Metropolitan Government of Nashville And Davidson County, Tennessee v. Teleport Communications America, LLC ( 2017 )


Menu:
  •                                                                                            11/29/2017
    IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    September 5, 2017 Session
    METROPOLITAN GOVERNMENT OF NASHVILLE AND DAVIDSON
    COUNTY, TENNESSEE v. TELEPORT COMMUNICATIONS AMERICA,
    LLC
    Appeal from the Chancery Court for Davidson County
    No. 02-679-I, 02-749-III Russell T. Perkins, Chancellor
    No. M2016-02222-COA-R3-CV
    The Metropolitan Government of Nashville and Davidson County (“Metro”) sued
    Teleport Communications America, LLC (“TCG”) in the Chancery Court for Davidson
    County (“the Trial Court”) to recover a fee for TCG’s use of Metro’s public rights-of-
    way. TCG contended the fee was unlawful and refused to pay. Metro and TCG
    previously had entered into a franchise agreement in keeping with an ordinance requiring
    telecommunications providers to pay 5% of their gross revenues to Metro. The
    Tennessee Court of Appeals later ruled in another case against an ordinance purporting to
    set a gross revenue franchise fee as being akin to a tax. The Trial Court cited this holding
    to invalidate the ordinance in the present case. Metro nevertheless pursued this action
    further, seeking to recover under a contractual theory. After extensive litigation, the Trial
    Court found that TCG owed damages to Metro in the amount of $550,000. The Trial
    Court reasoned that even though the underlying ordinance was invalid, the parties had
    entered into a franchise agreement and Metro was entitled to some measure of
    compensation. TCG appealed. We affirm the judgment of the Trial Court.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed;
    Case Remanded
    D. MICHAEL SWINEY, C.J., delivered the opinion of the court, in which FRANK G.
    CLEMENT, JR., P.J., M.S., and W. NEAL MCBRAYER, J., joined.
    William L. Harbison and John L. Farringer, IV, Nashville, Tennessee, and, Hans J.
    Germann, Chicago, Illinois, for the appellant, Teleport Communications America, LLC.
    Jon Cooper, Director of Law, Law Department of the Metropolitan Government of
    Nashville and Davidson County, J. Brooks Fox and Lora Barkenbus Fox, Nashville,
    Tennessee, for the appellee, the Metropolitan Government of Nashville and Davidson
    County.
    OPINION
    Background
    This long-running case began in 2002 when Metro sued TCG seeking to recover
    franchise fees.1 TCG asserted that the franchise fees were unlawful and refused to pay
    them.2 Years of protracted litigation followed.
    In 1997, TCG, a full-service provider of telecommunication services, entered into
    an agreement with Nashville Electric Service (“NES”), an independent agency of Metro,
    to install a system of cables. This system would service NES and TCG customers. TCG
    was to own 50% of the system and NES would own 50%, with NES retaining the option
    of asserting ownership over TCG’s facilities. NES exercised its option to acquire TCG’s
    system in 2002. TCG later conveyed the entirety of the system to NES in 2008, when a
    Bill of Sale issued. TCG continued to use the system through an indefeasible right of
    use. In addition to entering the agreement with NES, TCG entered into a franchise
    agreement with Metro. The franchise agreement included, in keeping with a franchise
    ordinance, a charge of 5% of TCG’s gross revenue in Nashville each year to be paid to
    Metro. A severability clause in the franchise agreement purported to preserve the
    remainder of the agreement should any particular provision of the contract be invalidated.
    In 2004, during the course of this lawsuit, the Tennessee Court of Appeals entered
    its opinion in the case of BellSouth Telecommunications, Inc. v. City of Memphis, 
    160 S.W.3d 901
    (Tenn. Ct. App. 2004). In BellSouth, this Court struck down an ordinance
    that charged a 5% franchise fee, holding that the fee did not bear a reasonable relation to
    the city’s regulatory costs. The Trial Court applied the BellSouth holding in the present
    case to find that “the gross revenue and dark fiber compensation provisions of the
    franchise ordinance (§§6.26.230 and 6.26.240) are invalid and unenforceable . . . .”
    As a result of BellSouth and the Trial Court’s ensuing holding regarding the
    invalidity of the ordinance, Metro changed its legal strategy. Metro sought leave to
    1
    As a result of a merger, Teleport Communications America, LLC was substituted for the party originally
    sued by Metro, TCG Midsouth, Inc. Defendant has continued to be referred to as TCG.
    2
    Another party, XO Communications Services, Inc., also was sued by Metro, but these parties eventually
    settled their claims and XO is not a party to this appeal.
