Jefferson County Schools v. Tennessee Risk Management Trust ( 2018 )


Menu:
  •                                                                                                  03/15/2018
    IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    January 16, 2018 Session
    JEFFERSON COUNTY SCHOOLS v. TENNESSEE RISK MANAGEMENT
    TRUST, ET AL.
    Appeal from the Chancery Court for Jefferson County
    No. 14-CV-120    Ben W. Hooper, II, Judge
    No. E2017-01346-COA-R3-CV
    In this appeal concerning insurance coverage, Jefferson County Schools (“Plaintiff”) sued
    its insurers, Tennessee Risk Management Trust and Travelers Indemnity Company
    (“Defendants”), in the Chancery Court for Jefferson County (“the Trial Court”). Building
    8 at Jefferson County High School collapsed during a rainstorm. The Tennessee State
    Fire Marshal’s Office ordered Plaintiff to implement repairs to prevent a future collapse
    of both the damaged and undamaged portions. Plaintiff asserted that, pursuant to an
    “ordinance or law” provision in its insurance policy, Defendants were responsible for
    coverage for additional work in undamaged portions of Building 8 in order to comply
    with the Fire Marshal’s directive. Defendants argue in response that the additional work
    was discretionary and went beyond what the insurance policy covered. After a hearing,
    the Trial Court entered judgment in favor of Defendants. Plaintiff appeals. We hold that
    the Fire Marshal’s directive, issued under that office’s authority, qualified as an
    “ordinance or law.” Defendants were, therefore, required to cover the additional work.1
    We reverse the judgment of the Trial Court and remand for determination and entry of a
    monetary judgment in favor of Plaintiff.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Reversed;
    Case Remanded
    D. MICHAEL SWINEY, C.J., delivered the opinion of the court, in which CHARLES D.
    SUSANO, JR. and THOMAS R. FRIERSON, II, JJ., joined.
    Albert J. Harb and Bart C. Williams, Knoxville, Tennessee, for the appellant, Jefferson
    County Schools.
    1
    Tennessee Risk Management Trust, while a party on appeal, no longer is actively involved in this
    litigation. We refer to the defendants collectively for convenience.
    Russell E. Reviere and Jonathan D. Stewart, Jackson, Tennessee, for the appellees,
    Tennessee Risk Management Trust and the Travelers Indemnity Company.
    OPINION
    Background
    On July 7, 2013, a major rainstorm occurred in Jefferson County. A portion of
    Building 8, an aging vocational building at Jefferson County High School, collapsed. No
    one was present at the time. Building 8 was covered through Tennessee Risk
    Management up to $100,000 less a $500 deductible. Excess claims were covered by
    Travelers Indemnity Company. The insurance policy contained an “ordinance or law”
    provision providing for coverage of expenses “caused by the enforcement of any
    ordinance or law.” The policy provided as relevant:
    f. Ordinance or Law
    If a Covered Cause of Loss occurs to Covered Property, the Company will
    pay for:
    (1) The loss to the undamaged portion of a covered building caused by
    the enforcement of any ordinance or law that:
    (a) Requires the demolition of parts of the same property not damaged by a
    Covered Cause of Loss;
    (b) Regulates the construction or repair of buildings, or establishes zoning
    or land use requirements at the Insured’s premises; and
    (c) Is in force at the time of loss.
    The most the Company will pay for loss or damage under this portion of
    Ordinance or Law is the Limit of Insurance specified for Ordinance or Law
    — Undamaged Portion shown in the Supplemental Coverage Declarations.
    ***
    (3) The increased cost to repair, rebuild or construct the Covered
    Property caused by enforcement of building, zoning, land use or any other
    ordinance or law when the Covered Property is insured for replacement
    cost. If the covered building is repaired or rebuilt, it must be intended for
    similar occupancy as the current building, unless otherwise required by
    zoning or land use ordinance or law.
    -2-
    The Company will not pay for increased construction costs until the
    Covered Property is actually repaired or replaced, at the same location or
    elsewhere; and unless the repairs or replacement are made as soon as
    reasonably possible after the loss or damage but not to exceed 2 years. The
    Company may extend this period in writing during the 2 years.
