Charles Pesce v. East Tennessee Construction Services, Inc. ( 2011 )


Menu:
  •                 IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    January 31, 2011 Session
    CHARLES PESCE v. EAST TENNESSEE
    CONSTRUCTION SERVICES, INC.
    Appeal from the Circuit Court for McMinn County
    No. 25444     J. Michael Sharp, Judge
    No. E2010-01071-COA-R3-CV - Filed February 28, 2011
    Charles Pesce (“the Owner”) is a practicing dentist. He contracted with East Tennessee
    Construction Services, Inc. (“the Builder”) to build him a new office for his practice on a lot
    owned by him. The Builder constructed the building, but with numerous undisputed defects.
    The Owner filed this action which culminated in a bench trial that lasted several days. Based
    upon diminution in value, the trial court awarded the Owner $282,000 in damages. The trial
    court expressly found that the cost to repair the structure was an unacceptable measure of
    damages because it “is disproportionate . . . to the difference in the value of the structure
    actually constructed and the one contracted for.” The court awarded the Owner discretionary
    costs of over $10,000. The Owner appeals challenging the measure of damages as well as
    the amount awarded under the diminution in value measure. The Owner also challenges the
    trial court’s failure to order the Builder to reimburse him for fees charged by one of the
    Owner’s experts in connection with his discovery deposition taken by the Builder. The
    Builder challenges the award of discretionary costs and argues that the damages awarded are
    excessive. We reverse in part and affirm the remaining judgment as modified.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court
    Reversed in Part; Remaining Judgment Affirmed as Modified;
    Case Remanded with Instructions
    C HARLES D. S USANO, JR., J., delivered the opinion of the Court, in which H ERSCHEL P.
    F RANKS, P.J., joined. D. M ICHAEL S WINEY, J., filed a separate concurring opinion.
    D. Mitchell Bryant, Athens, Tennessee, for the appellant, Charles Pesce.
    Jerry M. Martin, Knoxville, Tennessee, for the appellee, East Tennessee Construction
    Services, Inc.
    OPINION
    I.
    It is undisputed at this stage of the litigation that the parties had a verbal contract for
    the Builder to construct a dental office for the Owner on the latter’s lot. It was a cost plus
    contract. The only plans were sketches by the Builder and drawings prepared by suppliers
    of furnishings and fixtures for the office. Also, various components came with
    manufacturer’s installation instructions and sketches. For example, the “Andersen” windows
    called for flashing and caulking around the perimeter of the windows. It is undisputed that
    the Builder constructed a building with numerous code violations and structural deficiencies.
    The primary problem with the building is water leakage into the interior of the building with
    resulting mold and mildew. Some of the water leakage appears to have come from around
    windows that were not properly flashed and caulked. Much of the water leakage is into the
    basement itself because of improper flashing and water-proofing around the perimeter of the
    basement. The basement is the same size as the primary floor of the building, i.e, 2750
    square feet. Originally, one-half the basement space, or 1375 square feet, was to be finished
    to office grade space. The basement as constructed, has some interior walls but is otherwise
    unfinished. Because of the water problems, the basement can only be used for storage.
    Another major problem with the building is that the structural floor trusses are installed
    below ground level. At the time of trial, repairs had not been made, but the Owner had, for
    several years, been using the building as the site of his profitable dental practice.
    The Owner hired numerous experts in an attempt to prove his case. One of the experts
    is Mr. Faris Eid. The Builder took Mr. Eid’s deposition over the course of two days. On the
    first day, the Builder asked Mr. Eid to provide copies of all his files in the case, including any
    remedial plans and all his computer files. Mr. Eid informed the Builder’s counsel that it
    would take several days of work to locate, copy, and organize all the material he had
    requested, especially since it required revisiting computer web sites. Nevertheless, the
    Builder insisted on the copies. Mr. Eid, with the help of his office staff, complied. They
    assembled in excess of 1500 documents over the course of several days and produced them
    at which time the deposition was resumed and completed on the second day.