    -2-
    amend its complaint to allege that it was entitled to recovery in quasi-contract because,
    notwithstanding the invalidity of the ordinance, Metro and TCG did enter into an
    agreement and TCG did receive the benefits under that agreement. In 2007, the Trial
    Court granted Metro leave to amend. This case was tried in May 2013. The relevant
    period for which Metro seeks damages is 1997 through 2012.
    The record contains substantial evidence as to the parties’ respective proposed
    methodologies for calculating costs. Metro’s method involved calculating the total costs
    for public rights-of-way, then determining which portion was incurred by utilities. Metro
    then determined that TCG, in 2007, occupied 0.07486% of Metro’s rights-of-way. Metro
    applied indices to arrive at a figure of $1,511,856 in costs owed by TCG. A report
    entered in the record as Metro’s exhibit 11 elaborated upon Metro’s allocation of costs as
    follows:
    4.2 Pricing Implications
    For the reasons explored at some length in the 2010 Reports (e.g.,
    see Part 2.2), TAI [Technical Associates, Inc., a consulting firm retained by
    Metro] has concluded that the application of a fully-allocated cost (“FAC”)
    methodology based on a cubic feet measure of cost-causation best meets
    the goals of fairness, reasonableness, and nondiscrimination in the instant
    case. Further, while an ideal application of FAC methodology involves a
    distinction between joint/common costs and directly-attributable costs
    when warranted, TAI has treated all of the PROW costs incurred by Metro
    as being of a joint-common nature; i.e., to be shared equally among Metro
    PROW user organizations at the same amount per cubic foot of space that
    their facilities consume of Metro’s PROW. Anecdotal evidence exists that
    some of the PROW costs incurred by Metro in certain of its Departments
    are likely to be of a directly-attributable nature. But at the same time,
    TAI’s prior work for Metro also revealed that only through significant
    additional research might these directly-attributable costs be meaningfully
    quantified. This finding was confirmed during the recent Event (F)
    meetings outlined earlier in Part 2.2.
    The treatment of all Metro PROW costs during FY2007 as
    joint/common converted to approximately $4.41 per 1,000 cubic feet in the
    2010 Reports. This figure has now risen to $5.05; i.e.,
    $129,018,131/25,559,987 thousand cubic feet per Table 1A(Revised).
    Thus, and with respect to the flat and one-part rate design discussed in Part
    4.7 of the 2010 Reports, the relevant price has become $5.05 per 1,000
    cubic feet of Metro PROW space utilization. Upward movements in rates
    are also applicable to the other potential pricing structures outlined in TAI’s
    -3-
    earlier reports. To illustrate, regarding the issue of recognizing the benefits
    conferred on other Metro PROW user organizations by Metro Stormwater
    and Metro SL facilities, where a corresponding rate of $5.26 per 1,000
    cubic feet was found to be appropriate on Page 57 of the November 15,
    2010 Report, this amount has increased to approximately $6.23 per 1,000
    cubic feet.
    Other than with respect to specific rate levels, all elements of the
    discussions in Part 4.7 of the 2010 Reports remain unchanged. Put
    alternatively, while the revisions and corrections incorporated in this 2012
    Report have necessarily modified the prices that Metro may appropriately
    charge for the use of its PROW on a strict cost basis, the various rate design
    considerations (e.g., goals in addition to cost recovery, balancing among
    alternative goals, and bill offsets) addressed in the 2010 Reports of TAI
    remain valid.
    (Footnote omitted).
    Patricia Kravtin, an expert witness for TCG, advanced a much more restrictive
    methodological approach. Kravtin testified at trial in part, as follows:
    Q. Well, I thought I understood your testimony to be that the only cost that
    could be re-cooped by local government would be those marginal or
    incremental costs that are caused by, say in this example, TCG, and, in fact,
    TCG’s impact on the right-of-way?
    A. No. That was not my testimony.
    Q. Okay. So it’s not just that Metro should only recoup the marginal or
    incremental costs caused by TCG. Is that correct?
    A. Well, that wasn’t my testimony either. What I indicated was that in my
    professional opinion as an economist with experience in determining these
    types of fees for essential assets, that there are benefits, in my opinion.
    First best would be to set fees just at marginal costs, consistent --
    Q. First best --
    A. First best consistent with where policy is going in this area, specifically
    to incentivize and encourage these type of companies to provide broadband
    deployment.
    That said, I recognize that it’s been established over the past 30-
    some years of regulating these types of assets that its accepted to have a
    fully allocated cost standard, provided that standard is based on cost
    causative linkages to the use of that rights-of-way and not general excess
    compensation. So all of those factors governed and were part of the
    frameworks I applied.
    -4-
    But, again, to be clear, even my lower-bound estimate, it’s not an
    estimate of marginal cost. Because I would determine those on a net basis
    to be zero. So in terms of being generous and following fully-allocated
    principles, I developed a lower-bound that includes costs that are more than
    marginal costs that include some contribution to costs that exist for Metro,
    whether it had any other entities present in this right-of-way, other than
    what it would need to perform its basic city function services.