    The most the Company will pay for loss or damage under this portion of
    Ordinance or Law is the increased cost of construction repair or
    replacement:
    (a) Of a building of the same size and at the same premises, or another
    premises if required by the ordinance or law, and
    (b) Limited to the minimum requirements of such ordinance or law
    regulating the repair or reconstruction of the damaged property on the same
    site. not to exceed the Limit of Insurance specified for Ordinance or Law—
    Increased Cost of Construction shown in the Supplemental Coverage
    Declarations.
    ***
    D. EXCLUSIONS
    1. The company will not pay for loss or damage caused directly or
    indirectly by any of the following. Such loss or damage is excluded
    regardless of any other cause or event that contributes concurrently or in
    any sequence to the loss.
    ***
    h. ORDINANCE OR LAW
    The enforcement of any ordinance or law:
    (1) Regulating the construction, use or repair of any property; or
    (2) Requiring the tearing down of any property, including the cost of
    removing its debris;
    except as provided in the Covered Costs and Expenses, item B.2.f.
    Ordinance or Law
    The Ordinance or Law exclusion applies whether the loss results from an
    ordinance or law that is enforced even if the property has not been
    damaged; or from the increased costs incurred to comply with an ordinance
    -3-
    or law in the course of construction, remodeling or demolition of property,
    or removal of its debris, following a physical loss to that property.
    On July 8, 2013, David Pittman with the Tennessee State Fire Marshal’s Office
    issued a directive to school officials stating in part that “[a] structural engineer will need
    to evaluate the remaining structure of the vocational building to ensure that the structural
    integrity of the remaining building is in adequate condition and future collapses will not
    occur.” Plaintiff did that. Expensive work ensued. Travelers paid for reconstruction of
    the collapsed portion of Building 8, as well as certain additional work in the rest of the
    building. In all, Travelers paid out over $900,000 on the claim. However, disagreements
    arose as to coverage beyond this point. The engineer of record, Carl Taylor, retained by
    Plaintiff as directed by the Fire Marshal determined that compliance with the Fire
    Marshal’s directive required vertical reinforcement of the remainder of Building 8. Mark
    Buchanan, Defendants’ engineer, opined that additional reinforcement on the remainder
    of Building 8 went beyond what was necessary. Travelers declined to pay for this
    additional work.
    In October 2014, Plaintiff sued Defendants in the Trial Court. Plaintiff argues
    that, pursuant to the “ordinance or law” provision of the insurance policy, Defendants are
    responsible for the additional work undertaken in order to comply with the Fire Marshal’s
    directive. For their part, Defendants contend that they already have fulfilled their
    responsibilities under the insurance policy, and that their paying for the additional work
    would result in an undue windfall for Plaintiff.
    This case was tried without a jury in June 2017. The most pertinent testimony
    came from the sides’ respective engineers, Carl Taylor and Mark Buchanan.
    Carl Taylor, Plaintiff’s engineer, testified in part as follows:
    Q. Alright. Now, when you were looking around Building-8 in its
    collapsed state in terms of your trying to comply with that directive, and
    we’ve already marked it, I don’t need to keep plowing new ground so to
    speak, but what was it about that Building-8 that was of concern to you in
    terms of a structural evaluation? Let’s talk about the walls, the height of
    the halls, all the different factors, just talk to the Judge about that.
    A. Well, you are correct, the walls were one concern because of their
    height.
    Q. Do you remember how high --
    A. And the slenderness. No, I do not, but they’re relatively tall walls. We
    looked at how the bar joists were anchored to the walls, where it had fallen
    you had access to the actual joists, and the joist-bearing were not adequate.
    -4-
    Q. Both in the collapsed area and the non-collapsed?
    A. Yes.
    THE COURT: The joist-bearings?
    A. Yes, where the bar joists rest on the wall, how they’re anchored. And
    so we did that on, I believe the 10th, and on the 11th I believe we went up
    in a lift and I tried to look at the other portions of the building at the joist-
    anchorage, looked for any distress that was obvious to the naked eye in the
    building.
    ***
    Q. Okay. Would this building be, in terms of a classification, a sound
    building, fragile building? Do you understand what I’m asking? And
    you’re looking at it from a structural-engineering standpoint.
