Kadrmas, Lee & Jackson, Inc. v. Morris , 2010 S.D. 61 ( 2010 )


Menu:
  • #25289-rev & rem-JKK
    
    2010 SD 61
    IN THE SUPREME COURT
    OF THE
    STATE OF SOUTH DAKOTA
    * * * *
    KADRMAS, LEE AND JACKSON, INC.,
    a North Dakota Corporation,               Plaintiffs and Appellees,
    v.
    MITCH MORRIS a/k/a MITCHEL
    E. MORRIS, individually and
    doing business as MORRIS
    RANCH GROUP,                              Defendants and Appellants.
    * * * *
    APPEAL FROM THE CIRCUIT COURT
    OF THE SEVENTH JUDICIAL CIRCUIT
    PENNINGTON COUNTY, SOUTH DAKOTA
    * * * *
    HONORABLE JOHN J. DELANEY
    Judge
    * * * *
    RONDA MILLER                                    Attorney for plaintiffs
    Belle Fourche, South Dakota                     and appellees.
    BRAD A. SCHREIBER                               Attorney for defendants
    Pierre, South Dakota                            and appellants.
    * * * *
    CONSIDERED ON BRIEFS
    ON APRIL 26, 2010
    OPINION FILED 07/21/10
    #25289
    KONENKAMP, Justice
    [¶1.]        In this breach of contract action, plaintiff alleged that defendant failed
    to pay on two written contracts, but defendant claimed that he paid a $10,000
    retainer on those contracts. Plaintiff responded that the $10,000 payment was on
    an oral contract that had been completed. The circuit court instructed the jury that
    if it found that the oral contract existed, “the $10,000 must be applied to the claim
    for work performed under that contract.” Because the court told the jury that it
    must apply the payment only to the purported oral contract, it took from the jury
    the job of resolving a disputed issue of fact. We reverse and remand for a new trial.
    Background
    [¶2.]        Mitch Morris sought to develop some land two miles south of Rapid
    City, South Dakota. His real estate agent, Stan Hauck, put Morris in touch with
    Kadrmas, Lee and Jackson, Inc., a regional engineering and planning firm.
    Kadrmas began preliminary work in December 2004. Rodney Senn, an engineer
    with Kadrmas, sent Stan Hauck a letter indicating that the cost of the preliminary
    work would be $12,000. Morris later testified that Hauck had no authority to make
    a binding contract on Morris’s behalf. The preliminary work was completed in July
    2005. Morris paid Kadrmas $10,000 in October of that year, and later in the same
    month Kadrmas and Morris executed two written contracts. One contract was for
    the design on extending water services to the land; the other was for the design of
    the sewer system.
    [¶3.]        Beginning in November 2005, Kadrmas sent Morris invoices for
    services provided on the design of the water line extension. In February 2006,
    Kadrmas sent invoices to Morris for services related to the sewer lines. These
    invoices were later offered in evidence along with summaries of the hours worked
    on the Morris project. The charges on these services were: preliminary work —
    $9,625.73; water line extension — $20,136.66; sewer line extension — $7,650.72.
    [¶4.]         At some point, Morris telephoned Kadrmas to say that he was not
    receiving any invoices. Senn later testified that he sat down with Morris and
    showed him the invoices. Except for the initial $10,000 he paid in October 2005,
    Morris made no other payments. In February 2006, Kadrmas stopped work on the
    project.
    [¶5.]         Kadrmas brought suit against Morris for breach of contract. At trial,
    Morris claimed that the $10,000 he paid to Kadrmas was a retainer for the two
    October 2005 contracts. Kadrmas, on the other hand, claimed that the $10,000 was
    payment for the preliminary work and that Morris breached the two contracts when
    he failed to pay on the invoices. The jury awarded $27,787.38 in damages to
    Kadrmas. After trial, the circuit court denied Morris’s renewed motion for
    judgment as a matter of law or in the alternative a new trial. He appeals asserting
    that the court improperly instructed the jury in two respects and that Kadrmas
    failed to prove its damages. 1 We find only one assertion of error meritorious.
    Analysis and Decision
    1.      We review for abuse of discretion a trial court’s decision to grant or deny a
    motion for new trial and a renewed motion for judgment as a matter of law.
    SDCL 15-6-50(b); SDCL 15-6-59(a); Duda v. Phatty McGees, Inc., 
    2008 SD 115
    , ¶19, 758 NW2d 754, 759-60 (citations omitted). We review the court’s
    wording and arrangement of jury instructions for an abuse of discretion.
    Carlson v. Const. Co., 
    2009 SD 6
    , ¶6 n1, 761 NW2d 595, 597 n1 (citations
    omitted). But a court has no discretion to give incorrect or misleading
    instructions, and to do so prejudicially constitutes reversible error. 
    Id.
    (citations omitted).
    [¶6.]         At trial, the parties contested the purpose of the $10,000 payment.
    Kadrmas asserted that the payment was for preliminary work done before the two
    contracts were signed. Morris maintained that the $10,000 was a retainer for the
    two October 2005 contracts; that he made no oral agreement to pay for preliminary
    work; and that Hauck was not his agent for the purpose of contracting for
    preliminary engineering services.
    [¶7.]         On appeal, Morris argues that the circuit court improperly instructed
    the jury to apply the $10,000 to the preliminary contract if it found such contract
