Rose Mary Thompson v. Robert Boyd ( 2019 )


Menu:
  •                                                                                        04/09/2019
    IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    Assigned on Briefs March 1, 2019
    ROSE MARY THOMPSON V. ROBERT BOYD
    Appeal from the Circuit Court for Knox County
    No. 1-378-17     Kristi M. Davis, Judge
    No. E2018-01098-COA-R3-CV
    A homeowner and a contractor entered into a contract requiring the contractor to repair
    damage to the homeowner’s house caused by a kitchen fire. The repairs to be performed
    were those covered by the homeowner’s insurance policy as outlined in a detailed
    estimate of repair work. After the contractor abandoned the project, the homeowner
    hired another contractor to complete the work and sued the original contractor for breach
    of contract. We affirm the decision of the trial court to the extent of the court’s
    determination that the contractor breached the contract by his undue delay and poor
    workmanship. We have concluded, however, that the trial court’s decision fails to
    adequately explain the award of damages or to dispose of the contractor’s counterclaim.
    Therefore, we vacate the damages award and remand for more specific findings regarding
    the basis for the damages award and a disposition of the counterclaim.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Affirmed in
    Part, Vacated in Part, and Remanded
    ANDY D. BENNETT, J., delivered the opinion of the Court, in which D. MICHAEL SWINEY,
    C.J., and JOHN W. MCCLARTY, J., joined.
    Robert Boyd, Knoxville, Tennessee, pro se.
    Barbara W. Clark, Knoxville, Tennessee, for the appellee, Rose Mary Thompson.
    MEMORANDUM OPINION1
    FACTUAL AND PROCEDURAL BACKGROUND
    A kitchen fire on June 5, 2015, caused damage to Rose Mary Thompson’s home
    on Spring Place Circle in Knoxville. Ms. Thompson’s insurance company determined
    that she was entitled to $80,063.552 for the repairs. On October 27, 2015, Ms. Thompson
    entered into a contract with Robert Boyd to perform the repairs.
    On October 13, 2017, Ms. Thompson filed a complaint for breach of contract
    against Mr. Boyd. The complaint includes the following pertinent allegations:
    8. The Defendant commenced work shortly after the contract was signed
    by the Plaintiff on October 27, 2015, and received his first payment draft on
    November 18, 2015, in the amount of $40,000.00. The Defendant received
    subsequent payments in the amount of $13,620.30.
    9. Throughout the course of the repair project, the Defendant would fail to
    show up on numerous occasion[s] causing unnecessary delays, and more
    than 50% of the repair work remains unfinished.
    ....
    11. The work the Defendant did perform was substandard, causing the
    Plaintiff to seek the service of other contractors to make corrections to his
    poor quality workmanship.
    ....
    12. The contract for restoration of Plaintiff’s residence required the
    Defendant to restore the residence pursuant to the contract signed by the
    parties on October 27, 2015. The Defendant did not complete work
    pursuant to the contract, in a timely workmanlike manner.
    13. The failure of the Defendant to complete the restoration work
    constitutes a breach of contract.
    Mr. Boyd answered the complaint, denying the allegations and stating his version of
    events. He also asserted a counterclaim.
    1
    Rule 10 of the Rules of the Court of Appeals of Tennessee provides:
    This Court, with the concurrence of all judges participating in the case, may affirm,
    reverse or modify the actions of the trial court by memorandum opinion when a formal
    opinion would have no precedential value. When a case is decided by memorandum
    opinion it shall be designated “MEMORANDUM OPINION,” shall not be published, and
    shall not be cited or relied on for any reason in any unrelated case.
    2
    This figure includes an actual cash value of $67,232.71 and a replacement cash value of $12,830.84.