    Dr. Michael Ileo, an expert witness for Metro, testified in rebuttal to Kravtin as
    follows:
    Q. Dr. Ileo, you were present during -- were you present during all of Ms.
    Kravtin’s testimony?
    A. I was.
    Q. And you heard her testify about incremental or marginal costs and how
    that weighed into her analysis. Can you -- is there anything you want to
    rebut on that?
    A. Ms. Kravtin’s statement as to the incremental costs associated with
    TCG’s use of Metro’s public of right-of-way is likely at or near zero. It
    personifies the classic free-rider problem in economics. All of us would
    like to be able to pay the incremental cost that we impose. That’s totally
    and separately attributable to us for any goods of service. The prices we
    would pay would be extraordinarily low because individually each of us
    imposes very few incremental costs in the production of any good or
    service.
    However, there’s a whole bucket, since that term has been used a lot
    in this case, of what is known as common and joint costs that all users of a
    good or service have to bear on a fair and reasonable basis. Ms. Kravtin’s
    studies are essentially void of any consideration of those common and joint
    costs. It is true, however, that whereas she poses her lower-bound results as
    her primary recommendation, she also sets forth mid-range and lower-
    bound recommendations in which she attributes certain amounts of
    common and joint costs to TCG and telecommunications.
    In September 2016, the Trial Court entered its detailed Memorandum and Final
    Order. The Trial Court found in favor of Metro and awarded it compensation from TCG,
    albeit considerably less than what Metro asked for. The Trial Court stated as follows, in
    part:
    Metro’s position is that this Court should award it fair and
    reasonable compensation in the form of franchise fees because it is
    -5-
    undisputed that TCG built and used (for more than ten years) a
    telecommunications system in Metro’s PROW under the parties’ contract.
    In this connection, Metro urges that this Court’s ruling (in keeping with two
    Tennessee Court of Appeals decisions) that the portions of Franchise
    Agreement and Franchise Ordinance setting the franchise fee at 5% of
    TCG’s gross receipts were unenforceable did not invalidate TCG’s
    payment obligation under the Franchise Agreement and the Franchise
    Ordinance. Metro is claiming that it is entitled to recover franchise fees
    under the Franchise Agreement, the Franchise Ordinance and that Tenn.
    Code Ann. § 65-21-103 (“the 1907 Act”) authorizes this recovery. Metro
    asserts that the federal Telecommunications Act of 1996 (and the attendant
    prohibition against charging franchise fees retroactively) and the doctrine of
    separation of powers do not operate to bar its right to recover reasonable
    franchise fees here. Accordingly, Metro urges that applicable law allows it
    to recover reasonable franchise fees as damages awarded by the Court.
    TCG vigorously disagrees. It urges that the Franchise Agreement
    and the corresponding Franchise Ordinance were ultra vires because they
    provided for franchise fees (5% of gross revenue) that were not shown to
    bear a reasonable relationship to the actual cost impact on the PROW.
    TCG urges that Metro cannot recover any franchisee fees because these
    fees cannot be saved by any severability concept, this Court’s general
    authority to award damages, or the Tennessee appellate court decisions that
    generally permit reasonable franchise fees to be recovered. In light of the
    Federal Telecommunications Act of 1996 (the “federal act”), TCG argues
    that Metro is not permitted to recover for TCG’s use of the PROW given
    that the 5% franchise fee was declared unenforceable and given that Metro
    did not publicly disclose the alternative compensation it was seeking by, for
    example, amending the Franchise Ordinance. Additionally, TCG urges that
    this Court cannot award reasonable compensation because of separation of
    powers and, alternatively, that any amount the Court purports to set can
    only be on a going-forward basis. Further, the parties have fundamental
    disagreements regarding the appropriate methodology for calculating any
    such franchise fees.
    ***
    Here, Metro and TCG entered the Franchise Agreement, based on
    the Franchise Ordinance, which publicly disclosed that the compensation
    for use of the PROW would be 5% of TCG’s applicable gross receipts. As
    far as the parties actually knew, this was a legally permissible arrangement
    -6-
    at the time, despite TCG’s arguments to the contrary. When TCG accepted
    the benefits of the Franchise Agreement and built and used the fiber optic
    system in the PROW, it ratified its contractual duty to pay reasonable
    franchise fees. TCG successfully attacked the fee based on 5% of TCG’s
    applicable gross receipts on the ground that the flat 5% fee could not be
    shown to be tied to Metro’s actual reasonable costs, even though franchise
    fees are otherwise recoverable under state and federal law. Consequently,
    when the 5% franchise fee arrangement was declared unenforceable, TCG
    was subject to the obligation to pay a franchisee fee as long as the fee was
    reasonable and did not exceed the previously publicly disclosed fee of 5%
    of TCG’s applicable gross receipts. As previously determined by the
    Court, the fee based on 5% of TCG’s applicable gross receipts was not
    ultra vires; it was legally permissible at the time the contract was entered.