    Mr. Eid sent a bill in the amount of $6,667.46 directly to the Owner, who, through his
    counsel, presented the bill to counsel for the Builder for payment. The Builder refused to pay
    the bill. The Owner then filed a motion with the court requesting that the Builder be
    compelled to pay the bill. The bill is attached to the motion. It reflects a total of 23 hours
    for the witness at the rate of $200 per hour, approximately $300 for staff work, 1335 pages
    of color copies at the rate of $1.00 per copy, and approximately 3400 pages of black and
    -2-
    white copies at a rate of an average of approximately 12 cents per copy. Upon hearing the
    motion, the court found
    there was an implied agreement for the [Builder] to pay
    reasonable fees to [the Owner’s] expert, Mr. Faris Eid . . ., for
    making [himself] available at the request of the [Builder], for a
    discovery deposition. [The Owner] is entitled to immediate
    reimbursement for those fees which he has already paid.
    The court found that the portion of the bill already paid by the Owner that was ripe for
    reimbursement was “the amount of $1,582 consisting of 7.91 hours for actual deposition time
    at $200 per hour.” The court further ordered “that the balance of the Motion to Compel
    Payment and for Costs and Fees related to the remainder of the billing submitted by Mr. Eid
    for deposition preparation time, as well as the time of other individuals at his firm, used to
    copy and collate various documents requested by the [Builder], as well as costs for bringing
    this Motion shall be deferred until time of further hearing in this cause.” The court
    specifically noted that the reimbursement the Owner was requesting did not qualify as
    discretionary costs under Tenn. R. Civ. P. 54.
    The record does not reflect any effort by either party to bring the unresolved issue to
    the court’s attention until the hearing on the Owner’s motion for discretionary costs. At that
    juncture, the Owner included Mr. Eid’s fees and expenses for which he had not been
    reimbursed in his request for discretionary costs. At the hearing on the motion, the Owner
    renewed his request that he be reimbursed for the remainder of his payment of Mr. Eid’s bill,
    without regard to whether it was called discretionary costs or something else. Specifically,
    counsel argued:
    Obviously, the full amount has been paid by [the Owner] to Mr.
    Eid for that. The [Builder] has paid the $1582, or reimbursed
    that . . . they were ordered to pay. And we are asking, whether
    it be in the nature of discretionary costs or just regular
    [litigation] costs, we are asking for the balance of $5085.46 to
    be . . . reimbursed to Dr. Pesce. . . . [I]t was [done] at the
    [Builder’s] request and demand. . . . .
    . . . . So, that’s why I’m saying, you can look at it, I guess, as a
    discretionary cost or you can look at it as just a litigation cost
    based upon demands made by the [Builder] that were not paid.
    -3-
    In its memorandum opinion on the issue of discretionary costs, the court stated,
    With regard to. . . the expert fees paid to Mr. Faris Eid, this
    court finds that the $1,582 already paid to Mr. Eid is a
    recoverable discretionary cost. . . . . This court holds that any
    other fees paid to Mr. Eid should not be recoverable, given the
    facts and circumstances of this case, and given the limitations of
    Tennessee Rule of Civil Procedure 54.02(2).
    In its final order, the court stated its denial in slightly different terminology.
    The Court further finds that [the Owner] is entitled to recover
    the sum of $1,582 for expenses incurred related to Mr. Eid’s
    deposition, and that said amount of $1,582 has already been
    reimbursed to him by the [Builder].
    The Owner chose to present his case, and specifically the issue of damages, from the
    perspective of cost of repair. The Owner did not present proof of diminution in value and
    neither did the Builder. In fact, the Builder’s only witness as to the value of the building
    made his appraisal without inspecting the interior of the building and based his appraisal on
    a street-side inspection with the assumption that the building’s condition was “good with no
    deficiencies.” After hearing proof for approximately seven days, the court expressed its
    concern that the cost of repairing the building could well exceed what it cost to build it. Out
    of concern that the cost of repair would prove unreasonable and disproportionate to the
    diminished value of the structure, the court ordered the parties to present proof of the
    diminution in value as an alternative measure of damages under Wilkes v. Shaw Enterprises,
    LLC, No. M2006-01014-COA-R3-CV, 
    2008 WL 695882
     (Tenn. Ct. App. M.S., filed March
    14, 2008).