    A. It would be a building that I would consider to be in impossible distress.
    And then after reviewing the existing drawings, to see the fact that the walls
    are not reinforced or anything else, I would have to at least consider it to be
    deficient, given that there had been a collapse.
    Q. Alright. Now, you said that you looked at the original drawings and
    they weren’t reinforced, what do you mean by reinforcement?
    A. There was not any reinforcing steel in the block walls, any vertical
    reinforcement.
    Q. And would you normally combine concrete in conjunction with that
    steel --
    A. Yes.
    Q. -- to solidify that joint?
    A. Right, yes sir.
    Q. What’s the effect of that, especially on a building like this that’s just
    collapsed, what would that do to this building?
    A. It would reduce greatly any possible distress or concerns with it.
    Concrete block and brick have no strength when it comes to bending.
    When you have wind loads or something like on the wall and the wall
    bends, mortar has almost no strength. It’s like concrete is not strong in
    tension, when you try to bend it concrete’s not strong. So you have
    reinforcing steel to take those loads, to hold the elements of the block wall
    together.
    Q. Alright. So the process of filling these block walls with concrete and
    rebar is designed to cure that problem?
    A. Yes.
    Q. Now, let’s take a quick look, if we could, at the Fire Marshal’s
    directive, which has been marked as Exhibit 3A. We’ve got two different
    -5-
    ones, one is easier to read, so look at 3A. And in particular, I’d ask you to
    look at the last paragraph on the second page, 1-of-2, do you see that?
    A. Yes.
    Q. This was the directive, “A structural engineer will need to evaluate the
    remaining structure of the vocational building to ensure that the structural
    integrity of the remaining building is in adequate condition and future
    collapses will not occur.” Was that the charge as you understood it, sir?
    A. That is the charge, but I must say that one cannot state that there will be
    no future collapses.
    Q. Alright. So your duty was to satisfy the State Fire Marshal’s Office as
    best you could?
    A. As their intent of it being in adequate condition and that someone would
    sign off to say it is safe to be occupied.
    Q. And that someone would be?
    A. Me, under the circumstances.
    Mark Buchanan, Defendants’ engineer, testified in part as follows:
    Q. Alright. After you were able to determine what the mechanism of
    failure was, in your professional opinion, was that failure caused by the
    lack of reinforcement in the masonry in that wall?
    A. No, sir.
    Q. Explain that to the Court.
    A. Alright, so we have gravity loads which are vertical, they’re created
    from gravity. And we have lateral loads, wind loads, earthquakes, anything
    that pushes on the side of the building. Masonry is very, very strong under
    compression, gravity loads.
    Q. Explain what you just said when you said masonry is very strong under
    compression.
    A. So if we have a concrete block and we try to push on the top of it, it’s
    very strong in that direction. Gravity, down-force. If we try to bend a
    block wall like wind blowing on wall, it goes into bending. Just like a
    piece of paper, if I take this piece and apply force here, it bends. So, when I
    do this, this exterior face of the wall on this side goes into tension, it’s
    trying to pull itself apart, the inside is in compression. So when that
    masonry wall is built and is under pure gravity loads, is 100% pushing
    down, there’s no tension in the wall. I have never seen a masonry wall fail
    in compression, I’ve seen them fail in shear, which is very unique, I’ve seen
    them fail in flexure multiple times, but never in compression. So just the
    pure weight of the water pushing down on the joists, loading the wall,
    would not have created any failures on this building whatsoever.
    -6-
    Q. And how certain of that are you?
    A. 100%.
    ***
    Q. And in the end result, Mr. Buchanan -- again, not looking at it through
    the lens of what an insurance company paid or not paid -- did you interpret
    what had to be done as you would regardless of whether an insurance
    company had hired you or Jefferson County had hired you?
    A. It doesn’t matter who I work for.
    Q. Let me do it this way: If Jefferson County after this collapse had said
    we want to hire you to give us advice of what we have to do and need to do
    structurally to fix this, get it approved by the Fire Marshal, but make sure
    we have a structurally-sound building, to put kids and people like your
    parents in, teachers and all the people that work in and out of that building,
    would your plans have been any different than scenario A ones we looked
    at? Would that change what your professional opinion was about how to
    address this and fix it?
