James G. Clayton v. Davidson Contractors, LLC ( 2015 )


Menu:
  •                IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    July 9, 2014 Session
    JAMES G. CLAYTON, ET AL. v. DAVIDSON CONTRACTORS, LLC, ET AL.
    Appeal from the Chancery Court for Hamilton County
    No. 071016    Jeffrey M. Atherton, Chancellor
    No. E2013-02296-COA-R3-CV-FILED-APRIL 24, 2015
    In connection with the purchase of a newly constructed home, buyers signed an
    application for a home warranty, providing for arbitration of warranty disputes. After the
    buyers experienced several problems with their home, they sued the builders for breach
    of the implied warranty of habitability and negligent construction, among other things.
    Over five years after answering the buyers‟ complaint, the builders moved to stay the
    litigation and compel arbitration based on the home warranty‟s arbitration provision. The
    trial court denied the motion because the arbitration provision did not comply with the
    Tennessee Uniform Arbitration Act. The trial court also found that the builders‟ delay in
    seeking to compel arbitration constituted a waiver of their right to arbitrate. The builders
    appeal. Because we conclude that the Federal Arbitration Act governs the arbitration
    provision and consideration of the waiver defense was premature, we vacate and remand.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court
    Vacated and Remanded
    W. NEAL MCBRAYER, J., delivered the opinion of the Court, in which CHARLES D.
    SUSANO, JR., C.J., and THOMAS R. FRIERSON, J., joined.
    Tom D. Weldon, Ringgold, Georgia, for the appellants, Davidson Contractors, LLC,
    Phillip Lance Davidson and John Mason.
    John R. Anderson and Katherine H. Lentz, Chattanooga, Tennessee, for the appellees,
    John G. Clayton and Kaci W. Clayton.
    OPINION
    I. FACTUAL BACKGROUND
    In the fall of 2006, James and Kaci Clayton purchased a home on Belleau Ridge
    Drive in Ooltewah, Tennessee from Davidson Contractors, LLC. According to
    Ms. Clayton, the owners of Davidson Contractors, Lance Davidson and John Mason,
    assured the Claytons that they would correct any problems with the construction of the
    home. Mr. Davidson and Mr. Mason also told the Claytons that they would receive a “2-
    10 Warranty” that would cover both craftsmanship and construction for a period of ten
    years.
    At the closing, on November 28, 2006, the Claytons signed a document titled
    “Builder Application for Home Enrollment.” In pertinent part, the document provided as
    follows:
    Your Builder is applying to enroll your home in the 2-10 HBW® New
    Home Warranty program. By signing below, you acknowledge that you
    have read a sample copy of the Warranty Booklet, and CONSENT TO THE
    TERMS OF THESE DOCUMENTS INCLUDING THE BINDING
    ARBITRATION PROVISION contained therein. You further understand
    that when the warranty is issued on your new home, it is an Express
    Limited Warranty and that all claims and liabilities are limited to and by the
    terms and conditions of the Express Limited Warranty as stated in the 2-10
    HBW® Booklet. IF YOU, THE BUYER(S), HAVE NOT RECEIVED A
    CERTIFICATE OF WARRANTY COVERAGE AND A WARRANTY
    BOOKLET FROM 2-10 HBW® WITHIN THIRTY (30) DAYS AFTER
    CLOSING THEN THERE IS NO COVERAGE BY THE BUILDER‟S
    WARRANTY INSURER, YOU SHOULD CONTACT YOUR BUILDER.
    HBW is a service mark for Home Buyers Warranty Corporation, the warranty
    administrator. Home Buyers Warranty Corporation maintains offices in Aurora,
    Colorado; Tucker, Georgia; and Arlington, Texas.
