Rent-A-Center, West, Inc. v. Jackson , 130 S. Ct. 2772 ( 2010 )


Menu:
  • (Slip Opinion)              OCTOBER TERM, 2009                                       1
    Syllabus
    NOTE: Where it is feasible, a syllabus (headnote) will be released, as is
    being done in connection with this case, at the time the opinion is issued.
    The syllabus constitutes no part of the opinion of the Court but has been
    prepared by the Reporter of Decisions for the convenience of the reader.
    See United States v. Detroit Timber & Lumber Co., 
    200 U. S. 321
    , 337.
    SUPREME COURT OF THE UNITED STATES
    Syllabus
    RENT-A-CENTER, WEST, INC. v. JACKSON
    CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR
    THE NINTH CIRCUIT
    No. 09–497.      Argued April 26, 2010—Decided June 21, 2010
    Respondent Jackson filed an employment-discrimination suit against
    petitioner Rent-A-Center, his former employer, in a Nevada Federal
    District Court. Rent-A-Center filed a motion, under the Federal Ar
    bitration Act (FAA), to dismiss or stay the proceedings, 
    9 U. S. C. §3
    ,
    and to compel arbitration, §4, based on the arbitration agreement
    (Agreement) Jackson signed as a condition of his employment. Jack
    son opposed the motion on the ground that the Agreement was unen
    forceable in that it was unconscionable under Nevada law. The Dis
    trict Court granted Rent-A-Center’s motion. The Ninth Circuit
    reversed in relevant part.
    Held: Under the FAA, where an agreement to arbitrate includes an
    agreement that the arbitrator will determine the enforceability of the
    agreement, if a party challenges specifically the enforceability of that
    particular agreement, the district court considers the challenge, but if
    a party challenges the enforceability of the agreement as a whole, the
    challenge is for the arbitrator. Pp. 3–12.
    (a) Section 2 of the FAA places arbitration agreements on an equal
    footing with other contracts, Buckeye Check Cashing, Inc. v.
    Cardegna, 
    546 U. S. 440
    , 443, and requires courts to enforce them ac
    cording to their terms, Volt Information Sciences, Inc. v. Board of
    Trustees of Leland Stanford Junior Univ., 
    489 U. S. 468
    , 478, “save
    upon such grounds as exist under law or in equity for the revocation
    of any contract,” §2. Here, the Agreement included two relevant arbi
    tration provisions: it provided for arbitration of all disputes arising
    out of Jackson’s employment, including discrimination claims, and it
    gave the “Arbitrator . . . exclusive authority to resolve any dispute re
    lating to the [Agreement’s] enforceability . . . including . . . any claim
    2              RENT-A-CENTER, WEST, INC. v. JACKSON
    Syllabus
    that all or any part of this Agreement is void or voidable.” Rent-A-
    Center seeks enforcement of the second provision, which delegates to
    the arbitrator the “gateway” question of enforceability. See, e.g.,
    Howsam v. Dean Witter Reynolds, Inc., 
    537 U. S. 79
    , 83–85. The
    court must enforce the delegation provision under §§3 and 4 unless it
    is unenforceable under §2. Pp. 3–6.
    (b) There are two types of validity challenges under §2: one “chal
    lenges specifically the validity of the agreement to arbitrate,” and
    “[t]he other challenges the contract as a whole,” Buckeye, 
    supra, at 444
    . Only the first is relevant to a court’s determination of an arbi
    tration agreement’s enforceability, see, e.g., Prima Paint Corp. v.
    Flood & Conklin Mfg. Co., 
    388 U. S. 395
    , 403–404, because under §2
    “an arbitration provision is severable from the remainder of the con
    tract,” Buckeye, 
    supra, at 445
    . That does not mean that agreements
    to arbitrate are unassailable. If a party challenges the validity under
    §2 of the precise agreement to arbitrate at issue, the federal court
    must consider the challenge before ordering compliance with the
    agreement under §4. That is no less true when the precise agree
    ment to arbitrate is itself part of a larger arbitration agreement. Be
    cause here the agreement to arbitrate enforceability (the delegation
    provision) is severable from the remainder of the Agreement, unless
    Jackson challenged the delegation provision specifically, it must be
    treated as valid under §2 and enforced under §§3 and 4. Pp. 6–9.
    (c) The District Court correctly concluded that Jackson challenged
    only the validity of the contract as a whole. In his brief to this Court
    he raised a challenge to the delegation provision for the first time,
    but that is too late and will not be considered. See 14 Penn Plaza
    LLC v. Pyett, 556 U. S. ___, ___. Pp. 9–12.
    
