease total of HVAC units,"
    and this would constitute payment outside the scope of the Contract.
    Although the special referee made specific findings as to $379.480.96 of the
    $390,888.33 in payments, $11,407.37 remains unaccounted for. Our review of the
    evidence reveals the special referee did not set forth a specific finding for
    $6,259.37 paid to S&D Coffee. Carter testified he did not know what services
    S&D Coffee provided and explained coffee would not have been a part of his work
    under the Contract. Nor did Carter's bid provide a line item for coffee equipment
    or any other kitchen equipment. Eagles Landing does not argue the special referee
    erred in not listing this payment as within the scope of the Contract, and we see no
    error here.
    And although the special referee credited Eagles Landing with $3,500 paid to
    Johnson Concrete for work performed within the scope of the Contract, the
    evidence in the record shows Eagles Landing actually paid Johnson Concrete
    $8,548 for kitchen concrete work. Thus, it appears the accounted for $5,048 is the
    difference between the total payments Eagles Landing made to Johnson Concrete
    less the $3,500 the special referee credited as within the scope of the Contract.
    We do find the special referee's order contains a scrivener's error of $100. The
    record establishes Eagles Landing paid Multi-tech Safety Products, Inc., a total of
    $26,622.00. However, the special referee's order lists $26,522.00 as the Multi-tech
    Safety Products payment. Correcting this results in the itemized list totaling
    $212,295.26. Therefore, we find the award to Carter should be reduced to
    $160,030.83 to account for this scrivener's error.1 Other than this $100 deviation,
    the evidence supports the special referee's damages calculation.
    III. Lost Profits
    Eagles Landing argues the special referee erred in failing to award $71,784.52 on
    its counterclaim for lost profits resulting from the postponement of the opening the
    restaurant due to construction delays. However, the record reflects that most, if not
    all, delays were due to Makawi's actions or circumstances beyond the control of
    either party. The initial delay in starting construction was the result of Makawi's
    difficulty obtaining financing. Other delays caused by the discovery of mold in the
    long-vacant building and Makawi's change orders cannot be attributed to Carter.
    Therefore, we find the special referee properly declined to award Eagles Landing
    damages for lost profits. See Branche Builders, Inc. v. Coggins, 
    386 S.C. 43
    , 48,
    
    686 S.E.2d 200
    , 202 (Ct. App. 2009) ("The elements for breach of contract are the
    existence of the contract, its breach, and the damages caused by such breach.").
    IV. Rule 59(e) motion
    Eagles Landing contends the special referee erred in applying an incorrect federal
    standard in considering the parties' Rule 59(e), SCRCP, motions. Although the
    special referee erred in its initial recitation of the law, we find this error does not
    require reversal. In denying both parties' Rule 59(e) motions, the special referee
    explained:
    After considering the grounds raised in the motions of the
    Plaintiff and Defendant, and after reviewing the
    1
    This adjustment would likewise reduce the $176,794.99 awarded by supplemental
    order to $176,694.99.
    transcript of the trial, including the testimony of the
    witnesses and the exhibits that were admitted into
    evidence, as well as the notes from the trial, this Court
    denies both the Plaintiff's Motion to Reconsider and the
    Defendant's Motion to Amend. The testimony and
    exhibits admitted into evidence at trial support the
    Court's findings and conclusions.
    Because the special referee based its denial of the post-trial motions on the
    testimony and exhibits admitted into evidence—and the evidence supports the
    referee's findings—we find the order's error in reciting a federal standard does not
    warrant reversal or remand. See e.g., Elam v. S.C. Dep't of Transp., 
    361 S.C. 9
    , 21,
    
    602 S.E.2d 772
    , 778–79 (2004) (holding "it is proper to view a Rule 59(e) motion
    not only as a vehicle to request the trial court 'alter or amend the judgment,' but
    also as a vehicle to seek 'reconsideration' of issues and arguments. A motion under
    Rule 59(e) long has been viewed as [a] 'motion for reconsideration' despite the
    absence of those words from the rule. Consequently, a party usually is allowed to
    ask the court to reconsider its decision even if it means rehashing all or part of an
    argument previously presented.").
    Conclusion
    Based on the foregoing, we affirm the special referee's order as modified to
    account for the $100 scrivener's error in the damages award, thereby decreasing the
    amount Eagles Landing owes Carter to $176,694.99.
    AFFIRMED AS MODIFIED.
    THOMAS, MCDONALD, and HEWITT, JJ., concur.
    

Document Info

Docket Number: 2022-UP-347

Filed Date: 8/24/2022

Precedential Status: Non-Precedential

Modified Date: 10/22/2024