Casper Lodging, LLC v. Akers ( 2015 )


Menu:
  • #27074-aff in pt, rev in pt & rem-JMK
    
    2015 S.D. 80
    IN THE SUPREME COURT
    OF THE
    STATE OF SOUTH DAKOTA
    ****
    CASPER LODGING, LLC,                           Plaintiff and Appellee,
    v.
    ROBERT W. AKERS,                               Defendant, Third-Party
    Plaintiff and Appellant,
    v.
    ZAKCO COMMERCIAL
    CONSULTANTS, INC.,
    ABEL DELGADO, DONALD E. DELZER,
    DUSTY GRAY, KYLE HAGEN,
    PAUL LANDE, JR., JAMES C. HOYT,
    KEN PREISLER, SANDRA PREISLER,
    JOA SASSER, DEAN SHOELL,
    ANGIE SHOELL, BINSWANGER
    ENTERPRISES, LLC, MCCALL
    POOLS, INC., MOORE
    INSULATION, INC. and SHEET
    METAL SPECIALTIES, INC.,                       Third-Party Defendants.
    ****
    APPEAL FROM THE CIRCUIT COURT OF
    THE SEVENTH JUDICIAL CIRCUIT
    PENNINGTON COUNTY, SOUTH DAKOTA
    ****
    THE HONORABLE WALLY EKLUND
    Judge
    ****
    ARGUED ON MARCH 24, 2015
    OPINION FILED 10/28/15
    GREGORY J. ERLANDSON
    SARAH E. BARON HOUY
    TERRY L. HOFER of
    Bangs, McCullen, Butler,
    Foye & Simmons, LLP
    Rapid City, South Dakota    Attorneys for plaintiff
    and appellee.
    MITCHELL PETERSON
    ANTHONY M. HOHN of
    Davenport, Evans, Hurwitz
    & Smith, LLP
    Sioux Falls, South Dakota   Attorneys for defendant, third-
    party plaintiff and appellant.
    #27074
    KERN, Justice
    [¶1.]        In this breach of contract case, the jury found in favor of Casper
    Lodging, LLC, concluding that Robert Akers failed to deliver to James Koehler a
    Holiday Inn Express in compliance with the parties’ agreements. The jury awarded
    Casper Lodging $1,019,468.74. Prior to the verdict, the parties had stipulated that
    the circuit court would determine the date on which prejudgment interest would
    begin to accrue if there was a plaintiff’s verdict. Upon receipt of the verdict, the
    court declared that prejudgment interest accrued, as a matter of law, from the date
    of the delivery of the completed Hotel and awarded plaintiff $997,682.83 in
    prejudgment interest. The court further awarded plaintiff post-judgment interest
    on the combined sum of the jury verdict and the prejudgment interest calculation.
    In multiple post-trial motions, Akers asserted that the circuit court made erroneous
    evidentiary rulings and failed to correctly instruct the jury. Akers claimed that the
    errors warranted reversal of the jury’s verdict and a new trial. The court denied
    Akers’s motions and Akers appeals. We reverse the circuit court’s calculation of
    prejudgment interest and remand for the court to make a factual determination as
    to the date the loss on which prejudgment interest shall begin to accrue. We affirm
    on all remaining issues.
    BACKGROUND
    [¶2.]        On October 15, 2003, Robert Akers agreed to sell to James Koehler a
    “turn key Eighty-Four (84) unit Holiday Inn Express” in Casper, Wyoming. The
    purchase price was set at $4,850,400. The hotel was not yet built; therefore, the
    parties executed a contract entitled “Improvement Purchase Agreement”
    -1-
    #27074
    (Agreement). The Agreement “set forth the terms and conditions under which
    [Akers] agree[d] to sell to [Koehler] the improvements [Akers] is constructing[.]” In
    particular, Akers was to build the improvements “pursuant to the plans and
    specifications prepared by Associated Architects, Ltd. . . . and the improvements”
    were to be “constructed by Zakco Commercial Consultants, Inc.,” the general
    contractor.
    [¶3.]         The Agreement contained eight conditions precedent, “any of which
    may be waived by the buyer at any time[.]” One condition provided that Akers
    “must complete the construction of the improvements in a manner acceptable to
    [Koehler] in [Koehler’s] reasonably exercised judgment.” Another condition
    required Akers to “complete the construction of the improvements in compliance
    with all city, county, state, and federal government requirements; government
    approvals, if any, shall be provided to [Koehler] prior to closing.” Koehler was
    required, “[o]n a date prior to closing,” to obtain “the approval from the Holiday Inn
    Express system that the Hotel complies with all systems requirements and can be
    opened for business.”
    [¶4.]         The Agreement identified that Akers and Koehler “have been
    negotiating this agreement for at least six months.” The estimated completion date
    was set at the “end of 2003 of [sic] the beginning of 2004.” Koehler had a right to
    monitor the construction of the Hotel, but could “not make changes to any of
    [Akers’s] contracts unless the terms and conditions of this agreement [were]
    complied with.” Akers represented to Koehler that “he will transfer all warranties
    that are transferable by [him] to [Koehler] at closing[.]”
    -2-
    #27074
    [¶5.]        On January 16, 2004, Akers and Koehler executed an Addendum to the
    Agreement. The Addendum accelerated the purchase date to facilitate Koehler’s
    involvement in a 1031 tax-free exchange, with which Akers had previously agreed
    to cooperate. The Addendum acknowledged that construction of the Hotel “will not
    be completed in January, 2004, and it is not known when the [Hotel] will be
    completed,” and Koehler “must close the transaction, before the completion of the
    Improvements[.]” The parties incorporated the Addendum into the Agreement and
    provided that Akers “shall have a continuing obligation to construct and finish the
    Improvements in accordance with all governmental requirements and the standards
    and specifications of the Holiday Inn Express system.”
    [¶6.]        On February 5, 2004, Akers and Koehler closed on the sale and, on
    March 11, 2004, Koehler opened the Hotel. Koehler assigned his rights under the
    agreements to Casper Lodging, LLC, and Casper Lodging entered into a
    management agreement with The Koehler Organization (TKO) to staff, operate, and
    maintain the Hotel. Almost immediately after opening the Hotel, guests began
    complaining about the noise level from accompanying rooms, and Casper noticed
    issues with sound proofing. Koehler claimed that he informed Akers of the sound
    issue, to no avail. Ultimately, TKO hired Ernie Cuthbertson to facilitate the repair
    of the sound issue, which involved taking off sheetrock throughout the rooms and
    ceilings and installing soundboard. Casper also claimed that within the first six
    months it began to notice problems with water penetrating the Hotel’s exterior.
    Casper addressed the problems in-house by replacing moist sheetrock, repainting
    walls, and applying caulk to some windows.
    -3-
    #27074
    [¶7.]        Although the sound issue was remedied, Casper claimed that problems
    persisted with the poolroom and with water penetration in the guest rooms. In
    2007, TKO hired John Farr of Wiss, Janney, Elstner Associates, Inc. to inspect the
    poolroom and issue a report. Farr issued his report in late 2007. No formal steps
    were taken by Casper as a result of Farr’s report, although Koehler testified that he
    was in constant contact with Akers about the problems. Casper continued to
    address the problems in-house by using its maintenance staff to make repairs.
    Casper also hired certain outside professionals to assist.
    [¶8.]        In 2009, Koehler contacted Wendell Potratz of Pro Group to renovate
    the Hotel’s lighting and color in order to make the Hotel match the current Holiday
    Inn Express aesthetics. Casper also directed Potratz to address the moisture issues
    in the poolroom. Potratz was aware that Farr issued a report in 2007 concerning
    the poolroom. Potratz enlisted the help of Farr to assess the current state of the
    poolroom. Potratz’s original contract covered renovating the Hotel and repairing
    the issues in the poolroom. However, Potratz amended that contract after the
    project started because he and his team noticed additional concerns throughout the
    Hotel. Ultimately, Potratz’s contract price for the upgrade and repairs was
    $1,133,913.30, of which he related $802,383 to problems with the building’s original
    construction. The repairs, renovations, and upgrades were accomplished between
    2009 and 2010.
    [¶9.]        In October 2009, Casper brought suit against Akers for breach of
    contract. Casper alleged that Akers failed to provide an 84-unit turn-key Holiday
    Inn Express that met all city, county, state, and federal government requirements.
    -4-
    #27074
    Casper further claimed that Akers failed to build the Hotel in compliance with the
    controlling plans and specifications. Akers answered the complaint and asserted
    the affirmative defenses of failure to mitigate damages and waiver. After extensive
    discovery between the parties, Akers moved the circuit court to amend his answer to
    assert a third-party complaint against multiple subcontractors. The circuit court
    granted the motion over Casper’s objection, and Akers named fifteen additional
    parties. The parties stipulated to a trial date of August 2012, which was continued
    to February 2013, and continued again to December 2013, constituting a delay of
    sixteen months.
    [¶10.]       On July 23, 2013, five months prior to trial, Akers again moved the
    circuit court to amend his third-party complaint to add a claim against TKO and
    asked that TKO be joined as an indispensable party under SDCL 15-6-19(a). The
    court denied Akers’s motions. Ultimately, Akers settled his claims against certain
    third-party contractors and his claim against the general contractor was bifurcated.