    581 F. 3d 912
    , reversed.
    SCALIA, J., delivered the opinion of the Court, in which ROBERTS,
    C. J., and KENNEDY, THOMAS, and ALITO, JJ., joined. STEVENS, J., filed a
    dissenting opinion, in which GINSBURG, BREYER, and SOTOMAYOR, JJ.,
    joined.
    Cite as: 561 U. S. ____ (2010)                              1
    Opinion of the Court
    NOTICE: This opinion is subject to formal revision before publication in the
    preliminary print of the United States Reports. Readers are requested to
    notify the Reporter of Decisions, Supreme Court of the United States, Wash
    ington, D. C. 20543, of any typographical or other formal errors, in order
    that corrections may be made before the preliminary print goes to press.
    SUPREME COURT OF THE UNITED STATES
    _________________
    No. 09–497
    _________________
    RENT-A-CENTER, WEST, INC., PETITIONER v.
    ANTONIO JACKSON
    ON WRIT OF CERTIORARI TO THE UNITED STATES COURT OF
    APPEALS FOR THE NINTH CIRCUIT
    [June 21, 2010]
    JUSTICE SCALIA delivered the opinion of the Court.
    We consider whether, under the Federal Arbitration Act
    (FAA or Act), 
    9 U. S. C. §§1
    –16, a district court may decide
    a claim that an arbitration agreement is unconscionable,
    where the agreement explicitly assigns that decision to the
    arbitrator.
    I
    On February 1, 2007, the respondent here, Antonio
    Jackson, filed an employment-discrimination suit under
    Rev. Stat. §1977, 
    42 U. S. C. §1981
    , against his former
    employer in the United States District Court for the Dis
    trict of Nevada. The defendant and petitioner here, Rent-
    A-Center, West, Inc., filed a motion under the FAA to
    dismiss or stay the proceedings, 
    9 U. S. C. §3
    , and to com
    pel arbitration, §4. Rent-A-Center argued that the Mutual
    Agreement to Arbitrate Claims (Agreement), which Jack
    son signed on February 24, 2003 as a condition of his
    employment there, precluded Jackson from pursuing his
    claims in court. The Agreement provided for arbitration of
    all “past, present or future” disputes arising out of Jack
    son’s employment with Rent-A-Center, including “claims
    2         RENT-A-CENTER, WEST, INC. v. JACKSON
    Opinion of the Court
    for discrimination” and “claims for violation of any federal
    . . . law.” App. 29–30. It also provided that “[t]he Arbitra
    tor, and not any federal, state, or local court or agency,
    shall have exclusive authority to resolve any dispute
    relating to the interpretation, applicability, enforceability
    or formation of this Agreement including, but not limited
    to any claim that all or any part of this Agreement is void
    or voidable.” Id., at 34.
    Jackson opposed the motion on the ground that “the
    arbitration agreement in question is clearly unenforceable
    in that it is unconscionable” under Nevada law. Id., at 40.
    Rent-A-Center responded that Jackson’s unconscionability
    claim was not properly before the court because Jackson
    had expressly agreed that the arbitrator would have ex
    clusive authority to resolve any dispute about the enforce
    ability of the Agreement. It also disputed the merits of
    Jackson’s unconscionability claims.
    The District Court granted Rent-A-Center’s motion to
    dismiss the proceedings and to compel arbitration. The
    court found that the Agreement “ ‘ “clearly and unmistak
    enly [sic]” ’ ” gives the arbitrator exclusive authority to
    decide whether the Agreement is enforceable, App. to Pet.
    for Cert. 4a. (quoting Howsam v. Dean Witter Reynolds,
    Inc., 
    537 U. S. 79
    , 83 (2002)), and, because Jackson chal
    lenged the validity of the Agreement as a whole, the issue
    was for the arbitrator, App. to Pet. for Cert. 4a (citing
    Buckeye Check Cashing, Inc. v. Cardegna, 
    546 U. S. 440
    ,
    444–445 (2006)). The court noted that even if it were to
    examine the merits of Jackson’s unconscionability claims,
    it would have rejected the claim that the agreement to
    split arbitration fees was substantively unconscionable
    under Nevada law. It did not address Jackson’s proce
    dural or other substantive unconscionability arguments.
    Without oral argument, a divided panel of the Court of
    Appeals for the Ninth Circuit reversed in part, affirmed in
    part, and remanded. 
    581 F. 3d 912
     (2009). The court
    Cite as: 561 U. S. ____ (2010)            3
    Opinion of the Court
    reversed on the question of who (the court or arbitrator)
    had the authority to decide whether the Agreement is
    enforceable. It noted that “Jackson does not dispute that
    the language of the Agreement clearly assigns the arbitra
    bility determination to the arbitrator,” but held that where
    “a party challenges an arbitration agreement as uncon
    scionable, and thus asserts that he could not meaningfully
    assent to the agreement, the threshold question of uncon
    scionability is for the court.” 
    Id., at 917
    . The Ninth Cir
    cuit affirmed the District Court’s alternative conclusion
    that the fee-sharing provision was not substantively un
    conscionable and remanded for consideration of Jackson’s
    other unconscionability arguments. 
    Id.,
     at 919–920, and
    n. 3. Judge Hall dissented on the ground that “the ques
    tion of the arbitration agreement’s validity should have
    gone to the arbitrator, as the parties ‘clearly and unmis
    takably provide[d]’ in their agreement.” 
    Id., at 921
    .
    We granted certiorari, 558 U. S. ___ (2010).
    II
    A
    The FAA reflects the fundamental principle that arbi
    tration is a matter of contract. Section 2, the “primary
    substantive provision of the Act,” Moses H. Cone Memorial
    Hospital v. Mercury Constr. Corp., 
    460 U. S. 1
    , 24 (1983),
    provides:
    “A written provision in . . . a contract evidencing a
    transaction involving commerce to settle by arbitra
    tion a controversy thereafter arising out of such con
    tract . . . shall be valid, irrevocable, and enforceable,
    save upon such grounds as exist at law or in equity for
    the revocation of any contract.” 
    9 U. S. C. §2
    .
    The FAA thereby places arbitration agreements on an
    equal footing with other contracts, Buckeye, 
    supra, at 443
    ,
    and requires courts to enforce them according to their
    4         RENT-A-CENTER, WEST, INC. v. JACKSON
    Opinion of the Court
    terms, Volt Information Sciences, Inc. v. Board of Trustees
    of Leland Stanford Junior Univ., 
    489 U. S. 468
    , 478
    (1989). Like other contracts, however, they may be invali
    dated by “generally applicable contract defenses, such as
    fraud, duress, or unconscionability.” Doctor’s Associates,
    Inc. v. Casarotto, 
    517 U. S. 681
    , 687 (1996).
    The Act also establishes procedures by which federal
    courts implement §2’s substantive rule. Under §3, a party
    may apply to a federal court for a stay of the trial of an
    action “upon any issue referable to arbitration under an
    agreement in writing for such arbitration.” Under §4, a
    party “aggrieved” by the failure of another party “to arbi
    trate under a written agreement for arbitration” may
    petition a federal court “for an order directing that such
    arbitration proceed in the manner provided for in such
    agreement.” The court “shall” order arbitration “upon
    being satisfied that the making of the agreement for arbi
    tration or the failure to comply therewith is not in issue.”
    Ibid.
    The Agreement here contains multiple “written provi
    sion[s]” to “settle by arbitration a controversy,” §2. Two
    are relevant to our discussion. First, the section titled
    “Claims Covered By The Agreement” provides for arbitra
    tion of all “past, present or future” disputes arising out of
    Jackson’s employment with Rent-A-Center. App. 29.
    Second, the section titled “Arbitration Procedures” pro
    vides that “[t]he Arbitrator . . . shall have exclusive au
    thority to resolve any dispute relating to the . . . enforce
    ability . . . of this Agreement including, but not limited to
    any claim that all or any part of this Agreement is void or
    voidable.” Id., at 32, 34. The current “controversy” be
    tween the parties is whether the Agreement is uncon
    scionable. It is the second provision, which delegates
    resolution of that controversy to the arbitrator, that Rent-
    A-Center seeks to enforce. Adopting the terminology used
    by the parties, we will refer to it as the delegation provi
    Cite as: 561 U. S. ____ (2010)                      5
    Opinion of the Court
    sion.
    The delegation provision is an agreement to arbitrate
    threshold issues concerning the arbitration agreement.
    We have recognized that parties can agree to arbitrate
    “gateway” questions of “arbitrability,” such as whether the
    parties have agreed to arbitrate or whether their agree
    ment covers a particular controversy. See, e.g., Howsam,
    
