Aarene Contracting, LLC v. Krispy Kreme Doughnut ( 2016 )


Menu:
  •                IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    October 19, 2016 Session
    AARENE CONTRACTING, LLC v. KRISPY KREME DOUGHNUT
    CORPORATION
    Appeal from the Chancery Court for Hamilton County
    No. 15-0436      Pamela A Fleenor, Chancellor
    ___________________________________
    No. E2016-01155-COA-R3-CV-FILED-DECEMBER 20, 2016
    ___________________________________
    A contractor sued an owner for violations of the Prompt Pay Act, 
    Tenn. Code Ann. §§ 66-34-101
     et seq., and notified the owner of its violations by Federal Express and e-
    mail. The owner moved for summary judgment on the ground that the contractor failed
    to strictly comply with the notice provision requiring notice be sent by registered or
    certified mail, return receipt requested. The trial court found strict compliance was
    required and dismissed the contractor‟s claims under the Act. The contractor appealed,
    and we reverse the trial court‟s judgment, holding substantial compliance is sufficient
    under the facts of this case.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court
    Reversed and Remanded
    ANDY D. BENNETT, J., delivered the opinion of the court, in which D. MICHAEL SWINEY,
    C.J., and JOHN W. MCCLARTY, J., joined.
    David K. Taylor and Bridget Brodbeck Parkes, Nashville, Tennessee, for the appellant,
    Aarene Contracting, LLC.
    Christopher D. Owens, Johnson City, Tennessee, for the appellee, Krispy Kreme
    Doughnut Corporation.
    OPINION
    I. FACTUAL AND PROCEDURAL BACKGROUND
    This is a construction case in which Aarene Contracting, LLC (“ACL”)
    agreed to renovate a store for Krispy Kreme Doughnut Corporation (“KKD”) in
    Chattanooga, and KKD agreed to pay ACL $524,027 for the work. The contract
    was executed in November 2013 and provided for progress payments. Paragraph
    3.4 of the contract provided that KKD would pay ACL 90% of the amount owing
    for the work “completed and accepted by [KKD],” and the remaining 10% was to
    be withheld as “retainage.” ACL submitted two applications for payment, less
    retainage, in February and March 2018, which KKD approved and paid. The total
    retainage withheld by KKD was $49,283.16.
    On or about September 30, 2014, counsel for ACL sent a letter by way of
    Federal Express and e-mail to counsel for KKD regarding disagreements that had
    arisen between the parties up to that point, including claims ACL had against KKD
    under the Tennessee Prompt Pay Act of 1991, 
    Tenn. Code Ann. §§ 66-34-101
     et
    seq. (“Prompt Pay Act” or “the Act”). ACL‟s letter informed KKD of the
    following, inter alia:
    As you are aware, the Tennessee Prompt Pay Act of 1991 applies to all
    private contracts for construction performed in Tennessee. Additionally, the
    law applies to contracts where the base contract price exceeds $500,000,
    and it prohibited Krispy Kreme from withholding more than 5% in
    retainage. 
    Tenn. Code Ann. § 66-34-103
    (a). Krispy Kreme was also
    required to create a separate escrow account with a third party for retained
    amounts. 
    Tenn. Code Ann. § 66-34-104
    (a). At no time during the
    performance of this contract did Krispy Kreme comply with Tennessee law.
    The General Contract was in the original principal amount of $524,027.00,
    and Krispy Kreme has unlawfully withheld amounts in excess of 5%.
    Additionally, it does not appear that Krispy Kreme utilized a third party
    escrow account as necessary. Further, under Tennessee law, Krispy Kreme
    was required to pay the retained amounts within ninety (90) days after
    substantial completion of the work. In our case, the work was substantially
    completed in May 2014 as Krispy Kreme has had full use of the
    improvements since that time. Therefore, the retainage is long past due.
    The statute also provides that there is a $400.00 penalty per day for each
    and every day that the retained funds are not deposited into a third-party
    escrow account. As the first payment [was] received by my client for
    which funds were retained on March 31, 2014, . . . this penalty accrues
    from March 31, 2014. Through the date of this letter Krispy Kreme
    currently owes the sum of $73,200.00 in additional penalties, plus interest.