    If Metro had, for example, passed another ordinance in 2005 after
    the Memphis ruling, TCG may have refused to agree to an amended
    agreement based on that ordinance and/or taken the position that the
    amended ordinance could not be applied retrospectively to allow recovery
    of pre-2005 franchise fees. Further, TCG might have objected to
    calculation methodologies proposed by Metro for inclusion in the amended
    ordinance. In the final analysis, the parties may well have been left in the
    position of having a “battle of experts” trial even if the Metropolitan
    Council passed an amended ordinance with franchise fee provisions that
    were later shown to comply with the Memphis case.
    The language in the Federal Act requiring “publicly disclosed”
    franchise fees was not designed to allow telecommunications providers to
    agree to publicly disclosed franchise fees, use the public rights-of-way for
    several years and escape the responsibility for paying any franchise fees
    when the fees had been disclosed and agreed upon in terms that were
    legally permissible at the time of formation. This is especially true where,
    as here, the telecommunications provider was never prohibited, delayed, or
    restricted in the use of the PROW. Although rate-making methodologies
    were offered as proof at trial, the Court is not setting rates here, but, rather,
    is awarding damages in an amount lower than the amount previously
    publicly disclosed and agreed to in the Franchise Agreement.
    Consequently, the Court concludes that awarding Metro fair and reasonable
    compensation for use of the public-right-of-way is not retroactive rate
    evoking.
    Contracts are subject to local, state, and federal law. All local
    ordinances are subject to state law. State laws are generally subject to
    federal law. This Court did not have to wait on Metro to pass a new
    ordinance before it had authority under the law to determine that the 5% flat
    -7-
    fee was unenforceable or to determine that the Franchise Agreement is
    enforceable in all other relevant respects. The requirement that changes to
    the Franchise Agreement be made by ordinance relates to consensual
    changes to the Franchise Agreement initiated jointly by the parties. The
    Court concludes that this “amendment by ordinance” provision does not
    prevent a court from applying the law and determining damages in a
    contract ( or quasi-contract) case where a calculation provision has been
    declared unenforceable (but legally severable) and where, as here, the Court
    respectfully declines to allow telecommunication providers to exercise veto
    power over any franchisee fee sought by a municipality when that
    telecommunication provider has already received the full benefit of the
    contracted arrangement.
    ***
    The Court adopts Metro’s approach, in part. The Court rejects
    TCG’s methodology to the extent that because it is narrowly tied to the
    proposition that Metro’s franchise fees can only relate to Metro’s cost of
    supervising and regulating TCG’s use of the PROW because TCG’s
    approach does not yield franchise fees that bear a reasonable relationship to
    the actual cost impact on the PROW. Similarly, the so-called “free rider”
    approach urged by TCG operates as a windfall which intrudes upon
    Metro’s exercise of its police powers and its statutorily delegated authority
    to supervise and regulate the use of the PROW.
    At trial, the parties offered expert proof on how a reasonable
    franchise fee can be calculated in the event that the Court ruled that Metro
    could recover. Metro’s approach took into account all its costs. TCG’s
    approach was a more focused approach based, in part, on its legal position
    that if Metro could recover, such a recovery should be tailored to reflect
    only Metro’s cost of supervising and regulating the use of the PROW.
    Specifically, Metro claimed that TCG owed Metro $1,511,856.00 for use of
    the PROW from 1997 through 2012. See Metro’s Post-Trial Brief, p. 1.
    TCG asserted that if the Court determined, over its vigorous objection, that
    Metro was entitled to anything, Metro could only recover franchise fees on
    a going-forward basis. TCG urged, however, in the alternative, that if the
    Court decided that Metro was entitled to recover franchise fees for the years
    1997 through 2012 that the recovery should total no more than $26,618.00
    in the aggregate. See Post-Trial Brief of Defendant TCG Midsouth, Inc., p.
    29.
    ***
    -8-
    Based on the exhaustive proof offered by Plaintiff’s three experts,
    the Court concludes that Metro’s methodology and calculations leads to a
    range of reasonable fees that satisfy the Memphis case, including the full
    amount Metro is claiming. Here, because it is particularly difficult to
    determine with precision what a reasonable fee should be here, the Court
    hereby awards Metro $550,000.00 in the aggregate, as reasonable franchise
    fees for the entire period addressed by the proof at trial. Because of the
    uncertainty of the precise amount and because of the vigorously disputed
    question of liability and amount, the Court concludes that Metro is not
    entitled to interest which may have occurred prior to the entry of judgment.
