Clayton Ward v. Illinois Central Railroad Company ( 2013 )


Menu:
  •                 IN THE COURT OF APPEALS OF TENNESSEE
    AT JACKSON
    May 21, 2013 Session
    CLAYTON WARD v. ILLINOIS CENTRAL RAILROAD COMPANY
    Direct Appeal from the Circuit Court for Shelby County
    No. CT-006235-07     Jerry Stokes, Judge
    No. W2012-01839-COA-R3-CV - Filed June 20, 2013
    Appellant, former employee of Appellee railroad, appeals the trial court’s grant of
    Appellee’s motion for summary judgment on the ground of preclusion. Appellant filed this
    lawsuit under the Federal Employers’ Liability Act, seeking damages for injuries he allegedly
    suffered as a result of walking on ballast in Appellant’s railyard. Appellee moved for
    summary judgment on the ground that Appellant’s claim concerning ballast was precluded
    by the Federal Railroad Safety Act regulation 49 C.F.R. § 213.103. The trial court granted
    summary judgment, concluding that Appellant failed to meet his burden to negate Appellee’s
    proof that it complied with 49 C.F.R. § 213.103. We have determined that Appellant satisfied
    his burden of production to negate Appellee’s proof regarding whether the ballast rock at
    issue provided adequate drainage in compliance with 49 C.F.R. § 213.103, making summary
    judgment inappropriate. Reversed and remanded.
    Tenn. R. App. P. 3. Appeal as of Right; Judgment of the Circuit Court Reversed and
    Remanded
    J. S TEVEN S TAFFORD, J., delivered the opinion of the Court, in which A LAN E. H IGHERS,
    P.J.,W.S., and H OLLY M. K IRBY, J., joined.
    Chester H. Lauck, III, Little Rock, Arkansas, for the appellant, Clayton Ward.
    S. Camille Reifers and Brooks E. Kostakis, Memphis, Tennessee, for the appellee, Illinois
    Central Railroad Company.
    OPINION
    I. Factual and Procedural History
    This is the second appeal of this case. In Ward v. Illinois Central R. R. Co., No.
    W2012-00950-COA-R9-CV, 
    2011 WL 255146
     (Tenn. Ct. App. Jan. 20, 2011) (“Ward I”),
    this Court granted Appellee Illinois Central Railroad Company’s (“ICRR”) request for
    interlocutory appeal to address the question of whether Appellant Clayton Ward’s claims
    were barred by the applicable three-year statute of limitations. The trial court denied ICRR’s
    motion for summary judgment on the statute of limitations ground. In Ward I, we affirmed
    the trial court, holding that there was a dispute of fact concerning when Mr. Ward discovered
    his injury, and that the trial court was correct in denying the railroad summary judgment at
    that time. A full recitation of the factual history of the case is set out in Ward I. In the
    interest of continuity and judicial economy, we restate the relevant facts here:
    Clayton Ward . . . began working for Illinois Central
    Railroad Company . . . as a carman in April of 2003, when he
    was thirty years old. Initially, he worked inside a car shop,
    where he inspected and repaired train cars. After four to five
    months, however, he began working outside in the train yard,
    where he was required to walk along the length of the trains and
    inspect the railcars for defects.
    Toward the end of 2004, [Mr. Ward] began to experience
    swelling and pain in his left ankle. [Mr. Ward] could not recall
    any particular activity that he was engaged in when he first felt
    pain in his ankle. He said he had no “warning symptoms,” but
    the pain gradually got worse every day for a couple of weeks.
    [Mr. Ward] described the pain and swelling as “mainly
    constant,” and he said he did not get any relief from his
    symptoms at night. [Mr. Ward] said that his ankle would hurt
    worse when he walked on the ballast when inspecting trains, but
    that he had problems walking at home as well. He had no
    problems with his right ankle.
    After experiencing these symptoms for two to three
    weeks, [Mr. Ward] sought medical attention at Campbell Clinic
    in November 2004. An orthopedic surgeon diagnosed [Mr.
    Ward] with posterior tibial tendinitis. He gave [Mr. Ward] a
    “walking boot,” ordered physical therapy, and placed him on
    medical leave from his employment. [Mr. Ward] was later told
    to discontinue physical therapy and to limit movement of his
    ankle. Thereafter, he was placed in an “Aircast” brace. In April
    of 2005, [Mr. Ward] was released from his physician's care and
    allowed to return to work. According to Plaintiff, his ankle
    -2-
    seemed to be fine at that point. Plaintiff passed a required
    medical examination and was determined to be qualified by
    Illinois Central's Medical Department, whose findings included
    a “normal [left] ankle [and] foot exam.”
    [Mr. Ward] was not placed under any work restrictions
    by his physician, but for whatever reason, when he returned to
    Illinois Central, he went to work inside the car shop again. He
    worked there for approximately two years until April of 2007,
    when he accepted a position in the train yard performing the
    same duties that he had previously performed there. Around
    June of 2007, [Mr. Ward] again began to experience pain and
    swelling in his left ankle. He was again diagnosed with posterior
    tibial tendinitis, and he underwent surgery in order to have his
    damaged tendon replaced in October 2007.
    Ward I, 
    2011 WL 255146
    , at *1.