    The court convened a hearing on June 23, 2009, to hear proof on diminished value.
    The Builder’s only live witness, Mr. Cobble, testified that diminished value should be
    calculated by simply subtracting the cost of repair, which he placed at $107,451, from the
    normal market value of the structure, whatever that value was. Mr. Cobble made it clear that
    he did not attempt to value the building, either in its supposed-to-be constructed state or its
    unrepaired state.
    The primary focus of the proof became the testimony of Bryan Glascock. It was his
    testimony that the court used as the basis for its findings related to damages. Glascock is a
    commercial real estate appraiser, a real estate broker, and a real estate auctioneer, who has
    been in the real estate business for 36 years. He is also licensed in Tennessee to do property
    -4-
    tax appeals. Glascock inspected the building inside and outside and had numerous
    conversations with the Owner about the building. He also reviewed all of the drawings and
    sketches, such as they were. He based his appraisal of diminished value upon the actual
    building, as is with its numerous defects, compared to a hypothetical building, “built to code
    [with] no deficiencies, no leaks.” He based his values on two valuation methods, the first
    being sales of comparable structures and the second being a cost to build the structure.
    According to Glascock the two methods, as applied to the facts of this case, produced similar
    figures. Glascock readily admitted that he did not find sales of dental offices, so he used
    sales of other commercial offices, including medical offices and retail stores, as comparables.
    Also, he admitted that his cost figures were based on a computer program using low grade
    or deficient quality to produce the as built cost, and higher grade material to produce the
    hypothetical building that the Owner expected based upon the contract for a dental office.
    He also admitted that his methods produced a “wide range of values for buildings that are
    well-built and well-designed, and then a range of values for buildings that are not so well-
    built or maybe older or not really as well located.” Glascock testified that his appraisals are
    “90 percent accurate.” The “bottom line” was a value of $722,000 for the hypothetical
    building without deficiencies and $275,000 for the building as is. He explained in direct that
    the latter figure was produced by multiplying the ground floor area of 2750 square feet, by
    a value of $100 per square foot, to arrive at $275,000. He did not explain in direct how he
    arrived at the calculation of $722,000 other than to say he based it upon a fully finished
    ground floor and a basement of the same size with only one-half of the basement area
    finished.
    On cross-examination, Glascock was asked whether he assigned any value to the
    basement in the as built, less than desirable, structure. He admitted that he did not assign a
    value to the basement space, and he also admitted that the basement obviously had value.
    He explained that he treated the basement as an “amenity,” the amenity being “storage space”
    that was included in comparable sales that resulted in his valuation of the main floor at $100
    per square foot rather than a lower figure. The cross-examination clarified the basis for the
    valuation of the hypothetical structure at $722,000. He based it upon comparable sales in the
    range of $160 to $180 per square foot and used $175 per square foot as the value per square
    foot of the hypothetical building. He then multiplied his value per square foot by a gross
    square footage of 4125, or the 2750 square feet of the ground floor plus 1375 square feet of
    the basement that were supposed to have been finished. Glascock admitted on cross-
    examination that in reaching his final diminished value of $447,000 he placed “great
    reliance” on an estimate the Owner provided him reflecting cost to repair of $456,000. When
    the attorneys finished with their questions, the court asked a few of its own “to make sure [it]
    understood.”
    -5-
    The Court: . . . . In your report, you figured 4,125 square feet in
    order to come up with your 722 value?
    The Witness: Yes.
    The Court: And you figured the 2,750 square feet and come up
    with the 275 value?
    The Witness: That’s correct.
    The Court: Okay. Which effectively, then, you didn’t figure
    anything for basement space. And I heard your testimony as to
    why. But it did figure a half-finished basement space, fully
    usable basement space on the first?
    The Witness: That’s correct.
    The Court: All right. If you had figured in that we just had
    unfinished basement space[,] . . . do you have a square foot
    figure on that?
    The Witness: The per square foot figure for . . . a class A
    building with no deficiencies and had a completely wide open
    basement space would probably be more per square foot than
    my conclusions were for A. Let’s say we had 2,750 square feet
    on both buildings.