    As you know, Krispy Kreme has had use of the premises since the work
    was completed in May 2014. It has now been over one hundred twenty
    -2-
    (120) days since the work was substantially completed. Unless the sum of
    $262,024.63 is paid immediately and no later than ten (10) days of the date
    hereof, then Aarene shall proceed with all of its legal and equitable
    remedies, and will also seek to recover interest on all sums due, and its
    attorney‟s fees and all court costs and litigation expenses.
    KKD responded to ACL by letter dated October 8, 2014, and addressed each of
    the issues ACL raised in its letter. With respect to ACL‟s claim under the Prompt Pay
    Act, KKD disagreed with ACL‟s interpretation and application of the statute. Then, by
    letter dated October 13, 2014, ACL replied to KKD‟s response. With regard to its
    complaint under the Prompt Pay Act, ACL wrote: “Keep in mind that the retainage
    penalty is accumulating every single day of the Owner‟s violation of Tennessee law.”
    II. TRIAL COURT PROCEEDINGS
    On August 4, 2015, ACL filed a sworn complaint against KKD in Hamilton
    County Chancery Court. In addition to breach of contract and mechanic‟s lien claims,
    ACL asserted claims under the Prompt Pay Act: it claimed KKD had violated the
    retainage laws by (1) withholding 10% as retainage rather than the 5% permitted under
    Tennessee law and (2) failing to create or fund an interest-bearing escrow account to hold
    the retainage as required by the Act. KKD answered the complaint, and in response to
    the retainage claims, KKD asserted that ACL had failed to comply with the statutory
    notice requirements because ACL did not notify KKD of its Prompt Pay Act claims by
    registered or certified mail, return receipt requested.
    KKD filed a motion for summary judgment in August 2015 in which it argued
    ACL‟s claims under the Act were barred and should be dismissed because ACL failed to
    comply with the notice requirements of the statute. ACL responded to KKD‟s motion
    and filed its own motion for summary judgment in October 2015. The trial court heard
    oral argument and issued an order in January 2016 granting KKD‟s motion and denying
    ACL‟s motion. The trial court wrote:
    The Court finds that the Plaintiff has not given notice of its intent to
    seek relief under the Prompt Pay Act by registered or certified mail return
    receipt requested, but instead gave notice to the Defendant by Federal
    Express and by e-mail.
    ....
    As to the legal analysis, Plaintiff filed this action, inter alia, for a
    violation of the Prompt Pay Act. Defendant argues that Plaintiff failed to
    comply with the notice provisions of the statute, and as such, is precluded
    from seeking remedies under the Act.
    -3-
    The Court finds that Tennessee Code Annotated § 66-34-602(a)(1)
    provides that a contractor who has not received payment from an owner or
    a subcontractor, materialman, or furnisher who has not received payment
    from a contractor or other subcontractor, materialman, or furnisher in
    accordance with this chapter, shall notify the party failing to make payment
    of the provisions of this chapter and of the notifying party‟s intent to seek
    relief provided for within this chapter.
    Then, in subsection 2: The notification shall be made by registered
    or certified mail return receipt requested. It is undisputed that Plaintiff
    failed to send the notification by registered or certified mail return receipt
    requested. Instead, Plaintiff notified Defendant by Federal Express and e-
    mail.
    ....
    . . . This Court is not going to legislate from the bench by expanding this
    notice statute. This is a statutory remedy in derogation of common law.
    The Court finds that to seek the remedies under this statute, which are
    additional remedies to any contract remedies, the party must follow the
    notice provisions.
    ACL filed a motion seeking permission to file an interlocutory appeal pursuant to
    Tenn. R. Civ. P. 9, which the trial court granted. Ultimately, however, ACL filed a notice
    of voluntary nonsuit of its breach of contract and mechanic‟s lien claims pursuant to
    Tenn. R. Civ. P. 41.01(3). Then, following the trial court‟s order dismissing those claims
    without prejudice, ACL filed a notice of appeal. On appeal, ACL argues the trial court
    erred by granting KKD‟s motion for summary judgment and for denying its competing
    motion for summary judgment.
