total-building-maintenance-inc-v-j-j-contractorsraines-brothers-a ( 2009 )


Menu:
  •                     IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    November 6, 2008 Session
    TOTAL BUILDING MAINTENANCE, INC., v. J & J
    CONTRACTORS/RAINES BROTHERS, a Joint Venture, J & J
    CONTRACTORS, IN., RAINES BROTHERS, INC., ST. PAUL FIRE &
    MARINE INSURANCE COMPANY, and FIDELITY & DEPOSIT CO. OF
    MARYLAND
    Direct Appeal from the Chancery Court for Hamilton County
    No. 06-0227     Hon. W. Frank Brown, III, Chancellor
    No. E2008-00678-COA-R3-CV - FILED MARCH 13, 2009
    In this action plaintiff sued for money owed under its subcontract with the defendant contractor. The
    defendants’ contractor denied liability, raised as affirmative defenses, waiver/estoppel, unclean
    hands and breach of contract, filed a counter-claim alleging that plaintiff failed to complete its work
    in a timely and proper manner and permitted the roof to be harmed by others during the construction
    and generally failed to cooperate. Following an evidentiary hearing, the Trial Judge determined that
    both parties had breached the contract, that plaintiff was guilty of unclean hands, denied both parties
    any recovery and dismissed the case. On appeal, we affirm.
    Tenn. R. App. P.3 Appeal as of Right; Judgment of the Chancery Court Affirmed.
    HERSCHEL PICKENS FRANKS, P.J., delivered the opinion of the Court, in which CHARLES D. SUSANO ,
    JR., J., and D. MICHAEL SWINEY , J., joined.
    Timothy M. Gibbons, Chattanooga, Tennessee, for appellant.
    Randy Wilson and Robert F. Parsley, Chattanooga, Tennessee, for appellees.
    OPINION
    Plaintiff in this action alleged that it was owed money for work performed on the new
    headquarters for the Electric Power Board in Chattanooga. Further, that defendants J&J Contractors
    and Raines Brothers, Inc., (hereinafter “contractor”) formed a joint venture to act as general
    contractor for the construction project, and that unnamed defendants were the performance bond
    sureties.
    Plaintiff averred that it entered into two contracts with contractor to work as a roofing
    subcontractor on this project, and attached copies of the subcontract agreements and alleged that it
    had a number of disputes with contractor regarding the fact that contractor sought to hold plaintiff
    liable for damage caused by other parties to the work performed by plaintiff.
    Plaintiff charged that contractor also tried to increase the scope of the work, and
    refused to execute change orders for the additional work. Plaintiff asserted that it had completed all
    of the work, but had not been fully paid, and was owed $193,000.00, because contractor had
    breached the contract, interfered with the contract and breached covenants of good faith and fair
    dealing.
    Plaintiff later amended its Complaint to add St. Paul Fire & Marine Insurance
    Company and Fidelity & Deposit Company of Maryland, as sureties on the bonds.
    Defendants answered, denying any liability, pleading waiver/estoppel, unclean hands,
    breach of contract, comparative fault, laches, insufficiency of process, etc. Defendants also filed a
    Counterclaim asserting that plaintiff had failed to complete its work in a timely and proper manner,
    failed to insure that the roof was inspected by a representative of the manufacturer to obtain a
    warranty, permitted the roof to be harmed by others during construction, and withheld necessary lien
    releases. Defendants attached an Interim Agreement which the parties had executed.
    Plaintiff filed a Reply to Counterclaim, denying it had breached any of its
    responsibilities, and the case went to trial before the Trial Judge on November 27-30, 2007.
    The Trial Court filed a Memorandum Opinion, and found that plaintiff was the
    roofing subcontractor on the new EPB office building in downtown Chattanooga, and that the
    defendant joint venture was the general contractor on the project. The Court found that the parties
    and the architect all agreed the roof installation began too early, and that the contractor was in charge
    of scheduling the work, and did ask plaintiff to install the roof earlier than normal, but that the
    contractor contended that plaintiff was supposed to protect its work. The Court said that other parties
    were still working in the roof area, and that the roof was damaged by water, and part of it had to be
    replaced. The Court found that the roofing manufacturer, Garland Company, would not warranty
    the roof until a second cap sheet was installed over the initial one, and that plaintiff claimed
    defendants owed them for this installation. The Court found that plaintiff also claimed to be owed
    for all the repair work to the roof.