    According to deposition testimony, within a year after moving into their new
    home, the Claytons began experiencing problems with both the structure and the
    property. The Claytons‟ complaints ranged from the minor, cracked tiles and a leaking
    shower, to the major, cracks in the foundation and mold growth. In addition to incurring
    costs to repair various items, the Claytons allege that their youngest daughter began
    suffering health issues from mold. Ultimately, the Claytons vacated the home.
    -2-
    On November 27, 2007, the Claytons filed suit against Davidson Contractors, as
    well as Mr. Davidson and Mr. Mason individually. The Claytons alleged fraudulent
    and/or reckless inducement to contract, violations of the Tennessee Consumer Protection
    Act, breach of implied warranty of habitability, and negligent construction. The
    defendants each filed answers in January 2008. In their answers, Davidson Contractors,
    Mr. Davidson, and Mr. Mason included a statement that the Claytons‟ complaint could
    not be heard by the trial court due to an arbitration clause included in the home warranty.
    After a long period of inactivity, on June 21, 2010, the trial court entered an initial
    scheduling order. The order set the case for trial on November 2, 2010. Between 2010
    and 2013, the court rescheduled the trial six different times. Davidson Contractors,
    Mr. Davidson, and Mr. Mason requested at least four of those continuances. During that
    same time period, the defendants participated in two mediation sessions and several
    depositions and propounded and answered written discovery. On September 6, 2013,
    Davidson Contractors, Mr. Davidson, and Mr. Mason filed a “Motion for Stay and
    Referral of this Matter to Arbitration Pursuant to Arbitration Agreement.” In the motion,
    the defendants requested that the trial court stay the litigation and compel arbitration in
    accordance with the 2-10 Home Buyers Warranty contract.
    On October 7, 2013, the trial court held an evidentiary hearing on the motion.
    Despite the acknowledgement contained in the “Builder Application for Home
    Enrollment,” Ms. Clayton testified that she and her husband did not receive a sample
    warranty booklet at the closing. She also maintained that they did not receive a warranty
    certificate or a warranty booklet within thirty days of the closing, or ever, from Davidson
    Contractors or HBW. She stated that they only obtained a sample warranty booklet from
    a neighbor after their lawsuit had been filed.
    Both Mr. Davidson and Mr. Mason maintained that Mr. Mason had given a sample
    warranty booklet to the Claytons at the closing. Davidson Contractors did not keep a
    copy of the document that they claim was presented to the Claytons. Through
    Mr. Mason, the defendants introduced a sample warranty booklet obtained from HBW in
    September 2013. Mr. Mason testified that the sample warranty booklet was the same as
    that given to the Claytons in 2006. The sample warranty booklet contained an arbitration
    clause, providing in part as follows:
    ARBITRATION. Any and all claims, disputes and controversies by or
    between the homeowner, the Builder, the Warranty Insurer and/or
    HBW, or any combination of the foregoing, arising from or related to
    this Warranty, to the subject Home, to any defect in or to the subject
    Home or the real property on which the subject Home is situated, or
    the sale of the subject Home by the Builder, including without
    -3-
    limitation, any claim of breach of contract, negligent or intentional
    misrepresentation or nondisclosure in the inducement, execution or
    performance of any contract, including this arbitration agreement, and
    breach of any alleged duty of good faith and fair dealing, shall be
    settled by binding arbitration. Agreeing to arbitration means you are
    waiving your right to a jury trial.
    ....
    This arbitration agreement shall be deemed to be a self-executing
    arbitration agreement. Any disputes concerning the interpretation or
    the enforceability of this arbitration agreement, including without
    limitation, its revocability or voidability for any cause, the scope of
    arbitrable issues, and any defense based upon waiver, estoppel or
    laches, shall be decided by the arbitrator.
    The initiation of or participation by any party in any judicial
    proceeding concerning this arbitration agreement or any matter
    arbitrable hereunder shall not be deemed a waiver of the right to
    enforce this arbitration agreement, and notwithstanding any provision
    of law to the contrary, shall not be asserted or accepted as a reason to
    delay, to refuse to participate in, or to refuse to enforce this arbitration
    agreement.