    *   *     *
    One . . . is well-built. One of them may have problems. The
    basements are wide open. On the well-built 2,750 square foot
    building without a basement, the value per square foot would, in
    my opinion, be greater than the $175 because you have a smaller
    building, and usually the smaller the building the greater the
    value per square foot. I would . . . estimate approximately
    $100,000 difference because of the half-finished basement.
    So . . . if I were asked to appraise 2,750 square foot building, I
    would probably be in the mid $600 – 600,000 range. The
    finished basement adds probably another $100,000 to that, and
    -6-
    is based generally on what it would cost to – to have finished
    space in the basement.
    So the number I came up with, $175, I’m saying, you know,
    really nice buildings out there are selling for more than two
    hundred dollars a foot; however, if I’m including the basement
    space in this I’d have to pull my value per square foot down to
    reflect that some of my space is not aboveground [sic] space.
    Upon hearing the proof, the court rendered its memorandum opinion in favor of the
    Owner. The court noted that the construction cost of the building was approximately
    $460,000. The court also noted that the testimony regarding the cost of repair ranged
    “anywhere from the low $30,000 range, based upon the [Builder’s] proof, all the way up to
    . . . exceeding $660,000 based upon the [Owner’s] proof.” However, the court effectively
    narrowed that range to exclude the Builder’s proof when it rejected testimony on behalf of
    the Builder that the building could be repaired for $107,000. The court rejected the
    testimony because the testimony falsely assumed the building did not have substantial defects
    and because repairs of $107,000 would not bring the building up to code or even allow it to
    pass a building inspection. With regard to the proper measure of damages the court found:
    The court adopts the Glascock appraisal as the court’s proper
    measure to show the diminution in value damages. The court
    does not believe that the cost of repairs that would be required
    to repair this building are reasonable. The court specifically
    finds that the cost of repair is disproportionate when compared
    to the difference in the value of the structure actually
    constructed and the one contracted for. Therefore, the court
    finds the diminution in value is the proper measure of damages
    in this matter.
    Despite adopting the Glascock appraisal, the court made some modifications to the
    appraisal based upon its understanding of the testimony.
    Mr. Glascock pointed out, and the court agrees, that any
    potential buyer will not only want a dry building, they will
    require a dry building that is mold and mildew free. Otherwise,
    it would be extremely difficult, if not impossible, to market a
    healthcare facility building, and in this specific case, a dental
    office. Mr. Glascock’s “type A” appraised value is $722,000.
    However, this was assuming the building had a fully completed
    -7-
    and usable basement area. After further questioning by the
    court, Mr. Glascock testified that the $722,000 value should be
    decreased by about $100,000 due to the value put on the
    basement in his “type A” value. Thus, the “type A” value
    should be $622,000. Mr. Glascock’s “type B” value was
    $275,000. However, he placed no value for the basement space
    in his “type B” value. The court wishes to point out here that
    the court questioned the [Owner’s] other expert witness, Ken
    True, a Tennessee licensed building contractor licensed and
    experienced in the building of dental offices a[s] to what the
    basement value would be and/or what a basement in a similar
    building would cost. The court also questioned the [Builder’s]
    expert appraiser as to the basement value. The court finds the
    actual basement value to be $65,000, which should be added to
    Mr. Glascock’s “type B” appraisal value, for a total of $340,000.
    Thus, the court finds Mr. Glascock’s diminution in value
    damages to be $282,000.
    The Owner moved the court to alter or amend the judgment to allow cost of repair
    damages or to allow diminution in value damages according to Glascock’s report without
    modifications. The Owner also moved the court to allow substantial discretionary costs.
    Initially, the Owner did not file an affidavit in support of the motion for discretionary costs.
    The Builder responded that the court should deny the motion for discretionary costs for lack
    of a supporting affidavit. The Owner eventually submitted supporting affidavits, and the
    court allowed the parties significant time after the hearing on the motion to submit legal
    support for their positions. The court eventually entered a final order denying the motion to
    alter or amend and allowing discretionary costs of over $10,000 after allowing the Builder
    credits for amounts it had paid. The Owner has appealed.