    [¶11.]       A ten-day jury trial on Casper’s claim against Akers was held in
    December 2013. Koehler and Akers testified about the Agreement and Addendum.
    Koehler described the extensive construction defects in the building and what
    actions he took to remedy the problems. Koehler also testified about his efforts to
    exercise any alleged warranty rights. James Hopkins, the maintenance person
    employed by the Hotel, testified about the actions he and Casper took to address the
    poolroom problems. Tom Pogroszewski, the Hotel supervisor, reiterated the
    measures Hopkins and Casper took to remedy the problems with the Hotel. Doug
    Vogt, the general manager for TKO, testified that TKO hired Ernie Cuthbertson to
    -5-
    #27074
    repair the sound issues, at a cost between $200,000 and $250,000. Vogt also
    testified that, although Farr was hired in 2007 to evaluate the poolroom problems,
    TKO and Casper did not act on that report.
    [¶12.]       Both parties presented expert testimony about the condition of the
    Hotel on the date Koehler took possession, identifying the problems that occurred
    and the cause of the defects. Dave Stafford, an architect and expert for Casper,
    testified about the plans and specifications governing the construction of the Hotel
    under the parties’ Agreement and Addendum. He opined that the plans and
    specifications did not properly provide that the wall and floor assembly must meet a
    certain soundness level.
    [¶13.]       Ryan Pace was in charge of the day-to-day repairs and renovations
    undertaken by Potratz, which took nearly a year to complete. He testified in detail
    about the problems he observed, the reasons for them, and the steps taken to rectify
    the damage. Pace explained that in order to make the repairs, it was necessary to
    remove the exterior stucco on portions of the building and strip it down to the
    oriented standard boards (OSB). The OSB are a veneered waferboard similar to
    sheets of plywood. He described problems including: the insulation and studs were
    damaged in the poolroom due to moisture, 90% of the walls did not have the
    required vapor barrier to prevent moisture from the outside getting to the inside,
    some of the anchor bolts were deficient, all of the air conditioning units were
    installed without caulk or seal, and the studs had a lot of “mis-nails.” Pace testified
    that in order to properly secure the structure it took two laborers three full days
    and 25,000 additional nails to re-nail the exterior of the building. He further
    -6-
    #27074
    indicated that the doors and windows were installed without the necessary flashing
    or weatherproofing barriers, which caused water penetration problems throughout
    the Hotel. He testified that to renovate the poolroom, they had to replace certain
    windows, repair the ceiling, and increase the air handler in the poolroom to reduce
    condensation. Additionally, he testified that portions of the roof were too short and
    the entire roof needed a new drip edge and ice and water shield.
    [¶14.]       Trent Nelson, a structural engineer hired by Potratz to conduct a site
    inspection of the building, opined that the building did not comply with the 1997
    Uniform Building Code. Specifically, he testified that the structure of the building
    was lost and was not to code because the studs rotted in response to moisture. He
    further opined (over Akers’s objection) that the building was structurally unsafe at
    the time of construction. Nelson based this opinion in part on Pace’s previous
    testimony that 25,000 additional nails had to be used to ensure a proper nailing
    pattern. Nelson also explained that the poolroom should have contained shear
    walls made up of “studs, properly attached sheathing, and anchors[,]” and that all
    three must be properly installed to make the structure sound. He testified that the
    OSB were not properly fastened to the wall by mechanical anchors or hold-downs.
    Because the OSB were not properly fastened, Nelson opined that the “portion of the
    intended shear wall in that pool structure” was rendered “useless” and unsafe. He
    also observed that the exterior grade in front of the building at ground level was
    about a foot higher than the floor inside. He attributed this to the fact that “there
    may have been some cultured stone or stucco on the outside” and “typical wood stud
    framing, non-treated lumber, OSB sheathing” on the inside. According to Nelson,
    -7-
    #27074
    “code requires that any untreated wood needs to be a minimum of 6 inches above
    the exterior finish grade.” Because “non-treated wood noncompliant with the code
    had been placed below grade basically along” the front portion of the Hotel, Nelson
    opined that “over time [it] would likely deteriorate.”
    [¶15.]       Akers moved for a mistrial after the cross-examination of Nelson,
    asserting that Nelson testified to a previously undisclosed expert opinion and that
    Nelson’s testimony prejudiced Akers. On cross-examination, Nelson admitted that
    his opinion that the building was unsound from day one was made for the first time
    at trial and was formed in response to Pace’s trial testimony that the nailing
    pattern was inadequate. The court, disturbed by the new opinion, took a short
    break to consider the motion for a mistrial. Akers then requested that the court
    strike Nelson’s testimony and admonish the jury. The court granted Akers’s
    request and admonished the jury immediately after the break. The court had also
    directed Akers that it would admonish the jury again at the end of trial. (At the end
    of trial, Akers did not request the second admonishment and none was given.)
    [¶16.]       Loren Schoeneman testified next. Potratz had hired Schoeneman to
    address the dehumidification issues in the poolroom. Schoeneman, a mechanical
    engineer, testified that the dehumidification system was deficient and any improper
    or inadequate maintenance measures taken by Casper were immaterial. He then
    explained the reasons for his opinion and what actions were needed to rectify the
    problem.
    [¶17.]       Potratz, as the person hired to oversee the renovations and repairs,
    testified about the scope of the repairs undertaken. He explained that he assessed
    -8-
    #27074
    the needed repairs against code requirements and concluded that the Hotel was not
    delivered to Koehler in accordance with the required plans and specifications. He
    also testified to each expense incurred in relation to the type of repair necessary and
    used as a reference Casper’s damages summary prepared pursuant to now-
    renumbered SDCL 19-19-1006 (Rule 1006). 1 He opined that $1,019,468.74 was a
    reasonable and necessary amount to fix the Hotel’s problems.
    [¶18.]         In response to Potratz’s opinion regarding damages, Akers sought to
    admit the rebuttal opinion of its expert Merl Potter. Potter is a construction
    manager and had given two depositions in preparation for the case. Prior to
    Potter’s testimony at trial, Casper moved in limine to prevent Potter from testifying
    specifically in regard to Casper’s Rule 1006 damages summary. Casper argued that
    Potter did not, in either deposition, express an opinion related to Casper’s specific
    damages and, therefore, any opinion by Potter on Casper’s damages would be new
    and previously undisclosed. Akers responded that he had previously identified
    Potter as an expert on damages. He further claimed that Potter’s testimony was
    not a new opinion, but instead, was to be given in rebuttal to the testimony of
    Potratz. Akers further claimed that Casper only recently issued its Rule 1006
    damages summary. The court indicated it would reserve its ruling; however, during
    Potter’s testimony the court prevented Potter from testifying specifically to Casper’s
    claimed damages. Akers made an offer of proof following Potter’s testimony.
    1.       The Code Commission, at the direction of the Supreme Court, renumbered
    the sections in SDCL chapters 19-9 to 19-13, inclusive, and 19-14 to 19-18.
    Although SDCL 19-18-6 (Rule 1006) has been renumbered to SDCL 19-19-
    1006, the previous code section is cited in this opinion.
    -9-
    #27074
    [¶19.]       Despite being precluded from testifying in specific reference to the
    damages Casper incurred, Potter did testify about the unsatisfactory efforts Casper
    undertook to remedy the deficiencies in the building and thereby mitigate its
    damages. In particular, Potter explained that Casper’s failure to take immediate
    action to repair known issues exacerbated the damage to the Hotel. Potter further
    testified that even though there were problems with the dehumidification system
    from day one and the PTAC (packaged terminal air conditioner) units were sloped
    incorrectly and improperly sealed, Casper failed to timely identify and remedy these
    issues. In regard to the sound issue, Potter asserted that it was unreasonable for
    Casper to engage in the repair work before addressing other issues that could have
    contributed to the problem. Potter admitted that the windows were likely installed
    incorrectly, but claimed that the problems should have been noticed before the
    stucco went on and addressed in a different manner. He further testified that it
    was unreasonable to repair the water damage by cutting out wet drywall, air drying
    it, replacing it, and painting it. Finally, in Potter’s expert opinion, Casper sat on its
    warranty rights when it failed to conduct the one-year warranty walk through and
    when it failed to exercise and enforce its warranty rights as problems arose.
    [¶20.]       At the close of the case, Akers moved for a directed verdict—now called
    a judgment as a matter of law. Akers argued that Casper failed to meet its burden
    of proof on damages because Casper did not present evidence on both the cost of
    repair and the diminution in value measures of damages. Akers further claimed
    that he did not breach the parties’ contract as a matter of law because Casper failed
    to identify any provision in the Agreement or Addendum that Akers breached.
    -10-
    #27074
    Further, Akers argued that because Casper failed to pursue certain warranty
    rights, Casper waived its right to seek relief. Finally, Akers asserted that Casper
    failed to mitigate its damages as a matter of law when it waited until 2009 to
    address the issues with the Hotel. The court denied Akers’s motion for a judgement
    as a matter of law.