    A. If they had come to me as a client, I would sit down with them and
    explain the different scenarios. You can’t have reinforcement? You don’t
    have to have reinforcement. It’s a good idea, it’s an expensive idea. Is it
    safe without it? It meets the code. I would explain that and have them
    make an informed decision. I call this the golden rule, the person with the
    gold gets to make the rule. I don’t care if they reinforce their block or not,
    my only objective is to meet the minimum standards of the code that I’m
    given in order to provide a safe environment for whoever’s in the building.
    Now, that’s not to say that reinforcing block is a bad idea, it’s not. I
    designed a facility for Arnold Engineering for 350 mile-an-hour winds,
    there has never been 350 mile-an-hour winds tracked on the interior of the
    United States of America. And I pointed that out to them. And their
    answer was, pardon my French, “We don’t give a s---, that’s what we want
    you to [do].” And that’s what I did. They had the gold, they made the rule,
    I complied. In this particular case, the code says what I did is exactly spot
    on. There’s no doubt in my mind I did the right thing.
    Q. And was that the same thing you would’ve done in 2008, 2009, 2011?
    A. Whenever. Today.
    Q. So, to be very clear, is there any question in your mind about what you -
    - and it was you telling Travelers, right? [Y]ou were the one making this
    judgment, they were using you?
    A. I’m the one that was responsible for that, yes sir.
    -7-
    Q. Any doubt in your mind that what you ultimately showed to the Court
    and the drawings you just explained, complied in every respect with what
    the 2006 IBC code said had to be done?
    A. Structurally, that’s a correct statement.
    Q. Without any doubt?
    A. No doubt.
    Evidence at trial reflected $575,955.93 as the cost for the disputed additional work.
    In June 2017, the Trial Court entered its final judgment, finding in favor of
    Defendants. The Trial Court found and held as follows:
    With the request for a jury trial being waived, this case came on for
    hearing on June 7 and 8, 2017, before the Court. A review of the file shows
    a complaint for declaratory judgment based on a significant rain event
    occurring July 7, 2013, and causing the partial collapse of the roof of
    Building 8 and structural damage to the building.
    The issue from the court files presented the question of whether or
    not certain repairs required to put Building 8 in compliance with the
    “Standards and Codes” was a covered loss under the policy. (Exhibit # 21).
    This issue was then agreed upon by the parties that the rain event of July 7,
    2013, was in fact a Covered Cause Loss and the policy was a Replacement
    Cost Policy. The part of the policy that must be construed by the Court is
    found under Section B.(2)(f), page 6 of the Property Coverage Form
    attached hereto and being a page from Exhibit 21. As stated in the
    plaintiff’s written argument (Plaintiff’s Statement of Facts and
    Conclusions) “the analysis of this claim, therefore, must depend upon
    whether the facts of this case provide coverage under the above cited
    provisions”.
    Tennessee Risk Management Trust is no longer involved in this
    litigation. To conduct this analysis requires looking at every exhibit filed
    and admitted, all the evidence introduced, and the written arguments of
    counsel. The parties did provide some relief to the Court by stipulating
    that:
    a. The Tennessee State Fire Marshal’s Office (TSFMO) is empowered to
    adopt building codes for the State of Tennessee.
    b. At the time of the loss, the building codes adopted by the TSFMO and
    that were in effect were the 2006 International Building Code (2006 IBC),
    as well as the 2003 National Fire Protection Association 101 (2003 NFPA
    101).
    -8-
    c. The TSFMO has exclusive jurisdiction of the enforcement of these codes
    as they apply to schools.
    There was a collapsed portion of Building 8 that created no dispute
    and was paid for by the defendant, Travelers. In addition, Travelers noted a
    problem of no bar joist ties into the walls, and they repaired and paid for
    this work even though it was in the uncollapsed portion of Building 8.
    Their work, also included a whole new roof and scuppers for overflow
    water, plus providing $170,000 to accommodate the needs of the shop
    which had been damaged.
    It was here that the generosity of Travelers came to an end and they
    refused to cover and pay for the reinforcement of the masonry walls in the
    uncollapsed portion of Building 8.