    According to his deposition testimony, Mr. Ward described Johnston Yard as “where
    the trains come in and leave from,” and further testified that his job as a carman in the yard
    required him to “walk and inspect each inbound and outbound train.” Mr. Ward further
    stated that when he was assigned to a particular section of Johnston Yard, he was required
    to inspect any train that came in on any track in that section of the yard. As noted above, Mr.
    Ward began to experience pain and swelling in his left ankle, which he described as “mainly
    constant.” When asked whether there were any particular activities that exacerbated his
    ankle pain, Mr. Ward stated in his deposition: “Just inspecting trains, walking on the ballast.”
    On December 17, 2007, Mr. Ward filed a complaint against Appellee Illinois Central
    Railroad Company (“ICRR”). The complaint, which was filed pursuant to the Federal
    Employers’ Liability Act (“FELA”), 45 U.S.C. § 51 et seq., alleged that, “[d]uring his tenure
    with [ICRR], [Mr. Ward] was negligently, in whole or in part, required and instructed by
    [ICRR] to work in unsafe working conditions that required him to walk for long periods of
    time on hard, uneven surfaces.”1 Mr. Ward alleged that these conditions “ultimately resulted
    1
    45 U.S.C.A. § 51 provides, in relevant part:
    Every common carrier by railroad while engaging in commerce ... shall be
    liable in damages to any person suffering injury while he is employed by
    such carrier in such commerce, ... for such injury or death resulting in
    whole or in part from the negligence of any of the officers, agents, or
    (continued...)
    -3-
    in a severe and permanently disabling cumulative trauma disorder to [Mr. Ward’s] left
    ankle.” ICRR filed its answer on February 21, 2008, generally denying the material
    allegations contained in the complaint, and asserting that Mr. Ward’s claims were preempted
    or precluded by federal law. Mr. Ward was granted leave to amend his complaint to specify
    the amount of damages; the amended complaint was filed on March 20, 2008. The crux of
    Mr. Ward’s complaint is that ICRR’s use of ballast in its Memphis railyard, where Mr. Ward
    worked periodically from 2003 until 2007, was not reasonably safe. He alleges that his job
    duties as carman, which included walking alongside tracks on a ballast surface while
    inspecting trains, caused or contributed to his diagnosed condition of posterior tibial
    tendonitis in his left ankle in November of 2004, and subsequent surgery for that injury in
    February of 2007.
    On March 28, 2012, ICRR filed a motion for summary judgment on the ground of
    federal preemption or preclusion of all claims asserted by Mr. Ward. In support of its
    motion, ICRR provided the affidavit of its Assistant Chief Engineer, Montie Chapman. In
    relevant part, Mr. Chapman testified that ICRR had complied with Federal Railroad Safety
    Act (“FRSA”), 49 C.F.R. § 213.103, see further discussion infra.
    Specifically, Mr. Chapman testified that, during Mr. Ward’s tenure with ICRR, ICRR
    used ballast in its operations. Mr. Chapman stated that the ballast: (1) transmits and
    distributes the load of the track and railroad rolling equipment to the subgrade; (2) restrains
    the track laterally, longitudinally, and vertically under dynamic loads imposed by railroad
    equipment and thermal stress exerted by the rails; (3) provides adequate drainage for the
    track; and (4) maintains proper track crosslevel, surface and alignment.
    On April 27, 2012, Mr. Ward filed a response in opposition to ICRR’s motion for
    summary judgment. The motion was heard by the trial court on May 4, 2012. By Order of
    May 23, 2012, the trial court granted ICRR’s motion for summary judgment. The trial
    court’s order states, in relevant part, that:
    This matter came to be heard on May 4, 2012, on [ICRR’s]
    Motion for Summary Judgment based on federal preemption.
    The Court has fully considered the pleadings, the affidavit of
    1
    (...continued)
    employees of such carrier, or by reason of any defect or insufficiency, due
    to its negligence, in its cars, engines, appliances, machinery, track, roadbed,
    works, boats, wharves, or other equipment.
    -4-
    Montie Chapman, the authorities submitted by the parties, the
    arguments of counsel, the entire record in this cause, and the
    Sixth Circuit’s holding in Nickels v. Grand Trunk Western R.R.,
    Inc., 
    560 F.3d 426
     (6th Cir. 2009). The Court finds that there
    are no material facts in dispute concerning the preemption of
    [Mr. Ward’s] claims in this action, and that [ICRR’s] motion
    should be granted.
    The Court finds that the Federal Railroad Safety Act
    (FRSA) regulation 49 C.F.R. § 213.103 substantially subsumes
    the area of requirements as to ballast size, and that [Mr. Ward’s]
    allegations in this action brought pursuant to the Federal
    Employers’ Liability Act (FELA) are preempted. The Court
    specifically finds that the subject matter of the lawsuit, the
    ballast utilized by . . . Illinois Central Railroad Company in
    areas where Clayton Ward worked, primarily in Johnston Yard
    (currently known as Harrison Yard) in Memphis, Tennessee, is
    preempted by the FRSA and federal law.
    On June 19, 2012, Mr. Ward filed a motion to alter or amend the judgment, which
    motion was opposed by ICRR. A hearing on the motion to alter or amend was held on July
    20, 2012. By order of July 30, 2012, the trial court denied Mr. Ward’s motion.
    II. Issues
    Mr. Ward appeals; he raises two issues for review as stated in his brief:
    1. Did the trial court err in granting summary judgment in favor
    of [ICRR] on the basis of federal preemption?