    537 U. S., at
    83–85; Green Tree Financial Corp. v. Bazzle,
    
    539 U. S. 444
    , 452 (2003) (plurality opinion). This line of
    cases merely reflects the principle that arbitration is a
    matter of contract.1 See First Options of Chicago, Inc. v.
    ——————
    1 There is one caveat. First Options of Chicago, Inc. v. Kaplan, 
    514 U. S. 938
    , 944 (1995), held that “[c]ourts should not assume that the
    parties agreed to arbitrate arbitrability unless there is ‘clea[r] and
    unmistakabl[e]’ evidence that they did so.” The parties agree the
    heightened standard applies here. See Brief for Petitioner 21; Brief for
    Respondent 54. The District Court concluded the “Agreement to
    Arbitrate clearly and unmistakenly [sic] provides the arbitrator with
    the exclusive authority to decide whether the Agreement to Arbitrate is
    enforceable.” App. to Pet. for Cert. 4a. The Ninth Circuit noted that
    Jackson did not dispute that the text of the Agreement was clear and
    unmistakable on this point. 
    581 F. 3d 912
    , 917 (2009). He also does
    not dispute it here. What he argues now, however, is that it is not
    “clear and unmistakable” that his agreement to that text was valid,
    because of the unconscionability claims he raises. See Brief for Re
    spondent 54–55. The dissent makes the same argument. See post, at
    5–8 (opinion of STEVENS, J.).
    This mistakes the subject of the First Options “clear and unmistak
    able” requirement. It pertains to the parties’ manifestation of intent,
    not the agreement’s validity. As explained in Howsam v. Dean Witter
    Reynolds, Inc., 
    537 U. S. 79
    , 83 (2002), it is an “interpretive rule,” based
    on an assumption about the parties’ expectations. In “circumstance[s]
    where contracting parties would likely have expected a court to have
    decided the gateway matter,” ibid., we assume that is what they agreed
    to. Thus, “[u]nless the parties clearly and unmistakably provide
    otherwise, the question of whether the parties agreed to arbitrate is to
    be decided by the court, not the arbitrator.” AT&T Technologies, Inc. v.
    Communications Workers, 
    475 U. S. 643
    , 649 (1986).
    The validity of a written agreement to arbitrate (whether it is legally
    binding, as opposed to whether it was in fact agreed to—including, of
    6           RENT-A-CENTER, WEST, INC. v. JACKSON
    Opinion of the Court
    Kaplan, 
    514 U. S. 938
    , 943 (1995). An agreement to arbi
    trate a gateway issue is simply an additional, antecedent
    agreement the party seeking arbitration asks the federal
    court to enforce, and the FAA operates on this additional
    arbitration agreement just as it does on any other. The
    additional agreement is valid under §2 “save upon such
    grounds as exist at law or in equity for the revocation of
    any contract,” and federal courts can enforce the agree
    ment by staying federal litigation under §3 and compelling
    arbitration under §4. The question before us, then, is
    whether the delegation provision is valid under §2.
    B
    There are two types of validity challenges under §2:
    “One type challenges specifically the validity of the
    agreement to arbitrate,” and “[t]he other challenges the
    contract as a whole, either on a ground that directly af
    fects the entire agreement (e.g., the agreement was
    fraudulently induced), or on the ground that the illegality
    of one of the contract’s provisions renders the whole con
    tract invalid.” Buckeye, 
    546 U. S., at 444
    . In a line of
    cases neither party has asked us to overrule, we held that
    only the first type of challenge is relevant to a court’s
    determination whether the arbitration agreement at issue
    is enforceable.2 See Prima Paint Corp. v. Flood & Conklin
    Mfg. Co., 
    388 U. S. 395
    , 403–404 (1967); Buckeye, 
    supra,
     at
    ——————
    course, whether it was void for unconscionability) is governed by §2’s
    provision that it shall be valid “save upon such grounds as exist at law
    or equity for the revocation of any contract.” Those grounds do not
    include, of course, any requirement that its lack of unconscionability
    must be “clear and unmistakable.” And they are not grounds that First
    Options added for agreements to arbitrate gateway issues; §2 applies to
    all written agreements to arbitrate.
    2 The issue of the agreement’s “validity” is different from the issue
    whether any agreement between the parties “was ever concluded,” and,
    as in Buckeye Check Cashing, Inc. v. Cardegna, 
    546 U. S. 440
     (2006),
    we address only the former. 
    Id., at 444, n. 1
    .
    Cite as: 561 U. S. ____ (2010)            7
    Opinion of the Court
    444–446; Preston v. Ferrer, 
    552 U. S. 346
    , 353–354 (2008).
    That is because §2 states that a “written provision” “to
    settle by arbitration a controversy” is “valid, irrevocable,
    and enforceable” without mention of the validity of the
    contract in which it is contained. Thus, a party’s chal
    lenge to another provision of the contract, or to the con
    tract as a whole, does not prevent a court from enforcing a
    specific agreement to arbitrate. “[A]s a matter of substan
    tive federal arbitration law, an arbitration provision is
    severable from the remainder of the contract.” Buckeye,
    
    546 U. S., at 445
    ; see also 
    id., at 447
     (the severability rule
    is based on §2).
    But that agreements to arbitrate are severable does not
    mean that they are unassailable. If a party challenges the
    validity under §2 of the precise agreement to arbitrate at
    issue, the federal court must consider the challenge before
    ordering compliance with that agreement under §4. In
    Prima Paint, for example, if the claim had been “fraud in
    the inducement of the arbitration clause itself,” then the
    court would have considered it. 
    388 U. S., at
    403–404.
    “To immunize an arbitration agreement from judicial
    challenge on the ground of fraud in the inducement would
    be to elevate it over other forms of contract,” 
    id., at 404, n. 12
    . In some cases the claimed basis of invalidity for the
    contract as a whole will be much easier to establish than
    the same basis as applied only to the severable agreement
    to arbitrate. Thus, in an employment contract many
    elements of alleged unconscionability applicable to the
    entire contract (outrageously low wages, for example)
    would not affect the agreement to arbitrate alone. But
    even where that is not the case—as in Prima Paint itself,
    where the alleged fraud that induced the whole contract
    equally induced the agreement to arbitrate which was part
    of that contract—we nonetheless require the basis of
    challenge to be directed specifically to the agreement to
    arbitrate before the court will intervene.
    8            RENT-A-CENTER, WEST, INC. v. JACKSON
    Opinion of the Court
    Here, the “written provision . . . to settle by arbitration a
    controversy,” 
    9 U. S. C. §2
    , that Rent-A-Center asks us to
    enforce is the delegation provision—the provision that
    gave the arbitrator “exclusive authority to resolve any
    dispute relating to the . . . enforceability . . . of this
    Agreement,” App. 34. The “remainder of the contract,”
    Buckeye, 
    supra, at 445
    , is the rest of the agreement to
    arbitrate claims arising out of Jackson’s employment with
    Rent-A-Center. To be sure this case differs from Prima
    Paint, Buckeye, and Preston, in that the arbitration provi
    sions sought to be enforced in those cases were contained
    in contracts unrelated to arbitration—contracts for con
    sulting services, see Prima Paint, 
    supra, at 397
    , check
    cashing services, see Buckeye, 
    supra, at 442
    , and “personal
    management” or “talent agent” services, see Preston,
    