    (emphasis in original).
    On an offer by the Claytons, the trial court also accepted into evidence HBW‟s
    response to deposition upon written questions. HBW indicated that it mailed a certificate
    of warranty and a “2-10 Home Buyers Warranty Booklet” to the Claytons. However,
    HBW did not indicate when the documents were mailed. HBW acknowledged that no
    transmittal letters accompanied the certificate of warranty or warranty booklet. HBW did
    respond that, as a regular business practice, a record was made when mailed items were
    returned and that there was no such record relative to the Claytons. HBW also responded
    that the “homeowner” contacted HBW about a warranty claim on November 27, 2007.
    At the conclusion of the proof, the trial court denied the motion to stay and compel
    arbitration. After the oral ruling, counsel for Davidson Contractors, Mr. Davidson, and
    Mr. Mason asked the trial court if it was finding that “a warranty agreement and [ ] an
    arbitration provision” existed. In response, the court clarified that it was only ruling on
    compliance with state law and equitable principles. In its October 10, 2013 order
    denying the motion, the court cited the Tennessee Uniform Arbitration Act, specifically
    -4-
    the “failure to comply with 
    Tenn. Code Ann. § 29-5-302
    (a) as the clause providing for
    arbitration was not additionally signed or initialed by the parties.” As an additional or
    alternative basis for denying the motion, the trial court found that the “Defendants waived
    their right to arbitration and/or to invoke the arbitration provision contained in the 2-10
    HBW New Home Warranty Booklet by virtue of their conduct and participation in the
    instant litigation.”
    II. ANALYSIS
    The appellants, Davidson Contractors, Mr. Davidson, and Mr. Mason, challenge
    both grounds relied on by the trial court for denying the motion to compel arbitration. On
    the first ground, Appellants argue that, although the arbitration clause found in the
    sample warranty book was not separately initialed, the proximity of the Claytons‟
    signatures to the acknowledgment found in the “Builder Application for Home
    Enrollment” was sufficient to satisfy Tennessee Code Annotated § 29-5-302(a).
    Alternatively, they claim that the Tennessee Uniform Arbitration Act (“TUAA”) does not
    apply at all. On the second ground, Appellants argue that the arbitration clause prohibits
    a finding of waiver based upon their participation in a judicial proceeding.
    A. APPLICABLE LAW
    As an initial matter, we must determine whether the TUAA or the Federal
    Arbitration Act (“FAA”) applies to the parties‟ agreement.1 When the FAA applies,
    states may not impose requirements on arbitration agreements beyond those found in the
    FAA. See Southland Corp. v. Keating, 
    465 U.S. 1
    , 15-16 (1984); Wells v. Tenn.
    Homesafe Inspections, LLC., No. M2008-00224-COA-R3-CV, 
    2008 WL 5234724
    , *3
    (Tenn. Ct. App. Dec. 15, 2008); Hubert v. Turnberry Homes, LLC, No. M2005-00955-
    COA-R3-CV, 
    2006 WL 2843449
    , *6 (Tenn. Ct. App. Oct. 4, 2006). Although the TUAA
    requires that agreements to arbitrate regarding residential structures be separately signed
    or initialed, the FAA does not. 
    Tenn. Code Ann. § 29-5-302
    (a) (2012). Therefore, where
    the FAA applies, this requirement may not be imposed on the agreement of the parties.
    The FAA applies to “[a] written provision in . . . a contract evidencing a
    transaction involving commerce to settle by arbitration a controversy thereafter arising
    out of such contract or transaction.” 
    9 U.S.C.A. § 2
     (2009) (emphasis added). The term
    “commerce” as used in the FAA includes “commerce among the several States.” 
    Id.
     § 1.