    III. ANALYSIS
    A party filing a motion for summary judgment should prevail “if the pleadings,
    depositions, answers to interrogatories, and admissions on file, together with the
    affidavits, if any, show that there is no genuine issue as to any material fact and that the
    moving party is entitled to a judgment as a matter of law.” TENN. R. CIV. P. 56.04. If the
    moving party does not bear the burden of proof at trial, it is entitled to summary
    judgment if it “(1) [s]ubmits affirmative evidence that negates an essential element of the
    nonmoving party‟s claim; or (2) [d]emonstrates to the court that the nonmoving party‟s
    evidence is insufficient to establish an essential element of the nonmoving party‟s claim.”
    
    Tenn. Code Ann. § 20-16-101
    . We review the trial court‟s judgment granting KKD‟s
    motion for summary judgment de novo, according it no presumption of correctness. See
    -4-
    Rye v. Women’s Care Ctr. of Memphis, MPLLC, 
    477 S.W.3d 235
    , 250 (Tenn. 2015);
    Martin v. Norfolk S. Ry. Co., 
    271 S.W.3d 76
    , 84 (Tenn. 2008).
    This case turns on the interpretation and application of the notice provision of the
    Prompt Pay Act, 
    Tenn. Code Ann. §§ 66-34-101
     et seq. The construction of a statute is
    an issue of law, which is reviewed de novo, with no presumption of correctness applied
    to the trial court‟s rulings. Hayes v. Gibson Cnty., 
    288 S.W.3d 334
    , 337 (Tenn. 2009);
    Carter v. Bell, 
    279 S.W.3d 560
    , 564 (Tenn. 2009); State v. Edmondson, 
    231 S.W.3d 925
    ,
    927 (Tenn. 2007). „“The most basic principle of statutory construction is to ascertain and
    give effect to the legislative intent without unduly restricting or expanding a statute‟s
    coverage beyond its intended scope.‟” State v. Howard, __ S.W.3d __, 
    2016 WL 5933430
    , at *5 (Tenn. Oct. 12, 2016) (quoting Owens v. State, 
    908 S.W.2d 923
    , 926
    (Tenn. 1995)). Courts interpret statutes to avoid reaching absurd results. The Tennessean
    v. Metro. Gov’t of Nashville & Davidson Cnty., 
    485 S.W.3d 857
    , 872 (Tenn. 2016).
    The notice provision is found in Part 6 of the Act, which is titled “Remedies for
    Delinquent Payment or Nonpayment.” 
    Tenn. Code Ann. §§ 66-34-601
    ‒602. The section
    containing the notice provision is called “Remedies for Delinquent Payment or
    Nonpayment” and provides as follows:
    (a)(1) A contractor who has not received payment from an owner, or a
    subcontractor, materialman or furnisher who has not received payment
    from a contractor or other subcontractor, materialman or furnisher, in
    accordance with this chapter, shall notify the party failing to make payment
    of the provisions of this chapter and of the notifying party‟s intent to seek
    relief provided for within this chapter.
    (2) The notification shall be made by registered or certified mail,
    return receipt requested.
    (3) If the notified party does not, within ten (10) calendar days after receipt
    of such notice, make payment or provide to the notifying party a response
    giving adequate legal reasons for failure of the notified party to make
    payment, the notifying party may, in addition to all other remedies
    available at law or in equity, sue for equitable relief, including injunctive
    relief, for continuing violations of this chapter, in the chancery court of the
    county in which the real property is located.
    (4) The failure to make the only payment due under the contract may be
    considered to be a continuing violation under this chapter.
    (b) Reasonable attorney‟s fees may be awarded against the nonprevailing
    party; provided, that such nonprevailing party has acted in bad faith.
    -5-
    (c) A bond in double the amount claimed or ordered to be paid shall be
    filed with good sureties to be approved by the clerk prior to the issuance of
    any injunctive relief.
    
    Tenn. Code Ann. § 66-34-602
     (emphasis added).
    The parties agree that there are no genuine issues of material fact with respect to
    the issue of notice. There is no dispute that ACL notified KKD of the Act‟s provisions
    and of its intent to seek relief under the statute, and that its notification was sent by letter,
    via Federal Express and e-mail. KKD responded to ACL‟s notice letter within ten days,
    and when the parties were unable to reach a satisfactory resolution of ACL‟s claims,
    ACL filed its complaint several months later.