    [¶21.]       During the settling of jury instructions, Akers objected to the court’s
    instruction on damages. Instruction 47 provided:
    If you decide for Casper Lodging on the question of liability, you
    must then fix the amount of money which will reasonably and
    fairly compensate Casper Lodging for any elements of loss
    suffered, proved by the evidence to have been legally caused by
    Akers’ conduct, taking into consideration the nature, extent, and
    duration of the damages, whether such loss could have been
    anticipated or not, namely:
    The reasonable expense of necessary repairs to the damaged
    property.
    Whether any elements of damages have been proved by the
    evidence is for you to determine. Your verdict must be based on
    evidence and not upon speculation, guesswork, or conjecture.
    Akers claimed that the proper measure of damages was the lesser of the diminution
    in value and the cost of repairs. The court overruled the objection because, in its
    view, diminution in value would only come into play when there is an issue whether
    the building cannot be repaired and, here, it clearly could. The court further
    refused Akers’s requested instruction 45, which would have provided that the
    measure of damages was the lesser of the diminution in value of the property and
    the reasonable expense of repair.
    [¶22.]       Akers also objected to the court’s proposed Instruction 50 defining
    Casper’s duty to mitigate its damages, which provided in part: “If you find that
    -11-
    #27074
    Casper Lodging took reasonable steps in an effort to mitigate its damages, then you
    must find that Casper Lodging properly mitigated its damages.” Akers argued that
    the court’s proposed instruction would allow the jury to conclude that, so long as
    Casper took any step that was reasonable, it mitigated its damages. The court
    overruled the objection and included Instruction 50. Akers also requested an
    instruction telling the jury that under Wyoming law Koehler had certain warranty
    rights against the contractors who worked on the Hotel. 2 Akers’s requested
    warranty instruction further provided that Akers did not give Koehler any
    warranties related to the work on the Hotel. The court refused the instruction.
    [¶23.]         The jury returned a verdict in favor of Casper, awarding Casper the
    full amount requested: $1,019,468.74. In a post-trial hearing to address the parties’
    stipulation that the court determine the date upon which Casper’s prejudgment
    interest accrued, Casper argued that interest should accrue from the date Koehler
    received the defective Hotel—March 11, 2004. Akers, however, submitted that it
    2.       Akers’s requested instruction provided:
    As a purchaser of property, Plaintiff was given implied
    warranties from the contractors who performed work on the
    Casper, Wyoming, Holiday Inn Express. Those warranties
    provided that the contractors’ work would be performed in a
    skillful, careful, diligent, and workmanlike manner. Plaintiff
    had the ability to assert warranty claims and enforce their
    warranty rights against the contractors involved in the project
    with regard to any allegedly defective work performed on the
    project.
    As a non-builder seller of the hotel, Defendant Robert W. Akers
    did not provide any warranties, express or implied, to Plaintiff
    or James Koehler with regard to the work performed at the
    hotel.
    -12-
    #27074
    should accrue from the time Casper incurred damages—2009 or 2010. The court
    ruled that under Gettysburg School District v. Helms & Associates, it was required
    to award prejudgment interest from the date Casper received the defective Hotel,
    March 11, 2004, because that was the date of the breach of contract. See 
    2008 S.D. 35
    , 
    751 N.W.2d 266
    . The court awarded Casper $997,682.83 in prejudgment
    interest. The court also awarded post-judgment interest set to accrue on the
    combined jury award and prejudgment interest calculation.
    [¶24.]       Akers moved for a mistrial and new trial, asserting that the court
    improperly admitted Nelson’s expert opinion on the nailing pattern, erred when it
    excluded Potter’s rebuttal expert testimony and erred when it allowed counsel for
    Casper to make improper and highly prejudicial comments during closing
    argument. In closing argument, counsel for Casper stated, “Mr. Akers has his own
    remedies against Sheet Metal Specialties.” Akers claimed this was in direct
    violation of the court’s order in limine precluding either party from referring to
    third-party liability. Further, during Casper’s rebuttal closing, counsel remarked
    that if Akers wanted the pictures, “all they had to do was ask.” This was in
    response to Akers’s counsel’s closing argument that Casper was hiding or concealing
    evidence of photos taken by Pace. The court denied Akers’s motion for a mistrial.
    [¶25.]       Thereafter, Akers moved for a judgment as a matter of law and, in the
    alternative, a new trial. Akers restated the same issues he asserted in his motion
    for a mistrial and alleged four additional errors. Akers submitted that (1) Casper
    failed to meet its burden of proof on damages because Casper did not present
    evidence on the diminution in value measure of damages, (2) the court improperly
    -13-
    #27074
    instructed the jury on mitigation of damages, (3) Casper failed to identify any
    provision of the Agreement or Addendum that Akers breached, and (4) Casper failed
    to exercise its warranty rights as a matter of law. The court denied the motion.
    [¶26.]       Akers appeals, and we restate the issues as follows:
    1. The circuit court committed reversible error when it denied
    Akers’s motion for a judgment as a matter of law due to Casper’s
    failure (a) to present evidence identifying what specific terms of
    the Agreement or Addendum Akers breached, (b) to present
    evidence of the diminution in value measure of damages, and (c)
    to mitigate damages and exercise its warranty rights.
    2. The circuit court committed reversible error when it denied
    Akers’s motion for a mistrial and later motion for a new trial
    based on (a) the court admitting Nelson’s previously undisclosed
    expert opinion, (b) the court excluding Potter’s rebuttal expert
    testimony on damages, and (c) Casper’s counsel’s inflammatory
    and prejudicial closing remarks.
    3. The circuit court abused its discretion when it refused to
    instruct the jury on Casper’s warranty rights, when it refused to
    instruct the jury that the appropriate measure of damages was
    the lessor of the diminution in value and cost of repair, and
    when it improperly instructed the jury on the issue of mitigation
    of damages.
    4. The circuit court committed reversible error when it awarded
    Casper prejudgment interest from March 11, 2004, and when it
    allowed post-judgment interest to accrue on prejudgment
    interest.
    5. The circuit court committed reversible error when it struck
    Akers’s third-party complaint against TKO and when it did not
    compel joinder of TKO as an indispensable party defendant.
    ANALYSIS
    1. Judgment as a Matter of Law
    [¶27.]       Under SDCL 15-6-50(a), a court may grant a judgment as matter of
    law against a party “[i]f during a trial by jury a party has been fully heard on an
    -14-
    #27074
    issue and there is no legally sufficient evidentiary basis for a reasonable jury to find
    for that party on that issue[.]”
    a. Evidence of a Breach of the Agreement or Addendum
    [¶28.]       Akers claims that he was entitled to a judgment as a matter of law on
    Casper’s breach of contract claim because neither the Agreement nor the Addendum
    promised a certain quality of construction. He further contends that Koehler
    waived the “Conditions Precedent” when he accepted the Hotel before construction
    was complete. Lastly, Akers contends that Casper’s dissatisfaction with the lack of
    sound proofing does not establish a breach of contract because neither the
    Agreement nor Addendum contains a sound rating requirement.
    [¶29.]       We review the court’s decision to deny a judgment as a matter of law
    for an abuse of discretion. Bertelsen v. Allstate Ins. Co., 
    2013 S.D. 44
    , ¶ 16, 
    833 N.W.2d 545
    , 554 (citing Jacobs v. Dakota, Minn. & E. R.R. Corp., 
    2011 S.D. 68
    , ¶ 9,
    
    806 N.W.2d 209
    , 212). We do not weigh the evidence. 
    Id. “We ‘view
    the evidence
    and testimony in a light most favorable to the verdict’” and determine if the
    evidence did support the verdict or if it would have supported it. 
    Id. (citation omitted).
    “If sufficient evidence exists so that reasonable minds could differ,
    judgment as a matter of law is not appropriate.” 
    Id. (quoting Roth
    v. Farner-Bocken
    Co., 
    2003 S.D. 80
    , ¶ 8, 
    667 N.W.2d 651
    , 659).
    [¶30.]       From our review of the record, there is sufficient evidence to support
    the jury’s verdict that Akers breached the parties’ contract. The parties agreed as a
    term of the initial contract that Akers would sell to Koehler a turn-key Hotel “built
    pursuant to the plans and specifications prepared by Associated Architects[.]” This
    -15-
    #27074
    was not one of the enumerated conditions precedent. The Agreement also provided,
    as a condition precedent, that Akers was to “complete the construction of the
    improvements in compliance with all city, county, state, and federal government
    requirements[.]” The Addendum further required that Akers “shall have a
    continuing obligation to construct and finish the Improvements in accordance with
    all governmental requirements and the standards and specifications of the Holiday
    Inn Express system.”
    [¶31.]       At trial, the jury heard evidence that Akers constructed the Hotel in
    violation of applicable code provisions because of improperly installed windows and
    air conditioning units, inadequate wind-load requirements, and the absence of
    necessary vapor barriers on many wall assemblies. The jury also heard testimony
    that, contrary to the plans and specifications, the poolroom dehumidification system
    was defective, windows were installed in violation of manufacturer instructions,
    portions of the Hotel roof lacked proper edging and necessary underlayment or tar
    paper and were too short, the stucco system was not properly constructed, and the
    windows and PTAC units were not properly flashed. On the sound rating issue,
    Casper presented evidence that the Hotel standards required a certain sound rating
    and that Akers did not construct the walls to this rating.