    -2-
    According to Mr. Boyd’s counterclaim, the parties had a meeting on June 25,
    2017. At that meeting, Ms. Thompson gave Mr. Boyd a deadline of July 31, 2017, to
    complete the work, and he told her that he would be focusing on the insurance claims,
    and not on any additional projects she wanted to be done. The counterclaim further
    alleges:
    12. The Defendant notified Wells Fargo Bank [Ms. Thompson’s mortgage
    company] to set up an inspection and updated the progress of work.
    13. July 5, 2017 the Plaintiff locked the Defendant out of the property 5601
    Springplace Circle Knoxville, TN.
    14. The Plaintiff stated to the Defendant that his service was no longer
    needed.
    15. The Defendant spoke to the Plaintiff about retrieving his tools and
    building materials from her property. Also to set up a time for the Wells
    Fargo Bank inspector.
    16. The Plaintiff refused the Defendant[’s] requests.
    17. The Defendant immediately contacted Well[s] Fargo Bank[ ]
    (mortgage lender) and Capstone ISG [insurance adjuster] to inform them of
    the situation therefore avoiding any confrontation with the Plaintiff.
    18. Wells Fargo Bank informed the Defendant that all funds are [frozen] at
    this time. The Plaintiff and Defendant would have to come up with a
    mutual agreement before the contract can be closed.
    19. Plaintiff refused the Defendant[’s] requests; therefore the Defendant
    was forced to take legal action. . . .
    Mr. Boyd asserted that the work was 75% complete when he received his second
    payment from the bank and that Ms. Thompson was responsible for change orders and
    additional work not included on the insurance repair sheets. He requested the following
    relief:
    10. The Plaintiff owes the Defendant $5,000.00.
    11. Defendant has the 3rd draw left to be issue[d] to him for the amount
    [of] $13,612.41 from Wells Fargo Bank. The Defendant would have
    received the full amount if he had completed the remaining work.
    12. Tools, Materials and Supplies Plaintiff refused to return to Defendant
    [in the] amount of $6,700.00.
    13. For actual damages in [the] amount of $25,312.41.
    14. Punitive Damages of $50,000.00.
    15. [Breach] of contract in the amount of $25,500.00.
    16. Defamation of character in [the] amount of $50,500.00.
    The case went to trial on June 11, 2018. The record does not include a transcript
    of the hearing, but it does include a statement of the evidence describing the testimony
    -3-
    presented at trial. The trial court adopted Ms. Thompson’s statement of the evidence as
    the “fair, accurate, and complete account of what transpired at trial.” According to the
    statement of the evidence, the trial court heard the following:
    Testimony of Rose Mary Thompson
    The Plaintiff, Rose Mary Thompson, testified that on or about June
    5, 2015, she sustained damage to her home at 5601 Spring Place Circle,
    Knoxville, TN 37924 because of a kitchen fire. The loss was timely
    reported to the Plaintiff’s homeowner’s insurance and Capstone ISG, an
    independent adjusting company, compiled a computer report for repairs to
    be made at a total cost of depreciation of $80,321.12, exclusive of
    depreciation of $19,625.00 and the $2,500.00 deductible. A copy of the
    report was admitted as an exhibit to Plaintiff/Appellee’s testimony.
    The Plaintiff/Appellee entered into a contract with the
    Defendant/Appellant, Robert Boyd, on October 27, 2015, to complete the
    repairs on her home. Numerous delays caused by the Defendant/Appellant
    occurred and in July 2017, the parties’ relationship totally broke down and
    Ms. Thompson told Mr. Boyd to stay away from her residence, and
    solicited the services of another renovation contractor, Mr. Clayton
    Johnson, to finish the job Mr. Boyd started in October 2015.
    Wells Fargo, Plaintiff/Appellee’s Mortgage Company was
    responsible for disbursing the funds to Mr. Boyd after an inspection was
    performed. On April 30, 2016, Wells Fargo performed an inspection of the
    work[ ] performed by Mr. Boyd and found that he had completed 75% of
    the repairs. No other inspections were performed. Much of the work
    performed by Mr. Boyd was not performed in a workmanlike manner.