    ACL makes two arguments on appeal. First, ACL argues the trial court erred by
    applying the notice provision to its retainage claims because ACL‟s claims under the Act
    are not based on a “payment” KKD owes it, as that term is used in 
    Tenn. Code Ann. § 66
    -
    34-602(a)(1). Instead, ACL argues, its claims are based on KKD‟s failure to comply with
    the retainage laws that are set forth in Part 1 of the Act, titled “General Provisions,” that
    set forth the percentage that can legally be retained and mandate the establishment of an
    escrow account to hold the retainage.1 Part 1 also provides the parameters for the escrow
    account that must be established to hold the retainage.2 ACL points out that the notice
    1
    Part I of the Prompt Pay Act includes the following relevant provisions:
    (a) All construction contracts on any project in this state, both public and private, may
    provide for the withholding of retainage; provided, however, that the retainage amount
    may not exceed five percent (5%) of the amount of the contract.
    ....
    (e)(1) It is an offense for a person, firm or corporation to fail to comply with subsection
    (a) or (b) or § 66-34-104(a).
    (2)(A) A violation of this subsection (e) is a Class A misdemeanor, subject to a fine only
    of three thousand dollars ($3,000).
    (B) Each day a person, firm or corporation fails to comply with subsection (a) or (b) or
    § 66-34-104(a) is a separate violation of this subsection (e).
    (C) Until the violation of this subsection (e) is remediated by compliance, the
    punishment for each violation shall be consecutive to all other such violations.
    (3) In addition to the fine imposed pursuant to subdivisions (e)(2)(A) and (B), the court
    shall order restitution be made to the owner of the retained funds. In determining the
    appropriate amount of restitution, the formula stated in § 40-35-304 shall be used.
    
    Tenn. Code Ann. § 66-34-103
    .
    2
    Tennessee Code Annotated section 66-34-104 provides, in pertinent part:
    (a) Whenever, in any contract for the improvement of real property, a certain amount or
    -6-
    provision appears in Part 6 of the Act, which is titled “Remedies for Delinquent Payment
    or Nonpayment,” and contends that it is not seeking payment of the amount KKD
    retained pursuant to the Act. Rather, ACL explains, it is seeking payment from KKD
    through its breach of contract claim. Second, ACL contends that if the trial court was
    correct in applying the notice requirement to its retainage claims, ACL substantially
    complied with the notice provision and the trial court erred in dismissing its claims under
    the Act.
    We will address ACL‟s second argument first. ACL asserts that strict compliance
    should not be required in this case because KKD does not deny receiving its notice
    letters; KKD responded to the first letter and denied any retainage law violations; and
    KKD is unable to show it was prejudiced by the method ACL selected to serve it with
    notice of ACL‟s claims under the Prompt Pay Act. ACL relies on two Tennessee
    Supreme Court cases in support of its position, Arden v. Kozawa, 
    466 S.W.3d 758
     (Tenn.
    2015), and Thurmond v. Mid-Cumberland Infectious Disease Consultants, PLC, 
    433 S.W.3d 512
     (Tenn. 2014). Both of these cases arose in the medical malpractice context.
    In Arden, the issue was whether a medical malpractice claim was subject to dismissal
    because the plaintiff notified the defendants of his claim via Federal Express rather than
    by certified mail, return receipt requested, as the statute required. Arden, 
    466 S.W.3d at 760
    . As was the case here, the defendants in Arden did not contend they failed to receive
    notice or that they were prejudiced by the plaintiff‟s method of service, but they moved
    for summary judgment on the basis that the plaintiff failed to comply strictly with the
    percentage of the contract price is retained, that retained amount shall be deposited in a
    separate, interest-bearing, escrow account with a third party which must be established
    upon the withholding of any retainage.
    (b) As of the time of the withholding of the retained funds, the funds shall become the
    sole and separate property of the prime contractor or remote contractor to whom they are
    owed, subject to the rights of the person withholding the retainage in the event the prime
    contractor or remote contractor otherwise entitled to the funds defaults on or does not
    complete its contract.
    (c) In the event that the party withholding the retained funds fails to deposit the funds into
    an escrow account as provided herein, such party shall be responsible for paying the
    owner of the retained funds an additional three hundred dollar ($300) penalty per day for
    each and every day that such retained funds are not deposited into such escrow account.