    supra, at 352
    . In this case, the underlying contract is
    itself an arbitration agreement. But that makes no differ
    ence.3 Application of the severability rule does not depend
    on the substance of the remainder of the contract. Section
    2 operates on the specific “written provision” to “settle by
    arbitration a controversy” that the party seeks to enforce.
    Accordingly, unless Jackson challenged the delegation
    provision specifically, we must treat it as valid under §2,
    ——————
    3 The
    dissent calls this a “breezy assertion,” post, at 1, but it seems to
    us self-evident. When the dissent comes to discussing the point, post,
    at 11, it gives no logical reason why an agreement to arbitrate one
    controversy (an employment-discrimination claim) is not severable from
    an agreement to arbitrate a different controversy (enforceability).
    There is none. Since the dissent accepts that the invalidity of one
    provision within an arbitration agreement does not necessarily invali
    date its other provisions, post, at 7, n. 7, it cannot believe in some sort
    of magic bond between arbitration provisions that prevents them from
    being severed from each other. According to the dissent, it is fine to
    sever an invalid provision within an arbitration agreement when
    severability is a matter of state law, but severability is not allowed
    when it comes to applying Prima Paint Corp. v. Flood & Conklin Mfg.
    Co., 
    388 U. S. 395
     (1967).
    Cite as: 561 U. S. ____ (2010)           9
    Opinion of the Court
    and must enforce it under §§3 and 4, leaving any chal
    lenge to the validity of the Agreement as a whole for the
    arbitrator.
    C
    The District Court correctly concluded that Jackson
    challenged only the validity of the contract as a whole.
    Nowhere in his opposition to Rent-A-Center’s motion to
    compel arbitration did he even mention the delegation
    provision. See App. 39–47. Rent-A-Center noted this fact
    in its reply: “[Jackson’s response] fails to rebut or other
    wise address in any way [Rent-A-Center’s] argument that
    the Arbitrator must decide [Jackson’s] challenge to
    the enforceability of the Agreement. Thus, [Rent-A-
    Center’s] argument is uncontested.” Id., at 50 (emphasis in
    original).
    The arguments Jackson made in his response to Rent-A-
    Center’s motion to compel arbitration support this conclu
    sion. Jackson stated that “the entire agreement seems
    drawn to provide [Rent-A-Center] with undue advantages
    should an employment-related dispute arise.” Id., at 44
    (emphasis added). At one point, he argued that the limita
    tions on discovery “further suppor[t] [his] contention that
    the arbitration agreement as a whole is substantively
    unconscionable.” Ibid. (emphasis added). And before this
    Court, Jackson describes his challenge in the District
    Court as follows: He “opposed the motion to compel on the
    ground that the entire arbitration agreement, including the
    delegation clause, was unconscionable.” Brief for Respon
    dent 55 (emphasis added). That is an accurate description
    of his filings.
    As required to make out a claim of unconscionability
    under Nevada law, see 
    581 F. 3d, at 919
    , he contended
    that the Agreement was both procedurally and substan
    tively unconscionable. It was procedurally unconscion
    able, he argued, because it “was imposed as a condition of
    10        RENT-A-CENTER, WEST, INC. v. JACKSON
    Opinion of the Court
    employment and was non-negotiable.” App. 41. But we
    need not consider that claim because none of Jackson’s
    substantive unconscionability challenges was specific to
    the delegation provision. First, he argued that the Agree
    ment’s coverage was one sided in that it required arbitra
    tion of claims an employee was likely to bring—contract,
    tort, discrimination, and statutory claims—but did not
    require arbitration of claims Rent-A-Center was likely to
    bring—intellectual property, unfair competition, and trade
    secrets claims. 
    Id.,
     at 42–43. This one-sided-coverage
    argument clearly did not go to the validity of the delega
    tion provision.
    Jackson’s other two substantive unconscionability ar
    guments assailed arbitration procedures called for by the
    contract—the fee-splitting arrangement and the limita
    tions on discovery—procedures that were to be used dur
    ing arbitration under both the agreement to arbitrate
    employment-related disputes and the delegation provision.
    It may be that had Jackson challenged the delegation
    provision by arguing that these common procedures as
    applied to the delegation provision rendered that provision
    unconscionable, the challenge should have been consid
    ered by the court. To make such a claim based on the
    discovery procedures, Jackson would have had to argue
    that the limitation upon the number of depositions causes
    the arbitration of his claim that the Agreement is unen
    forceable to be unconscionable. That would be, of course, a
    much more difficult argument to sustain than the argu
    ment that the same limitation renders arbitration of his
    factbound employment-discrimination claim unconscion
    able. Likewise, the unfairness of the fee-splitting ar
    rangement may be more difficult to establish for the arbi
    tration of enforceability than for arbitration of more
    complex and fact-related aspects of the alleged employ
    ment discrimination. Jackson, however, did not make any
    arguments specific to the delegation provision; he argued
    Cite as: 561 U. S. ____ (2010)                   11
    Opinion of the Court
    that the fee-sharing and discovery procedures rendered
    the entire Agreement invalid.
    Jackson’s appeal to the Ninth Circuit confirms that he
    did not contest the validity of the delegation provision in
    particular. His brief noted the existence of the delegation
    provision, Brief for Appellant in No. 07–16164, p. 3, but
    his unconscionability arguments made no mention of it,
    