    For the work performed by Mr. Boyd, he was paid $53,620.30. The
    parties agreed to minor changes during the restoration period which the
    Court considered in the final judgment.
    The testimony was undisputed that Mr. Boyd never completed the
    work he was contracted to perform.
    Testimony of Clayton Johnson
    Mr. Clayton Johnson, a renovation contractor, inspected the
    unfinished work and provided a report and took numerous photographs
    outlining the deficiencies in the work performed by Mr. Boyd. He testified
    in details of all items outlined in his report made as an Exhibit to his
    -4-
    testimony regarding the defective workmanship of Mr. Boyd in making the
    repairs to Ms. Thompson’s home. Mr. Johnson testified that the cost to
    complete the job and correct the defective workmanship is $34,342.00.
    Testimony of Clifford Foster, Sr.
    Mr. Clifford Foster was called as a witness by the
    Defendant/Appellant. He testified that he was a maintenance person who
    assisted the Defendant/Appellant in moving things out of the way, and did
    some of the painting during the repair project. He testified that several
    bundles of [insulation] was never installed, but stored in the basement. The
    project was started in October 2015, and was still not completed in July of
    2017.
    Testimony of Robert Boyd
    Mr. Robert Boyd testified to the agreement he had with Ms.
    Thompson to make the repairs for her fire damage. He admitted that the
    contract was signed in October 2015, and as of July 2017, he had not
    completed the project. Mr. Boyd testified that the parties made some
    changes to the repair order as the job progressed. Mr. Boyd’s delay was
    because he moved his family to Georgia and took several months to
    renovate a place in Georgia for his family. Mr. Boyd testified that there
    were several things not completed because of his delay in completing the
    job. In July 2017, Ms. Thompson told him to stay away, that she would
    have someone else to complete the work and fix the items he had repaired
    poorly.
    Testimony of Montecia Boyd
    The Defendant/Appellant’s wife testified that she was there when
    her husband guttered [sic] Ms. Thompson’s house to make the repairs in
    2015 and that she moved to the State of Georgia in 2016 and her husband
    was in Georgia for several months renovating a home for the family. She
    testified that prior to her moving, Mr. Boyd would work at the Plaintiff’s
    house overnight until early morning.
    After the trial, the court entered an order on June 20, 2018, including the following
    relevant findings of fact:
    4. The Defendant commenced work on the residence and because of
    numerous delays on the part of the Defendant, the work was never
    completed.
    -5-
    5. On or about July 6, 2017, the Plaintiff terminated the Defendant’s
    services and solicited the services of another renovation and repair service
    [owned] by Clayton Johnson to provide an estimate of the remaining work
    to complete the repairs on Plaintiff’s residence.
    6. Clayton Johnson provided to Plaintiff a detailed estimate and
    report of the remaining work. Further, Mr. Johnson provided testimony at
    trial regarding his report and the Court finds that some of the work
    performed by the Defendant, Robert Boyd, was not performed in a
    workmanlike manner, and the Defendant failed to perform some of the
    repairs.
    7. The Court finds that the Defendant was paid a total of $53,620.30
    for the work he performed.
    8. The estimate provided by Clayton Johnson to complete the
    repairs on Plaintiff’s home, including remediation of work previously done
    by the defendant in an unworkmanlike manner, is $34,342.06. The
    estimate, however, includes the installation of an HVAC system at a cost of
    $5,779.00. Replacement of the HVAC system was not included in the
    estimate provided by Capstone and the Court finds that the estimate
    provided by Clayton Johnson must be reduced by the amount of $5,779.00.
    9. The Court further finds that the parties entered into change order
    agreements for some of the repairs with costs of the change orders to be
    paid by the Plaintiff. The Court finds that the sum of $2,500.00 shall be
    deducted from the Johnson estimate for the change orders.
    The trial court awarded Ms. Thompson a judgment against Mr. Boyd in the amount of
    $26,063.06 and ordered Mr. Boyd to “retrieve his tools from the Plaintiff’s residence with
    arrangement[s] to be coordinated through Plaintiff’s counsel.”