    (d) The party with the responsibility for depositing the retained amount in a separate,
    interest-bearing, escrow account with a third party shall have the affirmative duty to
    provide written notice that it has complied with the requirements of this section to any
    prime contractor upon withholding the amount of retained funds from each and every
    application for payment, including:
    (1) Identification of the name of the financial institution with whom the escrow account
    has been established;
    (2) Account number; and
    (3) Amount of retained funds that are deposited in the escrow account with the third
    party.
    -7-
    notice requirement as set forth in the statute. 
    Id.
     The trial court in Arden granted the
    defendants summary judgment because it found the statute required strict compliance
    with the service requirements, and the Court of Appeals affirmed the trial court‟s
    judgment. 
    Id. at 760-61
    . The Supreme Court disagreed that strict compliance was
    required, however, and reversed the Court of Appeals decision. 
    Id. at 761
    .
    The statute at issue in Arden provided that service “shall be demonstrated by filing
    a certificate of mailing from the United States postal service” together with an affidavit of
    the person mailing the notice “establishing that the specified notice was timely mailed by
    certified mail, return receipt requested.” 
    Tenn. Code Ann. § 29-26-121
    (a)(4); see Arden,
    
    466 S.W.3d at 762-63
    . Despite the language used in the statute, the Supreme Court held
    that “the manner and proof of service requirements of [the statute] are not mandatory, but
    directory, and can be achieved through substantial compliance.” Arden, 
    466 S.W.3d at 764
    . The Court explained:
    So long as a health care defendant is not prejudiced by a plaintiff‟s
    deviations from the statutorily prescribed method of service—“certified
    mail, return receipt requested”—or the proof of service requirement—
    “filing a certificate of mailing from the United States [P]ostal [S]ervice”—
    substantial compliance with these statutory requirements will suffice. See
    Thurmond [v. Mid-Cumberland Infectious Disease Consultants, PLC], 433
    S.W.3d [512,] 518 [(Tenn. 2014)]; Stevens [ex. rel. Stevens v. Hickman
    Comm. Health Care Servs., Inc.], 418 S.W.3d [547,] 555 [(Tenn. 2013)];
    see also Henry v. Goins, 
    104 S.W.3d 475
    , 481 (Tenn. 2003) (recognizing
    the state public policy of deciding cases on their merits as opposed to
    dismissing on procedural technicalities).
    Arden, 
    466 S.W.3d at 764
    . The Arden Court continued:
    Further, we hold that delivery of pre-suit notice by private commercial
    carrier, such as FedEx, and filing of proof with the complaint constitutes
    substantial compliance with sections 29-26-121(a)(3)(B) and (a)(4) of the
    pre-suit notice statute. As long as a defendant is not prejudiced, it does not
    matter whether a commercial carrier or the U.S. Postal Service delivers the
    notice. The overarching purpose of the pre-suit notice statute is to ensure
    that health care defendants receive timely notice of a forthcoming lawsuit.
    While the method of delivery could constitute deficient service of pre-suit
    notice if a health care defendant claims lack of notice or prejudice, that is
    not the case before us.
    
    Id.
    In Thurmond, the Supreme Court determined that substantial compliance satisfied
    -8-
    the statutory requirement that an affidavit by the person who sends pre-suit notice by
    certified mail be attached to the complaint in medical malpractice cases. Thurmond, 433
    S.W.3d. at 513. In that case, the plaintiff failed to attach the affidavit to the complaint
    but filed it with the court five days later. Id. at 521. After reviewing other medical
    malpractice cases in which defendants argued strict compliance with notice provisions or
    particular forms was required, the Court wrote that “unless strict compliance with a
    notice content requirement „is essential to avoid prejudicing an opposing litigant,‟
    substantial compliance with a content requirement will suffice.” Id. at 520 (quoting
    Stevens, 418 S.W.3d at 555). Because the defendants did not allege they suffered any
    prejudice from the plaintiff‟s failure to file the affidavit with the complaint, the Court
    held that substantial compliance with the statutory affidavit requirement was sufficient.
    Id. at 521.