    II.
    The issues in this appeal, as restated by this court, are:
    Whether the evidence preponderates against the damages
    awarded for diminution in value.
    Whether cost of repair or diminution in value was the proper
    measure of damages.
    -8-
    Whether the trial court erred in not requiring the Builder to
    reimburse the Owner for fees charged by the Owner’s expert for
    copying and other services performed by the expert pursuant to
    the Builder’s request during the expert’s deposition.
    Whether the trial court erred in awarding the Owner
    discretionary costs based on a motion that was not supported
    with an affidavit, but was later supplemented with supporting
    affidavits.
    The last issue is raised by the Builder.
    III.
    The standard of review as to the measure and amount of damages was accurately
    stated as follows in Faulkner v. Tom Emmett Const. Co., No. E2010-00361-COA-R3-CV,
    
    2010 WL 4671008
    , at *7-8 (Tenn. Ct. App. E.S., filed Nov. 18, 2010).
    The factual findings of the Trial Court are accorded a
    presumption of correctness, and we will not overturn those
    factual findings unless the evidence preponderates against them.
    See Tenn. R. App. P. 13(d); Bogan v. Bogan, 
    60 S.W.3d 721
    ,
    727 (Tenn.2001). With respect to legal issues, our review is
    conducted “under a pure de novo standard of review, according
    no deference to the conclusions of law made by the lower
    courts.” Southern Constructors, Inc. v. Loudon County Bd. of
    Educ., 
    58 S.W.3d 706
    , 710 (Tenn. 2001). In Beaty v. McGraw,
    
    15 S.W.3d 819
    [, 827] (Tenn. Ct. App. 1998), this Court stated:
    Determinations concerning the amount of
    damages are factually driven. See Loftis v.
    Finch, 
    491 S.W.2d 370
    , 377 (Tenn. Ct. App.
    1972). Thus, the amount of damages to be
    awarded in a particular case is essentially a fact
    question. See Sholodge Franchise Sys., Inc. v.
    McKibbon Bros., Inc., 
    919 S.W.2d 36
    , 42 (Tenn.
    Ct. App. 1995); Buice v. Scruggs Equip. Co., 
    37 Tenn. App. 556
    , 571, 
    267 S.W.2d 119
    , 125
    (1953). However, the choice of the proper
    measure of damages is a question of law to be
    -9-
    decided by the court. See American Trust Inv.
    Co. v. Nashville Abstract Co., 
    39 S.W. 877
    , 881
    (Tenn. Chan. App. 1896); see also Business
    Men's Assurance Co. v. Graham, 
    891 S.W.2d 438
    , 449 (Mo. Ct. App. 1994); Town of Fifield v.
    State Farm Mut. Auto. Ins. Co., 
    119 Wis. 2d 220
    ,
    
    349 N.W.2d 684
    , 686 (Wis. 1984).
    Our de novo review is subject to the recognition that the trial judge saw and heard the
    witnesses and is in a better position than are we to evaluate the credibility of their testimony.
    Keaton v. Hancock County Bd. Of Educ., 
    119 S.W.3d 218
    , 223 (Tenn. Ct. App. 2003).
    “The party who takes issue on appeal with a trial court's decision regarding discretionary
    costs has the burden of demonstrating that the trial court abused its discretion.” Duran v.
    Hyundai Motor America, Inc., 
    271 S.W.3d 178
    , 215 (Tenn. Ct. App. 2008). A trial court’s
    decision on a discovery matter will not be reversed unless a clear abuse of discretion is
    shown. Benton v. Snyder, 
    825 S.W.2d 409
    , 416 (Tenn. 1992).
    IV.
    We begin with the issue of whether the evidence preponderates against the trial
    court’s finding that the diminution in value damages are $282,000. The Owner argues that
    having concluded that diminution in value was the correct measure of damages and having
    adopted Glascock’s appraisal as the basis for its findings, the court erred in modifying
    Glascock’s appraisal to reflect lesser damages. This equates with arguing that the evidence
    preponderates against interpreting Glascock’s testimony to allow the downward adjustment
    of the value of the hypothetical “type A,” i.e., correctly-built, structure by $100,000 and the
    upward adjustment of the value of the actual “type B,” i.e., built-with-defects, structure by
    $65,000. We agree in part with the Owner’s argument.