    On appeal, Mr. Boyd raises twelve issues. We consolidate and restate the issues
    as follows: (1) Whether the trial court erred in finding that Mr. Boyd breached the
    contract with Ms. Thompson; (2) whether the trial court erred in awarding damages to
    Ms. Thompson; and (3) whether the trial court erred in failing to award any damages to
    Mr. Boyd on his counterclaim.3
    3
    We have concluded that Mr. Boyd waived any of the issues not included in this restatement of the
    issues. For example, he asserts an issue regarding whether the trial court erred in granting damages to
    Ms. Thompson because her actions demonstrated bad faith, yet the argument section of his brief does not
    discuss the issue of bad faith. Tennessee Rule of Appellate Procedure 27(a)(7)(A) requires that an
    appellant’s argument set forth “the contentions of the appellant with respect to the issues presented, and
    the reasons therefor, including the reasons why the contentions require appellate relief, with citations to
    the authorities and appropriate references to the record (which may be quoted verbatim) relied on.” When
    a party fails to make an argument regarding an issue, we consider that issue waived. Bean v. Bean, 
    40 S.W.3d 52
    , 55 (Tenn. Ct. App. 2000).
    -6-
    STANDARD OF REVIEW
    With a bench trial, our review is de novo upon the record, accompanied by a
    presumption of correctness of the trial court’s findings of fact, unless the preponderance
    of the evidence is otherwise. TENN. R. APP. P. 13(d); Gregg v. Estate of Cupit, No.
    M2018-00379-COA-R3-CV, 
    2018 WL 5733289
    , at *3 (Tenn. Ct. App. Oct. 31, 2018);
    Nashville Ford Tractor, Inc. v. Great Am. Ins. Co., 
    194 S.W.3d 415
    , 424-25 (Tenn. Ct.
    App. 2005). We review the trial court’s legal conclusions with no presumption of
    correctness. Nashville Ford 
    Tractor, 194 S.W.3d at 425
    . We afford the trial court’s
    credibility determinations great deference because the trial court is able to assess the
    witnesses’ demeanor as they testify. Wells v. Tenn. Bd. of Regents, 
    9 S.W.3d 779
    , 783
    (Tenn. 1999).
    ANALYSIS
    We begin by noting that Mr. Boyd is a pro se litigant, both at trial and on appeal.
    This court has applied the following standards when evaluating the claims of pro se
    litigants:
    Parties who decide to represent themselves are entitled to fair and equal
    treatment by the courts. The courts should take into account that many pro
    se litigants have no legal training and little familiarity with the judicial
    system. However, the courts must also be mindful of the boundary between
    fairness to a pro se litigant and unfairness to the pro se litigant’s adversary.
    Thus, the courts must not excuse pro se litigants from complying with the
    same substantive and procedural rules that represented parties are expected
    to observe.
    Young v. Barrow, 
    130 S.W.3d 59
    , 62-63 (Tenn. Ct. App. 2003) (citations omitted); see
    also Hessmer v. Hessmer, 
    138 S.W.3d 901
    , 903 (Tenn. Ct App. 2003). We allow pro se
    litigants some latitude in preparing their briefs and endeavor to “give effect to the
    substance, rather than the form or terminology,” of their court filings. 
    Young, 130 S.W.3d at 63
    .
    We must also address the state of the appellate record in this case. Although there
    was a full hearing before the trial court, there is no transcript of the hearing in the record
    on appeal. Rather, the record contains the statement of the evidence set forth above.4
    4
    Tennessee Rule of Appellate Procedure 24(c) provides as follows:
    Statement of the Evidence When No Report, Recital, or Transcript Is Available. If
    no stenographic report, substantially verbatim recital or transcript of the evidence or
    proceedings is available, or if the trial court determines, in its discretion, that the cost to
    obtain the stenographic report in a civil case is beyond the financial means of the
    -7-
    Thus, we have only a synopsis of what occurred at trial. In accordance with Tenn. R.
