Pesall v. Mdu , 871 N.W.2d 649 ( 2015 )


Menu:
  • #27324-a-SLZ
    
    2015 S.D. 81
    IN THE SUPREME COURT
    OF THE
    STATE OF SOUTH DAKOTA
    ****
    GERALD PESALL,                             Intervener and Appellant,
    v.
    MONTANA DAKOTA UTILITIES, CO.,
    OTTER TAIL POWER and
    THE SOUTH DAKOTA PUBLIC
    UTILITIES COMMISSION,                      Appellees,
    and
    SCHURING FARMS, INC. and
    BRADLEY MOREHOUSE,                         Interveners.
    ****
    APPEAL FROM THE CIRCUIT COURT OF
    THE FIFTH JUDICIAL CIRCUIT
    DAY COUNTY, SOUTH DAKOTA
    ****
    THE HONORABLE SCOTT P. MYREN
    Judge
    ****
    N. BOB PESALL
    Flandreau, South Dakota                    Attorney for intervener
    and appellant.
    ****
    CONSIDERED ON BRIEFS
    ON AUGUST 31, 2015
    OPINION FILED 11/04/15
    THOMAS J. WELK
    JASON R. SUTTON of
    Boyce Law Firm, LLP
    Sioux Falls, South Dakota                  Attorneys for appellees
    Montana Dakota Utilities Co.
    and Otter Tail Power.
    MARTY J. JACKLEY
    Attorney General
    JOHN J. SMITH
    KAREN E. CREMER
    Special Assistant Attorneys General
    South Dakota Public Utilities Commission
    Pierre, South Dakota                       Attorneys for appellee the
    South Dakota Public Utilities
    Commission.
    #27324
    ZINTER, Justice
    [¶1.]         Montana Dakota Utilities Co. and Otter Tail Power Company
    (Applicants) filed an application with the South Dakota Public Utilities Commission
    (PUC or Commission) for a permit to construct a high-voltage electrical
    transmission line. Appellant Gerald Pesall objected to the project because he was
    concerned that excavating and moving soil to construct the project might unearth
    and spread a crop parasite. The PUC granted the permit on conditions, including a
    condition to identify and mitigate the potential parasite problem. The circuit court
    affirmed. Pesall’s appeal raises two issues: whether the permit condition relating to
    the parasites constituted an improper delegation of authority to a private party;
    and, whether the PUC exceeded a twelve-month time limit for rendering complete
    findings on the application. We affirm.
    Facts and Procedural History
    [¶2.]         On August 23, 2013, Applicants applied for a permit to construct a
    345-kilovolt transmission line that would start near Ellendale, North Dakota; would
    run through Brown, Day, and Grant counties in South Dakota; and would terminate
    near Big Stone City. The construction involved the suspension of high-voltage
    electrical lines from steel monopole towers. Each tower would be approximately 120
    to 155 feet in height. The towers were to be attached to cylindrical concrete
    foundations, six to eleven feet in diameter and twenty-five to thirty feet deep.
    Construction required the removal and disposal of approximately thirty cubic yards
    of soil for each tower.
    -1-
    #27324
    [¶3.]         Applicants’ project would cross one part of Pesall’s farm. Pesall
    intervened and was granted party status. 1 In a subsequent contested-case hearing,
    Dr. Gregory Tylka, one of Pesall’s witnesses, testified about soybean cyst nematodes
    (SCNs). He testified that SCNs are soil-born parasites that can decrease soybean
    productivity in infected fields. SCNs may exist in soil at depths of six feet, and they
    may remain dormant for ten years. SCNs have been found in three of the counties
    through which the transmission line would traverse. SCNs can spread by any
    activity that moves soil. There is no dispute that the construction necessary to
    build the proposed line could spread the parasite. However, wind, water erosion,
    burns, typical farming practices, and even people walking over infected soil can also
    spread SCNs. Furthermore, there was no evidence that SCNs infected any soil
    along the project route.