    The United States Supreme Court has interpreted the term “involving commerce,” and
    therefore the reach of the FAA, as concurrent with that of the Commerce Clause. See,
    e.g., Perry v. Thomas, 
    482 U.S. 483
    , 490 (1987) (The FAA “embodies Congress‟ intent
    1
    The FAA and “arbitration law appl[y] in state as well as federal courts.” Buckeye Check
    Cashing, Inc. v. Cardegna, 
    546 U.S. 440
    , 446 (2006).
    -5-
    to provide for the enforcement of arbitration agreements within the full reach of the
    Commerce Clause.”).
    In this case, we conclude that the transaction at issue involves commerce.
    Davidson Contractors is a Tennessee limited liability company. The home was also
    constructed in Tennessee and purchased by Tennessee residents. However, the Claytons
    attribute many of their claims to the alleged actions or inaction of Mr. Davidson and
    Mr. Mason, residents of Georgia. Documents produced by HBW and introduced into
    evidence also show Davidson Contractors maintained a Ringgold, Georgia address.
    Furthermore, HBW, the intended warranty administrator, is headquartered in Colorado.
    Consequently, the trial court erred in relying on the TUAA and its requirement that
    arbitration clauses be additionally signed or initialed.2
    B. WAIVER
    The arbitration clause at issue here contains a delegation provision, “an agreement
    to arbitrate threshold issues concerning the arbitration agreement.” Rent-A-Center, West,
    Inc. v. Jackson, 
    561 U.S. 63
    , 68 (2010). Threshold issues may include whether the
    parties have agreed to arbitrate any dispute at all, whether the agreement covers a
    particular controversy, or whether the agreement is enforceable. See 
    id. at 68-69
    ;
    1 Thomas H. Oehmke & Joan M. Brovins, Commercial Arbitration § 20:5 (2014). In this
    case, the delegation provision defines enforceability issues to include “any defense based
    upon waiver” and delegates that issue to the arbitrator.
    The FAA requires courts to enforce delegation provisions just as they are required
    to enforce arbitration agreements. Id. at 70 (Delegation provisions are “simply an
    additional, antecedent agreement the party seeking arbitration asks the . . . court to
    enforce, and the FAA operates on this additional arbitration agreement just as it does on
    any other.”). However, “the making of the agreement” must not be at issue. 
    9 U.S.C.A. § 4
     (2009).
    2
    Although it is not dispositive of the issue, we also note that the arbitration clause found in the
    sample warranty booklet provides as follows:
    The parties expressly agree that this Warranty and this arbitration agreement
    involve and concern interstate commerce and are governed by the provisions of the
    Federal Arbitration Act (
    9 U.S.C. § 1
    , et seq.) now in effect and as the same may
    from time to time be amended, to the exclusion of any different or inconsistent state
    or local law, ordinance or judicial rule . . . .
    (emphasis in original).
    -6-
    The Claytons specifically placed the making of the agreement for arbitration at
    issue. Yet, the trial court found that Appellants had waived the right to arbitrate. Finding
    waiver, without first addressing whether an agreement to arbitrate existed, is problematic
    in this circumstance. If an agreement to arbitrate did exist, the delegation provision
    places the issue of waiver with the arbitrator rather than the court.
    C. ARBITRABILITY3
    The Claytons claim they did not enter into the warranty contract. The FAA
    provides that the court must be “satisfied that the making of the agreement for arbitration
    or the failure to comply therewith is not in issue.” 
    Id.
     However, the warranty contract
    contains an arbitration agreement and a delegation provision providing that “[a]ny
    disputes concerning . . . the enforceability of this arbitration agreement . . . shall be
    decided by the arbitrator.” In light of the delegation provision, we must determine
    whether the court or the arbitrator decides the Claytons‟ claim that there was no warranty
    agreement. To do so, we review United States Supreme Court precedent interpreting the
    FAA.