    The Court will not go into detail about all the evidence offered, other
    than to say there was a lot and that all of it is important except for the fact
    that the first bridge to cross is whether or not this claim can survive the
    language of the policy of insurance. The Court finds that it cannot. The
    court will state the defendant’s witness, Mike Buchanan was found to be
    very knowledgeable and credible and his testimony was given substantial
    weight. Section (f). Ordinance or Law says:
    “If a Covered Cause of Loss occurs to Covered Property, the Company will
    pay for:
    (1) The loss to the undamaged portion of a covered building caused by the
    enforcement of any ordinance or law that:”
    Considering this portion of the policy, and keeping in mind that the word
    “undamaged” is used, whereas during the trial of this case it was usually
    referred to as “uncollapsed”, it can be seen that there must be a loss caused
    by the enforcement of any ordinance or law. The plaintiff, having this
    burden, has failed. There has been no showing of a code violation
    (ordinance or law). The fire marshal’s directive set out no code violation,
    nor can one be found anywhere in the evidence of this case as to the
    undamaged or uncollapsed portion of Building 8. If the Court is wrong,
    then the first subsection under (1) is “(a) Requires the demolition of parts of
    the same property not damaged by a Covered Cause of Loss;”. This
    condition has certainly not been met by the evidence. There is no coverage
    under the policy of insurance. Plaintiff’s claim is dismissed with costs to
    the plaintiff. Lastly, do not assume for one moment that the brevity of this
    Judgment is any indication of the amount of time it has taken this Court to
    come to this conclusion.
    -9-
    Plaintiff timely appealed to this Court.
    Discussion
    We restate and consolidate the issues Plaintiff raises on appeal into the following
    dispositive issue: (1) whether the Trial Court erred in holding that Defendants did not
    provide coverage for and, therefore, were not responsible for the additional work
    performed throughout Building 8.
    Our review is de novo upon the record, accompanied by a presumption of
    correctness of the findings of fact of the trial court, unless the preponderance of the
    evidence is otherwise. Tenn. R. App. P. 13(d); Bogan v. Bogan, 
    60 S.W.3d 721
    , 727
    (Tenn. 2001). A trial court’s conclusions of law are subject to a de novo review with no
    presumption of correctness. S. Constructors, Inc. v. Loudon County Bd. of Educ., 
    58 S.W.3d 706
    , 710 (Tenn. 2001).
    “In general, courts should construe insurance contracts in the same manner as any
    other contract.” American Justice Ins. Reciprocal v. Hutchison, 
    15 S.W.3d 811
    , 814
    (Tenn. 2000). In interpreting the policy, this Court’s task is to determine the intention of
    the parties, and view the “[t]he language of the policy . . . in its plain, ordinary and
    popular sense.” Id.; Guiliano v. Cleo, Inc., 
    995 S.W.2d 88
    , 95 (Tenn. 1999).
    Accordingly, this Court has held:
    [an insurance policy] should not be given a forced, unnatural or
    unreasonable construction which would extend or restrict the policy beyond
    what is fairly within its terms, or which would lead to an absurd conclusion
    or render the policy nonsensical and ineffective.
    Dixon v. Gunter, 
    636 S.W.2d 437
    , 441 (Tenn. Ct. App. 1982) (citing 44 C.J.S. Insurance
    § 296); see also Demontbreun v. CNA Ins. Co., 
    822 S.W.2d 619
    , 621 (Tenn. Ct. App.
    1991) (holding that an insurance policy should not be construed to extend “coverage
    beyond its intended scope”). This Court has a “duty to enforce contracts according to
    their plain terms[,]” and we are “precluded from creating a new contract for the parties.”
    Bob Pearsall Motors, Inc. v. Regal Chrysler-Plymouth, Inc., 
    521 S.W.2d 578
    , 580 (Tenn.
    1975).
    Defendants argue that the Fire Marshal’s directive, lacking as it was in any
    citations to specific code violations, fails to constitute an “ordinance or law” for purposes
    of coverage under the insurance policy. As stated by the Trial Court in its final judgment,
    -10-
    the parties in this case stipulated to the following with respect to the Fire Marshal’s
    authority:
    a. The Tennessee State Fire Marshal’s Office (TSFMO) is empowered to
    adopt building codes for the State of Tennessee.
    b. At the time of the loss, the building codes adopted by the TSFMO and
    that were in effect were the 2006 International Building Code (2006 IBC),
    as well as the 2003 National Fire Protection Association 101 (2003 NFPA
    101).
    c. The TSFMO has exclusive jurisdiction of the enforcement of these codes
    as they apply to schools.