    App. P. 24, it is the duty of the appellant to prepare the record and to provide “the
    appellate court a ‘fair, accurate and complete account’ of what transpired at the trial
    level.” Jennings v. Sewell-Allen Piggly Wiggly, 
    173 S.W.3d 710
    , 713 (Tenn. 2005)
    (quoting State v. Ballard, 
    855 S.W.2d 557
    , 560 (Tenn. 1993)). The appellee “shares the
    responsibility for ensuring the appellate court has a complete record.” 
    Id. (citing Tenn.
    R. App. P. 24(a), (b), (d)). In this case, the trial court found Ms. Thompson’s statement
    of the evidence to be a complete and accurate account of what transpired at the trial and
    adopted it.5
    I. Breach of contract.
    Implicit in the trial court’s order awarding damages to Ms. Thompson is a finding
    that Mr. Boyd breached the contract between the parties. The trial court expressly found
    that the work was never completed “because of numerous delays on the part of” Mr.
    Boyd and that remediation by Mr. Johnson was required for “work previously done by
    the defendant in an unworkmanlike manner.” Mr. Boyd argues that Ms. Thompson was
    at fault in locking him out of the house, thereby preventing him from completing his
    work. He further asserts that Ms. Thompson was in breach of the contract when she
    declined to allow Wells Fargo Mortgage to inspect Mr. Boyd’s work.
    The first party to materially breach a contract “is not entitled to damages
    stemming from the other party’s later material breach of the same contract.” McClain v.
    Kimbrough Constr. Co., Inc., 
    806 S.W.2d 194
    , 199 (Tenn. Ct. App. 1990). The trial
    appellant or that the cost is more expensive than the matters at issue on appeal justify,
    and a statement of the evidence or proceedings is a reasonable alternative to a
    stenographic report, the appellant shall prepare a statement of the evidence or
    proceedings from the best available means, including the appellant’s recollection. The
    statement should convey a fair, accurate and complete account of what transpired with
    respect to those issues that are the bases of appeal. The statement, certified by the
    appellant or the appellant’s counsel as an accurate account of the proceedings, shall be
    filed with the clerk of the trial court within 60 days after filing the notice of appeal. Upon
    filing the statement, the appellant shall simultaneously serve notice of the filing on the
    appellee, accompanied by a short and plain declaration of the issues the appellant intends
    to present on appeal. Proof of service shall be filed with the clerk of the trial court with
    the filing of the statement. If the appellee has objections to the statement as filed, the
    appellee shall file objections thereto with the clerk of the trial court within fifteen days
    after service of the declaration and notice of the filing of the statement. Any differences
    regarding the statement shall be settled as set forth in subdivision (e) of this rule.
    5
    Tennessee Rule of Appellate Procedure 24(e) states, in pertinent part: “Any differences regarding
    whether the record accurately discloses what occurred in the trial court shall be submitted to and settled
    by the trial court regardless of whether the record has been transmitted to the appellate court. Absent
    extraordinary circumstances, the determination of the trial court is conclusive.”
    -8-
    court identified the first material breaches in this case to be Mr. Boyd’s poor
    workmanship and delay. See generally Greeter Constr. Co. v. Tice, 
    11 S.W.3d 907
    , 910
    (Tenn. Ct. App. 1999) (discussing contractor’s delay and inferior workmanship as factors
    justifying other party’s termination of contract). The evidence does not preponderate
    against the trial court’s finding that much of Mr. Boyd’s work was not performed in a
    workmanlike manner. The trial court credited the testimony of Clayton Johnson, the
    renovation contractor, who presented a detailed report regarding Mr. Boyd’s defective
    workmanship in repairing Ms. Thompson’s home and the cost required to correct the
    defects. Moreover, Ms. Thompson and Mr. Boyd signed a contract in October 2015.