    In Prima Paint Corp. v. Flood & Conklin Manufacturing Company, 
    388 U.S. 395
    (1967), the Court addressed “whether a claim of fraud in the inducement of the entire
    contract is to be resolved by the federal court” or by an arbitrator. 
    388 U.S. at 402
    . The
    parties had entered into a consulting agreement in connection with the sale of a business.
    
    Id. at 397
    . The agreement included a broad arbitration clause delegating to an arbitrator
    “any controversy or claim arising out of or relating to” the contract. 
    Id. at 398
    . After a
    dispute between the parties arose, the purchaser sought to enjoin the arbitration, claiming
    that the consulting agreement was invalid because it was fraudulently induced. 
    Id.
     The
    seller maintained that the purchaser‟s claim was a question for the arbitrator, not the
    court. 
    Id. at 399
    .
    The Court first concluded that section two of the FAA requires that arbitration
    clauses be severable from the contracts in which they are embedded. 
    Id. at 404
    . This
    principle became known as the severability rule. See, e.g., Buckeye Check Cashing, Inc.
    v. Cardegna, 
    546 U.S. 440
    , 440 (2006). Because the arbitration clause was severable
    from the remainder of the contract and separately enforceable, the court could not
    consider the seller‟s claim that the entire contract was invalid because of fraud in the
    inducement of the contract generally. Prima Paint, 
    388 U.S. at 404
    . Only, “if the claim
    [wa]s fraud in the inducement of the arbitration clause itself—an issue which goes to the
    „making‟ of the agreement to arbitrate—[could] the federal court [ ] proceed to adjudicate
    it.” 
    Id. at 403-04
    . The Court later acknowledged that the Prima Paint severability rule
    3
    Arbitrability is defined as “[t]he status, under applicable law, of a dispute‟s being or not being
    resolvable by arbitrators because of the subject matter.” Black‟s Law Dictionary (10th ed. 2014).
    -7-
    allows a “court to enforce an arbitration agreement in a contract that the arbitrator later
    finds to be void.” Buckeye, 
    561 U.S. at 448
    . However, the opposite approach would
    permit a “court to deny effect to an arbitration provision in a contract that the court later
    finds to be perfectly enforceable.” Id. at 448-49. “Prima Paint resolved this conundrum
    . . . in favor of the separate enforceability of arbitration provisions.” Id. at 449.
    Almost forty years later, in Buckeye Check Cashing, Inc. v. Cardegna, 
    546 U.S. 440
     (2006), the Court applied the severability rule to contracts that may be void as well
    as voidable. 
    546 U.S. at 447-78
    . In that case, borrowers claimed that a lending
    agreement they signed with Buckeye Check Cashing was rendered invalid because the
    agreement‟s usurious finance charge was illegal. 
    Id. at 443
    . The Court reiterated that,
    unless a party specifically challenges the arbitration clause itself, rather than the validity
    of the contract as a whole, an arbitrator decides whether the contract is valid. 
    Id.
     at 445-
    46. Therefore, because the borrowers argued that “the contract as a whole (including its
    arbitration provision) [wa]s rendered invalid,” the arbitration provision remained
    separately enforceable. 
    Id. at 444, 445-46
    . However, the Court distinguished situations
    where the issue was “the contract‟s validity,” as in the case before it, from situations
    where the issue was “whether any agreement between the alleged obligor and obligee
    was ever concluded.” 
    Id. at 444, n.1
    .
    In Rent-A-Center, West, Inc. v. Jackson, 
    561 U.S. 63
     (2010), the Court applied the
    severability rule to arbitration agreements with delegation provisions. 
    561 U.S. at 72
    . In
    that case, an employee signed an arbitration agreement with Rent-A-Center as a condition
    of his employment. 
    Id. at 68
    . The delegation provision of the agreement stated, “the
    Arbitrator, and not any federal, state, or local court or agency, shall have exclusive
    authority to resolve any dispute relating to the interpretation, applicability, enforceability,
    or formation of this Agreement including, but not limited to any claim that all or any part
    of this Agreement is void or voidable.” 