    (Footnote omitted). TCG timely appealed to this Court.
    Discussion
    Although not stated exactly as such, TCG raises the following issues on appeal: 1)
    whether the Trial Court erred in awarding damages to Metro in light of the fact that the
    underlying ordinance establishing a 5% gross revenue fee has been held invalid; 2)
    whether the Trial Court erred in crediting Metro’s methodology in determining costs
    when it did not identify specifically which costs TCG’s use of right-of-ways caused
    Metro to incur; 3) whether the Trial Court erred in finding that Metro could recover any
    damages from TCG for the period after TCG conveyed ownership of its system to NES;
    and, 4) Whether the Trial Court’s award to Metro was consistent with 47 U.S.C. § 253(c),
    which, as pertinent, permits a local government to require fair and reasonable
    compensation for a telecommunications provider’s use of the rights-of-way if the
    compensation is imposed on a nondiscriminatory basis and is publicly disclosed by the
    local government. Metro raises its own issue of whether the Trial Court erred in
    awarding roughly only one-third of what Metro sought and presented evidence for in
    damages.
    Our review is de novo upon the record, accompanied by a presumption of
    correctness of the findings of fact of the trial court, unless the preponderance of the
    evidence is otherwise. Tenn. R. App. P. 13(d); Bogan v. Bogan, 
    60 S.W.3d 721
    , 727
    (Tenn. 2001). A trial court’s conclusions of law are subject to a de novo review with no
    presumption of correctness. S. Constructors, Inc. v. Loudon County Bd. of Educ., 
    58 S.W.3d 706
    , 710 (Tenn. 2001).
    We first address whether the Trial Court erred in awarding damages to Metro in
    light of the fact that the underlying ordinance establishing a 5% gross revenue fee has
    -9-
    been held invalid. Local governments may use their police powers to assess reasonable
    compensation for a telecommunication providers’ use of the public rights-of-way. A
    statute from 1907 features prominently in this case. The 1907 Act provides as follows:
    Any village or city within which such line may be constructed shall have all
    reasonable police powers to regulate the construction, maintenance, or
    operation of the line within its limits, including the right to exact rentals for
    the use of its streets and to limit the rates to be charged; provided, that such
    rentals and limitations as to rates are reasonable and imposed upon all
    telephone and telegraph companies without discrimination. No village,
    town, or city shall have the right to prevent the company from constructing,
    maintaining, and operating the line within the village, town, or city, so long
    as the line is being constructed, maintained, or operated within the village,
    town, or city, in accordance with the reasonable police regulations.
    Tenn. Code Ann. § 65-21-103 (2015).
    In the present case, the franchise fee ordinance was ruled invalid, and Metro does
    not contest that ruling on appeal. Two key opinions by this Court, City of Chattanooga v.
    BellSouth Telecommunications, Inc., No. E1999-01573-COA-R3-CV, 
    2000 WL 122199
    (Tenn. Ct. App. Jan. 26, 2000), no appl. perm. appeal filed, and BellSouth
    Telecommunications, Inc. v. City of Memphis, 
    160 S.W.3d 901
    (Tenn. Ct. App. 2004),
    stand for the proposition that a local government may not charge a telecommunication
    provider a flat gross revenue fee untethered to any actual cost incurred by the city. The
    United States District Court for Tennessee, Western Division, analyzed the BellSouth and
    Chattanooga decisions together as follows:
    First, Level 3 argues that the Use Agreement was not voluntary.
    Level 3 avers the City initially informed Level 3 that it would not be
    allowed to install its network facilities on the PROW unless and until it
    entered into a written agreement. (Compl. ¶ 29.) Subsequently, and as a
    result of the City’s threat to deny the permits Level 3 needed to install its
    network facilities in the City’s PROW, Level 3 contends that it was
    compelled to enter into the Use agreement with the City on February 25,
    2000.
    Second, Level 3 argues that regardless of whether the agreement was
    voluntary, the City exceeded the bounds of the 1907 and 1885 Acts’
    provisions. Level 3 concedes that proprietary and governmental powers
    were granted to the City by the 1869-70 and 1879 Acts. However, Level 3
    argues that the 1907 Act limits the proprietary powers of the City, as
    -10-
    established in the 1869-70 and 1879 Acts, with respect to regulating
    telecommunication companies’ use of the City’s PROW. Level 3 relies on
    two Tennessee Court of Appeals decisions, Chattanooga v. BellSouth, No.