    2. Did the trial court err in denying [Mr. Ward’s] motion to alter
    or amend the order granting [ICRR’s] motion for summary
    judgment based on federal preemption?
    III. Standard of Review
    A motion for summary judgment should be granted only “if the pleadings, depositions,
    answers to interrogatories, and admissions on file, together with the affidavits, if any, show
    that there is no genuine issue as to any material fact and that the moving party is entitled to
    a judgment as a matter of law.” Tenn. R. Civ. P. 56.04. “The party seeking the summary
    -5-
    judgment has the burden of demonstrating that no genuine disputes of material fact exist and
    that it is entitled to a judgment as a matter of law.” Green v. Green, 
    293 S.W.3d 493
    , 513
    (Tenn. 2009) (citing Martin v. Norfolk S. Ry., 
    271 S.W.3d 76
    , 83 (Tenn. 2008); Amos v.
    Metro. Gov't of Nashville & Davidson County, 
    259 S.W.3d 705
    , 710 (Tenn. 2008)).
    “A moving party who seeks to shift the burden of production to the nonmoving party
    who bears the burden of proof at trial must either: (1) affirmatively negate an essential
    element of the nonmoving party's claim; or (2) show that the nonmoving party cannot prove
    an essential element of the claim at trial.” Hannan v. Alltel Publ'g Co., 
    270 S.W.3d 1
    , 9
    (Tenn. 2008) (footnote omitted).2 “It is not enough for the moving party to challenge the
    nonmoving party to ‘put up or shut up’ or even to cast doubt on a party's ability to prove an
    element at trial.” Id. at 8. If the moving party makes a properly supported motion, the burden
    of production shifts to the nonmoving party to establish the existence of a genuine issue of
    material fact. Byrd v. Hall, 
    847 S.W.2d 208
    , 215 (Tenn. 1993).
    The resolution of a motion for summary judgment is a matter of law, which we review
    de novo with no presumption of correctness. Martin, 271 S.W.3d at 84. However, “we are
    required to review the evidence in the light most favorable to the nonmoving party and to
    draw all reasonable inferences favoring the nonmoving party.” Id. (citing Staples v. CBL &
    Assocs., Inc., 
    15 S.W.3d 83
    , 89 (Tenn. 2000)).
    The material facts in the instant case are undisputed. The sole question is whether Mr.
    Ward’s claims, filed under the FELA, are precluded by the FRSA. This inquiry is a question
    of law that is subject to de novo review on appeal. Leggett v. Duke Energy Corp., 
    308 S.W.3d 843
    , 851 (Tenn. 2010) (quoting Friberg v. Kan. City S. Ry. Co., 
    267 F.3d 439
    , 442
    (5th Cir. 2001)).
    IV. Railway Safety Regulation Preemption/Preclusion History
    We begin our analysis with a semantic distinction that is often confused in our
    caselaw—that is, the distinction between preemption and preclusion. As noted in Joseph
    Mark Miller, Federal Preemption & Preclusion: Why the Federal Railroad Safety Act Should
    Not Preclude the Federal Employer's Liability Act, 51 Loy. L.Rev. 947, n.7 (Winter 2005),
    “preemption” occurs when federal law bars state law. “Preclusion” occurs when one federal
    law bars another federal law. Mr. Miller goes on to explain:
    2
    Recently, the Tennessee General Assembly enacted a new law that modified the summary judgment
    standard in Tennessee. See Tenn. Code Ann. § 20-16-101. However, the statute applies only to cases filed
    on or after July 1, 2011. Thus, in this appeal, we apply the summary judgment standard set forth in Hannan.
    -6-
    The source of the preemption doctrine is most often
    attributed by scholars to the Supremacy Clause of the
    Constitution, which declares that the laws of the United States
    shall be the supreme law of the land. U.S. Const. art. VI, cl. 2.
    Express preemption occurs when a federal statute explicitly
    excludes state regulation in a particular area. Field preemption
    occurs when a federal regulation is so “pervasive” that courts
    infer that Congress intended to occupy the field entirely and
    exclude all state law. Finally, conflict preemption occurs when
    a federal regulation conflicts with a state law, which is
    “overridden.”
    Id. at n.6 (internal citations omitted).
    It is well settled that a federal regulation adopted pursuant to the FRSA preempts any
    state “law, rule, regulation, order or standard relating to railroad safety” that covers the same
    subject matter as the federal regulation. 49 U.S.C.A. § 20106(a)(2). This includes state tort
    claims. CSX Transp., Inc. v. Easterwood, 
    507 U.S. 658
    , 664 (1993); Emery v. Southern Ry.
    Co., 
    866 S.W.2d 557
    , 561 (Tenn. Ct. App. 1993). In the instant case, however, the question
    is not whether state law is preempted by the federal law, but rather, whether the FELA is
    precluded by the federal regulations set forth in the FRSA.