    In the workers‟ compensation context, the Supreme Court has held that strict
    compliance was not required for a subcontractor to recover workers‟ compensation
    benefits under a general contractor‟s insurance policy when neither the general contractor
    nor the subcontractor provided notice to the Department of Labor of the subcontractor‟s
    election to be so covered, as required by the statute at issue. Presley v. Bennett, 
    860 S.W.2d 857
    , 860 (Tenn. 1993). Concluding that the notice requirement was directory
    rather than mandatory, the Court wrote:
    In general, when determining whether a procedural requirement of a statute
    is directory or mandatory, the object is to ascertain the legislative intent by
    consideration of the entire statute, including its nature and purpose, and the
    consequences that would result from a construction one way or the other.
    Directory provisions require only substantial compliance. Statutory
    provisions relating to the mode or time of doing an act to which the statute
    applies are ordinarily held to be directory rather than mandatory.
    
    Id.
     (citations omitted); see also Thurmond, 433 S.W.3d at 520 (citing Presley with
    approval).
    KKD relies on Vulcan Materials Company v. Gamble Construction Company,
    Inc., 
    56 S.W.3d 571
     (Tenn. Ct. App. 2001), to support its position that the notice
    provision in the Prompt Pay Act requires strict compliance. The action in Vulcan
    Materials was to enforce a materialman‟s lien. Vulcan Materials Co., 
    56 S.W.3d at 572
    .
    The statute at issue required notice of nonpayment for work, services, or materials to be
    provided to the owner and contractor and provided that the notice “shall be served by
    registered or certified mail, return receipt requested.” 
    Id. at 573
     (quoting 
    Tenn. Code Ann. § 66-11-145
    (a)). The plaintiff in Vulcan Materials was a manufacturer and seller of
    materials and delivered its notice of nonpayment to the owner by hand rather than by
    registered or certified mail, return receipt requested. 
    Id. at 572
    . The defendant moved
    for summary judgment and sought dismissal of the complaint due to improper service of
    -9-
    the notice, which the trial court granted. 
    Id.
     Relying on a Supreme Court case from
    1931, the Court of Appeals affirmed, noting that a materialman‟s lien is a creature of
    statute and stating that „“when the lawmaking body prescribes the terms upon which it
    may be asserted, it is beyond the power of [courts] to waive its provisions or substitute
    others.”‟ 
    Id. at 573-74
     (quoting McDonnell v. Amo, 
    34 S.W.2d 212
    , 213 (Tenn. 1931)).
    The Court of Appeals further wrote that “[a]s an intermediate appellate court, it is not our
    prerogative to set policy or substitute our judgment for that of the legislative branch.” 
    Id.
    at 575 (citing Cavender v. Hewitt, 
    239 S.W. 767
    , 768 (Tenn. 1922)).
    The Supreme Court‟s decision in Arden reflects a more practical way of
    examining such issues. While it is tempting to merely write that the statute says what it
    says and to blame the legislature for the result, the Supreme Court has implicitly
    recognized that the courts would be abandoning their constitutional role of interpreting
    statutes using reason and practicality with the intent of the legislature in mind. “An old
    and familiar rule in the exposition of statutes is that the reason and intention of the law,
    when obvious, will prevail over the literal sense of the words.” Sands v. Brock Candy
    Co., 
    101 S.W.2d 1113
    , 1117 (Tenn. 1937); see also Heirs of Ellis v. Estate of Ellis, 
    71 S.W.3d 705
    , 712 (Tenn. 2002) (“the polestar of statutory interpretation has always been
    the intent of the legislature. As such, where the „carrying out of the legislative intention,
    which is the prime and sole object of all rules of construction, can only be accomplished
    by departure from the literal interpretation of the language employed,‟ then the legislative
    intent should be applied over „the literal import of the words.‟”) (quoting Tenn. Title Co.
    v. First Fed. Sav. & Loan Ass’n, 
    203 S.W.2d 697
    , 700 (Tenn. 1947)); Polk Cnty. v. State
    Bd. of Equalization, 
    484 S.W.2d 49
    , 58-59 (Tenn. Ct. App. 1972) (“a reviewing court
    will look to the legislative purpose of a statute and follow that purpose even though a
    literal reading of the language would suggest a different conclusion.”).