    E1999-01573-COA-R3-CV, 
    2000 WL 122199
    (Tenn. Ct. App.) (Jan. 26,
    2000) and BellSouth, 
    160 S.W.3d 901
    , in support of that proposition. In
    Chattanooga, the court considered an ordinance which required anyone
    attempting to provide telecommunication services within the city of
    Chattanooga to obtain a franchise from the city and would pay a franchise
    fee of “five percent of its gross revenue to the city each year.” 
    2000 WL 122199
    at * 1. The court held that the ordinance was invalid because it was
    not a reasonable exercise of the city’s police powers. The Chattanooga
    court held that the city, “in its proprietary capacity” may “exact a charge for
    the use of its rights of way unrelated to the costs of maintaining the rights-
    of-way, but in its governmental capacity, it may only act through an
    exercise of its police power to regulate specific activity or to defray the cost
    of providing services or benefit to the party paying the fee.” Chattanooga,
    
    2000 WL 122199
    , at *1 (citations omitted). In BellSouth, the court
    considered Ordinance 4404 which mandates that telecommunications
    service providers obtain or enter into a franchise agreement with the City
    for the right “to construct, maintain and operate a telecommunications
    system [in the public rights-of-way] ... within the City of 
    Memphis.” 160 S.W.3d at 905
    (citing Memphis City Ordinance No. 4404). Pursuant to the
    franchise agreement, a telecommunications service provider is required to
    pay the City as “general compensation” equal to five percent of the
    corporation’s gross revenues for each quarter of a compensation year. 
    Id. The court
    held that although the City has broad powers under the 1879 Act,
    it must exercise them “with recognition of the State’s grant to the
    telecommunication provider” in the 1885 
    Act. 160 S.W.3d at 913
    . The
    BellSouth court found that “[t]he 1907 Act delineates the authority of
    municipalities in dealing with [a telecommunications] carrier and limits the
    charges to what is reasonable necessary for the supervision and regulation
    of the [the carrier’s] use of the [PROW].” 
    Id. at 916.
    The City argues that neither the 1885 Act nor the 1907 Act displaced
    the City’s power to enter into contracts regarding its PROW. The City
    contends that the BellSouth and Chattanooga decisions do not hold that the
    City lacks proprietary power to enter into PROW contracts with
    telecommunications companies. Rather, the City posits that both decisions
    hold that the 1907 Act only proscribes the City from unilaterally dictating
    the terms of a private utility company’s access to the PROWs in the
    absence of an agreement, such as in a municipal ordinance. In other words,
    -11-
    the City argues that it is not prohibited from exercising its proprietary
    powers to enter into PROW contracts, so long as this exercise involves a
    voluntary agreement between the City and a telecommunications company.
    The Court need not determine whether the Use Agreement between
    Level 3 and the City was voluntary because the City’s municipal powers
    were limited by the 1907 Act regardless of whether the Use Agreement was
    voluntary. The Court declines to adopt the City’s interpretation of the
    BellSouth and Chattanooga decisions. Nothing in the text of 1907 Act or
    the 1885 Act explicitly or by implication refer to limiting the reasonable
    police powers language to situations in which there is no voluntary
    agreement. In BellSouth, the court cites to the 1907 Act stating that it
    “expressly restricts the fees that municipalities may impose upon telephone
    companies pursuant to the municipalities’ police 
    powers.” 160 S.W.3d at 908
    . The court did not limit this holding to whether the fees were imposed
    by a city on the macro level by a city ordinance or on the micro level
    through individual contracts. This distinction that the City asks the court to
    make is not in line with the policy behind the 1907 Act. The 1907 Act
    seeks to limit municipalities’ regulation of telecommunication companies.
    It logically follows that this limit should apply in this case, where the City
    contends use of the PROW was regulated through an individual contract
    with a telecommunications company rather than a municipal ordinance.
    Therefore, the Court finds that the 1907 Act applies in this case and
    accordingly, limits the City’s actions to its reasonable police powers.
    ***
    Level 3 has not put forth competent evidence, to establish that the fees
    imposed on Level 3 do not bear a reasonable relationship to the City’s
    PROW costs.        Level 3 asks the Court to make several factual
    determinations about the reasonableness of the fees based on the terms of
    the Use Agreement and the City’s admissions in prior litigation. At the
    summary judgment stage, the Court is constrained from engaging in a
    weighing of the facts or factual determinations. Anderson v. Liberty Lobby,
    Inc., 
    477 U.S. 242
    , 255 (1986). Determining the reasonableness of the fees
    is an issue for the fact finder. Because that issue cannot be determined
    here, summary judgment is inappropriate as to Count III, regarding the
    reasonableness of the fees imposed.
    ***
    -12-
    Pursuant to Tennessee law, a municipal action may be declared ultra
    vires for either of two reasons: (1) because the action was entirely outside
    the scope of the city’s authority under its charter or a statute, or (2) because
    the action was not undertaken consistent with the mandatory provisions of
    its charter or a statute. City of Lebanon v. Baird, 
    756 S.W.2d 236
    , 241-42
    (Tenn. 1988). “Thus, the law recognizes a difference between the existence
    of a municipal power and the manner or mode of exercising municipal
    power legitimately.” 