    existed. 2 Kadrmas claims that Morris failed to object to this instruction, and
    2.      On page three of the instructions, the court charged the jury on the burden of
    proof:
    One asserting a claim must prove that claim by the greater
    convincing force of the evidence. If the evidence is evenly
    balanced so that you conclude that neither party has produced
    the greater convincing force, then you must find against the
    party who has the burden of proof.
    In this case, the Corporation has the burden of proving:
    a. As to the preliminary contract that the parties created either
    an express or an implied contract. If that contract exists, the
    $10,000 must be applied to the claim for work performed under
    that contract.
    b. That Mr. Morris had a contractual obligation to pay the
    Corporation for work it had performed pursuant to each of the
    written contracts; and
    c. That he breached those contracts by failing and refusing to do
    so; and
    d. The damages which were incurred as a result of that breach.
    Mr. Morris has the burden of proving that the Corporation has
    not performed the work or services which entitled it to all or
    some of the payments the Corporation claims are due and owing
    under the contract.
    (continued . . .)
    therefore, waived the issue. From our review of the record, however, Morris
    sufficiently objected to preserve the issue.
    [¶8.]        At the time of settling jury instructions, the court did not have its
    prepared instructions. Rather, the court and parties were reviewing Kadrmas’s
    proposed instructions. Morris objected to two instructions that related to the
    written contracts and alleged oral contract. The court responded,
    It seems to me that I would instruct that there are three
    contracts at issue. There is a question of a contract for
    preliminary work. And there are two written contracts.
    As to the contract for preliminary work, the instruction
    relevant to quantum meruit may apply.
    As to contracts two and three, the written contracts - - I
    mean, by its terms that instruction would only apply to that.
    Because if I talk to the jury, I would say that there is one oral
    contract alleged and two written ones. The written contracts are
    admitted; and there is a dispute over the existence of the oral
    contract.
    In either event, there is $10,000 that has been paid and
    admitted and that needs to be deducted from the damages you
    find, if any, on behalf of the plaintiff. I think I need an
    instruction to that end of some sort. So that’s basically what I
    am inclined to do.
    As part of his objection, Morris’s counsel argued, “So the only issue, I think, is
    whether or not the $10,000 applies to those [two written] contracts or not and we
    don’t need to discuss the validity or invalidity of a prior agreement. So I would
    object to both of these on that basis. And simply an instruction either the jury
    thinks the $10,000 gets applied or it doesn’t get applied.”
    __________________
    (. . . continued)
    (Emphasis added.)
    [¶9.]          After listening to the parties’ arguments, the court recessed to draft its
    own jury instructions. Upon reconvening, counsel for Morris objected to page three
    of the court’s instructions: “I think the issue is much simpler than that. . . . I think
    the jury can be instructed that there was $10,000 that has been paid and they can
    be instructed that it’s either been paid for the work that was performed beforehand
    or it was paid for the work that was performed under the two contracts.” The court
    denied Morris’s objection. 3
    [¶10.]         It is undisputed that Morris argued that the $10,000 applied to the two
    written contracts and that Kadrmas maintained that the $10,000 applied to a
    previously completed oral agreement for preliminary work. There is also no dispute
    that the jury was left to determine if such a preliminary contract existed. When the
    court then instructed the jury that it was required to apply the $10,000 paid to such
    preliminary agreement, the court took away from the jury the question whether
    Morris proved that the $10,000 applied to the two written contracts. Certainly, the
    3.       There was a latent ambiguity in the court’s instructions. In the last
    instruction, the court reminded the jury: “Remember in reaching a damage
    figure that Mr. Morris has paid and the Corporation has received the sum of
    $10,000.” Neither side suggests how this should be resolved.
    jury could have found that a preliminary agreement existed, that Kadrmas
    performed under that agreement free of charge, and that the $10,000 was paid as a
    retainer on services to be provided under the two written contracts. Therefore, it
    was error for the court to instruct the jury that if it found a preliminary contract to
    exist it must apply the $10,000 to that contract. Morris was prejudiced by this error
    as the jury was not free to apply the $10,000 where it deemed warranted. Morris is
    entitled to a new trial.
    [¶11.]       Reversed and remanded.
    [¶12.]       GILBERTSON, Chief Justice, and ZINTER, MEIERHENRY, and
    SEVERSON, Justices, concur.
    

Document Info

Docket Number: 25289

Citation Numbers: 2010 SD 61, 786 N.W.2d 381, 2010 S.D. 61, 2010 S.D. LEXIS 102, 2010 WL 2856359

Judges: Gilbertson, Konenkamp, Meierhenry, Severson, Zinter

Filed Date: 7/21/2010

Precedential Status: Precedential

Modified Date: 11/12/2024