    Given these stipulations, we can see no way that the Fire Marshal’s directive could be
    construed as merely discretionary rather than having the force of law. Plaintiff had to
    comply with the Fire Marshal’s directive before it could use a repaired Building 8.
    Defendants, in their brief on appeal, acknowledge the Fire Marshal has the power
    to “to force compliance with specific portions of the International Building Code that
    would be enforcement of an ordinance or law” but that “Plaintiff has not shown
    enforcement of any such provisions” and “[t]he existence of the power alone is not
    enforcement of an ordinance or law.” Respectfully, the Fire Marshal exercised this
    power when the directive was issued to Plaintiff. A review of relevant 2006 IBC
    provisions is illuminating. Under Section 115.1 the 2006 International Building Code,
    “Unsafe structures shall be taken down and removed or made safe, as the building official
    deems necessary and as provided for in this section.” Section 506.2.1 of the International
    Existing Building Code states: “Regardless of the extent of structural damage, dangerous
    conditions shall be eliminated.” Section 110.1 of the 2006 IBC provides further: “No
    building or structure shall be used or occupied, and no change in the existing occupancy
    classification of a building or structure or portion thereof shall be made until the building
    official has issued a certificate of occupancy therefor as provided herein.” While the Fire
    Marshal’s directive did not cite these specific provisions, there is no question that the Fire
    Marshal had the authority to enforce these code provisions. Additionally, there is no
    question this is exactly what the Fire Marshal did when it directed the school officials to
    retain a structural engineer to “evaluate the remaining structure of the vocational building
    to ensure that the structural integrity of the remaining building is in adequate condition
    and future collapses will not occur.”
    In a case from the Fifth Circuit United States Court of Appeals, the court
    discussed the building officials’ authority and affirmed in part the district court’s ruling
    in a factually analogous case:
    -11-
    HSIC next asserts that the Ordinance does not require demolition or
    regulate repair as required by the Policy but merely gives discretion to the
    building officials. Section 116.1 of the Ordinance provides that “[u]nsafe
    structures shall be taken down and removed or made safe, as the building
    official deems necessary.” This language mandates the removal or repair of
    unsafe structures. HSIC, however, points out that, though there were five
    previous fires at the Property, the building official did not mandate a re-
    design of the flex duct work until the December 2012 fire. This does not
    change our conclusion. The Lafayette Consolidated Government (the
    “City”) did not adopt the Ordinance until 2011, and the five previous fires
    all occurred between 1997 and 2010. Even if the building official’s prior
    lack of action was sufficient to preclude coverage under Section 2.f.(1), the
    Ordinance was not in effect at the time of the earlier fires.
    HSIC also asserts that the correspondence between City officials and
    Meadows West’s management shows that the Ordinance did not “require
    demolition” or “regulate repair.” We disagree. In his January 18, 2013,
    letter (the “January 18 Letter”) to Nevils, Manuel threatened to resort to
    legal action. Further, though the January 18 Letter does not specifically
    cite any ordinance or law, Manuel again corresponded with Nevils on April
    12, 2013 (the “April 12 Letter”). In the April 12 Letter, Manuel explicitly
    stated that he was authorized by law to take necessary steps to “resolve this
    problem [of potential fire hazards] under [Section 116], which has been
    adopted by the Lafayette Consolidated Government.” Manuel issued a
    repair deadline of September 30, 2013, and informed Nevils that he would
    disrupt the power to all of the unrepaired units if the repairs referenced in
    the January 18 Letter were not completed. Taken together, the January 18
    Letter and the April 12 Letter indicate that Manuel “deemed [the Property]
    an unsafe condition” and “specifie [d] the required repairs or improvements
    to be made to abate the unsafe condition ... within a stipulated time” as
    required by the Ordinance.