    [¶32.]       Because there is a legally sufficient evidentiary basis for the jury to
    find for Casper on the issue of breach, the circuit court did not abuse its discretion
    when it denied Akers a judgment as a matter of law on this issue.
    -16-
    #27074
    b. Diminution in Value Measure of Damages
    [¶33.]       Akers first contends that the court abused its discretion when it did
    not enter a judgment as a matter of law against Casper on Casper’s failure to
    present evidence of competing measures of damages. According to Akers, the
    proper measure of damages is the lesser of (1) the difference between the reasonable
    value of the Hotel with and without the construction defects and (2) the reasonable
    cost to repair the Hotel. Akers further argues that Casper bore the burden of
    presenting evidence of both measures of damage to the jury. Akers submits that to
    hold otherwise would allow Casper to recover more than it would have gained had
    Akers not breached the Agreement or Addendum.
    [¶34.]       Casper, on the other hand, relies on SDCL 21-2-1, which sets forth that
    the general measure of damages in a contract dispute “is the amount which will
    compensate the party aggrieved for all the detriment proximately caused thereby,
    or which, in the ordinary course of things, would be likely to result therefrom.”
    Casper argues it was not required to present evidence on the diminution in value
    because it presented evidence to support the amount that was necessary to
    compensate it for the damage proximately caused by the breach, namely the cost of
    making the repairs. Moreover, Casper contends that Akers had the burden to
    present evidence that Casper’s method of proving damages was unreasonable or
    unwarranted.
    [¶35.]       We have said that the purpose of contract damages is to put the
    injured party in the same position it would have been in had there not been a
    breach. Lamar Adver. of S.D., Inc. v. Heavy Constructors, Inc., 
    2008 S.D. 10
    , ¶ 14,
    -17-
    #27074
    
    745 N.W.2d 371
    , 376; see also SDCL 21-1-5 (cannot recover more than what the
    party could have gained by full performance by both sides). However, “[n]o
    damages can be recovered for a breach of contract which are not clearly
    ascertainable in both their nature and their origin.” SDCL 21-2-1. Moreover,
    “[d]amages must in all cases be reasonable[.]” SDCL 21-1-3.
    [¶36.]       Akers relies upon our holding in Rupert v. City of Rapid City, a recent
    inverse condemnation case, in which we recognized that a “landowner may
    generally only recover restoration costs if that amount does not exceed the
    diminution in value of the property.” See 
    2013 S.D. 13
    , ¶ 27, 
    827 N.W.2d 55
    , 66.
    This is because this Court has “traditionally held that the proper measure of
    damages in condemnation cases involving a partial taking or damaging of property
    ‘is the difference between the fair market value of the unit before the taking and the
    fair market value of what remains after the taking[.]” 
    Id. ¶ 20
    (emphasis added)
    (citing Corson Vill. Sanitary Dist. v. Strozdas, 
    539 N.W.2d 876
    , 879 (S.D. 1995)
    (quoting City of Sioux Falls v. Kelley, 
    513 N.W.2d 97
    , 103 (S.D. 1994))). This case,
    however, is not a condemnation case and, therefore, Rupert is not controlling.
    [¶37.]       Akers next directs this Court to Ward v. LaCreek Electric Association,
    Inc., where we held that the proper measure of damages “is the lesser of the
    following: I. The difference between the reasonable value of the house immediately
    before and immediately after its injury, or II. The reasonable expense of repair if
    the house can thereby be substantially restored to its former condition.” See 
    83 S.D. 584
    , 594, 
    163 N.W.2d 344
    , 349 (1968). He further relies on Subsurfco, Inc. v. B-Y
    Water District, a breach of contract case in which we reversed because “B-Y
    -18-
    #27074
    recovered an improper measure of damages contrary to the diminution in value rule
    and SDCL 21-1-3 and [SDCL] 21-1-5.” 
    337 N.W.2d 448
    , 455 (S.D. 1983).
    [¶38.]       A closer reading of both cases, however, reveals that neither Ward nor
    Subsurfco, Inc., stand for the proposition that in order to recover damages for a
    breach of contract, the plaintiff must present evidence on both the diminution in
    value and cost of repair measures of damages. In Ward, the plaintiff presented
    evidence to support the diminution in value measure of damages and the defendant
    countered with evidence on the cost of repair measure of 
    damages. 83 S.D. at 591
    ,
    163 N.W.2d at 348. We held that “with reference to the house in this case” the
    proper measure of damages was the lesser of the diminution in value and cost of
    repair. 
    Id. at 594,
    163 N.W.2d at 349. Here, however, the jury did not have before
    it evidence of both measures of damages. Further, Akers does not claim that
    Casper’s damages were not clearly ascertainable in their nature and origin in
    violation of SDCL 21-1-5.
    [¶39.]       In Subsurfco, Inc., the defendant presented evidence that the plaintiff’s
    damage award violated the diminution in value rule. The defendant further
    claimed that the damage award was unreasonable, unconscionable, and grossly
    oppressive in violation of SDCL 21-1-5, and that, in violation of SDCL 21-1-3, the
    plaintiff recovered more than it would have had the contract been fully 
    performed. 337 N.W.2d at 455
    . We held that the plaintiff recovered an improper measure of
    damages because the defendant established that “the defects cannot be remedied
    without reconstruction of a substantial portion of the work[,]” and the plaintiff
    “recovered damages totalling [sic] 49% of the bid price of the entire contract and
    -19-
    #27074
    almost a million dollars more than the price bid for the material and installation of
    the pipe in question.” 
    Id. Yet, here,
    Akers does not allege that, by recovering the
    cost of repair, Casper was placed in a better position than it would have been in had
    Akers performed under the contract. Akers further has not alleged or presented
    evidence that the defects caused by Akers’s breach could only be remedied by
    reconstruction of a substantial portion of the Hotel.
    [¶40.]       “Frequently, both measures of damages are in evidence and are
    complimentary to the other,” but “[a]n injured party may choose to present his case
    using either or both methods of measuring damages[.]” John Thurmond & Assocs.,
    Inc. v. Kennedy, 
    668 S.E.2d 666
    , 668-69 (Ga. 2008). See Martin v. Design Constr.
    Servs., Inc., 
    902 N.E.2d 10
    , 15 (Ohio 2009); GSB Contractors, Inc. v. Hess, 
    179 S.W.3d 535
    , 543 (Tenn. Ct. App. 2005); Legacy Builders, LLC v. Andrews, 
    335 P.3d 1063
    , 1069-70 (Wyo. 2014). Therefore, if an injured party seeks to recover the fair
    market value of the damaged property, the injured party must present evidence to
    support a claim for damages under that method. The defendant, then, “has the
    burden to present any contradictory evidence challenging the reasonableness or
    proportionality of those damages and where appropriate, evidence of an alternative
    measure of damages for the jury’s consideration.” John Thurmond & Assocs., 
    Inc., 668 S.E.2d at 669
    .
    [¶41.]       Because neither Ward nor Subsurfco, Inc., are controlling, and Akers,
    as the party challenging the reasonableness of Casper’s damages, had the burden to
    present evidence to support his claim that Casper’s damages were unwarranted,
    -20-
    #27074
    unreasonable, or excessive, the circuit court did not abuse its discretion when it
    denied Akers’s motion for a judgment as a matter of law on this issue.
    c. Mitigation of Damages and Warranty Rights
    [¶42.]       Akers argues that he is entitled to a judgment as a matter of law on
    his affirmative defenses that Casper failed to mitigate its damages and that Casper
    waived its right to recover when it failed to exercise its warranty rights under
    Wyoming law. In regard to Casper’s duty to mitigate its damages, Akers contends
    that many of the problems with the Hotel were observable in 2004, which problems
    Casper ignored and failed to repair until 2009–2010. Akers further claims that
    Casper, as a subsequent purchaser, had implied warranty rights under Wyoming
    law. Because Casper failed to pursue these rights, Akers submits that the “risk of
    construction defects was allocated to Casper[.]”
    [¶43.]       A judgment as a matter of law is not appropriate when sufficient
    evidence exists such that reasonable minds could differ. Bertelsen, 
    2013 S.D. 44
    ,
    ¶ 
    16, 833 N.W.2d at 554
    . With reference to Casper’s alleged failure to mitigate its
    damages, the jury heard testimony from Akers’s witnesses related to the actions
    Casper and its agents failed to take when the water penetration problems were first
    observed at the Hotel. The jury then heard contradictory evidence from Casper’s
    witnesses that Casper mitigated its damages because it continued to take action to
    address the problems as they occurred. On the warranty issue, Akers presented
    evidence that he transferred his warranty rights to Koehler and that Casper failed
    to timely exercise these rights. Casper, however, presented evidence through
    Koehler’s testimony that it attempted to contact certain subcontractors when
    -21-
    #27074
    defective work was observed, but that the subcontractors would not respond.
