Krsnak v. South Dakota Department of Environment & Natural Resources ( 2012 )


Menu:
  • #26367-a-LSW
    
    2012 S.D. 89
    IN THE SUPREME COURT
    OF THE
    STATE OF SOUTH DAKOTA
    ****
    JIMMY KRSNAK and
    LINDA L. KRSNAK,                           Appellants,
    v.
    SOUTH DAKOTA DEPARTMENT OF
    ENVIRONMENT and NATURAL
    RESOURCES, STEVEN M. PIRNER,
    DEPARTMENT SECRETARY and STAFF,
    IN THEIR OFFICIAL CAPACITIES,              Appellees.
    ****
    APPEAL FROM THE CIRCUIT COURT OF
    THE SIXTH JUDICIAL CIRCUIT
    HUGHES COUNTY, SOUTH DAKOTA
    ****
    THE HONORABLE MARK BARNETT
    Judge
    ****
    JAY M. LEIBEL of
    Issenhuth & Leibel, LLP
    Madison, South Dakota                      Attorneys for appellants.
    MARTY J. JACKLEY
    Attorney General
    PATRICIA ARCHER
    Assistant Attorney General
    Pierre, South Dakota                       Attorneys for appellees.
    ****
    ARGUED NOVEMBER 7, 2012
    OPINION FILED 12/12/12
    #26367
    WILBUR, Justice
    [¶1.]        The Krsnaks sought a writ of mandamus to stay or rescind the
    Department of Environment and Natural Resources’ (DENR) approval of the plans
    and specifications for the Brant Lake Sanitary District project. The Krsnaks claim
    DENR did not meet the requirements contained in statutes, administrative rules,
    and internal manuals. The trial court denied the writ of mandamus. The Krsnaks
    appeal. We affirm.
    FACTS AND PROCEDURAL BACKGROUND
    [¶2.]        The Brant Lake Sanitary District was organized under SDCL chapter
    34A-5 to provide a wastewater system for 235 residents and businesses near Brant
    Lake in Lake County, South Dakota. On March 26, 2012, DENR approved plans
    and specifications for the Brant Lake Sanitary District’s wastewater treatment
    facility (Brant Lake facility) in accordance with SDCL 34A-2-27(1). Residents and
    businesses near Brant Lake currently utilize private septic systems to handle their
    wastewater disposal. The Brant Lake facility plans propose to join and expand the
    Chester Sanitary District’s existing wastewater disposal system.
    [¶3.]        Chester’s current treatment system consists of two cells or lagoons
    covering approximately eight acres. In order to accommodate the increased flow of
    wastewater from Brant Lake, the plans include the construction of an additional
    treatment lagoon, which will tie into the existing two-cell lagoon system. Further,
    the plans include the construction of additional piping to transport wastewater to
    the treatment lagoons.
    -1-
    #26367
    [¶4.]         Chester’s existing wastewater disposal system operates under a
    surface water discharge permit that was previously issued by DENR under SDCL
    34A-2-36. Currently, the water discharge from the Chester facility flows into Skunk
    Creek, a tributary of the Big Sioux River. Once the Brant Lake facility is
    completed, discharge will continue to flow into Skunk Creek. Because the Brant
    Lake facility is an add-on to the Chester facility, there are no pending applications
    for any state-issued environmental permits by the Brant Lake Sanitary District.
    However, when the Chester surface water discharge permit comes up for renewal,
    the application permit will include the Chester and Brant Lake facility in its
    entirety.
    [¶5.]         Jimmy and Linda Krsnak reside in Lake County where they operate a
    vegetable farm called “Linda’s Gardens.” The Krsnaks’ home and business are near
    the proposed lagoon. The Krsnaks assert that the raw sewage from the Brant Lake
    and Chester facility will enter the lagoon closest to the Krsnaks’ home, potable well,
    and business. The Krsnaks estimate that their well is approximately 1000 feet from
    the lagoon and that their home is approximately 1090 feet from the lagoon. Water
    from the Krsnaks’ well is consumed by the Krsnaks and their employees, is used for
    the irrigation of vegetable fields, and is used to clean and hydrate vegetables prior
    to sale. Accordingly, the Krsnaks have opposed both the Chester and Brant Lake
    facilities.