    Id. at 66
    . The employee claimed that the
    arbitration agreement, including the delegation clause, was invalid because the entire
    agreement was unconscionable. 
    Id.
     Relying on the delegation provision, Rent-A-Center
    sought to compel arbitration of the employee‟s unconscionability claim. 
    Id. at 68
    .
    Although the whole agreement in Rent-A-Center was a stand-alone arbitration
    agreement, the Court still held the severability rule applicable. 
    Id. at 72
    . The Court held
    that, where a party seeking to compel arbitration relies on a delegation provision, only if
    a party specifically challenges the enforceability of the delegation provision will the court
    consider the challenge. 
    Id.
     “[B]ut if a party challenges the enforceability of the
    agreement as a whole, the challenge is for the arbitrator.” 
    Id. at 63
    . However, the Court
    again cautioned that “[t]he issue of the agreement‟s „validity‟ is different from the issue
    whether any agreement between the parties „was ever concluded,‟ and, as in Buckeye . . .,
    we address only the former.” 
    Id. at 70, n.2
     (quoting Buckeye, 
    561 U.S. at 444, n.1
    ).
    -8-
    Three days after the Rent-A-Center decision, the Court decided Granite Rock Co.
    v. International Brotherhood of Teamsters, 
    561 U.S. 287
     (2010), finally addressing the
    arbitrability issue in light of a party‟s claim that an agreement between the parties “was
    [n]ever concluded.” See Rent-A-Center, 
    561 U.S. 70
    , n.2. In Granite Rock, an employer
    sued an international and local union, alleging that a labor strike breached a no-strike
    clause in the parties‟ collective bargaining agreement (“CBA”).4 Granite Rock, 
    561 U.S. at 287
    . The parties disputed when the CBA was ratified by the union and, thus, disagreed
    over when the CBA was formed. 
    Id. at 297, 297, n.4
    . The local union sought to have the
    dispute decided by an arbitrator. 
    Id. at 287
    .
    The Court began its analysis by noting that “a court may order arbitration of a
    particular dispute only where the court is satisfied that the parties agreed to arbitrate that
    dispute.” 
    Id. at 297
    ; see also 
    9 U.S.C.A. § 4
    . To satisfy itself that such an agreement
    exists, the court must resolve: (1) any issue questioning the formation of the parties‟
    arbitration agreement; and (2) absent a valid delegation provision, any issue regarding the
    enforceability or applicability of the arbitration agreement to the dispute. Granite Rock,
    561 U.S. at 299.
    In Prima Paint, Buckeye, and Rent-A-Center, the Court only compelled arbitration
    “after . . . [being] persuaded that the parties‟ arbitration agreement was validly formed
    and that it covered the dispute in question and was legally enforceable.” Granite Rock,
    
    561 U.S. at 300
    . In Prima Paint, the parties did not dispute that they entered into a
    consulting agreement—the seller alleged only that the contract as a whole should be
    declared invalid because it was fraudulently induced. Prima Paint, 
    388 U.S. at 402
    . In
    Buckeye, the formation of the parties‟ agreement was not at issue because the parties
    agreed they had concluded an agreement to arbitrate in their loan contract. Buckeye, 
    546 U.S. at 444
    . Instead, the borrower claimed that the contract should be declared invalid
    because it was illegal. 
    Id.
     Similarly, the parties in Rent-A-Center did not dispute that
    they agreed to an arbitration agreement—the employee claimed that the entire contract
    should be declared invalid for unconscionability. Rent-A-Center, 
    561 U.S. at 68
    .
    Because the parties in those cases did not challenge their consent to the agreement to
    arbitrate within the broader contract, the severability rule applied, and the arbitration
    provision was enforced. See, e.g., Buckeye, 561 U.S. at 448.