    In order to answer this question, we begin with a discussion of the relevant caselaw
    dealing with questions of preemption and/or preclusion by passage of railroad safety
    regulations. In CSX Transp., Inc. v. Easterwood, 
    507 U.S. 658
    , 664 (1993), the United
    States Supreme Court stated, in relevant part:
    FRSA was enacted in 1970 “to promote safety in all areas of
    railroad operations and to reduce railroad-related accidents, and
    to reduce deaths and injuries to persons....” 45 U.S.C. § 421. To
    aid in the achievement of these goals, the Act specifically directs
    the Secretary of Transportation to study and develop solutions
    to safety problems posed by grade crossings. § 433. In addition,
    the Secretary is given broad powers to “prescribe, as necessary,
    appropriate rules, regulations, orders, and standards for all areas
    of railroad safety . . . .” § 431(a). The pre-emptive effect of these
    regulations is governed by § 434, which contains express saving
    and pre-emption clauses. Thus, the States are permitted to
    “adopt or continue in force any law, rule, regulation, order, or
    standard relating to railroad safety until such time as the
    -7-
    Secretary has adopted a rule, regulation, order, or standard
    covering the subject matter of such State requirement.” Even
    after federal standards have been promulgated, the States may
    adopt more stringent safety requirements “when necessary to
    eliminate or reduce an essentially local safety hazard,” if those
    standards are “not incompatible with” federal laws or
    regulations and not an undue burden on interstate commerce.
    CSX Transp., Inc. v. Easterwood, 
    507 U.S. 658
    , 661-62 (1993) (footnote omitted). The
    Easterwood Court further noted that “[a]ccording to § 434, applicable federal regulations
    may pre-empt any state ‘law, rule, regulation, order, or standard relating to railroad safety.’
    Legal duties imposed on railroads by the common law fall within the scope of these broad
    phrases.” Id. at 664.
    In analyzing the railroad’s preemption argument concerning plaintiff’s common law
    claim based upon the alleged speed of the train, the Easterwood Court noted that train speed
    had specifically been addressed by the Secretary of Transportation and corresponding
    regulations that covered the subject matter at issue, to wit:
    Federal regulations issued by the Secretary pursuant to FRSA
    and codified at 49 CFR § 213.9(a) (1992) set maximum
    allowable operating speeds for all freight and passenger trains
    for each class of track on which they travel. The different
    classes of track are in turn defined by, inter alia, their gage,
    alignment, curvature, surface uniformity, and the number of
    crossties per length of track. See §§ 213.51-213.143. The track
    at the Cook Street crossing is class four, for which the maximum
    speed is 60 miles per hour. Although respondent concedes that
    petitioner's train was traveling at less than 60 miles per hour, she
    nevertheless contends that petitioner breached its common-law
    duty to operate its train at a moderate and safe rate of speed. See,
    e.g., Central of Georgia R. Co. v. Markert, 200 Ga.App. 851,
    852, 
    410 S.E.2d 437
    , 438, cert. denied, 200 Ga.App. 895 (1991).
    Petitioner contends that this claim is pre-empted because the
    federal speed limits are regulations covering the subject matter
    of the common law of train speed.
    On their face, the provisions of § 213.9(a) address only the
    maximum speeds at which trains are permitted to travel given
    the nature of the track on which they operate. Nevertheless,
    -8-
    related safety regulations adopted by the Secretary reveal that
    the limits were adopted only after the hazards posed by track
    conditions were taken into account. Understood in the context
    of the overall structure of the regulations, the speed limits must
    be read as not only establishing a ceiling, but also precluding
    additional state regulation of the sort that respondent seeks to
    impose on petitioner.
    Easterwood, 507 U.S. at 673–74 (footnote omitted). Accordingly, the Easterwood Court
    concluded that the plaintiff’s excessive speed claim “cannot stand in light of the Secretary’s
    adoption of the regulation in § 213.9,” and held that “federal regulations adopted by the
    Secretary of Transportation pre-empt respondent’s negligence action only insofar as it asserts
    that petitioner’s train was traveling at an excessive speed.” Id.
    Likewise, in the case of Norfolk Southern Ry. Co. v. Shanklin, 
    529 U.S. 344
     (2000),
    the Supreme Court again addressed the question of claim preemption in the context of
    railway safety regulations dealing with railroad crossings. In Shanklin, the plaintiff, widow
    of the decedent who was killed in a railway crossing accident, brought her case in the
    Tennessee state court. Specifically, plaintiff alleged that the defendant railroad had failed
    to maintain adequate warning devices at the grade crossing. The Supreme Court ultimately
    held that “the FRSA pre-empts respondent’s state tort claim that the advance warning signs
    and reflectorized crossbucks installed at the. . .crossing were inadequate.” Id. at 358–59.
    In so ruling, the Supreme Court discussed the express preemption provision of the FRSA, 49
    U.S.C. § 20106, and the subsequent enactment by Congress of the Highway Safety Act and
    creation of the Federal Railway-Highway Crossing Program. Id. at 352–55. Through the
    Federal Highway Administration (“FHWA”), the Secretary of Transportation promulgated
    several regulations implementing the crossings program that addressed the design of
    crossing improvements. Id. Applying Easterwood and other applicable precedent concerning
    preemption, the Court held that because the Tennessee Department of Transportation had
    used federal funds for the installation of advance warning signs and reflectorized crossbucks
    (which plaintiff had alleged were inadequate), specific regulations of the FHWA governed
    the selection and installation of the devices. Therefore, once the installation project was
    approved by the FHWA and the signs were installed using federal funds, “the federal
    standard for adequacy displaced Tennessee statutory and common law addressing the same
    subject, thereby pre-empting respondent’s claim.” Id. at 358–59. Accordingly, the
    preemption provision of the FRSA was applied to preempt the plaintiff’s state claims
    alleging inadequate crossing devices.