    -2-
    The Court found that Marvin Cornelison, president of Raines Brothers, testified that
    everyone had responsibility for damaging the roof, and the company that caused the most damage
    was Staley Marble & Granite, Inc., the subcontractor. The Court found the contractor withheld
    $32,328.00 from Staley’s final payment to cover roof damages, and that the contractor explained in
    a letter to Staley that this was 20% of the amount invoiced for repairs by plaintiff ($161,638.00),
    because the contractor assessed that Staley was responsible for 20% of the roof damage. The Court
    found there was no evidence that any other sub was back-charged for roof damage, and there were
    pictures in evidence of other subs working on the roof, which could have caused damage.
    The Court found that the evidence was clear that plaintiff had to share in the blame
    for part of the roof damage, as there was proof that it had failed to properly install an ice and water
    shield in one area, and water damage resulted, and there was also proof of improperly installed
    flashing, as well as damage caused by improper precautions by plaintiff’s employees, and that
    plaintiff was largely responsible for the repair work needed on the roof.
    The Court found the contractor agreed to pay plaintiff for certain repair work, and
    asked plaintiff to identify its costs associated with the same, by providing invoices, time cards, etc.,
    but that plaintiff never complied with this request until late in the discovery process, and did not
    provide a breakdown regarding which invoices were related to which work. The Court held that
    regarding the second cap sheet, plaintiff provided a quote for the work of $86,779.00, but the
    contractor got a quote from another for $47,000.00 for the same work. The Court found that plaintiff
    was directed to do the work pursuant to the subcontract, and to keep detailed cost records on the
    work, but plaintiff failed in this regard. The Court said the plaintiff was repeatedly asked by the
    contractor to itemize its expenses related to the second cap sheet, and the contractor referenced the
    contract requirements (found in the Supplementary Conditions) regarding financial information
    needed to consider a change order. The Court held that plaintiff never provided actual cost
    information, although it did provide a couple of estimates.
    The Court observed that the plaintiff’s credibility was damaged by the changing
    nature of its position regarding the actual costs associated with the second cap sheet, and that
    plaintiff’s invoices appeared to be “padded”, e.g., the repair associated with one balcony roof was
    billed to the contractor three different times.
    The Court observed that plaintiff’s claim was primarily based upon the testimony of
    Mr. Whitmore, and his credibility was damaged in several ways, and set forth examples.
    The Court determined that it would deny recovery to plaintiff because Whitmore
    admitted that plaintiff received formal, written change orders for some extra work, and that it was
    paid for that work; plaintiff did not receive change orders for the disputed repair work nor the
    second cap sheet, and should not have performed the work without change orders. The Court found
    that regarding the second cap sheet, plaintiff was told to keep detailed cost records, but did not, and
    plaintiff could not prove the actual costs with regard to any specific work, and could not explain
    billing discrepancies. Plaintiff admitted responsibility for failing to protect the field laps on the
    -3-
    balconies, but did not deduct for the repairs to the same, and failed to produce documentation for a
    long period of time, and as a result was guilty of unclean hands. Finally, the Court found that
    plaintiff was seeking quantum meruit recovery, and quantum meruit recovery should not be based
    on the value of the services of the one performing the same, but should instead be based on the value
    of the benefit conferred. The Court held there was no proof of the benefit conferred on the contractor
    by the repair work or the extra cap sheet. Moreover, plaintiff failed to adequately prove the value
    of its services.
    The Court also denied the contractor’s counterclaim, finding that it had failed to prove
    that plaintiff was contractually liable. Regarding attorney’s fees, the Court found that plaintiff was
    not entitled to an award of attorney’s fees, because most of the time spent on the case was due to
    plaintiff’s unwillingness to accept responsibility for any damage to the roof, and its unwillingness
    to produce its actual costs relating to the work. The Court also denied the contractor’s claim for
    attorney’s fees, and ordered that the contractor pay plaintiff the balance due on the adjusted contract
    price upon plaintiff’s satisfactory completion of the punch list and receipt of the warranty, but
    dismissed the remainder of plaintiff’s claims with prejudice.