    However, as the Court noted in Granite Rock, the severability rule does not apply
    when a “party resisting arbitration specifically challenges the enforceability of the
    4
    The same rules of arbitrability govern cases applying the FAA and the Labor Management
    Relations Act (“LMRA”). See Granite Rock, 
    561 U.S. at 298, n.6
    . For example, Granite Rock involved
    an arbitrability dispute under the LMRA, but the Court discussed and relied upon precedents applying the
    FAA.
    -9-
    arbitration clause itself,” Granite Rock, 
    561 U.S. at
    301 (citing Buckeye, 
    546 U.S. at
    443-
    45), or a party “claims the agreement to arbitrate was „[n]ever concluded.‟” Granite Rock,
    
    561 U.S. at 299, 301
     (quoting Buckeye 
    546 U.S. at 444
    , n. 1 and Rent-A-Center 
    561 U.S. at 70, n. 2
    ). In Granite Rock, the union claimed a contract had not been formed as of the
    date of the strike. Id. at 287. Therefore, the Court concluded that a court, rather than an
    arbitrator, must resolve the parties‟ formation dispute. Id. at 303.
    When read together, Prima Paint, Buckeye, Rent-A-Center, and Granite Rock
    stand for the proposition that the court resolves two types of issues relating to an
    agreement to arbitrate: (1) a challenge to the validity of the specific arbitration clause
    sought to be enforced; and (2) a challenge to the formation of a contract, which may
    include an agreement to arbitrate. See In re Morgan Stanley & Co., 
    293 S.W.3d 182
    , 187
    (Tex. 2009). Where there is a delegation provision, an arbitrator decides a party‟s
    challenge to the validity of the contract as a whole. 
    Id.
     Therefore, when a party claims it
    never concluded an agreement at all, it is for the court, not the arbitrator, to determine
    whether the parties agreed to the arbitration provision upon which the party seeking
    arbitration relies. Granite Rock, 
    561 U.S. at 299-300
    . Although there is a federal policy
    favoring arbitration, that policy does not override the principle of consent. 
    Id. at 302
    .
    The line between contract formation issues and contract validity issues is a fine
    one. See In re Morgan Stanley, 293 S.W.3d at 192 (Willett, J., concurring) (describing
    the line between contract formation and contract validity issues as “murky”).5
    Fortunately, the Court provided some guidance in Buckeye as to which contractual
    defenses are formation issues to be considered by the courts. See Buckeye, 
    546 U.S. 444
    ,
    n.1 (suggesting that the following defenses were formation issues: lack of signature on a
    contract; signor‟s lack of authority to bind principal; and mental capacity to assent). We
    can also conclude from Prima Paint, Buckeye, and Rent-A-Center that fraudulent
    inducement, illegality, and unconscionability are contract validity issues.
    In the case before us, the Claytons present a classic formation issue—they argue a
    contract was never formed. Specifically, they claim they never received the certificate of
    warranty coverage or warranty booklet within thirty days of closing. Under the “Builder
    Application for Home Enrollment,” receipt of the certificate and booklet is a prerequisite
    to “coverage by the builder‟s warranty insurer.” Their contract formation issue precludes
    application of the severability rule, so they were not required to specifically challenge the
    arbitration agreement or delegation provision in order to avoid arbitration. Granite Rock,
    561 U.S. at 299-301. They raise an issue that the court must resolve before compelling
    5
    Adding to the confusion, the plain language of the FAA suggests courts have the authority to
    consider both formation and validity issues before compelling arbitration. See Rent-A-Center, 
    561 U.S. at 78
     (Stevens J., dissenting) (citing Doctor’s Assocs., Inc. v. Casarotto, 
    517 U.S. 681
    , 687 (1996)); see also
    
    9 U.S.C.A. § 4
     (allowing courts to consider the “making” of the agreement for arbitration).