    [¶4.]         Before the evidentiary hearing, Applicants and PUC staff submitted a
    proposed settlement stipulation that would subject the permit to thirty-three
    conditions. One condition addressed SCN mitigation. Condition 17 provided:
    “Applicant shall develop and implement a mitigation plan to minimize the spread of
    [SCNs] . . . in consultation with a crop pest control expert.” Pesall objected to the
    proposed condition at the evidentiary hearing.
    [¶5.]         Following the hearing, PUC staff and Applicants entered into an
    amended settlement stipulation that further addressed SCN mitigation. Pesall also
    objected to this proposal. He did not, however, propose an alternative mitigation
    1.      Other parties/landowners also intervened, but they are not parties in this
    appeal.
    -2-
    #27324
    plan. Instead, he requested that the PUC deny the permit on grounds relating to
    SCN mitigation, require the Applicants to reapply within three years, and limit the
    reconsideration to SCN mitigation. The PUC acknowledged Pesall’s concerns, but
    denied his request. The PUC found that the risk of spreading SCNs from the
    project was not a serious threat. Additionally, in rendering its final decision to
    grant the permit, the PUC modified Condition 17 to require PUC oversight of any
    required SCN mitigation. Modified Condition 17 provided:
    After Applicants have finished the soil sample field assessment
    in accordance with the specifications for such assessment
    prepared in consultation with an expert in the proper
    methodology for performing such a sampling survey, Applicants
    shall submit to the Commission a summary report of the results
    of the field assessment and Applicants’ specific mitigation plans
    for minimizing the risk of the spread of soybean cyst nematode
    from contaminated locations to uncontaminated locations. At
    such time and throughout the construction period, one or more
    Commissioners or Staff shall have the right to request of
    Applicants confidential access to the survey results to enable
    verification of the survey results, assess the appropriateness of
    the mitigation measures to address such results, and monitor
    the execution of the plan during construction.
    The PUC ultimately found that Applicants’ SCN mitigation plan, together with
    modified Condition 17, would reasonably minimize the risk of spreading SCNs. The
    PUC entered a written Final Decision and Order granting the permit subject to this
    and other conditions.
    [¶6.]        Pesall appealed to the circuit court raising six issues. The circuit court
    affirmed. Pesall now appeals to this Court raising two issues: (1) whether the PUC
    improperly delegated its authority to a private party; and (2) whether the PUC
    exceeded a statutory twelve-month time limit for issuing complete findings. Pesall’s
    arguments raise questions of law and statutory interpretation. “[Q]uestions of law,
    -3-
    #27324
    including statutory interpretation, are reviewed de novo.” In re Establishment of
    Switched Access Rates for U.S. W. Commc’ns, Inc., 
    2000 S.D. 140
    , ¶ 13, 
    618 N.W.2d 847
    , 851.
    Decision
    [¶7.]        A permit is required to construct the type of electrical transmission
    line at issue in this case. See SDCL 49-41B-4. The Legislature conferred the
    authority to grant or deny these permits on the PUC. 
    Id. [¶8.] Pesall
    first argues that the PUC should have rejected Applicants’
    application because their mitigation proposal did not state with specificity what
    Applicants would do to mitigate the spread of SCNs; what Applicants would do with
    potentially contaminated soil; and how Applicants would prevent contaminated soil
    from being transported by equipment from one field to another. Pesall argues that
    the PUC should have required Applicants to correct these alleged defects and
    reapply within three years. See SDCL 49-41B-22.1 (authorizing this procedure). 2
    2.      SDCL 49-41B-22.1 provides:
    Nothing contained herein shall prohibit an applicant from
    reapplying for a permit previously denied pursuant to § 49-41B-
    24 or 49-41B-25 within three years from the date of the denial of
    the original permit. Upon the first such reapplication, the
    applicant shall have the burden of proof to establish only those
    criteria upon which the original permit was denied, provided
    that nothing in the reapplication materially changes the
    information presented in the original application regarding
    those criteria upon which the original permit was not denied.
    However, nothing contained in this provision shall prohibit the
    Public Utilities Commission from requiring such applicant to
    meet its burden of proof as to any criteria, upon a specific
    finding by the commission of a material change in the
    circumstances regarding those criteria, but the Public Utilities
    (continued . . .)