    Both parties filed Motions to Alter or Amend the Judgment, and the Trial Court found
    that considering the “big picture”, plaintiff was guilty of unclean hands, and thus should be denied
    all relief.
    Regarding the contractor’s motion, the Court also denied recovery because the Court
    found that the roof was begun too early, and further found the contractor also bore some
    responsibility in protecting the roof work. The Court reaffirmed its denial of attorney fees to the
    contractor, finding that both parties breached their agreement, concluding that both parties should
    be left where they are.
    Numerous issues have been presented on appeal, as follows:
    1.      Whether the Trial Court erred by applying the wrong legal standard in
    analyzing extra-contractual work by requiring clear and convincing proof?
    2.      Whether the Trial Court erred in misapplying the legal standards generally
    applicable to quantum meruit claims by requiring actual payment by the
    owner to the contractor for extra work performed by TBM?
    3.      Whether the Trial Court erred in applying contract terms assuming a change
    directive or a change order, neither of which existed and for which defendants
    presented no proof?
    4.      Whether the Trial Court erred in ruling cost information was withheld instead
    of acknowledging that counsel were in agreement on the production of
    documents?
    -4-
    5.      Whether the Trial Court ignored the extensive proof on costs and the time
    line of the project?
    6.      Whether the Court’s factual analysis is contrary to the manifest weight of the
    evidence?
    7.      Whether the Court erred in focusing on a conversation not taken seriously by
    any party and elevating it to one of the Court’s key findings?
    8.      Whether the Trial Court erred by failing to rule on TBM’s entitlement to
    relief based on the theory of cardinal change?
    9.      Whether the Court erred in failing to grant TBM a new trial?
    10.     Whether the Trial Court properly denied defendants’ claim for attorneys fees,
    and whether they are entitled to recover fees and costs on appeal?
    Plaintiff argues that the Trial Court applied the wrong standard in analyzing its
    quantum meruit claim, as the Trial Court required the claim to be proven by clear and convincing
    evidence. What the Trial Court actually said, however, was that damages needed to be proven by
    showing “actual documented expenses”, not that it was requiring clear and convincing evidence.
    The Trial Court explained that, even if plaintiff’s claims were not barred by its unclean hands,
    plaintiff did not prove its damages in quantum meruit because there was no adequate proof of the
    benefit conferred on the contractor, nor plaintiff’s actual costs. There is no adequate proof of the
    value of plaintiff’s services. The records/invoices supplied are ambiguous, contradictory, and
    difficult to decipher. The evidence does not preponderate against the Trial Judge’s determination.
    Tenn. R. App. P. 13(d).
    Plaintiff further argues that the Trial Court erred in requiring it to show the benefit
    conferred by showing actual payment to the contractor by the owner for the extra work performed
    by plaintiff. Plaintiff again mischaracterizes the Trial Court’s opinion. The Court explained that,
    in Tennessee, an award in quantum meruit is based on the value of the benefit conferred rather than
    the value of the services to the one performing the services. Citing Parris Roofing & Sheetmetal Co.
    v. SCR Electric, Inc., 
    2007 WL 596396
    (Tenn. Ct. App. Feb. 27, 2007). The Court then noted the
    fact that the owner did not pay the contractor any additional money as a result of the “extra” work.
    Moreover, plaintiff had not shown any proof of what its services were worth, thus resulting in the
    Court’s conclusion that there was no proof of a benefit conferred.
    In any event, plaintiff’s arguments regarding quantum meruit are largely moot given
    the Trial Court’s finding that plaintiff was guilty of unclean hands. Quantum meruit is an equitable
    remedy, and requires that a party seeking to rely upon it must be able to “overcome the equitable
    ‘lack of clean hands’ defense.” Castelli v. Lien, 
    910 S.W.2d 420
    (Tenn. Ct. App. 1995). Also see,
    Hogue v. Kroger Co., 
    373 S.W.2d 714
    , 716 (Tenn. 1963).
    -5-
    Next, plaintiff argues the Trial Court erred in quoting provisions of the contract that
    deal with change directives/change orders, when there was no change directive/order applicable to
    this work. Plaintiff cites to pages in the record, wherein the Trial Court does generally discuss the
    requirements for a change order, etc., but the Trial Court did not find that a change order was issued.