    In Waymire v. Norfolk & Western Railway Co., 
    218 F.3d 773
    , 774 (7th Cir. 2000),
    a train was involved in an accident with a truck at a railroad crossing. One of the railroad's
    -9-
    employees claimed he was injured and sued the railroad, alleging that it was negligent in
    allowing the train to travel at an unsafe speed and in failing to install additional warning
    devices at the railroad crossing. Id. However, the train was traveling well below the speed
    limit set by FRSA regulations, and the crossing was equipped with warning devices that were
    installed and approved in accordance with FRSA regulations. Id. The Seventh Circuit
    concluded that “in order to uphold FRSA's goal of uniformity,” the employee's FELA
    negligence claims should be superseded by the FRSA regulations. Id. at 776. Specifically,
    the Waymire Court stated:
    We are persuaded by the Supreme Court's reasoning [in
    Easterwood] and find that in order to uphold FRSA's goal of
    uniformity we must strike the same result. See 49 U.S.C. §
    20106 (“Laws, regulations, and orders related to railroad safety
    shall be nationally uniform to the extent practicable.”). In
    Easterwood, the train was operating within the FRSA prescribed
    60 miles per hour speed limit, as was N & W's train in this case.
    It would thus seem absurd to reach a contrary conclusion in this
    case when the operation of both trains was identical and when
    the Supreme Court has already found that the conduct is not
    culpable negligence.
    We are not alone in our conclusion. Of the other courts
    who have been presented with the issue as it relates to FELA
    and FRSA, two have held that the FELA plaintiff's unsafe speed
    claim cannot stand in light of the Secretary's adoption of the
    speed regulations in 49 C.F.R. Pt. 213. See Rice v. Cincinnati,
    New Orleans & Pacific Railway Company, 
    955 F. Supp. 739
    ,
    740-41 (E.D. Ky. 1997) and Thirkill v. J.B. Hunt Transport,
    Inc., 
    950 F. Supp. 1105
    , 1107 (N.D. Ala. 1996). Only one other
    court has reached the opposite result. See Earwood v. Norfolk
    Southern Railway Company, 
    845 F. Supp. 880
     (N.D. Ga.
    1993). We believe the former result to be the correct result in
    light of FRSA's goal of uniformity and the Supreme Court's
    holding in Easterwood and thus hold that Waymire's negligence
    claim based upon the speed of the train is superseded by FRSA
    and the regulations promulgated thereunder. The judgment of
    the District Court is affirmed in this regard.
    Waymire, 218 F.3d at 776; accord Lane v. R.A. Sims, Jr., Inc., 
    241 F.3d 439
    , 443–44 (5th
    Cir. 2001); Dickerson v. Staten Trucking, Inc., 
    428 F. Supp. 2d 909
    , 914 (E.D. Ark. 2006);
    -10-
    In re: Amtrak “Sunset Limited” Train Crash in Bayou Canot, Ala., on Sept. 22, 1993, 
    188 F. Supp. 2d 1341
    , 1348-49 (S.D. Ala.2000); Rice v. Cincinnati, New Orleans, & Pac. Ry. Co.,
    
    955 F. Supp. 739
    , 741 (E.D. Ky.1997). However, as noted by the Waymire Court, other courts
    have reached the opposite conclusion, holding that FELA claims are not preempted or
    precluded by FRSA regulations. See, e.g., Earwood v. Norfolk S. Ry. Co., 
    845 F. Supp. 880
    ,
    885 (N.D. Ga. 1993) (“The Court concludes that Plaintiff's FELA claims are not precluded
    by FRSA. The two statutes do not purport to cover the same areas . . . . Neither the FRSA nor
    the regulations purport to define the standard of care with which railroads must act with
    regard to employees.”); see further Myers v. Ill. Cent. R.R. Co., 323 Ill.App.3d 780, 
    257 Ill. Dec. 365
    , 
    753 N.E.2d 560
    , 565 (Ill. Ct. App. 2001) (“If Congress had intended FRSA to
    abolish FELA remedies for railroad employees, we believe Congress would have said so
    explicitly.”). Thus, the Waymire holding that FELA negligence claims can be precluded
    when a railroad is in compliance with FRSA regulations is by no means universally adopted.
    See Joseph Mark Miller, Federal Preemption & Preclusion: Why the Federal Railroad Safety
    Act Should Not Preclude the Federal Employer's Liability Act, 51 Loy. L.Rev. 947 (Winter
    2005) (discussing cases). However, the majority of cases decided since Easterwood have
    consistently held that the preemptive and/or preclusive effect of federal railroad safety
    regulations is applicable where the FRSA regulation “‘substantially subsume[s]’ the subject
    matter of the suit.” Nickles v. Grand Truck Western R.R., Inc., 
    560 F.3d 426
    , 429 (6 th Cir.
    2009) (citing Easterwood, 507 U.S. at 664)). The question, then, is whether the specific
    FRSA regulation concerning ballast, 49 C.F.R. § 213.103, “substantially subsumes” the
    subject matter of Mr. Ward’s lawsuit. We now turn to address that question.
    V. Nickels v. Grand Trunk Western R. R., Inc., 
    560 F.3d 426
     (6th Cir. 2009).