    id.,
     at 3–7. He also repeated the arguments he had made
    before the District Court, see supra, at 9, that the “entire
    agreement” favors Rent-A-Center and that the limitations
    on discovery further his “contention that the arbitration
    agreement as a whole is substantively unconscionable,”
    Brief for Appellant 7–8. Finally, he repeated the argu
    ment made in his District Court filings, that under state
    law the unconscionable clauses could not be severed from
    the arbitration agreement, see id., at 8–9.4 The point of
    this argument, of course, is that the Agreement as a whole
    is unconscionable under state law.
    Jackson repeated that argument before this Court. At
    oral argument, counsel stated: “There are certain elements
    of the arbitration agreement that are unconscionable and,
    under Nevada law, which would render the entire arbitra
    tion agreement unconscionable.” Tr. of Oral Arg. 43 (em
    phasis added). And again, he stated, “we’ve got both
    certain provisions that are unconscionable, that under
    Nevada law render the entire agreement unconscionable
    . . . , and that’s what the Court is to rely on.” Id., at 43–44
    ——————
    4 Jackson’s argument fails. The severability rule is a “matter of sub
    stantive federal arbitration law,” and we have repeatedly “rejected the
    view that the question of ‘severability’ was one of state law, so that if
    state law held the arbitration provision not to be severable a challenge
    to the contract as a whole would be decided by the court.” Buckeye, 
    546 U. S., at
    445 (citing Prima Paint, 
    388 U. S., at 400
    , 402–403; Southland
    Corp. v. Keating, 
    465 U. S. 1
    , 10–14 (1984); Allied-Bruce Terminix Cos.
    v. Dobson, 
    513 U. S. 265
    , 270–273 (1995)). For the same reason, the
    Agreement’s statement that its provisions are severable, see App. 37,
    does not affect our analysis.
    12           RENT-A-CENTER, WEST, INC. v. JACKSON
    Opinion of the Court
    (emphasis added).
    In his brief to this Court, Jackson made the contention,
    not mentioned below, that the delegation provision itself is
    substantively unconscionable because the quid pro quo he
    was supposed to receive for it—that “in exchange for ini
    tially allowing an arbitrator to decide certain gateway
    questions,” he would receive “plenary post-arbitration
    judicial review”—was eliminated by the Court’s subse
    quent holding in Hall Street Associates, L. L. C. v. Mattel,
    Inc., 
    552 U. S. 576
     (2008), that the nonplenary grounds for
    judicial review in §10 of the FAA are exclusive. Brief for
    Respondent 59–60. He brought this challenge to the
    delegation provision too late, and we will not consider it.5
    See 14 Penn Plaza LLC v. Pyett, 556 U. S. ___, ___ (2009)
    (slip op., at 24).
    *    *     *
    We reverse the judgment of the Court of Appeals for the
    Ninth Circuit.
    It is so ordered.
    ——————
    5 HallStreet Associates, L. L. C. v. Mattel, Inc., 
    552 U. S. 576
     (2008),
    was decided after Jackson submitted his brief to the Ninth Circuit, but
    that does not change our conclusion that he forfeited the argument.
    Jackson could have submitted a supplemental brief during the year and
    a half between this Court’s decision of Hall Street on March 25, 2008
    and the Ninth Circuit’s judgment on September 9, 2009. Moreover,
    Hall Street affirmed a rule that had been in place in the Ninth Circuit
    since 2003. 
    Id.,
     at 583–584, and n. 5.
    Cite as: 561 U. S. ____ (2010)            1
    STEVENS, J., dissenting
    SUPREME COURT OF THE UNITED STATES
    _________________
    No. 09–497
    _________________
    RENT-A-CENTER, WEST, INC., PETITIONER v.
    ANTONIO JACKSON
    ON WRIT OF CERTIORARI TO THE UNITED STATES COURT OF
    APPEALS FOR THE NINTH CIRCUIT
    [June 21, 2010]
    JUSTICE STEVENS, with whom JUSTICE GINSBURG,
    JUSTICE BREYER, and JUSTICE SOTOMAYOR join, dissent
    ing.
    Neither petitioner nor respondent has urged us to adopt
    the rule the Court does today: Even when a litigant has
    specifically challenged the validity of an agreement to
    arbitrate he must submit that challenge to the arbitrator
    unless he has lodged an objection to the particular line in
    the agreement that purports to assign such challenges to
    the arbitrator—the so-called “delegation clause.”
    The Court asserts that its holding flows logically from
    Prima Paint Corp. v. Flood & Conklin Mfg. Co., 
    388 U. S. 395
     (1967), in which the Court held that consideration of a
    contract revocation defense is generally a matter for the
    arbitrator, unless the defense is specifically directed at the
    arbitration clause, 
    id., at 404
    . We have treated this hold
    ing as a severability rule: When a party challenges a
    contract, “but not specifically its arbitration provisions,
    those provisions are enforceable apart from the remainder
    of the contract.”       Buckeye Check Cashing, Inc. v.
    Cardegna, 
    546 U. S. 440
    , 446 (2006). The Court’s decision
    today goes beyond Prima Paint. Its breezy assertion that
    the subject matter of the contract at issue—in this case, an
    arbitration agreement and nothing more—“makes no
    difference,” ante, at 7, is simply wrong. This written
    2         RENT-A-CENTER, WEST, INC. v. JACKSON
    STEVENS, J., dissenting
    arbitration agreement is but one part of a broader em
    ployment agreement between the parties, just as the
    arbitration clause in Prima Paint was but one part of a
    broader contract for services between those parties. Thus,
    that the subject matter of the agreement is exclusively
    arbitration makes all the difference in the Prima Paint
    analysis.
    I
    Under the Federal Arbitration Act (FAA), 
    9 U. S. C. §§1
    –16, parties generally have substantial leeway to
    define the terms and scope of their agreement to settle
    disputes in an arbitral forum. “[A]rbitration is,” after all,
    “simply a matter of contract between the parties; it is a
    way to resolve those disputes—but only those disputes—
    that the parties have agreed to submit to arbitration.”
    First Options of Chicago, Inc. v. Kaplan, 
    514 U. S. 938
    ,
    943 (1995). The FAA, therefore, envisions a limited role
    for courts asked to stay litigation and refer disputes to
    arbitration.
    Certain issues—the kind that “contracting parties would
    likely have expected a court to have decided”—remain
    within the province of judicial review. Howsam v. Dean
    Witter Reynolds, Inc., 
    537 U. S. 79
    , 83 (2002); see also
    Green Tree Financial Corp. v. Bazzle, 
    539 U. S. 444
    , 452
    (2003) (plurality opinion); AT&T Technologies, Inc. v.
    Communications Workers, 
    475 U. S. 643
    , 649 (1986).
    These issues are “gateway matter[s]” because they are
    necessary antecedents to enforcement of an arbitration
    agreement; they raise questions the parties “are not likely
    to have thought that they had agreed that an arbitrator
    would” decide. Howsam, 
    537 U. S., at 83
    . Quintessential
    gateway matters include “whether the parties have a valid
    arbitration agreement at all,” Bazzle, 
    539 U. S., at 452
    (plurality opinion); “whether the parties are bound by a
    given arbitration clause,” Howsam, 
    537 U. S., at 84
    ; and
    Cite as: 561 U. S. ____ (2010)                    3
    STEVENS, J., dissenting
    “whether an arbitration clause in a concededly binding
    contract applies to a particular type of controversy,” 
    ibid.
    It would be bizarre to send these types of gateway matters
    to the arbitrator as a matter of course, because they raise
    a “ ‘question of arbitrability.’ ”1 See, e.g., ibid.; First Op
    tions, 
    514 U. S., at 947
    .
    “[Q]uestion[s] of arbitrability” thus include questions
    regarding the existence of a legally binding and valid
    arbitration agreement, as well as questions regarding the
    scope of a concededly binding arbitration agreement. In
    this case we are concerned with the first of these catego
    ries: whether the parties have a valid arbitration agree
    ment. This is an issue the FAA assigns to the courts.2
    Section 2 of the FAA dictates that covered arbitration
    agreements “shall be valid, irrevocable, and enforceable,
    save upon such grounds as exist at law or in equity for the
    revocation of any contract.” 
    9 U. S. C. §2
    . “[S]uch
    grounds,” which relate to contract validity and formation,
    include the claim at issue in this case, unconscionability.
    See Doctor’s Associates, Inc. v. Casarotto, 
    517 U. S. 681
    ,
    687 (1996).
    Two different lines of cases bear on the issue of who
    decides a question of arbitrability respecting validity, such
    as whether an arbitration agreement is unconscionable.
    Although this issue, as a gateway matter, is typically for
    the court, we have explained that such an issue can be
    delegated to the arbitrator in some circumstances. When
    ——————
    1 Although it is not clear from our precedents, I understand “gateway
    matters” and “questions of arbitrability” to be roughly synonymous, if
    not exactly so. At the very least, the former includes all of the latter.
    2 Gateway issues involving the scope of an otherwise valid arbitration
    agreement also have a statutory origin. Section 3 of the FAA provides
    that “upon being satisfied that the issue involved in such suit . . . is
    referable to arbitration under such an agreement,” a court “shall . . .
    stay the trial of the action until such arbitration has been had.” 
    9 U. S. C. §3
    .
    4            RENT-A-CENTER, WEST, INC. v. JACKSON
    STEVENS, J., dissenting
    the parties have purportedly done so, courts must examine
    two distinct rules to decide whether the delegation is
    valid.
    The first line of cases looks to the parties’ intent. In
    AT&T Technologies, we stated that “question[s] of arbi
    trability” may be delegated to the arbitrator, so long as the
    delegation is clear and unmistakable. 
    475 U. S., at 649
    .
    We reaffirmed this rule, and added some nuance, in First
    Options. Against the background presumption that ques
    tions of arbitrability go to the court, we stated that federal
    courts should “generally” apply “ordinary state-law princi
    ples that govern the formation of contracts” to assess
    “whether the parties agreed to arbitrate a certain matter
    (including arbitrability).” 
    514 U. S., at 944
    . But, we
    added, a more rigorous standard applies when the inquiry
    is whether the parties have “agreed to arbitrate arbitrabil
    ity”: “Courts should not assume that the parties agreed to
    arbitrate arbitrability unless there is clear and unmistak
    able evidence that they did so.”3 
    Ibid.
     (internal quotation
    marks and brackets omitted). JUSTICE BREYER’s unani
    mous opinion for the Court described this standard as a
    type of “revers[e]” “presumption”4—one in favor of a judi
    cial, rather than an arbitral, forum. 
    Id., at 945
    . Clear and
    unmistakable “evidence” of agreement to arbitrate arbi
    trability might include, as was urged in First Options, a
    course of conduct demonstrating assent,5 
    id., at 946
    , or, as
    ——————
    3 We  have not expressly decided whether the First Options delegation
    principle would apply to questions of arbitrability that implicate §2
    concerns, i.e., grounds for contract revocation. I do not need to weigh in
    on this issue in order to resolve the present case.
    4 It is a “revers[e]” presumption because it is counter to the presump
    tion we usually apply in favor of arbitration when the question con
    cerns whether a particular dispute falls within the scope of a conced
    edly binding arbitration agreement. First Options, 
    514 U. S., at
    944–
    945.
    5 In First Options we found no clear and unmistakable assent to dele
    gate to the arbitrator questions of arbitrability, given the parties’
    Cite as: 561 U. S. ____ (2010)                  5
    STEVENS, J., dissenting
    is urged in this case, an express agreement to do so. In
    any event, whether such evidence exists is a matter for the
    court to determine.
    The second line of cases bearing on who decides the
    validity of an arbitration agreement, as the Court ex
    plains, involves the Prima Paint rule. See ante, at 6. That
    rule recognizes two types of validity challenges. One type
    challenges the validity of the arbitration agreement itself,
    on a ground arising from an infirmity in that agreement.
    The other challenges the validity of the arbitration agree
    ment tangentially—via a claim that the entire contract (of
    which the arbitration agreement is but a part) is invalid
    for some reason. See Buckeye, 
    546 U. S., at 444
    . Under
    Prima Paint, a challenge of the first type goes to the court;
    a challenge of the second type goes to the arbitrator. See
    