    Casper also argued to the jury that Akers had no evidence that Akers actually
    transferred to Casper the necessary warranty information as required in the
    Agreement.
    [¶44.]       Because we do not weigh the evidence and because we view the
    evidence in the record in a light most favorable to the verdict, we cannot say the
    court abused its discretion when it denied Akers a judgment as a matter of law on
    this issue. See Jacobs, 
    2011 S.D. 68
    , ¶ 
    9, 806 N.W.2d at 212
    . The jury could have
    believed that Casper’s efforts to mitigate the problems as they arose were sufficient
    and reasonable under the circumstances. Further, there is evidence in the record
    that may have led the jury to conclude that Casper did not waive its right to recover
    when it did not exercise alleged warranty rights.
    2. Motion for a Mistrial and Motion for a New Trial
    [¶45.]       “We review denials of mistrial and new trial motions for an abuse of
    discretion.” Walter v. Fuks, 
    2012 S.D. 62
    , ¶ 22, 
    820 N.W.2d 761
    , 767. “[A] new trial
    may follow only where the violation has prejudiced the party or denied him a fair
    trial. Prejudicial error is error which in all probability produced some effect upon
    the jury’s verdict and is harmful to the substantial rights of the party assigning it.”
    Kjerstad v. Ravellette Publ’ns, Inc., 
    517 N.W.2d 419
    , 426 (S.D. 1994).
    a. Previously Undisclosed Expert Opinion
    [¶46.]       Prior to Trent Nelson’s testimony and outside the presence of the jury,
    counsel for Akers asked the circuit court to prevent Nelson from testifying that the
    inadequate nailing pattern made the structure unsound and unsafe from day one.
    -22-
    #27074
    Akers submitted that the opinion was new and previously undisclosed and
    substantially prejudiced his defense. In response, Casper quoted Nelson’s
    deposition testimony and submitted to the court that nailing pattern meant
    fastening pattern and, therefore, Nelson’s opinion was not new. The court allowed
    the testimony, remarking that “a nail is a fastener” and, therefore, Nelson did give a
    previous opinion about the fastening pattern.
    [¶47.]       During direct examination, Nelson offered the opinion that from day
    one the Hotel was unsafe, structurally unsound, and in violation of the applicable
    code as a result of the inadequate nailing pattern related to the OSB. On cross-
    examination, Nelson admitted that his opinion was new—he formed it after
    listening to Pace’s previous trial testimony. Counsel for Akers then engaged in a
    lengthy cross-examination challenging the basis of Nelson’s opinions and his
    qualifications to render an opinion.
    [¶48.]       Akers now claims that the court abused its discretion when it denied
    his motions for a mistrial and new trial. According to Akers, Nelson’s opinion that
    the Hotel was unsound and unsafe from day one negated his critical and viable
    defense that Casper had failed to mitigate its damages. Thus, he submits that,
    although the court ultimately struck Nelson’s opinion and admonished the jury, he
    was denied a fair trial because the “damage had already been done.”
    [¶49.]       “As a general rule, if a court excludes improperly admitted evidence
    and directs the jury to disregard it, the error is cured.” Young v. Oury, 
    2013 S.D. 7
    ,
    ¶ 18, 
    827 N.W.2d 561
    , 567. “If, however, after probing the record, it appears the
    prejudicial effect of the admission was not fully overcome, despite the curative
    -23-
    #27074
    instruction, a new trial is warranted.” 
    Id. In Young,
    we identified certain
    considerations relevant to assessing whether the prejudicial effect of an admission
    was fully overcome. Those are: “(1) to what extent did the evidence go directly to a
    critical issue, (2) is the evidence inherently prejudicial and of such a character that
    it would likely impress itself upon the minds of the jurors, (3) was the curative
    instruction firm, clear, and accomplished without delay, and (4) was there any
    misconduct on the part of the offering party?” 
    Id. ¶ 19.
    [¶50.]        There is no doubt that Nelson’s testimony that the inadequate nailing
    pattern made the Hotel unsafe and unsound from day one related directly to a
    critical issue in the case. However, the court’s curative instruction was firm, clear,
    and accomplished without delay. 3 The instruction was crafted by the parties and
    was given at the first moment possible—after the jury returned from its recess. In
    regard to misconduct by Casper, there is no evidence that Casper knew Nelson was
    going to express this opinion until trial. Indeed, Nelson admitted he formed his
    opinion while listening to another witness’s testimony.
    [¶51.]        Lastly, we consider whether the evidence was “inherently prejudicial
    and of such a character that it would likely impress itself upon the minds of the
    3.       The admonishment provided:
    1. Mr. Nelson’s opinions that the OSB was improperly fastened
    or had insufficient nails is stricken by the court.
    2. Mr. Nelson’s opinions that the building was structurally
    unsound at the time Mr. Akers sold the building to the
    plaintiff based on improper fastening or not having enough
    nails in the OSB is stricken by the court.
    3. You shall disregard these opinions in their entirety.
    -24-
    #27074
    jurors.” See 
    id. In Young,
    we explained that this factor concerns “what the jury
    actually saw and heard and how much the jurors were expected to disregard.” 
    Id. ¶ 21.
    On direct examination, the jury heard Nelson testify that the OSB were
    improperly nailed during the original construction. The jury also heard Nelson
    explain that the improper nailing violated certain applicable code provisions and
    made the building unsafe and unsound from the day it was delivered to Koehler.
    This testimony spanned approximately five transcript pages. Then, through cross-
    examination, the jury heard Nelson admit that his opinion was new and was formed
    only after Nelson heard Pace previously testify. The jury also heard counsel for
    Akers explore and scrutinize the veracity of Nelson’s newly-disclosed opinion.
    [¶52.]       Based on our review of the character of the evidence, we cannot say
    that Nelson’s opinion was so inherently prejudicial so as to impress itself on the
    minds of the jurors. His new opinion, given on direct examination, was short in
    duration and delivered solely through verbal statements. Contra Young, 
    2013 S.D. 7
    , ¶ 
    21, 827 N.W.2d at 567
    (witness left the witness stand to use a laser pointer to
    draw attention to the chart). It is also relevant that Nelson’s opinion was not the
    first time the jury heard that the structure was short 25,000 nails; Pace had already
    alerted the jury to that fact and that it took two men three days to correct the
    problem.
    [¶53.]       After probing the record, we cannot say that the prejudicial effect of
    Nelson’s testimony was not fully overcome by the curative instruction and by the
    court’s admonition to the jury that the opinion be stricken and disregarded. The
    court promptly and sufficiently admonished the jury and struck the testimony. The
    -25-
    #27074
    improper testimony was not relied upon or highlighted through the remainder of
    the trial. The circuit court did not abuse its discretion when it denied Akers’s
    motions for a mistrial and new trial on this issue.
    b. Exclusion of Potter’s Rebuttal Expert Testimony on
    Damages
    [¶54.]       Akers next contends that the circuit court improperly excluded Akers’s
    rebuttal expert testimony on damages. Akers sought to have Potter testify in direct
    response to the damages testimony presented by Casper’s expert Potratz. Prior to
    Potter’s testimony, Casper moved in limine to prevent any opinion by Potter on
    Casper’s damages because Potter did not testify in his deposition about Casper’s
    alleged damages and did not update his expert opinion after Akers had in his
    possession Casper’s Rule 1006 damages summary. Akers responded that Potter
    was unable to testify in response to Casper’s damages summary because Casper
    submitted its damages summary after the deadline for disclosures. Akers further
    highlighted that even Casper’s expert—Potratz—could not testify to Casper’s
    damages summary during his deposition because the summary had just been
    completed. Because Potratz was allowed to testify about the new damages
    summary, Akers submitted Potter should similarly be permitted to testify. The
    court reserved ruling on Casper’s motion in limine, but ultimately sustained each
    objection by Casper related to any testimony from Potter on Casper’s damages
    summary.
    [¶55.]       On appeal, Akers argues that the circuit court abused its discretion
    when it denied his motions for a mistrial and new trial based on the exclusion of
    Potter’s rebuttal testimony. In Akers’s view, “there was no way Potter could answer
    -26-
    #27074
    specific questions regarding Casper’s damages” during his deposition because
    Casper did not provide its damages summary until after the deposition and after the
    expert disclosures deadline. Akers further contends that he was prejudiced because
    the jury awarded Casper 100% of its requested damages “[d]espite overwhelming
    evidence of Casper’s failure to mitigate damages, and Casper’s admission that
    prompt action would have reduced damages[.]”
    [¶56.]       A court has discretion to admit expert testimony and we review the
    decision to admit or exclude it for an abuse of discretion. Supreme Pork, Inc. v.
    Master Blaster, Inc., 
    2009 S.D. 20
    , ¶ 15, 
    764 N.W.2d 474
    , 481. It is well established
    that “parties are ‘under a duty seasonably to supplement [their] response[s] with
    respect to any question directly addressed to . . . the subject matter on which [the
    expert witness] is expected to testify, and the substance of [the expert’s] testimony.’”