    In Nickels v. Grand Trust Western R. R., Inc., 
    560 F.3d 426
     (6th Cir. 2009), the Sixth
    Circuit explicitly held that a federal regulation promulgated by the Secretary of
    Transportation “substantially subsumes the issue of ballast size.” Id. at 430. Accordingly,
    the Sixth Circuit affirmed the District Court’s decision to enter summary judgment against
    railroad employees who brought claims under the FELA, alleging injuries sustained from
    years of walking on “oversized” ballast. As in the instant case, in Nickels, the plaintiffs
    claimed that the railroad failed to provide a safe working environment when it used large
    mainline ballast, rather than smaller yard ballast underneath and adjacent to tracks receiving
    heavy foot traffic.3 Id. at 428. The defendant railroad moved for summary judgment on the
    ground of preemption under the FRSA. The District Court granted the railroad’s motion,
    concluding that to allow the plaintiffs to maintain their FELA claims would undermine the
    3
    As explained by the Nickels Court, “[t]rack ballast is the stone or other material placed underneath
    and around railroad tracks to provide the structural support, drainage, and erosion protection necessary for
    safe rail travel.” Nickels, 560 F.3d at 428.
    -11-
    FRSA’s express intent to achieve national uniformity in railroad safety regulations. Id. On
    appeal, the Sixth Circuit applied a de novo review to the District Court’s ruling. The Court
    noted that the case required it to examine the interplay between two federal statutes, both of
    which were designed to promote railway safety, the FELA and the FRSA. Id. The Sixth
    Circuit cited the FRSA’s preemption provision, providing that a plaintiff can bring an action
    under state law unless the Secretary of Transportation has prescribed a regulation or issued
    an order “covering the subject matter of the State requirement.” Id. at 430 (citing 49 U.S.C.
    § 20106). The Nickels Court recognized that: “A state-law negligence action is ‘covered’
    and therefore preempted if a FRSA regulation ‘substantially subsume[s]’ the subject matter
    of the suit.” Nickels, 560 F.3d at 429. The Sixth Circuit then noted that the Secretary has
    promulgated 49 C.F.R. § 213.103 on ballast. This is the same regulation that is at issue in
    the instant case; it provides:
    Unless it is otherwise structurally supported, all track shall be
    supported by material which will --
    (a) Transmit and distribute the load of the track and railroad
    rolling equipment to the subgrade;
    (b) Restrain the track laterally, longitudinally, and vertically
    under dynamic loads imposed by railroad rolling equipment and
    thermal stress exerted by the rails;
    (c) Provide adequate drainage for the track; and
    (d) Maintain proper track crosslevel, surface, and alignment.
    In relevant part, the Nickels Court noted that, “[r]ather than prescribing ballast sizes
    for certain types or classes of track, the regulation leaves the matter to the railroads’
    discretion so long as the ballast performs the enumerated support functions.” Nickels, 560
    F.3d at 431. The Nickels Court further concluded that “the regulation substantially subsumes
    the issue of ballast size.” Id. Accordingly, the Sixth Circuit held that “in § 213.103 the
    Secretary has directed railroads to install ballast sufficient to perform key support functions
    under the conditions applicable to the track. . . . The regulation thus determines what is a
    reasonable ballast composition and size for a particular track.” Id.
    As discussed above, the Nickels Court undisputedly held that ballast related claims
    are covered, i.e., preempted or precluded by FRSA regulation 49 C.F.R. § 213.103. In his
    brief, Mr. Ward devotes a majority of his argument to persuade this Court to deviate from
    the Sixth Circuit’s holding in Nickels. After considering his arguments, we respectfully
    decline to do so. Despite Appellant’s argument that the reasoning in Nickels is flawed, it is
    beyond dispute that Tennessee has adopted the Nickels analysis in cases involving the
    defense of preclusion or preemption of claims brought by FELA plaintiffs. In Melton v.
    -12-
    BNSF Railway Co., 
    322 S.W.3d 174
     (Tenn. Ct. App. 2010), this Court stated:
    The Sixth Circuit Court of Appeals has recently held that,
    “the uniformity demanded by the [Federal Railway Safety Act,
    49 U.S.C. § 20101, et seq. (“FRSA”) ] can be achieved only if
    federal rail safety regulations are applied similarly to a FELA
    plaintiff's negligence claim....” Nickels v. Grand Trunk Western
    R.R., Inc., 
    560 F.3d 426
    , 430 (6th Cir.2009)(citing Lane v. R.A.
    Sims, Jr., Inc., 
    241 F.3d 439
    , 443 (5th Cir.2001); and Waymire
    v. Norfolk & W. Ry. Co., 
    218 F.3d 773
    , 776 (7th Cir.2000)).
    Thus, if there is a federal regulation prescribed under FRSA,
    plaintiff's claims are preempted. As noted by the Nickels court,
    the Secretary of Transportation has promulgated a regulation on
    ballast and, therefore, negligence claims based on ballast may be
    preempted. Id. (citing 49 C.F.R. § 213.103). Similarly, there is
    also a regulation under FRSA on vegetation and claims based on
    vegetation consequently, may also be preempted. See 49 C.F.R.
    § 213.37.