    388 U. S., at
    403–404; see also Buckeye, 
    546 U. S., at
    444–
    445. The Prima Paint rule is akin to a pleading standard,
    whereby a party seeking to challenge the validity of an
    arbitration agreement must expressly say so in order to
    get his dispute into court.
    In sum, questions related to the validity of an arbitra
    tion agreement are usually matters for a court to resolve
    before it refers a dispute to arbitration. But questions of
    arbitrability may go to the arbitrator in two instances: (1)
    when the parties have demonstrated, clearly and unmis
    takably, that it is their intent to do so; or (2) when the
    validity of an arbitration agreement depends exclusively
    on the validity of the substantive contract of which it is a
    part.
    II
    We might have resolved this case by simply applying the
    ——————
    conduct. Respondents in that case had participated in the arbitration,
    but only to object to proceeding in arbitration and to challenge the
    arbitrators’ jurisdiction. That kind of participation—in protest, to
    preserve legal claims—did not constitute unmistakable assent to be
    bound by the result. 
    Id.,
     at 946–947.
    6            RENT-A-CENTER, WEST, INC. v. JACKSON
    STEVENS, J., dissenting
    First Options rule: Does the arbitration agreement at
    issue “clearly and unmistakably” evince petitioner’s and
    respondent’s intent to submit questions of arbitrability to
    the arbitrator?6 The answer to that question is no. Re
    spondent’s claim that the arbitration agreement is uncon
    scionable undermines any suggestion that he “clearly” and
    “unmistakably” assented to submit questions of arbitrabil
    ity to the arbitrator. See Restatement (Second) of Con
    tracts §208, Comment d (1979) (“[G]ross inequality of
    bargaining power, together with terms unreasonably
    favorable to the stronger party, may confirm indications
    that the transaction involved elements of deception or
    compulsion, or may show that the weaker party had no
    meaningful choice, no real alternative, or did not in fact
    assent or appear to assent to the unfair terms”); American
    Airlines, Inc. v. Wolens, 
    513 U. S. 219
    , 249 (1995)
    (O’Connor, J., concurring in judgment and dissenting in
    part) (“[A] determination that a contract is ‘unconscion
    able’ may in fact be a determination that one party did not
    intend to agree to the terms of the contract”).7 The fact
    ——————
    6 Respondenthas challenged whether he “meaningfully agreed to the
    terms of the form Agreement to Arbitrate, which he contends is proce
    durally and substantively unconscionable.” 
    581 F. 3d 912
    , 917 (CA9
    2009). Even if First Options relates only to “manifestations of intent,”
    as the Court states, see ante, at 5–6, n. 1 (emphasis deleted), whether
    there has been meaningful agreement surely bears some relation to
    whether one party has manifested intent to be bound to an agreement.
    7 The question of unconscionability in this case is one of state law.
    See, e.g., Perry v. Thomas, 
    482 U. S. 483
    , 492, n. 9 (1987). Under
    Nevada law, unconscionability requires a showing of “ ‘both procedural
    and substantive unconscionability,’ ” but “less evidence of substantive
    unconscionability is required in cases involving great procedural
    unconscionability.” D. R. Horton, Inc. v. Green, 
    120 Nev. 549
    , 553–554,
    