    Finally, Meadows West was required by City officials to reconfigure
    the flex duct work. Manuel identified the flex duct work as a fire hazard
    and instructed that it be removed and repaired.              Following this
    determination, Manuel: (1) requested that Meadows West hire a Louisiana
    licensed contractor; (2) instructed Meadows West to have the repair drawn
    and designed by a mechanical engineer; and (3) suggested acceptable
    repairs. While Manuel did not mandate a specific type of repair aside from
    the removal of the flex duct work, the repair plans still had to be approved
    by the Planning, Zoning, and Codes Department, and the repair itself was
    -12-
    subject to inspection by the fire marshal. Thus, Meadows West was
    required, by law and through the application of the Ordinance, to remove
    and replace the flex duct work, triggering the Ordinance or Law Provision.
    Houston Specialty Ins. Co. v. Meadows West Condo Ass’n, 640 Fed. Appx. 267, 272-73
    (5th Cir. 2016).
    In the present case, the Fire Marshal’s directive ordered school officials to retain a
    structural engineer to “evaluate the remaining structure of the vocational building to
    ensure that the structural integrity of the remaining building is in adequate condition and
    future collapses will not occur.” Plaintiff complied with the Fire Marshal’s directive, as
    it was required to do. Plaintiff’s engineer, Carl Taylor, determined that reinforcement of
    the walls in the non-collapsed parts of Building 8 was required in order to comply with
    the Fire Marshal’s directive. With respect to Buchanan, an experienced engineer, his
    opinion that the additional work was unnecessary does not negate that of the engineer of
    record retained by Plaintiff in accordance with the Fire Marshal’s directive to ensure the
    structural integrity of the remaining building. The Trial Court found Buchanan credible.
    While we afford great deference to a trial court’s credibility determinations, the
    credibility determination here is beside the point as it was not and is not relevant to the
    issue as stated by the Trial Court of “whether or not this claim can survive the language
    of the policy of insurance.” This language of the policy referred to by the Trial Court is
    the “ordinance or law” provision.
    As directed by the Fire Marshal, it was incumbent upon Plaintiff to retain an
    engineer and submit repair plans for official approval, which they did. Defendants have
    failed to identify how the Fire Marshal’s office exceeded its authority. We are not
    unmindful of Defendants’ concerns regarding the limits to their responsibility under the
    policy, which is not open-ended. However, we hold that it was the Fire Marshal’s
    authority under then existing Tennessee law to issue the directive it did. It was this
    directive that triggered the “ordinance or law” provision of the insurance policy.
    Building 8 was a covered property under the insurance policy. There was,
    indisputably, a covered cause of loss. The Fire Marshal’s directive carried the force of
    law and Plaintiff had to obey it if it wished to re-occupy Building 8. Mr. Pittman of the
    Tennessee State Fire Marshal’s Office issued a directive that required the Plaintiff to
    retain a structural engineer to “evaluate the remaining structure of the vocational building
    to ensure that the structural integrity of the remaining building is in adequate condition
    and future collapses will not occur.” Plaintiff was required to comply with this directive
    if it wished to occupy the building. Plaintiff, in compliance with the Fire Marshal’s
    directive, retained Carl Taylor as the engineer of record. It was Mr. Taylor’s
    determination, as the engineer of record retained pursuant to the State Fire Marshal’s
    -13-
    directive, that compliance with the Fire Marshal’s directive required the additional work
    in dispute. Plaintiff had no choice but to comply with the Fire Marshal’s directive if it
    wished to occupy the building. Plaintiff’s adherence to the Fire Marshal’s directive
    resulted in increased costs and, therefore, fell under the ambit of the replacement cost
    policy.
    We hold that, under the terms of the insurance policy and the evidence presented
    in this case, Defendants are responsible for covering the cost of the additional work
    necessary to comply with the Fire Marshal’s directive. We, therefore, reverse the
    judgment of the Trial Court. We remand this case for the Trial Court to determine the
    amount of the monetary judgment in favor of Plaintiff and to enter a judgment for that
    amount.
    Conclusion
    The judgment of the Trial Court is reversed, and this cause is remanded to the
    Trial Court for collection of the costs below and further proceedings consistent with this
    Opinion. The costs on appeal are assessed against the Appellees, Tennessee Risk
    Management Trust and the Travelers Indemnity Company.
    ____________________________________
    D. MICHAEL SWINEY, CHIEF JUDGE
    -14-