    Sometime in 2016, Mr. Boyd moved to Georgia with his family and was gone for several
    months. By July of 2017, Ms. Thompson’s project remained incomplete, and she decided
    to hire someone else to finish the work. The evidence in the record supports the trial
    court’s finding that Mr. Boyd breached the contract by his undue delay and abandonment
    of the project.
    We find no error in the trial court’s determination that Mr. Boyd materially
    breached the contract with Ms. Thompson.
    II. Damages awarded to Ms. Thompson.
    The amount of damages awarded is a question of fact and is, therefore, subject to
    review under the preponderance of the evidence standard. Memphis Light, Gas & Water
    Div. v. Starkey, 
    244 S.W.3d 344
    , 352 (Tenn. Ct. App. 2007).
    In assessing damages, the trial court relied upon the estimate provided by Mr.
    Johnson in the amount of $34,342.06, which was “to complete the repairs on Plaintiff’s
    home, including remediation of work previously done by the defendant in an
    unworkmanlike manner.” From this amount, the trial court subtracted $5,779.00 for the
    new HVAC system, which was not covered by the insurance estimate. After this
    reduction, the cost of completion would be $28,563.06. The trial court deducted another
    $2,500 from the estimate for change orders to be paid by Ms. Thompson, which would
    result in a total cost of completion of $26,063.06, the exact amount of the judgment
    entered by the court against Mr. Boyd in favor of Ms. Thompson. Thus, the trial court
    ordered Mr. Boyd to pay the entire cost of the project’s completion.
    We find this result puzzling for several reasons. First, as stated in the trial court’s
    order, the repairs were made “pursuant to the estimate provided by Capstone Independent
    Adjusting Company at a cost of $80,063.55 with $67,232.71 to be paid as actual cash
    value and $12,830.84 to be paid as replacement cash value once all work had been
    completed.” Thus, after Mr. Boyd received $53,620.30, insurance proceeds remained in
    the amount of $26,443.25. There is no accounting in the trial court’s order for the unused
    insurance funds, and no explanation for requiring Mr. Boyd to pay the entire cost of the
    completion of the project.
    -9-
    Second, Mr. Boyd points out a number of charges in Mr. Johnson’s invoices that
    are not covered by the insurance estimate. For example, the insurance estimate does not
    cover a new front door (total $600), new gutters around the house ($1,560), or a
    hardwood floor in the basement (materials $2,300). The trial court subtracted $2,500 for
    change orders, but that amount does not explain all of the discrepancies between Mr.
    Johnson’s invoices and the insurance estimate. Moreover, the trial court’s order does not
    resolve Mr. Boyd’s counterclaim.6
    On the record before this court, we find the trial court’s order inadequate. We
    affirm the portion of the order finding Mr. Boyd to be the party in breach of the contract.
    We vacate the remainder of the trial court’s decision and remand for further proceedings
    consistent with this opinion. In particular, the trial court should make specific findings
    regarding its calculation of the amount of the judgment against Mr. Boyd, the distribution
    of the remaining insurance proceeds, and the disposition of Mr. Boyd’s counterclaim
    against Ms. Thompson.
    CONCLUSION
    The judgment of the trial court is affirmed in part and vacated in part, and this
    matter is remanded with costs of appeal assessed equally against the appellant and the
    appellee, for which execution may issue if necessary.
    ________________________________
    ANDY D. BENNETT, JUDGE
    6
    We have determined that, rather than remanding this case for the entry of a final order, the more
    appropriate course is for this court to waive the finality requirement in accordance with Tenn. R. App. P.
    2 and to address all of the inadequacies of the trial court’s order prior to remand. See Bayberry Assocs. v.
    Jones, 
    783 S.W.2d 553
    , 559 (Tenn. 1990); Hopwood v. Hopwood, No. M2016-01752-COA-R3-CV, 
    2017 WL 2964886
    , at *3 n.4 (Tenn. Ct. App. July 12, 2017).
    - 10 -