    However, to be preempted the railroad must be in
    compliance with the federal regulations. Michael v. Norfolk
    Southern Ry. Co., 
    74 F.3d 271
    , 273 (11th Cir.1996). If the
    railroad is not in compliance, then the claim is not preempted.
    Id. While preemption is a question of law, Nickels, 560 F.3d at
    429, whether the railroad was complying with the federal
    regulation at issue is a question of fact. Id.
    Melton, 322 S.W.3d at 190. In Melton, this Court reversed the grant of summary judgment
    in favor of the railroad on the ground of preemption because the defendant had “not
    affirmatively shown that it was in compliance with the federal regulations.” Id. at 190. We
    will address the question of whether there is any dispute within the record concerning
    whether ICRR complied with 49 C.F.R. § 213.103 below. However, before turning to that
    question, we first address Mr. Ward’s argument that the Nickels holding is inapplicable to
    his particular claims.
    VI. Whether Mr. Ward’s Ballast Claims are Distinguishable from the Nickels Claims
    Mr. Ward argues that 49 C.F.R. § 213.03, “on its face, does not require the use of
    ballast in rail yard areas or mention the safety of walking surfaces for railroad employees.”
    Although we concede that some courts outside of Tennessee and the Sixth Circuit have found
    the Nickels analysis to be distinguishable based on the use of “mainline” ballast and “yard”
    -13-
    ballast, as noted above, the Nickels Court explicitly held that “the regulation [i.e., 49 C.F.R.
    § 213.03] substantially subsumes the issue of ballast size,” and that “in § 213.03 the
    Secretary has directed railroads to install ballast sufficient to perform key support functions
    under the conditions applicable to the track . . . . The regulation thus determines what is a
    reasonable ballast composition and size for a particular track.” Nickels, 560 F.3d at 431. It
    is undisputed in the record that the track in the Johnston Yard, where Mr. Ward worked from
    2004 until 2007, used ballast in its operations to perform the essential functions contemplated
    by the FRSA at 49 C.F.R. § 213.103. Although Mr. Ward urges this Court to conclude that
    walkways and ballast are distinguishable in a railyard, in the instant case, this is a distinction
    without a difference. As Mr. Ward states in his deposition, “the yard is the tracks.” In other
    words, carmen are required to walk the tracks themselves, which are supported by ballast.
    The ballast, therefore, are the walkways. At oral argument, Mr. Ward’s attorney couched Mr.
    Ward’s claim as “whether walkways are covered” under the federal regulation. He further
    stated that “walkways are distiguish[able] from ballast.” As a hypothetical, Mr. Ward’s
    attorney stated that, under the Nickels holding, “anywhere [ICRR] put ballast rock [e.g.,
    inside its offices] would be precluded under [the FRSA, 49 C.F.R.§ 213.103].” Although
    Mr. Ward’s counsel makes a cogent argument, we are not persuaded that simply putting
    ballast materials (e.g., rock) in a location, ipso facto, makes that location a ballast (i.e., a
    support structure for a rail line). Rather, it is clear from our review of the record that Mr.
    Ward’s claims arise from the composition, or type of ballast employed for use in ICRR’s
    Johnston Yard. By his own testimony, Mr. Ward states that his injuries were caused by his
    work “inspecting trains, walking on the ballast.” In short, the crux of Mr. Ward’s claim is
    that he was injured by walking on ballast in the yard. These types of claims have been found
    to be encompassed within the Sixth Circuit’s holding in Nickels. For example, in Munns v.
    CSX Transp., Inc., No. 3:07CV2507, 
    2009 WL 805133
     (N.D. Ohio Mar. 27, 2009), the
    United States District Court for the Northern District of Ohio summarized that plaintiff’s
    claims as follows:
    Plaintiff claims that CSX used “mainline”-i.e., larger-ballast in
    areas of the Willard yard and elsewhere where it could have
    used smaller “yard” ballast to support its track, provide drainage
    and fulfill the other functions for which ballast is employed. The
    gravamen of plaintiff's contention about unsuitable ballast
    appears to be that mainline ballast, being bigger, creates a more
    uneven surface, is more difficult to walk upon and creates more
    physical stress than the smaller yard ballast.
    Munns, 
    2009 WL 805133
     at *3. In Munns, the District Court was unpersuaded by
    plaintiff’s attempt to avoid the railroad defendant’s preclusion defense, to wit:
    -14-
    Under the Federal Railway Safety Act [FRSA], 49 U.S.C. §
    20101 et seq., the Secretary of Transportation has adopted a
    regulation relating to ballast. 49 C.F.R. § 213.103. Rejecting
    contentions similar to those made here by the plaintiff that the
    regulation does not preempt ballast-related FELA claims, the
    Sixth Circuit held in Nickels v. Grand Trunk Western R.R.,
    Inc.., 
    560 F.3d 426
    , ---- 
    2009 WL 691040
    , *6 (6th Cir.), that
    “[b]ecause 49 C.F.R. § 213.103 covers the issue of ballast size
    . . . [it] precludes the plaintiffs’ FELA claims.”