    -4-
    #27324
    Although this was an alternative for the PUC, the PUC chose to grant the permit
    subject to SCN mitigation conditions. The Legislature expressly authorized the
    PUC’s choice, see SDCL 49-41B-24, 3 and we give “deference to PUC’s expertise and
    special knowledge in the field of electric utilities,” Matter of N. States Power Co.,
    
    489 N.W.2d 365
    , 370 (S.D. 1992). Pesall has not demonstrated an error of law or an
    abuse of discretion in the PUC’s decision to grant a conditional permit rather than
    requiring reapplication.
    [¶9.]         Pesall next argues that modified Condition 17 improperly delegated
    the PUC’s authority to a private party. Pesall relies on In re Nebraska Power
    District, 
    354 N.W.2d 713
    (S.D. 1984).
    [¶10.]        In Nebraska Power District, the Nebraska Public Power District
    (NPPD) applied for a permit to construct an electrical transmission facility. 
    Id. at 715.
    Certain affected landowners had concerns about the soil handling procedures
    to be used in the project. See 
    id. at 716.
    In response, the PUC conditioned the
    permit on a requirement that NPPD offer soil treatment options to the affected
    landowners. 
    Id. The options
    allowed the landowners to “require that NPPD utilize
    ________________________
    (. . . continued)
    Commission shall not, in any event, prepare or require the
    preparation of an environmental impact statement.
    3.       SDCL 49-41B-24 provides:
    Within twelve months of receipt of the initial application for a
    permit for the construction of energy conversion facilities,
    AC/DC conversion facilities, or transmission facilities, the
    commission shall make complete findings in rendering a
    decision regarding whether a permit should be granted, denied,
    or granted upon such terms, conditions or modifications of the
    construction, operation, or maintenance as the commission
    deems appropriate.
    -5-
    #27324
    other specified topsoil preservation procedures on their land.” 
    Id. We concluded,
    “SDCL 49-41B-24 dictates that the PUC is the only body which can impose terms
    and conditions. Because no other statute expressly states that landowners can
    dictate topsoil restoration conditions, the PUC had unlawfully delegated its
    authority.” 
    Id. at 719.
    [¶11.]         Nebraska Power District does not, however, apply in this case. In
    Nebraska Power District, the private parties “could, if they desired, require that
    NPPD utilize other specified topsoil preservation procedures on their land.” 
    Id. at 716.
    We acknowledge that the PUC specified other procedures. Nevertheless, this
    Court characterized the topsoil restoration program as a matter involving private
    party “choice.” 
    Id. at 720.
    In this case, the Applicants may not choose the
    mitigation procedure because the PUC retained oversight authority to make the
    ultimate decision. Consequently, Nebraska Power District is no support for the
    proposition that the PUC delegated its authority to the Applicants. 4
    [¶12.]         On the contrary, the permit and the PUC’s modifications of Condition
    17 reflect that the PUC retained its authority to make the ultimate decision
    regarding SCN mitigation. There is no dispute that the PUC itself granted the
    permit and imposed the mitigation conditions. Concededly, modified Condition 17
    does not include a specific mitigation plan, but the condition requires Applicants to
    4.       Pesall also relies on two federal cases. See Ass’n of Am. R.Rs. v. U.S. Dep’t of
    Transp., 
    721 F.3d 666
    (D.C. Cir. 2013), vacated on other grounds sub nom.
    Dep’t of Transp. v. Ass’n of Am. R.Rs., ___ U.S. ___, 
    135 S. Ct. 1225
    , 191 L.
    Ed. 2d 153 (2015); and Carter v. Carter Coal Co., 
    298 U.S. 238
    , 269, 
    56 S. Ct. 855
    , 858, 
    80 L. Ed. 1160
    (1936). These cases are inapposite because they
    involved private actors exercising regulatory authority over other private
    actors.
    -6-
    #27324
    conduct a field assessment to determine if SCNs contaminate the soil. Additionally,
    Applicants must consult an expert to ensure their field assessment follows a proper
    methodology. Then, the permit condition requires Applicants to submit the field
    assessment and a specific mitigation plan to the PUC for a sufficiency review.