    We note that the court in Vulcan Materials did not address whether the defendant
    suffered any prejudice as a result of the method the plaintiff chose to serve its notice. To
    the extent the Court of Appeals‟ ruling in Vulcan Materials is inconsistent with the
    Supreme Court‟s rulings in Arden and Thurmond, we find the Supreme Court‟s rulings
    announce the principles that control the outcome of this case. The intent of 
    Tenn. Code Ann. § 66-34-602
    (a)(2) is to ensure that the party failing to make payment is notified of
    the Prompt Pay Act and of the notifying party‟s intent to seek relief provided for by the
    Act. A method of notification that accomplishes this intent without prejudice to the party
    being notified is sufficient. The language of the statute as to the method is merely
    directory.
    We also note KKD‟s argument that the Prompt Pay Act is a penal statute because
    it provides for the assessment of penalties if its terms are violated and that penal statutes
    are to be strictly construed. See 
    Tenn. Code Ann. § 66-34-104
    (c) (providing that if party
    withholding retained funds fails to deposit funds into escrow account, party shall pay
    owner of funds $300 penalty per day until funds are so deposited). However, in Beacon4,
    - 10 -
    LLC v. I & L Investments, LLC, No. E2015-01298-COA-R3-CV, 
    2016 WL 4545736
    (Tenn. Ct. App. Aug. 30, 2016), the Court of Appeals determined that the Prompt Pay
    Act has “remedial aims.” Beacon4, 
    2016 WL 4545736
    , at *46. The court noted that
    remedial statutes include those that provide „“means or method[s] whereby causes of
    action may be effectuated, wrongs redressed and relief obtained.‟” 
    Id.
     (quoting Nutt v.
    Champion Int’l Corp., 
    980 S.W.2d 365
    , 368 (Tenn. 1998)). The court wrote:
    We determine the [Prompt Pay Act] in general to have remedial aims in
    that it operates to effectuate the means by which those it was designed to
    protect may recover their already existing property and contractual rights in
    funds they have earned. Legitimate business enterprises and consumers as a
    whole are then protected from the consequences of contractors,
    subcontractors, materialmen, furnishers, architects, and engineers receiving
    less than they have bargained for and earned.
    
    Id.
     (footnote omitted).
    The Prompt Pay Act was enacted „“to provide for timely payments to contractors,
    subcontractors, materialmen, furnishers, architects, and engineers and to provide for
    interest on late payments.”‟ 
    Id.
     (quoting 1991 TENN. PUB. ACTS CH. 45 (H.B. 875)). As
    the contractor for the KKD project, ACL is an intended beneficiary of the Act. For the
    reasons the Supreme Court set forth in Arden, Thurmond, and Presley, we hold that the
    mode of pre-suit notice set forth in 
    Tenn. Code Ann. § 66-34-602
    (a)(2) is directory rather
    than mandatory and requires only substantial compliance. Because ACL provided KKD
    with the information it was required to provide under the statute before it filed suit, and
    because KKD was not prejudiced by the method ACL used to provide notice, we
    conclude ACL substantially complied with the statute and that the trial court erred in
    granting KKD‟s motion for summary judgment and dismissing ACL‟s claims under the
    Act. In light of our holding that ACL has substantially complied with the Act‟s notice
    requirement, we need not address ACL‟s alternative argument that the notice provision
    does not apply to its retainage claims under the Prompt Pay Act.
    In its motion for summary judgment, ACL sought a ruling that KKD violated the
    retainage laws; a monetary judgment in the amount of $180,000; a statutory award of
    $300 for each day that KKD failed to deposit the retainage into an interest bearing escrow
    account; and its reasonable attorney‟s fees. On appeal, ACL requests that we grant it the
    relief it sought in its motion for summary judgment. The trial court did not address
    ACL‟s requests for relief once it determined that ACL had not complied with the notice
    requirements of the Prompt Pay Act, and it is not appropriate for this Court to address
    these issues before the trial court has an opportunity to do so. Therefore, we remand this
    case to the trial court with instructions that the trial court address ACL‟s motion for
    summary judgment to determine the relief, if any, that ACL should be awarded.
    - 11 -
    IV. CONCLUSION
    For the reasons stated above, we reverse the trial court‟s award of summary
    judgment to KKD and remand the case for further proceedings. Costs of this appeal shall
    be taxed to the appellee, Krispy Kreme Doughnut Corporation.
    _________________________
    ANDY D. BENNETT, JUDGE
    - 12 -