    [¶6.]         After DENR approved the plans for the Brant Lake facility, the
    Krsnaks filed an application for a writ of mandamus with the trial court on April
    23, 2012. The application sought a writ ordering DENR to “stay the approval of the
    -2-
    #26367
    [Brant Lake Sanitary District] project until all requirements of the [internal
    manuals], administrative rules and law have been met.” On the same day, the trial
    court entered an alternative writ of mandamus directing DENR to show cause why
    a permanent writ of mandamus should not issue. On May 2, 2012, the trial court
    filed an amended alternative writ of mandamus ordering the parties to appear on
    May 14, 2012, for a hearing on DENR’s anticipated motion to quash.
    [¶7.]        On May 4, 2012, DENR filed a motion to quash the amended
    alternative writ of mandamus. The trial court held a hearing on May 14, 2012, and
    issued a bench decision denying the Krsnaks’ request for mandamus relief. The
    Krsnaks appeal on the following issue: Whether the trial court abused its discretion
    in denying the writ of mandamus requiring DENR to comply with applicable South
    Dakota statutes, administrative rules, and DENR internal guidelines in approving
    the plans and specifications for the Brant Lake facility.
    STANDARD OF REVIEW
    [¶8.]        “This Court reviews the decision to grant or deny a writ of mandamus
    under an abuse of discretion standard.” Grant Cnty. Concerned Citizens v. Grant
    Cnty. Bd. of Comm’rs, 
    2011 S.D. 5
    , ¶ 6, 
    794 N.W.2d 462
    , 464 (citing Vitek v. Bon
    Homme Cnty. Bd. of Comm’rs, 
    2002 S.D. 45
    , ¶ 5, 
    644 N.W.2d 231
    , 233). “An abuse
    of discretion refers to a discretion exercised to an end or purpose not justified by,
    and clearly against reason and evidence.” Argus Leader v. Hagen, 
    2007 S.D. 96
    , ¶ 7,
    
    739 N.W.2d 475
    , 478 (quoting Schafer v. Deuel Cnty. Bd. of Comm’rs, 
    2006 S.D. 106
    ,
    ¶ 4, 
    725 N.W.2d 241
    , 243). Further, “[s]tatutory interpretation and application are
    -3-
    #26367
    questions of law that we review de novo.” State v. Goulding, 
    2011 S.D. 25
    , ¶ 5, 
    799 N.W.2d 412
    , 414.
    ANALYSIS AND DECISION
    [¶9.]         South Dakota law allows a trial court to issue a writ of mandamus
    where no “plain, speedy, and adequate remedy [exists] in the ordinary course of
    law.” SDCL 21-29-1, 1 -2. “A writ of mandamus is an extraordinary remedy that
    will issue only when the duty to act is clear.” Woodruff v. Bd. of Comm’rs for Hand
    Cnty., 
    2007 S.D. 113
    , ¶ 3, 
    741 N.W.2d 746
    , 747 (quoting Baker v. Atkinson, 
    2001 S.D. 49
    , ¶ 16, 
    625 N.W.2d 265
    , 271); see also Atkinson v. City of Pierre, 
    2005 S.D. 114
    , ¶ 26, 
    706 N.W.2d 791
    ,799 (stating that “[m]andamus can only issue when the
    duty to act is unequivocal”). A writ of mandamus “commands the fulfillment of an
    existing legal duty, but creates no duty itself, and” does not act “upon . . . doubtful
    or unsettled law.” Woodruff, 
    2007 S.D. 113
    , ¶ 3, 
    741 N.W.2d at 747
     (quoting Sorrels
    v. Queen of Peace Hosp., 
    1998 S.D. 12
    , ¶ 6, 
    575 N.W.2d 240
    , 242). “To prevail on a
    writ of mandamus or prohibition, Petitioners must show ‘a clear legal right to
    performance of the specific duty sought to be compelled and the [respondent] must
    have a definite legal obligation to perform that duty.’” Cheyenne River Sioux Tribe
    1.      The full text of SDCL 21-29-1 provides:
    The writ of mandamus may be issued by the Supreme and
    circuit courts, to any inferior tribunal, corporation, board, or
    person, to compel the performance of an act which the law
    specifically enjoins as a duty resulting from an office, trust, or
    station; or to compel the admission of a party to the use and
    enjoyment of a right or office to which he is entitled, and from
    which he is unlawfully precluded by such inferior tribunal,
    corporation, board, or person.