    96 P. 3d 1159
    , 1162 (2004). I understand respondent to have claimed,
    in accord with Nevada law, that the arbitration agreement contained
    substantively unconscionable provisions, and was also the product of
    procedural unconscionability as a whole. See Brief for Respondent 3
    (“[Respondent] argued that the clause is procedurally unconscionable
    Cite as: 561 U. S. ____ (2010)                      7
    STEVENS, J., dissenting
    that the agreement’s “delegation” provision suggests
    assent is beside the point, because the gravamen of re
    spondent’s claim is that he never consented to the terms in
    his agreement.
    In other words, when a party raises a good-faith validity
    challenge to the arbitration agreement itself, that issue
    must be resolved before a court can say that he clearly and
    unmistakably intended to arbitrate that very validity
    question. This case well illustrates the point: If respon
    dent’s unconscionability claim is correct—i.e., if the terms
    of the agreement are so one-sided and the process of its
    making so unfair—it would contravene the existence of
    clear and unmistakable assent to arbitrate the very ques
    tion petitioner now seeks to arbitrate. Accordingly, it is
    necessary for the court to resolve the merits of respon
    dent’s unconscionability claim in order to decide whether
    the parties have a valid arbitration agreement under §2.
    Otherwise, that section’s preservation of revocation issues
    for the Court would be meaningless.
    This is, in essence, how I understand the Court of Ap
    peals to have decided the issue below. See 
    581 F. 3d 912
    ,
    917 (CA9 2009) (“[W]e hold that where, as here, a party
    challenges an arbitration agreement as unconscionable,
    and thus asserts that he could not meaningfully assent to
    ——————
    because he was in a position of unequal bargaining power when it was
    imposed as a condition of employment”); 
    id.,
     at 3–4 (identifying three
    distinct provisions of the agreement that were substantively uncon
    scionable); accord, 
    581 F. 3d, at 917
    .
    Some of respondent’s arguments, however, could be understood as
    attacks not on the enforceability of the agreement as a whole but
    merely on the fairness of individual contract terms. Such term-specific
    challenges would generally be for the arbitrator to resolve (at least so
    long as they do not go to the identity of the arbitrator or the ability of a
    party to initiate arbitration). Cf. Restatement (Second) of Contracts
    §208 (1979) (providing that “a contract or term thereof [may be] uncon
    scionable” and that in the latter case “the remainder of the contract
    without the unconscionable term” may be enforced).
    8            RENT-A-CENTER, WEST, INC. v. JACKSON
    STEVENS, J., dissenting
    the agreement, the threshold question of unconscionability
    is for the court”). I would therefore affirm its judgment,
    leaving, as it did, the merits of respondent’s unconscion
    ability claim for the District Court to resolve on remand.
    III
    Rather than apply First Options, the Court takes us
    down a different path, one neither briefed by the parties
    nor relied upon by the Court of Appeals. In applying
    Prima Paint, the Court has unwisely extended a “fantas
    tic” and likely erroneous decision. 
    388 U. S., at 407
    (Black, J., dissenting).8
    As explained at the outset, see supra, at 3–7, this case
    lies at a seeming crossroads in our arbitration jurispru
    dence. It implicates cases such as First Options, which
    address whether the parties intended to delegate ques
    tions of arbitrability, and also those cases, such as Prima
    Paint, which address the severability of a presumptively
    valid arbitration agreement from a potentially invalid
    contract. The question of “Who decides?”—arbitrator or
    court—animates both lines of cases, but they are driven by
    different concerns. In cases like First Options, we are
    concerned with the parties’ intentions. In cases like Prima
    Paint, we are concerned with how the parties challenge
    the validity of the agreement.
    Under the Prima Paint inquiry, recall, we consider
    whether the parties are actually challenging the validity
    of the arbitration agreement, or whether they are chal
    ——————
    8 Justice Black quite reasonably characterized the Court’s holding in
    Prima Paint as “fantastic,” id., at 407 (dissenting opinion), because the
    holding was, in his view, inconsistent with the text of §2 of the FAA,
    