    - 10 -
    arbitration. Buckeye, 
    546 U.S. at 444, n.1
    ; Rent-A-Center, 
    561 U.S. at 70, n.2
    ; Granite
    Rock, 
    561 U.S. at 299
    .
    Requiring the court to resolve the Claytons‟ claim that a contract was never
    formed is sound policy. Compelling a party to arbitrate whether he actually agreed to
    arbitrate a dispute is “hopelessly circular.” Bruni v. Didion, 
    73 Cal. Rptr. 3d 395
    , 408
    (Cal. Ct. App. 2008). Judicial determination of the Claytons‟ formation issue also avoids
    a serious “bootstrapping” problem regarding the arbitrator‟s authority. 
    Id. at 406
    ; see
    also Matterhorn, Inc. v. NCR Corp., 
    763 F.2d 866
    , 869 (7th Cir. 1985). If the Claytons
    were compelled to arbitrate whether they agreed to the warranty contract, including the
    delegation provision, the arbitrator would determine his own authority to decide the
    parties‟ dispute. If the arbitrator concluded the parties did not have a contract, the
    arbitrator had no authority to decide the dispute. If the arbitrator concluded the parties
    did have a contract, the arbitrator effectively granted himself jurisdiction. See In re
    Morgan Stanley, 293 S.W.3d at 193 (Hecht, J., dissenting). Finally, this outcome is
    consistent with arbitration law‟s focus on the parties‟ consent to arbitrate a particular
    dispute. Granite Rock, 
    561 U.S. at
    302 (citing First Options of Chicago, Inc. v. Kaplan,
    
    514 U.S. 938
    , 943 (1995)).
    Requiring the court to resolve the Claytons‟ claim that a contract was never
    formed is also consistent with the decisions of other courts. See, e.g., Bruni, 
    73 Cal. Rptr. 3d at 406
     (concluding that a court must consider a contract formation challenge before
    compelling arbitration in a dispute involving home buyers, builders, and an HBW
    warranty); Thompson v. Lithia Chrysler Jeep Dodge of Great Falls, Inc., 
    185 P.3d 332
    (Mont. 2008); Spahr v. Secco, 
    330 F.3d 1266
     (10th Cir. 2003); Sphere Drake Ins. Ltd. v.
    All Am. Ins. Co., 
    256 F.3d 587
     (7th Cir. 2001); Sandvik AB v. Advent Int’l Corp., 
    220 F.3d 99
     (3d Cir. 2000); Chastain v. Robinson-Humphrey Co., 
    957 F.2d 851
     (11th Cir.
    1992). Although these cases were decided before Rent-A-Center, that decision did not
    address a scenario where a party argued that no agreement “was ever concluded.” Rent-
    A-Center, 
    561 U.S. at 70, n.2
    . Moreover, Granite Rock confirms that courts must satisfy
    themselves that the parties agreed to arbitrate a particular dispute before compelling
    arbitration. 561 U.S. at 297; see also Kum Tat Ltd. v. Linden Ox Pasture, LLC, No. 14-
    CV-02857-WHO, 
    2014 WL 6882421
    , at *5 (N.D. Cal. Dec. 5, 2014) (appeal pending); In
    re Morgan Stanley, 293 S.W.3d at 188.
    Because the trial court must consider the Claytons‟ claim that no contract was
    formed, we remand this case to the trial court. On remand, the trial court must determine
    whether the Claytons entered into the HBW warranty contract, including its agreement to
    arbitrate disputes and delegation provision. If the trial court concludes that a contract
    was formed among HBW, Davidson Contractors, and the Claytons, an arbitrator must
    decide the parties‟ dispute, including the issue of waiver. If the trial court concludes that
    - 11 -
    a contract was not formed, the court may decide the parties‟ dispute.
    III. CONCLUSION
    For the foregoing reasons, we vacate the trial court‟s judgment and remand for
    further proceedings consistent with this opinion.
    ______________________________
    W. NEAL McBRAYER, JUDGE
    - 12 -