    -4-
    #26367
    v. Davis, 
    2012 S.D. 69
    , ¶ 13, 
    822 N.W.2d 62
    , 66 (quoting H & W Contracting, LLC v.
    City of Watertown, 
    2001 S.D. 107
    , ¶ 24, 
    633 N.W.2d 167
    , 175) (alteration in
    original).
    [¶10.]        “Mandamus may only be used to compel ministerial duties, not
    discretionary duties.” Sorensen v. Sommervold, 
    2005 S.D. 33
    , ¶ 9, 
    694 N.W.2d 266
    ,
    269 (citing Willoughby v. Grim, 
    1998 S.D. 68
    , ¶ 8, 
    581 N.W.2d 165
    , 168). “[W]hen
    public officials have a mandatory duty to perform . . . mandamus may require
    performance” but mandamus may not dictate details when there is discretion in
    how the duty is to be performed. Id. ¶ 9. Further, “an application for a writ of
    mandamus in the form of an affidavit [i]s sufficiently analogous to a complaint in a
    civil action to permit a defendant to move to quash the alternative writ” if a
    plaintiff’s application is found insufficient. McDonald v. State, 
    86 S.D. 570
    , 574, 
    199 N.W.2d 583
    , 585 (1972).
    Statutes: SDCL 34A-2-27 and SDCL 34A-2-29
    [¶11.]        The Krsnaks argue that the trial court improperly quashed the writ of
    mandamus because DENR had a duty to abide by the first provision of SDCL 34A-2-
    27. 2 Under the first provision of SDCL 34A-2-27, the Krsnaks argue that DENR
    should have required the Brant Lake Sanitary District to obtain a construction
    permit. Specifically, the provision requires “a valid construction permit from the
    water management board for the disposal of all wastes which are, or may be,
    discharged thereby into the groundwaters of the state[.]” SDCL 34A-2-27 (emphasis
    2.       The parties agree that SDCL 34A-2-27 has two distinct provisions.
    -5-
    #26367
    added). The State argues that this portion of SDCL 34A-2-27 is inapplicable. We
    agree.
    [¶12.]       The Krsnaks claim that the Brant Lake facility “seepage” will
    inevitably discharge into the surrounding groundwater and thus, require the facility
    to obtain a construction permit in compliance with the first provision of SDCL 34A-
    2-27. While the record indicates that the Brant Lake facility will discharge surface
    water into Skunk Creek, the Krsnaks’ application was insufficient to establish that
    the Brant Lake facility would discharge into the groundwaters of this State.
    Because the Krsnaks’ application for writ of mandamus failed to adequately
    establish groundwater discharge, the trial court correctly determined that DENR
    did not have a clear duty to obtain a construction permit under SDCL 34A-2-27.
    [¶13.]       The Krsnaks also argue that DENR abused its authority under the
    second provision of SDCL 34A-2-27 and SDCL 34A-2-29. Specifically, the second
    portion of SDCL 34A-2-27 provides:
    [N]or may any person carry on any of the following activities
    without approval of plans and specifications from the secretary
    of the department pursuant to § 34A-2-29 for the disposal of all
    wastes which are, or may be, discharged thereby into surface
    waters of the state:
    (1) The construction, installation, modification, or
    operation of any disposal system or part thereof, or any
    extension or addition thereto[.]