    388 U. S., at 412
    , as well as the intent of the draftsmen of the legisla
    tion, 
    id.,
     at 413–416. Nevertheless, the narrow holding in that case has
    been followed numerous times, see Buckeye Check Cashing, Inc. v.
    Cardegna, 
    546 U. S. 440
     (2006), and Preston v. Ferrer, 
    552 U. S. 346
    (2008), and, as the Court correctly notes today, neither party has asked
    us to revisit those cases, ante, at 6.
    Cite as: 561 U. S. ____ (2010)             9
    STEVENS, J., dissenting
    lenging, more generally, the contract within which an
    arbitration clause is nested. In the latter circumstance,
    we assume there is no infirmity per se with the arbitration
    agreement, i.e., there are no grounds for revocation of the
    arbitration agreement itself under §2 of the FAA. Accord
    ingly, we commit the parties’ general contract dispute to
    the arbitrator, as agreed.
    The claim in Prima Paint was that one party would not
    have agreed to contract with the other for services had it
    known the second party was insolvent (a fact known but
    not disclosed at the time of contracting). 
    388 U. S., at 398
    .
    There was, therefore, allegedly fraud in the inducement of
    the contract—a contract which also delegated disputes to
    an arbitrator. Despite the fact that the claim raised would
    have, if successful, rendered the embedded arbitration
    clause void, the Court held that the merits of the dispute
    were for the arbitrator, so long as the claim of “fraud in
    the inducement” did not go to validity of “the arbitration
    clause itself.” 
    Id., at 403
     (emphasis added). Because, in
    Prima Paint, “no claim ha[d] been advanced by Prima
    Paint that [respondent] fraudulently induced it to enter
    into the agreement to arbitrate,” and because the arbitra
    tion agreement was broad enough to cover the dispute, the
    arbitration agreement was enforceable with respect to the
    controversy at hand. 
    Id., at 406
    .
    The Prima Paint rule has been denominated as one
    related to severability. Our opinion in Buckeye, set out
    these guidelines:
    “First, as a matter of substantive federal arbitration
    law, an arbitration provision is severable from the
    remainder of the contract. Second, unless the chal
    lenge is to the arbitration clause itself, the issue of the
    contract’s validity is considered by the arbitrator in
    the first instance.” 
    546 U. S., at
    445–446.
    Whether the general contract defense renders the entire
    10          RENT-A-CENTER, WEST, INC. v. JACKSON
    STEVENS, J., dissenting
    agreement void or voidable is irrelevant. 
    Id., at 446
    . All
    that matters is whether the party seeking to present the
    issue to a court has brought a “discrete challenge,” Preston
    v. Ferrer, 
    552 U. S. 346
    , 354 (2008), “to the validity of the
    . . . arbitration clause.” Buckeye, 
    546 U. S., at 449
    .
    Prima Paint and its progeny allow a court to pluck from
    a potentially invalid contract a potentially valid arbitra
    tion agreement. Today the Court adds a new layer of
    severability—something akin to Russian nesting dolls—
    into the mix: Courts may now pluck from a potentially
    invalid arbitration agreement even narrower provisions
    that refer particular arbitrability disputes to an arbitra
    tor. See ante, at 6–7. I do not think an agreement to
    arbitrate can ever manifest a clear and unmistakable
    intent to arbitrate its own validity. But even assuming
    otherwise, I certainly would not hold that the Prima Paint
    rule extends this far.
    In my view, a general revocation challenge to a stand
    alone arbitration agreement is, invariably, a challenge to
    the “ ‘making’ ” of the arbitration agreement itself, Prima
    Paint, 
    388 U. S., at 403
    , and therefore, under Prima Paint,
    must be decided by the court. A claim of procedural un
    conscionability aims to undermine the formation of the
    arbitration agreement, much like a claim of unconscion
    ability aims to undermine the clear-and-unmistakable
    intent requirement necessary for a valid delegation of a
    “discrete” challenge to the validity of the arbitration agree
    ment itself, Preston, 552 U. S., at 354. Moreover, because
    we are dealing in this case with a challenge to an inde
    pendently executed arbitration agreement—rather than a
    clause contained in a contract related to another subject
    matter—any challenge to the contract itself is also, neces
    sarily, a challenge to the arbitration agreement.9 They are
    ——————
    9 As respondent asserted in his opposition to petitioner’s motion to
    compel arbitration, “the lack of mutuality regarding the type of claims
    Cite as: 561 U. S. ____ (2010)                   11
    STEVENS, J., dissenting
    one and the same.
    The Court, however, reads the delegation clause as a
    distinct mini-arbitration agreement divisible from the
    contract in which it resides—which just so happens also to
    be an arbitration agreement. Ante, at 6–7. Although the
    Court simply declares that it “makes no difference” that
    the underlying subject matter of the agreement is itself an
    arbitration agreement, ante, at 7, that proposition does not
    follow from—rather it is at odds with—Prima Paint’s
    severability rule.
    Had the parties in this case executed only one contract,
    on two sheets of paper—one sheet with employment
    terms, and a second with arbitration terms—the contract
    would look much like the one in Buckeye. There would be
    some substantive terms, followed by some arbitration
    terms, including what we now call a delegation clause—
    i.e., a sentence or two assigning to the arbitrator any
    disputes related to the validity of the arbitration provi
    sion. See Buckeye, 
    546 U. S., at 442
    . If respondent then
    came into court claiming that the contract was illegal as a
    whole for some reason unrelated to the arbitration provi
    sion, the Prima Paint rule would apply, and such a gen
    eral challenge to the subject matter of the contract would
    go to the arbitrator. Such a challenge would not call into
    question the making of the arbitration agreement or its
    invalidity per se.
    Before today, however, if respondent instead raised a
    challenge specific to “the validity of the agreement to
    arbitrate”—for example, that the agreement to arbitrate
    was void under state law—the challenge would have gone
    to the court. That is what Buckeye says. See 
    546 U. S., at 444
    . But the Court now declares that Prima Paint’s plead
    ——————
    that must be arbitrated, the fee provision, and the discovery provision,
    so permeate the Defendant’s arbitration agreement that it would be
    impossible to sever the offending provisions.” App. 45.
    12         RENT-A-CENTER, WEST, INC. v. JACKSON
    STEVENS, J., dissenting
    ing rule requires more: A party must lodge a challenge
    with even greater specificity than what would have satis
    fied the Prima Paint Court. A claim that an entire arbi
    tration agreement is invalid will not go to the court unless
    the party challenges the particular sentences that delegate
    such claims to the arbitrator, on some contract ground
    that is particular and unique to those sentences. See ante,
    at 8–10.
    It would seem the Court reads Prima Paint to require,
    as a matter of course, infinite layers of severability: We
    must always pluck from an arbitration agreement the
    specific delegation mechanism that would—but for present
    judicial review—commend the matter to arbitration, even
    if this delegation clause is but one sentence within one
    paragraph within a standalone agreement. And, most
    importantly, the party must identify this one sentence and
    lodge a specific challenge to its validity. Otherwise, he
    will be bound to pursue his validity claim in arbitration.
    Even if limited to separately executed arbitration
    agreements, however, such an infinite severability rule is
    divorced from the underlying rationale of Prima Paint.
    The notion that a party may be bound by an arbitration
    clause in a contract that is nevertheless invalid may be
    difficult for any lawyer—or any person—to accept, but this
    is the law of Prima Paint. It reflects a judgment that the
    “ ‘national policy favoring arbitration,’ ” Preston, 
    552 U. S., at 353
    , outweighs the interest in preserving a judicial
    forum for questions of arbitrability—but only when ques
    tions of arbitrability are bound up in an underlying dis
    pute. Prima Paint, 
    388 U. S., at 404
    . When the two are so
    bound up, there is actually no gateway matter at all: The
    question “Who decides” is the entire ball game. Were a
    court to decide the fraudulent inducement question in
    Prima Paint, in order to decide the antecedent question of
    the validity of the included arbitration agreement, then it
    would also, necessarily, decide the merits of the underly
    Cite as: 561 U. S. ____ (2010)           13
    STEVENS, J., dissenting
    ing dispute. Same, too, for the question of illegality in
    Buckeye; on its way to deciding the arbitration agree
    ment’s validity, the court would have to decide whether
    the contract was illegal, and in so doing, it would decide
    the merits of the entire dispute.
    In this case, however, resolution of the unconscionability
    question will have no bearing on the merits of the underly
    ing employment dispute. It will only, as a preliminary
    matter, resolve who should decide the merits of that dis
    pute. Resolution of the unconscionability question will,
    however, decide whether the arbitration agreement itself
    is “valid” under “such grounds as exist at law or in equity
    for the revocation of any contract.” 
    9 U. S. C. §2
    . As
    Prima Paint recognizes, the FAA commits those gateway
    matters, specific to the arbitration agreement, to the
    court. 
    388 U. S., at
    403–404. Indeed, it is clear that the
    present controversy over whether the arbitration agree
    ment is unconscionable is itself severable from the merits
    of the underlying dispute, which involves a claim of em
    ployment discrimination. This is true for all gateway
    matters, and for this reason Prima Paint has no applica
    tion in this case.
    IV
    While I may have to accept the “fantastic” holding in
    Prima Paint, 
    id., at 407
     (Black, J., dissenting), I most
    certainly do not accept the Court’s even more fantastic
    reasoning today. I would affirm the judgment of the Court
    of Appeals, and therefore respectfully dissent.
    

Document Info

Docket Number: 09-497

Citation Numbers: 177 L. Ed. 2d 403, 130 S. Ct. 2772, 561 U.S. 63, 2010 U.S. LEXIS 4981

Judges: Scalia, Roberts, Kennedy, Thomas, Alito, Stevens, Ginsburg, Breyer, Sotomayor

Filed Date: 6/21/2010

Precedential Status: Precedential

Modified Date: 10/19/2024

Cited By (556)

Eakins v. Corinthian Colleges CA4/2 ( 2015 )

OMG, L.P. v. Heritage Auctions, Inc. , 612 F. App'x 207 ( 2015 )

Wawock v. Super. Ct. CA2/5 ( 2013 )

Seldin v. Estate of Silverman , 305 Neb. 185 ( 2020 )

Citizens of Humanity v. Applied Underwriters , 299 Neb. 545 ( 2018 )

Seldin v. Estate of Silverman , 305 Neb. 185 ( 2020 )

Lp Louisville East, LLC D/B/A Signature Healthcare of East ... ( 2021 )

Nadine Kelly v. Capital Senior Living Corp ( 2021 )

BONNIE MARIE COTTRELL, ETC. VS. NATHAN HOLTZBERG, M.D (L-... ( 2021 )

Kingery Constr. Co. v. 6135 O St. Car Wash , 312 Neb. 502 ( 2022 )

Jacqueline Harris v. Volt Management Corporation ( 2021 )

District No. 1, Pacific Coast District, Marine Engineers' ... ( 2021 )

DARRYL SEELHORST VS. IMMUNOMEDICS, INC. (L-1226-20, MORRIS ... ( 2021 )

Citizens of Humanity v. Applied Underwriters , 299 Neb. 545 ( 2018 )

Seldin v. Estate of Silverman , 305 Neb. 185 ( 2020 )

Seldin v. Estate of Silverman , 305 Neb. 185 ( 2020 )

Seldin v. Estate of Silverman , 305 Neb. 185 ( 2020 )

Peter Anderson, Jr. v. Charter Comm'ns, Inc. ( 2021 )

Joseph Ciccio v. SmileDirectClub, LLC ( 2021 )

Timothy Boykin v. Family Dollar Stores of Mich. ( 2021 )

View All Citing Opinions »