    It is clear to us that the trial court misunderstood or misinterpreted Glascock’s
    testimony when it stated that “[a]fter further questioning by the court, Mr. Glascock testified
    that the $722,000 value should be decreased by about $100,000 due to the value put on the
    basement in his ‘type A’ value.” Glascock’s testimony must be read with the understanding
    that he clearly explained during cross-examination how he valued the “type A” structure. He
    determined a per square foot value of $175 and multiplied it by 4,125 square feet. The 4,125
    square feet is made up of 2750 square feet on the ground floor and 1375 square feet in the
    basement that was to have been finished. The product of $175 per square foot multiplied by
    4,125 square feet is $721,875. The court’s questions to Glascock were apparently prompted
    by concerns that Glascock did not assign value to the basement in the “type B” structure, the
    as-built structure. Unfortunately, the response spilled over into the “type A” structure. In
    -10-
    his attempt to respond to the questions, Glascock conceded that basement space would drive
    the overall per square foot value of a structure down below the per square foot value of a
    similar structure that did not have basement space, but that the basement space would still
    add value to the structure. In his attempt to relate his response to the facts of this case,
    Glascock explained that a building similar to Dr. Pesce’s office but without defects and
    without a basement would probably be worth approximately $650,000 (approximately $240
    x 2750), and then he would add, not subtract, approximately $100,000 for the basement.
    Both ways, according to Glascock, he essentially arrived at the same figure – somewhere
    above $700,000. The only reference to reducing the value for a basement in Glascock’s
    testimony was that the inclusion of basement space drove the overall per square foot value
    of a given structure down below the per square foot value of an identical building without
    a basement. For the “type A” structure in the present case, the reduced figure was $175 per
    square foot that he ultimately used. It is clear to us that the trial court misunderstood
    Glascock’s reference to the $100,000 and how it related to the comparison of structures built
    with basement space and structures built without basement space. Accordingly, we agree
    that the evidence preponderates against the trial court’s modification of Glascock’s appraisal
    of the “type A” structure by subtracting $100,000 to reduce the value of the structure to
    $622,000 from $722,000.
    We disagree, however, with the Owner’s contention that the evidence preponderates
    against the trial court’s addition of $65,000 to Glascock’s valuation of the as built, “type B”
    structure for the existence of basement space. Glascock admitted both during cross-
    examination and in response to directed questioning of the court that he did not assign
    independent value to the basement even though it clearly existed and clearly had value. The
    court mentioned in the course of questioning Glascock that it understood his explanation that
    he had treated the basement as an “amenity” that was included in the valuation of the ground
    floor at $100 per square foot. However, it is clear that the court did not wholeheartedly
    accept that part of Glascock’s testimony. We note that the trial court gave Glascock ample
    opportunity to place a value on an unfinished basement but he did not. The trial court was
    in a better position than this court to evaluate the witness and his failure to give a direct
    answer to a direct question. See Keaton, 119 S.W.3d at 223. The evidence does not
    preponderate against the trial court’s decision to assign an independent value to the “type B”
    structure for the existence of the basement.
    Likewise, the evidence does not preponderate against the trial court’s valuation of the
    existing basement at $65,000. The Owner criticizes the court for the court’s statement that
    it questioned expert Thurman – this because Thurman did not appear in person but rather by
    deposition. The Owner also criticizes the court for taking a “basement” value from the
    testimony of Thurman after the court had stated that the Thurman appraisal was of no value
    to the court. Despite these criticisms we will not fault the trial court for taking one simple
    -11-
    figure, i.e., the value of an unfinished basement, from the Thurman testimony. It appears to
    us that the reasons the court gave for rejecting Thurman’s overall appraisal do not totally
    undercut his ability to place a value on an unfinished basement based on typical construction
    cost as a factor of square footage. We note that the Owner’s expert, Eid, testified that it
    would cost approximately $60 per square foot to build a basement, which cost alone would
    exceed the value that the court assigned to the basement. Therefore, we conclude that the
    evidence does not preponderate against the trial courts modification of the Glascock appraisal
    by adding $65,000 to the “type B” building for the value of the basement. The result of our
    holdings as to diminution in value is a modification of the court’s judgment. The $282,000
    in damages awarded will be increased by $100,000 thereby correcting the trial court’s
    erroneous interpretation of Glascock’s testimony. Accordingly, we hold that the evidence
    preponderates in favor of a damage award of $382,000 based upon diminution in value.