    
    Id. (alterations in
    original); SDCL 15-6-26(e).
    [¶57.]       Here, the record supports the court’s decision to exclude Potter’s
    rebuttal testimony on Casper’s Rule 1006 damages summary. Potter was deposed
    two days before Casper submitted to Akers its Rule 1006 damages summary.
    However, when Potter was deposed, Akers had received from Casper all documents
    that ultimately formed the basis of Casper’s Rule 1006 damages summary. More
    importantly, after Akers received Casper’s damages summary, Akers did not fulfill
    its duty to supplement Potter’s intended expert opinion as required by SDCL 15-6-
    26(e). It was insufficient to simply identify that Potter was an expert witness on the
    issue of damages.
    -27-
    #27074
    [¶58.]       We also note that, unlike Potter, Potratz gave a detailed opinion
    during his deposition on the damages claimed by Casper. Potratz offered his expert
    testimony on damages despite the fact that he (like Potter) did not have an
    opportunity to specifically examine Casper’s Rule 1006 damages summary.
    Furthermore, Potter made it clear in his deposition that he was not expressing an
    opinion on the damages claimed by Casper. Finally, the exclusion of Potter’s
    rebuttal testimony did not prevent Akers from presenting evidence contradicting
    Casper’s claimed damages or in support of his defense that Casper failed to mitigate
    its damages. The court did not abuse its discretion when it denied Akers’s motions
    for a mistrial and new trial on this issue.
    c. Closing Remarks by Casper’s Counsel
    [¶59.]       Prior to trial, the court issued an order instructing counsel to approach
    the bench before discussing Akers’s third-party claims in open court. During
    Casper’s closing argument, and without first approaching the bench, counsel stated,
    “Akers has his own remedies against Sheet Metal and Zakco.” Sheet Metal is a
    subcontractor and Zakco is the general contractor. Akers now claims that this
    statement “was equivalent to telling the jury that Akers had insurance in the form
    of remedies against contractors,” which statement he submits prejudiced him.
    Akers further contends that during Casper’s rebuttal closing argument, counsel
    “undercut a central defense theory by blaming Akers for Casper’s nondisclosure” of
    700 renovation photographs. In light of Casper’s remarks in closing argument,
    Akers insists the court abused its discretion when it did not order a mistrial or
    grant a new trial.
    -28-
    #27074
    [¶60.]       In reviewing the court’s decision to deny a new trial, we “interfere only
    when[,] from an examination of the entire record, [we are] convinced that there has
    been a miscarriage of justice.” Schoon v. Looby, 
    2003 S.D. 123
    , ¶ 18, 
    670 N.W.2d 885
    , 891 (quoting Roth, 
    2003 S.D. 80
    , ¶ 
    37, 667 N.W.2d at 664
    ). This is because “a
    plaintiff should not be penalized for the misstatements of his counsel and the
    granting of a new trial should not be used to discipline counsel.” 
    Id. Therefore, “a
    new trial may follow only where the violation has prejudiced the party or denied
    him a fair trial. Prejudicial error is error which in all probability produced some
    effect upon the jury’s verdict and is harmful to the substantial rights of the party
    assigning it.” Harter v. Plains Ins. Co., Inc., 
    1998 S.D. 59
    , ¶ 32, 
    579 N.W.2d 625
    ,
    633 (quoting Kjerstad v. Ravellette Publ’ns, Inc., 
    517 N.W.2d 419
    , 426 (S.D. 1994)).
    [¶61.]       From an examination of the entire record, counsel’s remarks in closing
    argument did not in all probability produce some effect on the jury’s verdict.
    Although Casper did not approach the bench before referring to Akers’s third-party
    claims, counsel’s statement was isolated and not inflammatory. Also, the statement
    was not the equivalent of putting evidence in the record that a person has liability
    insurance. See Atkins v. Stratmeyer, 
    1999 S.D. 131
    , ¶ 13, 
    600 N.W.2d 891
    , 896
    (plaintiff referred to health insurance, not liability insurance). In regard to
    Casper’s statement suggesting that Akers could have obtained the 700 pictures,
    Akers did not object to this statement. The failure to object deprived the circuit
    court of the opportunity to rule on the issue and admonish the jury, and Akers’s
    failure to object waived the right to argue the issue on appeal. See Veith v. O’Brien,
    
    2007 S.D. 88
    , ¶ 67, 
    739 N.W.2d 15
    , 34. Because there is no prejudice from counsel’s
    -29-
    #27074
    remarks during closing argument, the circuit court did not abuse its discretion
    when it denied Akers’s motions for a mistrial and new trial on this issue.
    3. Jury Instructions
    [¶62.]       It is well-settled that ‘‘[a] trial court has discretion in the wording and
    arrangement of its jury instructions, and therefore we generally review a trial
    court’s decision to grant or deny a particular instruction under the abuse of
    discretion standard.” Wangsness v. Builders Cashway, Inc., 
    2010 S.D. 14
    , ¶ 10, 
    779 N.W.2d 136
    , 140 (quoting State v. Cottier, 
    2008 S.D. 79
    , ¶ 7, 
    755 N.W.2d 120
    , 125).
    We have said that a circuit “court should instruct the jury on issues supported by
    competent evidence in the record”; however, the court “is not required to instruct on
    issues that do not find support in the record.” Bauman v. Auch, 
    539 N.W.2d 320
    ,
    323 (S.D. 1995). Moreover, it is not error to refuse to give an instruction that does
    not correctly set forth the law. 
    Id. a. Instruction
    on Warranty Rights
    [¶63.]       Akers requested an instruction describing the warranty rights Casper
    had available under Wyoming law. The requested instruction provided that Casper
    “had the ability to assert warranty claims and enforce [its] warranty rights against
    the contractors involved in the project” based on Wyoming law, and that Akers “did
    not provide any warranties, express or implied, to [Casper] or James Koehler with
    regard to the work performed at the hotel.” Akers asserts that this instruction
    supported his claim that Casper waived its right to seek relief because it failed to
    exercise its warranty rights. The court refused Akers’s requested instruction. On
    appeal, Akers submits that the instruction was a proper statement of the law and
    -30-
    #27074
    that, by refusing the instruction, Akers was prevented from adequately arguing to
    the jury that Casper’s failure to exercise its warranty rights constituted a failure to
    mitigate its damages.
    [¶64.]       From our review of the record, the court properly refused Akers’s
    requested instruction. The requested instruction was not supported by competent
    evidence in the record and would have improperly told the jury that, as a matter of
    law, Casper had certain warranty rights. Any warranty rights that Casper may
    have had (and waived) were disputed in the case. Moreover, the court adequately
    instructed the jury on the issue of waiver:
    A waiver occurs when one in possession of a right, whether
    obtained by law or by agreement, who with full knowledge of the
    facts, voluntarily and intentionally does or fails to do something
    inconsistent with the enforcement of that right.
    To support a defense of waiver, there must be a showing of a
    clear, unequivocal and decisive act or acts showing an intention
    to give up the existing right. There can be no waiver unless so
    intended by one party and so understood by the other. A person
    who has waived a right cannot recover based on that right.
    The burden of proof to establish waiver is on the party who
    seeks to rely on it.
    Instruction 42. Therefore, the court did not abuse its discretion when it refused
    Akers’s requested warranty and waiver instruction.
    b. Instruction on the Measure of Damages
    [¶65.]       Akers next claims that the court abused its discretion when it failed to
    instruct the jury that the appropriate measure of damages was the lesser of the
    diminution in value or the cost of repair. Because Akers did not present any
    -31-
    #27074
    evidence on the diminution in value measure of damages, the circuit court properly
    refused Akers’s requested instruction. See supra ¶¶ 38-41.
    c. Instruction on Mitigation
    [¶66.]       Akers contends the court’s instructions on mitigation of damages were
    incorrect and misled the jury, which error necessitates a new trial. The court
    provided two instructions on mitigation:
    Instruction 49
    In determining the amount of money which will reasonably
    compensate the plaintiff, you are instructed that a person whose
    property is damaged must exercise reasonable diligence and
    effort to minimize existing damages and to prevent further
    damages. The law imposes upon a party injured by another’s
    breach of contract the active duty of making reasonable exertion
    to render the injury as light as possible. If, by his negligence or
    willfulness, he allows the damages to be unnecessarily
    enhanced, the increased loss, which was avoidable by the
    performance of his duty, falls on him. Plaintiff cannot recover
    money for damage to property which could have been avoided by
    the exercise of reasonable diligence and effort.
    Instruction 50
    Akers has the burden of proving that Casper Lodging failed to
    mitigate its damages. Casper Lodging claims that it mitigated
    its damages. If you find that Casper Lodging took reasonable
    steps in an effort to mitigate its damages, then you must find
    that Casper Lodging properly mitigated its damages.
    Akers objected to Instruction 50, asserting that it would allow the jury to find
    against Akers if Casper took any reasonable step to mitigate. On appeal, Akers
    claims he was prejudiced by the court’s incorrect and misleading instruction from
    the fact “the jury awarded Casper every penny of its claim,” even though Casper
    admitted some damages could have been avoided by making repairs earlier.