    In fact, the Trial Court found that a change order was not issued for the work (as had been done for
    other “extra” work in the parties’ prior dealings) and this should have been a red flag to plaintiff not
    to continue with the work until an understanding was reached. The Court analogized the
    documentation required for a change order to that which was requested by the contractor for the extra
    work, and pointed out that plaintiff was specifically asked to keep records of its actual costs related
    to the second cap sheet, but failed to do so. The Court further observed that if plaintiff expected to
    be paid for the work, it should have expected to have to substantiate its costs involved, but failed to
    do so either before or during trial. There is no error in the Trial Court’s analysis.
    Next, plaintiff argues the Trial Court erred in finding that cost information was
    withheld, rather than acknowledging that counsel had agreed on a certain date for the production of
    documents. Plaintiff argues it should not be penalized for the time it took to provide the documents
    in discovery, as it is undisputed that the documents were provided on a date agreed upon by the
    attorneys for a mutual document exchange.
    What the Trial Court found, however, was that backup cost documentation was
    repeatedly requested by the contractor, and was never provided in an effort to substantiate plaintiff’s
    expenses in doing this work, which, theoretically, could have provided a basis for resolution of these
    issues without going to court. The contractor presented numerous letters and emails requesting this
    documentation, but it was undisputed that this was never provided before discovery in this case.
    While it appears that the document exchange was handled in a timely fashion once the case reached
    the discovery phase, this does not change the fact that the documents clearly could have been
    provided sooner, as requested by the contractor in an effort to determine if plaintiff could be paid for
    its work. Plaintiff’s failure to cooperate only lengthened the process and strengthened the animosity
    between the parties, as the Trial Court found. The fact that the discovery process was handled on
    schedule does not excuse the fact that plaintiff could have provided the information sooner if it had
    so elected. The evidence does not preponderate against the Trial Court’s finding. Tenn. R. App. P.
    13(d).
    Plaintiff also takes issue with other specific factual findings of the trial court, arguing
    that the Court ignored the extensive proof of actual costs contained in the Final Report, that the
    Court ignored the undisputed proof that everyone bore responsibility for damage to the roof, and that
    the Trial Court erred in its assessment of Whitmore’s credibility on several levels. We conclude the
    Trial Court’s opinion is detailed and specific, and is supported by the record.
    In addressing the specific issues raised by plaintiff, it is clear that the Find Report
    does contain cost information, and the Trial Court noted the same. However, a few of the Trial
    Court’s problems with the report were that it was not provided in a timely and cooperative fashion
    until discovery, and it did not specifically track costs relating to the second cap sheet even though
    -6-
    this was expressly requested by the contractor, and could have been done according to plaintiff’s
    office manager. Further, as stated earlier, the cost information provided in general was confusing,
    duplicitive, and contradictory, and the Trial Court stated that it did not feel that it could adequately
    assess any measure of damages based on the proof even without the unclean hands issue. The
    evidence does not preponderate against the Trial Court’s factual findings. Tenn R. App. P. 13(d).
    As to the damage to the roof, the testimony showed that everyone involved bore some
    responsibility, which the Trial Court found. The Trial Court relied upon this fact in basically holding
    that the most equitable resolution in this situation was to leave the parties where they were, because
    each party had liability and responsibility for the damage, as mistakes were made by both parties.
    Finally, regarding credibility, the parties agree that the Trial Court is the best judge
    of witness credibility, and that the Trial Court’s determination regarding same can be re-evaluated
    if there is clear and convincing evidence to the contrary. See Bingham v. Dyersburg Fabrics, Co.,
    Inc., 
    567 S.W.2d 169
    , 170 (Tenn. 1978). In this case, the record supports the Trial Court’s findings
    regarding Mr. Whitmore’s credibility, as his testimony was contradictory, confusing, and
    argumentative at times. The testimony regarding his comment about “padding” the bill was stated
    to be in jest, and the Trial Court merely commented that some of the plaintiff’s invoices did, in fact,
    appear to be “padded”. The Trial Court observed the witness and heard his testimony, and is the best
    judge of his credibility. There is no clear and convincing evidence that the Trial Court erred in its
    determination. We conclude the record in this case supports the factual findings made by the Trial
    Court, and we affirm the Trial Judge on these issues. Tenn. R. App. P. 13(d).