    The Builder argues that the evidence preponderates against a finding of damages in
    the amount of $282,000, a figure that we have now determined should have been $382,000.
    The argument is built upon select portions of the appraisals of the various experts, mainly
    Glascock and Thurman, combined in such a way as to produce a figure favorable to the
    Builder. The trial court’s rejection of Thurman’s appraisal and the correct adoption of
    Glascock’s is not against the preponderance of the evidence. Having so held, we will not
    allow the Builder to selectively blend the two appraisals to produce a figure out of proportion
    to both appraisals. There is no merit to the Builder’s argument.
    The second issue is arguably impacted by the resolution of the first. The Owner
    asserts that “[c]hanging the amount of damages awarded by the Trial Court, may justify the
    Court using cost of repair as opposed to Diminution in Value as the proper measure of
    damages.” As we understand the argument, the Owner is conceding that based on a finding
    that diminution in value was only $282,000 the trial court was correct to find that the cost of
    repair was disproportionate to diminution in value. However, the Owner is arguing that
    assuming this Court increases the diminution in value damages, which we have done, the cost
    of repair is no longer disproportionate and should become the correct measure of damages.
    We do not necessarily disagree with the logic of the argument, but we disagree that it
    changes the result in this particular case. Although we do not have the benefit of a specific
    finding as to the cost of repair, it is apparent that it would be close to, if not more than, the
    construction cost of approximately $460,000. If we were to make our own findings, we, like
    the trial court, would reject the modest cost of repairs asserted by the Builder’s witnesses.
    Thus, the result of adopting cost of repairs as the measure of damages in this case would be
    to award the Owner as much in damages as he paid to have the structure built and leave him
    in possession of a fully operational, profitable, dental office. This result, we believe, renders
    cost of repairs disproportionate to any substantially lesser figure. Since diminution in value
    -12-
    damages of $382,000 are at least $80,000 less than cost of repair, we hold that the trial court
    did not err in selecting diminution in value damages as the proper measure of damages.
    The Owner’s final argument is that the trial court erred in not requiring the Builder
    to reimburse him for the fees charged by expert witness Eid. The Builder’s brief is of little
    help on this issue. Without citing any authority, or mentioning the word “waiver,” the
    Builder seems to argue that the Owner waived the issue by not giving the trial court an
    opportunity, after the order which reserved the issue for further hearing, to consider the issue.
    We disagree. In the first hearing on the motion to compel payment by the Builder of the fees
    and expenses charged by the expert, the trial court specifically found that there was an
    implied agreement that the Builder would pay the reasonable charges of the expert. The
    court awarded such amounts as had been paid, which related to the actual time spent in sitting
    for deposition, and specifically ordered further hearing on the issue of additional fees
    included in the expert’s invoice. There were numerous parts of the record not sent up on
    appeal, including the transcript of the majority of the trial. Therefore, the record is unclear
    to us whether the matter was ever brought to the court’s attention before the hearing on
    discretionary costs. Even if it was not, we do not believe it was too late at that juncture to
    have the hearing that had been ordered much earlier in the proceedings. We do not see any
    prejudice to the Builder, and the judgment had not yet become final because of pending post-
    trial motions. We also note that the trial court did not articulate a finding that the Owner had
    waived the right to reimbursement of the subject charges. Accordingly, we hold that the
    Owner did not waive the right to reimbursement of Eid’s fees and expenses.