    -32-
    #27074
    [¶67.]       We recently explained that the duty to mitigate damage caused by a
    breach of contract is an “active duty of making reasonable exertion to render the
    injury as light as possible.” Arrowhead Ridge I, LLC v. Cold Stone Creamery, Inc.,
    
    2011 S.D. 38
    , ¶ 16, 
    800 N.W.2d 730
    , 735 (quoting Ducheneaux v. Miller, 
    488 N.W.2d 902
    , 917 (S.D. 1992)). Thus, if a plaintiff, by his negligence or willfulness, “allows
    the damages to be unnecessarily enhanced, the increased loss, that which was
    avoidable by the performance of his duty, falls upon him.” 
    Id. The burden
    is on the
    breaching party to prove that “damages would have been lessened by the exercise of
    reasonable diligence on the part of the non-breaching party.” 
    Ducheneaux, 488 N.W.2d at 918
    (citing Hepper v. Triple U Enters., Inc., 
    388 N.W.2d 525
    , 530 (S.D.
    1986); Renner Elevator Co. v. Schuer, 
    267 N.W.2d 204
    , 207 (S.D. 1978)).
    [¶68.]       Upon review of our prior cases, it is clear the last sentence of
    Instruction 50 should not have been given. That sentence reads: “If you find that
    Casper Lodging took reasonable steps in an effort to mitigate its damages, then you
    must find that Casper Lodging properly mitigated its damages.” Casper’s duty to
    mitigate its damages required that Casper exercise reasonable diligence, not take
    reasonable steps in an effort. See Sun Mortg. Corp. v. W. Warner Oils Ltd., 
    1997 S.D. 101
    , ¶ 26, 
    567 N.W.2d 632
    , 637 (defining reasonable diligence); see also
    Stadheim v. Becking, 
    290 N.W.2d 273
    , 275 (S.D. 1980).
    [¶69.]       Nonetheless, we do not view an instruction in isolation. Rather, “we
    construe jury instructions as a whole to learn if they provided a full and correct
    statement of the law.” Behrens v. Wedmore, 
    2005 S.D. 79
    , ¶ 37, 
    698 N.W.2d 555
    ,
    570 (quoting First Premier Bank v. Kolcraft Enters., Inc., 
    2004 S.D. 92
    , ¶ 40, 686
    -33-
    #
    27074 N.W.2d 430
    , 448). The court, consistent with our past cases, properly informed the
    jury that Akers had the burden of proving that Casper failed to mitigate its
    damages. The court further adequately defined for the jury that the duty to
    mitigate required Casper to “exercise reasonable diligence and effort to minimize
    existing damages and to prevent further damages.” Because the court’s
    instructions, taken as a whole, provided a correct statement of the law on mitigation
    of damages, we cannot say that “in all probability it produced some effect upon the
    verdict” or that it was harmful to Akers’s substantial rights. See 
    id. 4. Prejudgment
    Interest and Post-Judgment Interest
    [¶70.]       During the settling of the jury instructions, the parties agreed to allow
    the circuit court to determine the appropriate date to calculate prejudgment
    interest in the event the jury found in favor of Casper. At a post-trial hearing to
    determine prejudgment interest, Akers submitted that, assuming that there was a
    breach of contract, Casper did not suffer damage until the time Casper undertook
    substantial repairs, which was 2009 or 2010. During the oral argument before this
    Court, Casper admitted that it had incurred zero expense on March 11, 2004 (the
    date of the breach and delivery of the Hotel). However, Casper argued that based
    upon this Court’s decision in Gettysburg, the date of loss was March 11, 2004,
    notwithstanding that Casper had yet to incur an expense as a result of the breach.
    See 
    2008 S.D. 35
    , 
    751 N.W.2d 266
    .
    [¶71.]       At the post-trial hearing, the circuit court informed the parties that it
    believed Gettysburg required it to calculate prejudgment interest from March 11,
    2004. It remarked, “It’s contrary to my thinking that you can collect interest on
    -34-
    #27074
    something before you expend the money for repair, but that is what the Gettysburg
    school case tells me.” Counsel for Akers argued that Gettysburg did not stand for
    that proposition and urged the court to make a factual determination on the date
    Casper was damaged and suffered a loss. In response the court said,
    As much as I would like to accept your argument on that, I think
    the Gettysburg case tells me to the contrary. But the nice part
    about it is, it’s easily calculated for the Supreme Court to
    straighten me out if I’m wrong. And, truthfully, I think I may
    very well be wrong, but I think - - I mean, to me, common sense
    tells me you you shouldn’t collect interest on something that
    hasn’t gone out of your pocket yet. But on the other hand, Jim
    Koehler did pay for the hotel in full as of the date. So to that
    extent, he’s out that money.
    The court awarded prejudgment interest starting on March 11, 2004, which amount
    equaled $997,682.83.
    [¶72.]       In Gettysburg, the school district received a defective track in 2002,
    and for nearly two years, the contractor attempted to repair the problems with the
    track. 
    Id. ¶¶ 2-5.
    In June 2004, after efforts to correct the problems had failed, the
    school district hired an outside consultant to examine the track. 
    Id. ¶ 6.
    The
    consultant issued a report setting forth the underlying structural defects in the
    track’s construction and reached the conclusion that the defects would be nearly
    impossible to repair. Ultimately, the school district brought suit against the
    contractor for breach of contract and prevailed in a jury trial. The jury awarded the
    school district damages and prejudgment interest from July 4, 2004. 
    Id. ¶ 7.
    [¶73.]       On appeal the contractor asserted “that damages were too uncertain to
    be taxed with prejudgment interest” because the school district had not yet
    expended funds to repair the defective track. 
    Id. ¶ 23.
    We noted that prejudgment
    -35-
    #27074
    interest is calculated “from the day the loss or damage occurred.” 
    Id. ¶ 24
    (quoting
    SDCL 21-1-13.1). We then declared that “[t]he loss or damage occurred when the
    District received the faulty track.” 
    Id. Yet, the
    school district received the track in
    2002, and the jury awarded prejudgment interest to begin on July 4, 2004. From
    our review of this decision, we cannot ascertain the basis for the jury’s selection of
    this date. Regardless, this Court’s statement that “[t]he loss or damage occurred
    when the District received the faulty track” suggests that prejudgment interest in a
    breach of contract case must be calculated on the date of the breach. We now
    expressly reject this language, and to the extent Gettysburg created such a rule, it is
    overruled.
    [¶74.]       Prejudgment interest is mandatory and it is recoverable “from the day
    that the loss or damage occurred, except during such time as the debtor is
    prevented by law, or by act of the creditor, from paying the debt.” SDCL 21-1-13.1;
    see JAS Enters., Inc. v. BBS Enters., Inc., 
    2013 S.D. 54
    , ¶ 45, 
    835 N.W.2d 117
    , 129.
    The purpose of prejudgment interest “is to do justice to one who has suffered a loss
    at the hands of another.” S.D. Bldg. Auth. v. Geiger-Berger Assocs., P.C., 
    414 N.W.2d 15
    , 19 (S.D. 1987). An award of prejudgment interest “seeks to compensate
    the injured party for this wrongful detention of money owed.” 
    Id. [¶75.] Although
    the purpose of prejudgment interest is well established, our
    case law is not as clear on what date prejudgment interest should begin to accrue
    for each measure of damages. We find the Colorado Supreme Court’s analysis in
    Goodyear Tire & Rubber Co. v. Holmes, helpful on the proper method to compute
    prejudgment interest in a breach of contract case. See 
    193 P.3d 821
    , 828 (Colo.
    -36-
    #27074
    2008). Although Colorado’s prejudgment interest statute is distinguishable, we find
    the court’s analysis instructive. See 
    id. at 825.
    [¶76.]       The court in Goodyear explained that in order to seek recovery from a
    loss, a plaintiff must first quantify the loss by establishing a measure of damages.
    
    Id. at 826.
    “During the period between the time at which the plaintiff’s loss is
    measured and the judgment, the plaintiff is deprived of the use of the money or
    property that would constitute the award.” 
    Id. “As a
    result, the plaintiff suffers a
    loss, frequently termed ‘time value of money.’” 
    Id. “This lost
    value is caused by
    inflation, reducing the value of money over time, and by plaintiff’s inability . . . to
    earn a return on it.” 
    Id. [¶77.] In
    a case where the measure of damages is the diminution in the
    market value of the property, the “damages focus on the damaged asset and
    measure the resulting change in the plaintiff’s net worth.” 
    Id. at 827.
    Accordingly,
    when a plaintiff seeks damages for diminution in value, his loss is properly
    measured at the time of the injury to his property. To conclude otherwise would
    deny the plaintiff the ability “to earn a return on the amount of the damages, and
    he will also suffer a loss due to inflation between the time the damages are
    calculated and the time of the judgment.” 
    Id. at 827-28.
    [¶78.]       However, when the measure of damages is cost of repair, the focus is
    on the actual expenditures made by the plaintiff to make the repairs rather than
    the damaged property itself. This is because “the plaintiff retains the use of the
    money later used to repair or obtain a replacement and therefore can earn a return
    on it.” 