    Id. (citations omitted).
    At issue in this case is
    whether the City acted within its limits as to the mode of exercising its
    authority. The Court finds that a genuine issue of material fact remains as
    to this issue. As discussed above, the reasonableness of fees the City
    charged Level 3 for use of the City’s PROW is an issue of fact that could
    permit a reasonable jury to return a verdict for the City. The City could
    reasonably establish at trial that the fees imposed upon Level 3 were within
    its municipal authority and thus, that the Use Agreement was not ultra
    vires. Therefore, summary judgment is inappropriate as to Counts I and VI,
    regarding whether the Use Agreement was ultra vires.
    Level 3 Communications, LLC v. City of Memphis, No.: 06-02547, 
    2008 WL 11322104
    ,
    at *9-11 (W.D. Tenn. July 31, 2008).
    Metro submits that, notwithstanding the invalidity of the ordinance, the franchise
    agreement still must be enforced to the extent its other provisions are lawful. For its part,
    TCG argues that this case should have ended years ago with the ruling that the ordinance
    is invalid.
    We agree with the Trial Court that the invalidity of Metro’s 5% gross revenue
    franchise ordinance is not totally dispositive of this case. We reject TCG’s contention
    that having received the benefits of the franchise agreement it can escape paying any
    fees. Local governments in Tennessee may charge franchise fees provided they bear a
    reasonable relationship to cost incurred by the local government. TCG entered with eyes
    open into a franchise agreement with Metro. That agreement incorporated what only
    later was held to be an invalid 5% gross revenue fee. TCG, however, knew and agreed
    from the beginning it would have to pay fees. TCG was not ambushed. As it happened,
    the ordinance setting the rate is invalid because it sets a gross revenue fee akin to a tax.
    Because the ordinance later was held invalid does not mean Metro exceeded its authority
    in establishing a fee in the first place, which TCG agrees it may do. The Trial Court did
    not judicially establish a new rate. Instead, the Trial Court attempted to effectuate the fee
    provision of the franchise agreement as best it could in light of the invalidity of the
    ordinance. The Trial Court did not err in holding that Metro was entitled to
    compensation pursuant to the franchise agreement.
    -13-
    We next address whether the Trial Court erred in crediting Metro’s methodology
    in determining costs when it did not identify specifically which costs Metro incurred
    because of TCG’s use of rights-of-way. Metro’s method involved calculating the total
    costs for public rights-of-way, then determining which portion was incurred by utilities.
    Metro determined that TCG, in 2007, occupied 0.07486% of Metro’s rights-of-way.
    Metro applied indices to arrive at a figure of $1,511,865 of costs owed by TCG. TCG
    argues that Metro’s figure wrongly includes costs for all public rights-of-way, rather than
    just utilities. According to TCG, Metro’s methodology runs afoul of BellSouth because it
    factors in indirect costs. We think TCG misconstrues this Court’s holding in BellSouth
    and Chattanooga. The standard is one of reasonable relation to the cost to the city for use
    and maintenance, not just directly incurred costs. The Trial Court heard the evidence and
    credited Metro’s experts and their methodology, which took into account common and
    joint costs. We find no reversible error on this issue.
    We next address whether the Trial Court erred in finding that Metro could recover
    any damages from TCG for the period after TCG conveyed ownership of its system to
    NES. TCG argues that since it conveyed its facilities to NES in 2002, or, 2008 at the
    latest, when the Bill of Sale was issued, it should not be liable for any fees after the
    conveyance. TCG asserts in its brief that merely sending electrons and lightwaves do not
    constitute “use” for purposes of the 1907 Act. We believe that which entity owned the
    cable system when is beside the point. TCG entered into an agreement with Metro to use
    its public rights-of-way and paying a fee was a term of the agreement. For reasons
    discussed above, TCG remained liable to pay fees, although not a gross revenue fee as
    originally agreed to and intended. This liability did not cease with the conveyance of the
    system to NES because TCG continued to use and enjoy the benefit of the public-rights-
    of-way through its ongoing use of the system, if not ownership or operation. We find, as
    did the Trial Court, that pursuant to the terms of the franchise agreement, TCG continued
    to use the system and remained liable to pay fees so long as it used the public rights-of-
    way.