    SDCL 34A-2-29 provides that “[t]he secretary, under such conditions as the
    secretary may prescribe, may require the submission of such plans, specifications,
    and other information as the secretary deems necessary . . . .” (Emphasis added.)
    Although “the Legislature cannot abdicate its essential power to enact basic policies
    into law[,] . . . once the Legislature has created broad policy through its enactments,
    -6-
    #26367
    it may delegate in the execution of that policy certain quasi-legislative powers or
    functions to executive or administrative officers or agencies[.]” State v. Moschell,
    
    2004 S.D. 35
    , ¶ 15, 
    677 N.W.2d 551
    , 558 (citing Boe v. Foss, 
    76 S.D. 295
    , 313, 
    77 N.W.2d 1
    , 11 (1956)). The Legislature sets “standards to guide those officers or
    agencies in the exercise of such powers.” 
    Id.
    [¶14.]         Here, the Legislature established the overall fundamental policy
    regarding the prevention and regulation of water pollution in South Dakota. See
    SDCL chapter 34A-2 (covering “Water Pollution Control”). Further, the Legislature
    granted DENR the power to carry out these legislative objectives. See SDCL 34A-2-
    28. The record demonstrates that the Brant Lake Sanitary District submitted plans
    and specifications to DENR for approval and that those plans were appropriately
    reviewed and approved. The discretionary language in both SDCL 34A-2-27 and
    SDCL 34A-2-29 is indicative of the Secretary’s authority to act. Because those
    statutes gave DENR discretion to approve the plans for the Brant Lake facility, the
    trial court did not err in denying the writ based on DENR’s alleged failure to abide
    by SDCL 34A-2-27 or SDCL 34A-2-29.
    [¶15.]         Further, the Krsnaks’ application for writ of mandamus failed to
    establish that DENR disregarded a clear duty to act under SDCL 34A-2-27 or SDCL
    34A-2-29. Those statutes gave DENR discretion to require plans and specifications
    as DENR deemed necessary to carry out applicable administrative rules and
    statutes. 3 DENR’s approval of the Brant Lake facility plans and specifications was
    3.       DENR acknowledged, however, that this discretion cannot be “absolute” or
    “unfettered.”
    -7-
    #26367
    not a ministerial act, but rather an appropriate exercise of the discretion afforded
    DENR under SDCL 34A-2-27 and SDCL 34A-2-29. Accordingly, the trial court did
    not abuse its discretion in finding that DENR did not disregard a clear duty to act
    under either SDCL 34A-2-27 or SDCL 34A-2-29. See Woodruff, 
    2007 S.D. 113
    , ¶ 3,
    
    741 N.W.2d at
    747 (citing Baker, 
    2001 S.D. 49
    , ¶ 16, 
    625 N.W.2d at 271
    ).
    Administrative Rules
    [¶16.]       The Krsnaks argue that the trial court improperly quashed the writ of
    mandamus because DENR failed to follow the appropriate administrative rules
    when reviewing the plans and specifications for the Brant Lake facility.
    “Administrative rules have ‘the force of law and are presumed valid.’” State v.
    Guerra, 
    2009 S.D. 74
    , ¶ 32, 
    772 N.W.2d 907
    , 916 (quoting Sioux Falls Shopping
    News, Inc. v. Dep’t of Revenue & Regulation, 
    2008 S.D. 34
    , ¶ 24, 
    749 N.W.2d 522
    ,
    527). “[A]n agency is usually given a reasonable range of informed discretion in the
    interpretation and application of its own rules when the language subject to
    construction is technical in nature or ambiguous, or when the agency interpretation
    is one of long standing.” Id. ¶ 32 (quoting Nelson v. S.D. State Bd. of Dentistry, 
    464 N.W.2d 621
    , 624 (S.D. 1991)). Further, “[a]dministrative regulations are subject to
    the same rules of construction as are statutes.” Westmed Rehab, Inc. v. Dep’t of Soc.