    Id. at 828.
    Therefore, the loss or damage will not occur until sometime after
    -37-
    #27074
    the plaintiff is wronged. Indeed, “the plaintiff does not suffer any time value of
    money loss until the time when she incurs the replacement costs[.]” 
    Id. [¶79.] Applying
    these concepts to the facts of this case, we note that Casper
    sought and the circuit court authorized the cost of repair measure of damages.
    Therefore, Casper did not suffer any loss of return on its original investment until it
    incurred costs of repair. Although the circuit court was justified in relying on our
    holding in Gettysburg, upon remand the court is instructed to compute prejudgment
    interest based on the cost of repairs incurred by Casper from the date the expenses
    were incurred.
    [¶80.]       Akers further contends that the circuit court erred when it ordered
    that post-judgment interest was to accrue on the court’s award of prejudgment
    interest. Akers submits that the circuit court improperly awarded interest on
    interest. This Court has not before addressed the precise question whether an
    award of post-judgment interest can accrue on prejudgment interest. A review of
    cases from other courts, however, reveals that an award of post-judgment interest
    on an award of prejudgment interest does not result in an award of interest on
    interest. Air Separation, Inc. v. Underwriters at Lloyd’s of London, 
    45 F.3d 288
    , 290
    (9th Cir. 1995) (collecting cases); see also Arthur Young & Co. v. Reves, 
    937 F.2d 1310
    , 1338 (8th Cir. 1991) (analyzing similar federal rule, 28 U.S.C.A § 1961);
    Balder v. Haley, 
    441 N.W.2d 539
    , 544 (Minn. Ct. App. 1989). Post-judgment
    interest is intended to compensate an injured plaintiff for being deprived of
    compensation for a loss during the time of the ascertainment of the loss and the
    recovery. See SDCL 54-3-5.1. It is not designed to operate as a penalty. Thus,
    -38-
    #27074
    prejudgment interest is part of the loss—compensation to the injured party for that
    party’s loss of use of their money caused by the breach of contract. See Jackson v.
    Lee’s Travelers Lodge, Inc., 
    1997 S.D. 63
    , ¶ 40, 
    563 N.W.2d 858
    , 868. The circuit
    court did not err when it awarded Casper post-judgment interest on prejudgment
    interest.
    5. Claims against TKO by Akers
    [¶81.]       The Koehler Organization (TKO) is the management company for
    Koehler’s hotels. During his testimony, Koehler explained that he is in essence
    TKO because TKO is a sole proprietorship. Akers does not dispute that he knew of
    TKO and its role in the management of the Hotel. Nonetheless, Akers submits that
    SDCL 15-6-19 does not give the court discretion to join or exclude TKO as a party,
    and that he had a “right” to assert a third-party claim against TKO under SDCL 15-
    6-14(a).
    [¶82.]       A circuit court has no discretion whether to join an indispensable party
    because SDCL 15-6-19(a) is mandatory. Titus v. Chapman, 
    2004 S.D. 106
    , ¶ 15, 
    687 N.W.2d 918
    , 923. Thus, “[a] party’s status as an indispensable party is a conclusion
    of law.” 
    Id. Under SDCL
    15-6-19(a),
    A person who is subject to service of process shall be joined as a
    party in the action if:
    (1) In his absence complete relief cannot be accorded
    among those already parties; or
    (2) He claims an interest relating to the subject of the
    action and is so situated that the disposition of the action
    in his absence may (i) as a practical matter impair or
    impede his ability to protect that interest or (ii) leave any
    of the persons already parties subject to a substantial risk
    of incurring double, multiple, or otherwise inconsistent
    obligations by reason of his claimed interest. If he has not
    been so joined, the court shall order that he be made a
    -39-
    #27074
    party. If he should join as a plaintiff but refuses to do so,
    he may be made a defendant, or, in a proper case, an
    involuntary plaintiff. If the joined party objects to venue
    and his joinder would render the venue of the action
    improper, he shall be dismissed from the action.
    “[W]hether or not a person is an indispensable party is [a decision] which must be
    made on a case-by-case basis and is dependent upon the facts and circumstances of
    each case.” Titus, 
    2004 S.D. 106
    , ¶ 
    36, 687 N.W.2d at 927
    (citing Provident
    Tradesmens Bank Tr. Co. v. Patterson, 
    390 U.S. 102
    , 119, 
    88 S. Ct. 733
    , 743, 19 L.
    Ed. 2d 936 (1968)). However, simply because a person might have an interest in the
    outcome of litigation does not make the person an indispensable party. 
    Id. [¶83.] TKO
    is not an indispensable party. TKO does not “have a direct
    interest in the litigation[,]” and TKO’s interest is not “such that it cannot be
    separated from that of the parties to the suit[.]” See Smith v. Albrecht, 
    361 N.W.2d 626
    , 627-28 (S.D. 1985). TKO is not necessary to determine whether Akers
    breached the contract when Akers delivered the Hotel to Koehler. Nor is TKO’s
    presence necessary for the jury to determine Akers’s defenses of waiver and failure
    to mitigate damages. TKO is a potential joint tortfeasor, but that status does not
    make it an indispensable party. See Temple v. Synthes Corp., 
    498 U.S. 5
    , 7, 111 S.
    Ct. 315, 316, 
    112 L. Ed. 2d 263
    (1990); see also Whiting v. Hoffine, 
    294 N.W.2d 921
    (S.D. 1980). Because TKO is not an indispensable party, the court did not err in
    denying Akers’s motion to join TKO under SDCL 15-6-19(a).
    [¶84.]       Lastly, Akers contends that he had a right to amend his third-party
    complaint to assert a claim against TKO under SDCL 15-6-14 because his third-
    party complaint was served “no later than ten days after he serve[d] his original
    -40-
    #27074
    answer.” To Akers, his “original answer” for this issue concerns only his “answer” to
    a July 2013 third-party defendant counterclaim by Sheet Metal against Akers.
    Akers submits that Sheet Metal’s negligence counterclaim “was the first time Akers
    was alleged to be a tortfeasor,” and it was not until that point Akers was able to
    assert a counterclaim against TKO for contribution on Casper’s claims.
    [¶85.]       A close review of Sheet Metal’s amended answer to Akers’s amended
    third-party complaint does not support Akers’s contention. Sheet Metal asserted a
    counterclaim against Akers for indemnification and contribution in the event Sheet
    Metal would be found liable. Thus, Akers’s “answer” to Sheet Metal’s counterclaim
    was not an “original answer” to Casper’s claims as contemplated under SDCL 15-6-
    14(a). Because Akers filed his “original answer” to Casper’s complaint in 2009,
    Akers was required to obtain leave to assert the third-party claim against TKO
    when he sought to amend his third-party complaint in July 2013.
    [¶86.]       From our review of the record, the court did not abuse its discretion
    when it denied Akers leave to amend his third-party complaint to add a claim
    against TKO. Akers did not seek leave to add TKO until 2013, despite knowing well
    before then that TKO was the management company for the Hotel. Moreover, the
    court’s scheduling order set July 1, 2012, as the deadline to add new parties. Most
    importantly, Akers’s motion came only six months before trial in a case that
    involved extensive discovery and multiple continuances.
    CONCLUSION
    [¶87.]       The circuit court did not err when it denied Akers’s motion for a
    judgment as a matter of law because (1) there was sufficient evidence for the jury to
    -41-
    #27074
    conclude that Akers breached the Agreement or Addendum and that Akers did not
    meet his burden of proof on the issue of waiver or on his claim that Casper failed to
    mitigate its damages, and (2) Casper did not have a duty to present evidence on
    both the diminution in value and cost of repair measures of damages. The court
    further did not abuse its discretion when it denied Akers’s motions for a mistrial
    and new trial because (1) the court’s curative instruction and striking of Nelson’s
    undisclosed expert opinion was sufficient to overcome the prejudicial effect, (2) the
    court properly excluded Potter’s expert opinion on Casper’s line-item damages
    summary, and (3) Casper’s closing remarks were not inflammatory or prejudicial.
    [¶88.]       The court’s jury instructions, as a whole, properly set forth the
    applicable law, and, therefore, the court’s incorrect statement in one of the two
    instructions on mitigation does not necessitate a new trial. Furthermore, the court
    properly refused Akers’s requested warranty instruction and damages instruction.
    The court did not err when it refused to join TKO as an indispensable party and
    struck Akers’s amended third-party claim against TKO. Lastly, the court did not
    err when it calculated post-judgment interest on the award of prejudgment interest.
    [¶89.]       However, because we now overrule Gettysburg to the extent it created
    a rule that prejudgment interest begins to accrue on the date of the breach, the
    issue of prejudgment interest is remanded for the circuit court to identify the date
    Casper’s loss or damage occurred as a result of Akers’s breach. Thereafter, the
    circuit court must recalculate prejudgment interest and post-judgment interest.
    [¶90.]       GILBERTSON, Chief Justice, and ZINTER, SEVERSON, and
    WILBUR, Justices, concur.
    -42-