    As an additional issue, plaintiff argues the Trial Court should have awarded it relief
    pursuant to the theory of “cardinal change”, which it argues is applicable to construction contracts,
    and which allows the contractor to recover its costs, overhead, and profit when it is required to
    perform work outside its reasonable expectation at the time the contract was executed. Plaintiff
    acknowledges this doctrine has not been adopted by Tennessee courts.
    We conclude this is clearly not a case for the adoption/application of the cardinal
    change doctrine, which requires a showing that there is an “alteration in the work so drastic that it
    effectively requires the contractor to perform duties materially different from those originally
    bargained for.” Allied Materials & Equip. Co., Inc. v. United States, 
    569 F.2d 562
    , 563 (Ct. Cl.
    1978). The change must be so profound that it would constitute a breach of the original contract,
    and causes damage that is not redressable by the contract. Global Engineering & Const., LLC v.
    Merchants Bonding Co., 
    2007 WL 1752463
    (S.D. Ga. June 15, 2007). No profound change in this
    contract has been shown. Moreover, since this is an equitable remedy akin to quantum meruit, it
    would also be barred by plaintiff’s unclean hands.
    Plaintiff also argues the Trial Court erred in failing to grant it a new trial, because it
    was entitled to a new trial based on the Trial Court’s “serious errors” in refusing to credit certain
    testimony and overlooking material evidence. These issues have been addressed, and we have found
    that the record supports the Trial Court’s factual findings and legal conclusions. There is no basis
    -7-
    for the granting of a new trial.
    Defendants argue the Trial Court erred in failing to award them any attorney’s fees
    in this case, because plaintiff was shown to have breached the contract, to have unclean hands, etc.
    What the Trial Court found, however, was that both parties breached their agreement, and thus
    concluded that both parties should be left where they are. It appears that, based upon the evidence
    in this case, this was the most equitable resolution where it was shown that both parties bore
    responsibility for the problems leading up to the lawsuit, and both parties were technically in breach.
    The proof showed that the contractor directed the work on the roof to begin too early in construction,
    and the contractor also bore responsibility for failing to protect the roof.
    The contractor argues, however, that it should be awarded fees based on the contract
    provisions contained in either the Interim Agreement or the Subcontract itself. The Interim
    Agreement specifically provides that fees can be awarded from the “breaching” party to the “non-
    breaching” party, but since the Trial Court found breach on both sides, this is not applicable. The
    Subcontract, however, does not contain such language regarding a “breaching” party, rather, it
    simply states that if the contractor commences any action relating to the Subcontract or the
    subcontractor’s work, then the subcontractor is to reimburse the contractor for “all costs and
    expenses of such legal action, arbitration or other proceeding, including reasonable attorneys’ fees.”
    While the Trial Court found the contractor’s counterclaims against plaintiff would constitute the
    commencement of an action, the Court denied attorney’s fees, finding that both parties were in
    breach, as stated above. The Trial Court also found that the contractor might have a windfall of
    $47,000.00 based on Helton’s estimate of the cost of the second cap sheet, and took into
    consideration the potential “windfall” in denying the claim. We affirm the Trial Court’s judgment
    in denying attorney’s fees to the defendants, because under the familiar rule contracts are enforceable
    in accordance with equity and good conscience. Greene County Bank v. Southeastern Properties,
    Inc., et al., 
    1996 WL 471469
    (Tenn. Ct. App. Aug. 21, 1996); CGR Investments, Inc., v. Hackney
    Petroleum, Inc., 
    2000 WL 1285246
    (Tenn. Ct. App. Sept. 12, 2000); and Brown v. McCord, et al.,
    No. 03A01-9509-CH-00329 (Ct. App. issued Jan. 30, 1996).
    We affirm the Judgment of the Trial Court and remand, with one-half of the costs
    assessed to the plaintiff and one-half assessed to defendants.
    ______________________________
    HERSCHEL PICKENS FRANKS, P.J.
    -8-
    

Document Info

Docket Number: E2008-00678-COA-R3-CV

Judges: Judge Herschel Pickens Franks

Filed Date: 3/13/2009

Precedential Status: Precedential

Modified Date: 3/3/2016