    Finally, under the permit condition, the PUC must verify the survey results, assess
    the appropriateness of the mitigation measures, and monitor execution of the
    mitigation plan during construction. Thus, although the PUC did not specify a
    precise pre-construction mitigation plan, if SCNs are encountered during
    construction, Applicants do not have the ultimate authority to choose the final
    mitigation plan. Modified Condition 17 requires the PUC to oversee and determine
    the actual mitigation requirements in light of the variables that will be encountered
    in construction. 5 As the PUC indicated in its findings of fact, Condition 17 was
    modified to provide “clarity concerning exactly what process [Applicants] would
    follow in the SCN soil assessment[,] . . . mitigation plan development[,] [mitigation
    plan] execution[,] and [the PUC’s] ability to verify and exercise its oversite authority
    over the development and execution during construction.” (Emphasis added.) We
    5.    Applicants’ mitigation plan explained the dilemma:
    Mitigating the spread of SCN from an existing affected field to a
    non-SCN affected field, a variety of measures may be utilized,
    which are dependent on soil conditions, weather conditions,
    topography, distance traveled, equipment type, and cost.
    Unfortunately, one mitigation measure alone is not a “catch-all”
    and will be determined on a site-specific basis. Measures to
    assist in the control of soils on equipment may include: cleaning
    stations, utilizing clean crews for non-affected fields and a dirty
    crew for affected fields, equipment mats, and weather-
    dependent construction (i.e. frozen and dry soils). The measures
    ultimately used will depend on the results of the sampling effort,
    cost, resource availability, and contractor input.
    -7-
    #27324
    conclude that modified Condition 17 did not delegate the PUC’s authority to the
    Applicants. 6
    [¶13.]          Pesall also argues that the PUC did not issue complete findings on the
    permit within twelve months as required by SDCL 49-41B-24. Pesall points out
    that the PUC did not order a specific mitigation plan within a year after the
    application was filed. Pesall contends that the PUC lacks authority to act after that
    twelve-month deadline. The implication is that SDCL 49-41B-24 was violated
    because the PUC made no specific finding on the ultimate mitigation plan that
    would be implemented.
    [¶14.]          Applicants filed their application on August 23, 2013. On August 22,
    2014, the PUC issued its Final Decision and Order. Detailed findings and modified
    Condition 17 were included in the Final Decision and Order. Therefore, the PUC
    timely rendered a decision granting the permit on conditions and included detailed
    findings. We acknowledge Pesall’s point that specific mitigation plans are not
    included: modified Condition 17 contemplates future action after the one-year
    deadline. However, as previously noted, the future action involves PUC
    enforcement of modified Condition 17. The fact that the PUC retained jurisdiction
    to enforce its conditions does not mean they failed to render complete findings on
    the permit. SDCL 49-41B-33 authorizes future enforcement of conditions: “A
    permit may be revoked or suspended by [the PUC] for . . . [f]ailure to comply with
    the terms or conditions of the permit[.]” See also In re Otter Tail Power Co. ex rel.
    6.       Pesall also advances three policy considerations for not allowing the PUC to
    delegate its authority. We do not address those concerns because the PUC
    did not unlawfully delegate authority to a private party.
    -8-
    #27324
    Big Stone II, 
    2008 S.D. 5
    , ¶ 33, 
    744 N.W.2d 594
    , 604 (upholding a similar forward-
    looking enforcement provision in a case where the permit required “that the
    Applicants submit annual reviews of any regulations on CO2 emissions and their
    efforts to comply with those regulations”). Enforcement of conditions is often
    necessary in these types of cases. Pesall’s contrary suggestion is unsupported by
    the nature of the project and the PUC’s statutory authority.
    [¶15.]       The PUC did not delegate its regulatory authority to Applicants, and
    the PUC timely rendered complete findings on the permit application. We affirm.
    [¶16.]       GILBERTSON, Chief Justice, and SEVERSON, WILBUR, and KERN,
    Justices, concur.
    -9-