    Servs., 
    2004 S.D. 104
    , ¶ 8, 
    687 N.W.2d 516
    , 518 (citing Schroeder v. Dep’t of Soc.
    Servs., 
    1996 S.D. 34
    , ¶ 9, 
    545 N.W.2d 223
    , 227-28). “When regulatory language is
    clear, certain and unambiguous, our function is confined to declaring its meaning as
    clearly expressed.” 
    Id.
    -8-
    #26367
    [¶17.]         Here, the applicable administrative rules can be found under article
    74:53, which addresses “Water Supply and Treatment Systems.” There are five
    chapters under this title, one of which has been repealed. See ARSD 74:53:03.
    Each remaining chapter covers a different aspect of water supply and treatment
    systems. DENR evaluated the plans and specifications for the Brant Lake facility
    under article 74:53:04, entitled “Works of Sanitary Significance.” The Krsnaks do
    not contend that DENR abused its discretion in evaluating the plans and
    specifications of the Brant Lake facility in accordance with ARSD 74:53:04 or that
    DENR acted in violation of ARSD 74:53:04.
    [¶18.]         Rather, the Krsnaks claim that DENR failed to consider applicable
    administrative rules under chapter 74:53:01, titled “[i]ndividual and small on-site
    wastewater systems.” 4 An individual on-site wastewater system is defined as “a
    system or facility for treating, neutralizing, stabilizing, or dispersing wastes from
    one source[.]” ARSD 74:53:01:01(30) (emphasis added). DENR contends that
    chapter 74:53:01 is inapplicable because the Brant Lake facility will receive waste
    from more than one source and because the Brant Lake add-on does not constitute a
    “small on-site wastewater system.” We agree. The Brant Lake facility will provide
    4.       Our previous statements regarding the application of titles within the
    statutory context are equally applicable when reviewing administrative rules.
    “This court may refer to [a] title in an effort to interpret the statute at issue.”
    In re Certification of a Question of Law from the U.S. Dist. Court Dist. of S.D.,
    W. Div., 
    402 N.W.2d 340
    , 342 (S.D. 1987) (citation omitted). Although not
    determinative, a title may nonetheless be instructive. However, “[t]he title or
    heading of a statute may not be used to lessen or expand the meaning of the
    statute.” 
    Id.
     (citing Olson v. City of Sioux Falls, 
    63 S.D. 563
    , 
    262 N.W. 85
    , 87
    (1935)).
    -9-
    #26367
    a wastewater disposal system to approximately 235 persons within the Brant Lake
    community. Therefore, the rules in ARSD 74:53:01 do not apply to the Brant Lake
    Sanitary project.
    [¶19.]         Even if DENR were required to comply with administrative rules
    under ARSD 74:53:01, 5 an examination of the specific rules cited by the Krsnaks
    establish that they do not apply in this instance. Specifically, the Krsnaks assert
    that DENR was required to comply with ARSD 74:53:01:15, which addresses the
    “[s]eparation required above groundwater or geological formations.” The Krsnaks
    rely on appendices A-2 and A-3 of their brief, which were purportedly attached to
    their “affidavit in support of response to respondent’s motion to quash the amended
    writ of mandamus.” However, a review of the settled record reveals that the only
    document actually attached to that affidavit is a one-page list of documents that the
    Krsnaks included as exhibits to their trial brief. The trial brief, however, was not
    filed and therefore, the appendices the Krsnaks rely on are not part of the record
    before this Court.