    We next address whether the Trial Court’s award to Metro was consistent with 47
    U.S.C. § 253(c), which, as pertinent, permits a local government to require fair and
    reasonable compensation for a telecommunications provider’s use of the rights-of-way if
    the compensation is imposed on a nondiscriminatory basis and is publicly disclosed by
    the local government. 47 U.S.C. § 253(c) provides:
    (c) State and local government authority
    Nothing in this section affects the authority of a State or local government
    to manage the public rights-of-way or to require fair and reasonable
    -14-
    compensation from telecommunications providers, on a competitively
    neutral and nondiscriminatory basis, for use of public rights-of-way on a
    nondiscriminatory basis, if the compensation required is publicly disclosed
    by such government.
    In the first instance, we do not find that the Trial Court’s award defied the public
    disclosure requirement of this law because TCG, as did the public, knew when it entered
    into the agreement with Metro that it would have to pay a fee. The Trial Court observed
    “the Court is not setting rates here, but, rather, is awarding damages in an amount lower
    than the amount previously publicly disclosed and agreed to in the Franchise
    Agreement.” Therefore, neither TCG nor the public can claim any surprise or deception.
    With respect to non-discrimination, TCG argues that it is discriminatory for the
    Trial Court to have fashioned essentially a retroactive fee and imposed it on TCG while,
    for whatever reason, Metro never bothered to pass a valid ordinance. Naturally, had
    Metro enacted a valid franchise fee ordinance initially or at any time later and TCG paid
    its fees in conformity with the valid ordinance, it is perhaps less likely either party would
    have resorted to the courts. On the other hand, as noted by the Trial Court, there is no
    guarantee this matter would not have wound up in court anyway, resulting in a clash over
    methodology, rates, and so forth.
    TCG’s stance also is somewhat contradictory in that, with respect to the
    methodology issue, TCG objected to Metro’s methodology as being too non-specific
    relative to TCG, but on this issue, TCG actually protests that it is being singled out
    inappropriately. We reiterate that neither we, nor the Trial Court, have established
    judicially a new franchise fee. We instead are giving effect to the parties’ franchise
    agreement, including its fee provision, as consistent with current law. We hold that the
    Trial Court’s award did not contravene either the public disclosure or non-discrimination
    requirements of 47 U.S.C. § 253(c). In short, we cannot accept TCG’s position that our
    General Assembly and Congress intended for a user such as TCG to receive all the
    benefits of a franchise agreement for free even though it had agreed to pay for those
    benefits.
    The final issue we address is Metro’s issue of whether the Trial Court erred in
    awarding only roughly one-third of what Metro sought and presented evidence for in
    damages. Metro argues that “this Court should increase the damages to match the ‘full
    amount’ owed by TCG for 1997-2012: $1,511,856.” TCG, for its part, states: “[I]n the
    event the Court concludes that Metro was entitled to some recovery, the Court should
    remand and remit with direction to enter judgment for Metro in an amount not to exceed
    $26,618 . . . .” Alternatively, TCG suggests: “If the Court further concludes that Metro’s
    -15-
    recovery is limited to the 1997-2001 period (as TCG conveyed its facilities in 2002), this
    amount should be reduced to $9,021.”
    The Trial Court had this to say with respect to the range of damages: “Metro’s
    methodology and calculations leads to a range of reasonable fees that satisfy the Memphis
    case, including the full amount Metro is claiming. Here, because it is particularly
    difficult to determine with precision what a reasonable fee should be here, the Court
    hereby awards Metro $550,000.00 in the aggregate . . . .”
    A trial court’s award of damages is a question of fact and will be affirmed unless
    the trial court adopted the wrong measure of damages or the evidence preponderates
    against the amount of damages awarded. Wilson v. Monroe County, 
    411 S.W.3d 431
    ,
    443 (Tenn. Ct. App. 2013) (quoting Moody v. Lea, 
    83 S.W.3d 745
    , 751) (Tenn. Ct. App.
    2001). The Trial Court selected a figure between the low end, that is, $9,021 from TCG’s
    perspective, and the upper end, $1,511,856 from Metro. The Trial Court did not lay out
    precisely how it arrived at $550,000. However, a range of damages necessarily implies
    that more than one figure from within that range could legitimately be settled upon, and
    the evidence does not preponderate against this figure found by the Trial Court. We
    decline both Metro’s and TCG’s invitations to choose another figure from the range of
    damages supported by the evidence. We affirm the judgment of the Trial Court in its
    entirety.
    Conclusion
    The judgment of the Trial Court is affirmed, and this cause is remanded to the
    Trial Court for collection of the costs below. The costs on appeal are assessed against the
    Appellant, Teleport Communications America, LLC, and its surety, if any.
    ____________________________________
    D. MICHAEL SWINEY, CHIEF JUDGE
    -16-
    

Document Info

Docket Number: M2016-02222-COA-R3-CV

Judges: Chief Judge D. Michael Swiney

Filed Date: 11/29/2017

Precedential Status: Precedential

Modified Date: 11/30/2017