    As to the merits of the claim to reimbursement, we read the transcript of the hearing
    and the orders to show that the trial court simply failed to appreciate that the claim was one
    more properly being asserted under Tenn. R. Civ. P. 26.02(4) than 54.04(2). The finding in
    the initial order on the issue of Mr. Eid’s fees of an implicit agreement by the Builder to pay
    is entirely consistent with the language of Rule 26.02(4) with regard to the payment of
    testifying experts for their deposition: “Unless manifest injustice would result, . . . the court
    shall require that the party seeking discovery pay the expert a reasonable fee for time spent
    in responding to discovery [of an expert witness expected to testify at trial].” Thus, we hold
    that the trial court erred in denying the request altogether. We are not holding that any and
    all charges recorded on the invoice are chargeable to the Builder any more than we are
    holding that any particular charge is not to be charged to the Builder. On remand, the trial
    court is directed to hold a hearing and, in the exercise of its discretion based on suitable and
    necessary findings, order the Builder to reimburse the Owner for such charges of expert Eid
    as are just.
    The final issue is the one stated by the Builder, i.e., whether the court erred in
    awarding discretionary costs when the motion was made without supporting affidavits. We
    -13-
    interpret the Builder’s argument as an all or nothing challenge to discretionary costs in any
    amount and not a challenge to any one component of the award. We hold that the trial court
    did not err in considering the affidavits submitted after the motion. The present version of
    the applicable rule, 54.04(2)1 , does not explicitly require that the motion be accompanied by
    an affidavit or affidavits. All it requires, on its face, is that “a party requesting discretionary
    costs . . . file and serve a motion within thirty (30) days after entry of judgment.” Tenn. R.
    Civ. P. 54.04(2). Case law has held that the motion should be supported by an affidavit so
    as to allow the court to make the findings required for an award of discretionary costs. See,
    e.g., Waggoner Motors, Inc. v. Waverly Church of Christ, 
    159 S.W.3d 42
    , 65 (Tenn. Ct.
    App. 2004). By the time the court ruled on the Owner’s motion in this case, it had the benefit
    of the required affidavits. Although the Builder complains that the affidavits were filed only
    approximately three days before the hearing, the Builder has not shown how it was
    prejudiced by the belated filing, nor does it indicate that it asked the court for additional time
    to counter the affidavits. We note that the trial court specifically recited in an order that it
    wanted to “get it right” on this issue and allowed the parties additional time after the hearing
    to file legal argument and authority. We will not assume that the trial court would have
    overlooked a request for a continuance to overcome prejudice to the Builder. Accordingly,
    we hold that the trial court did not err in awarding discretionary costs based on affidavits
    filed after the motion for discretionary costs was filed and within a few days of the hearing
    on the motion.
    1
    A previous version of Rule 54.04(2), as quoted in Lock v. National Fire Ins. Co. Of
    Pittsburgh, Penn., 
    809 S.W.2d 483
     (Tenn. 1991), stated, in pertinent part:
    A party who desires to recover discretionary costs or any recoverable costs
    not included in the bill of costs prepared by the clerk of the trial court shall
    move the court to assess discretionary costs and attach thereto an itemized
    and verified bill of costs. The affidavit shall be made by the party or his
    duly authorized attorney or agent having knowledge of the facts, certifying
    that such items of costs are accurate and were reasonable and necessary to
    preparation and trial of the case and that the services for which such fees
    have been charged were actually performed.
    Id. at 489.
    -14-
    V.
    The judgment of the trial court is reversed in part and affirmed in part as modified.
    That part of the judgment denying the Owner reimbursement for the fees and expenses
    charged by expert Eid is reversed. The award of damages of $282,000 based on diminution
    in value is increased by $100,000 to $382,000. Costs on appeal are taxed to the appellee,
    East Tennessee Construction Services, Inc. This case is remanded, pursuant to applicable
    law, for a hearing to determine the amount of the reimbursement to the Owner for Eid’s fees
    and expenses related to his deposition; for enforcement of the judgment as modified; and for
    collection of costs assessed by the trial court.
    _______________________________
    CHARLES D. SUSANO, JR., JUDGE
    -15-