    [¶20.]         Further, an examination of the language of ARSD 74:53:01:15 removes
    any question about its applicability to the Brant Lake facility. The rule establishes
    certain requirements for “an absorption bed, trench, or seepage pit bottom . . . septic
    tank, or any other component of a subsurface absorption system[.]” The definitions
    5.       Here, we decline to address any other administrative rules that the Krsnaks
    allege were improperly complied with by DENR. In its initial application for
    writ of mandamus before the trial court, the Krsnaks made a general
    assertion that “specific portions of administrative rules” were not followed by
    DENR. However, the only rule specifically referenced by the Krsnaks was
    ARSD 74:53:01:15.
    -10-
    #26367
    found in ARSD 74:53:01:01 demonstrate that the Brant Lake facility, which is
    designed with a lagoon, does not fall within these categories. Accordingly, we
    cannot say that DENR had any duty, much less an unequivocal duty, to act under
    ARSD 74:53:01:15. See Atkinson, 
    2005 S.D. 114
    , ¶ 26, 
    706 N.W.2d at 799
    .
    Therefore, the trial court did not abuse its discretion in denying the Krsnaks’ writ of
    mandamus for DENR’s alleged failure to comply with administrative rules under
    chapter 74:53:01.
    Internal Manuals
    [¶21.]         Finally, the Krsnaks argue that the trial court erred in quashing the
    writ of mandamus because DENR failed to apply its own internal guidelines when it
    approved the plans and specifications for the Brant Lake facility. Specifically, the
    Krsnaks assert that DENR was required to consider the specifications outlined in
    two separate manuals. The first is the Recommended Design Criteria Manual for
    Wastewater Collection and Treatment Facilities (RDCM), a DENR manual
    published in 1991. 6 The second is a document entitled the Recommended
    Standards for Wastewater Facilities (RSWF), a document published by ten states
    termed the “Great Lakes – Upper Mississippi River,” a group that does not include
    South Dakota. This document was last updated in 2004.
    [¶22.]         In support of its contention that DENR’s failure to abide by these
    manuals was faulty, the Krsnaks cite to case law addressing the importance of
    6.       The affidavit of DENR engineer, Andrew Bruels provides that the guidelines
    within the RDCM “have not been adopted as rules by DENR” and that the
    document serves as “a guide for use by professional engineers in designing
    and preparing plans and specifications for wastewater facilities.”
    -11-
    #26367
    compliance with administrative rules, statutes, and ordinances. Yet, the manuals
    and the guidelines at issue have not been codified within our statutes or
    administrative rules. If DENR had “a specific duty to act, that duty must be
    apparent in state law[.]” See Jensen v. Lincoln Cnty. Bd. of Comm’rs, 
    2006 S.D. 61
    ,
    ¶ 11, 
    718 N.W.2d 606
    , 610-11. Further, the titles of the documents themselves
    suggest that they are “Recommended Standards” and “Recommended Design
    Criteria.” Therefore application of the standards would be discretionary on DENR’s
    part. Accordingly, the trial court did not abuse its discretion in quashing the writ of
    mandamus for DENR’s alleged failure to apply internal guidelines in the manner
    urged by the Krsnaks because DENR did not have a clear duty to apply the RDCM
    and RSWF when considering the plans and specifications for the Brant Lake
    facility.
    CONCLUSION
    [¶23.]       To prevail the Krsnaks must show a clear legal right to performance of
    the specific duty sought to be compelled (rescission by DENR of approval of the
    plans and specifications for the Brant Lake facility) and DENR must have a definite
    legal obligation to act (rescind the approval of the plans and specifications). The
    Krsnaks have not met their burden to show either their clear legal right or that
    DENR disregarded a clear duty to act under the applicable statutes, administrative
    rules, or manuals. Accordingly, the trial court did not abuse its discretion in
    denying the Krsnaks’ application for writ of mandamus.
    [¶24.]       Affirmed.
    -12-
    #26367
    [¶25.]     GILBERTSON, Chief Justice, and KONENKAMP, ZINTER, and
    SEVERSON, Justices, concur.
    -13-