    Munns, 
    2009 WL 805133
    , at *3 (footnote omitted). Rather, the Munns Court reiterated the
    holding in Nickels: “Nickels holds that the FRSA is preemptive as to claims of individual
    injury from using ballast in areas where railway employees will be walking.” Id. at *4
    (emphasis added); see also Kresel v. BNSF Ry. Co., No. 09-CV-2861, 
    2011 WL 1456766
    ,
    at *8 (D. Minn. April 15, 2011) (noting that the controlling factor in determining preemption
    under the FRSA is the undisputed fact that the plaintiff was standing immediately adjacent
    to the track and upon the ballast that was serving the functions of 49 C.F.R. § 213.103).
    In the recent case of Brenner v. Consolidated Rail Corp, 
    806 F. Supp. 786
     (E.D.
    Penn. April 18, 2011), the District Court addressed a claim that is nearly identical to that
    averred by Mr. Ward. In Brenner, the plaintiff’s claimed cumulative trauma injury to his
    knees from walking on ballast in a rail yard. The District Court found plaintiff’s claims were
    precluded by FRSA regulation 29 C.F.R. § 213.103. The Brenner Court examined the
    evidence in light of the Nickels holding, and determined that the railroad employee, similar
    to Mr. Ward’s claim in the instant case, alleged that his cumulative trauma injuries were
    caused by “walking on uneven or unleveled ballast.” Brenner, 806 F. Supp. at 795. The
    court noted that plaintiff’s claims related almost entirely to track ballast. Id. at 796.
    Ultimately, the Brenner Court held that “to the extent that Plaintiff’s claims are predicated
    upon allegations of negligence regarding the nature and size of ballast used for track
    stability, support, and drainage—including mainline, secondary and yard track—such
    claims are precluded by 49 C.F.R. § 213.103.” Id. (emphases added). Likewise, in the
    instant case, it is undisputed that Mr. Ward’s claims relate to injuries he allegedly sustained
    as a result of the nature (i.e., design, orientation, size, levelness) of the ballast used by ICRR
    in its Johnston Yard. Accordingly, under the foregoing authority, if there is no dispute as to
    whether ICRR complied with 49 C.F.R. § 213.103, Mr. Ward’s claims are precluded by the
    FRSA regulation. We now turn to address that question.
    VII. Burden Shifting
    As discussed by the Melton Court, “to be preempted the railroad must be in
    -15-
    compliance with the federal regulations.” Melton, 322 S.W.3d at 190 (citation omitted). “If
    the railroad is not in compliance, then the claim is not preempted.” Id. (citation omitted).
    While preemption is a question of law, Nickels, 560 F.3d at 429, whether the railroad was
    complying with the federal regulation at issue is a question of fact. Id.
    As discussed above, when a motion for summary judgment is made, the moving party
    has the burden of showing that “there is no genuine issue as to any material fact and the
    moving party is entitled to judgment as a matter of law.” Tenn. R. Civ. P. 56.04. The moving
    party may accomplish this by either: (1) affirmatively negating an essential element of the
    non-moving party's claim; or (2) showing that the non-moving party will not be able to prove
    an essential element at trial. Hannan v. Alltel Publ'g Co., 
    270 S.W.3d 1
    , 8–9 (Tenn. 2008).
    However, “[i]t is not enough for the moving party to challenge the nonmoving party to ‘put
    up or shut up’ or even to cast doubt on a party's ability to prove an element at trial.” Id. at 8.
    Turning to the record, in support of its motion for summary judgment, ICRR
    submitted the affidavit of Montie Chapman, ICRR’s Assistant Chief Engineer. In relevant
    part, Mr. Chapman testified:
    I have been an employee of [ICRR] since 1977. . . .
    2. The statements contained in this Affidavit are based upon my
    personal knowledge. I am competent to testify to the matters
    herein based on my training and experience, and my knowledge
    and understanding of maintenance and safety practices and
    protocols at [ICRR].
    3. At all times during Clayton Ward’s employment at Illinois Central,
    Illinois Central utilized ballast in its operations . . . . The ballast
    utilized by Illinois Central is in compliance with federal regulation 49
    C.F.R. § 213.103.
    From his affidavit, it is undisputed that, based on his position with ICRR, Mr.
    Chapman is qualified to testify as to ICRR’s compliance with the ballast requirements
    contained in 49 C.F.R. § 213.103, including the requirement that the ballast provide adequate
    drainage.4 His testimony is based upon his personal knowledge of railroad operations, as
    4
    In the trial court, Mr. Ward objected to the use of Mr. Chapman’s affidavit to shift the burden of
    production on the ground that Mr. Chapman was not disclosed as an expert pursuant to Rule 26.02 of the
    Tennessee Rules of Civil Procedure. In addition, Mr. Ward argued that ICRR failed to disclose any
    (continued...)
    -16-
    well as his familiarity with maintenance and safety practices. Accordingly, Mr. Chapman’s
    affidavit effectively shifted the burden of production to Mr. Ward. Because ICRR’s summary
    judgment motion was properly supported, “[t]he burden of production then shifts to the
    nonmoving party to show that a genuine issue of material fact exists.” Hannan v. Alltel
    Publ'g Co., 270 S.W.3d at 5. The non-moving party may accomplish this by: “(1) pointing
    to evidence establishing material factual disputes that were overlooked or ignored by the
    moving party; (2) rehabilitating the evidence attacked by the moving party; (3) producing
    additional evidence establishing the existence of a genuine issue for the trial; or (4)
    submitting an affidavit explaining the necessity for further discovery pursuant to Tenn. R.
    Civ. P. 56.06.” Martin v. Norfolk S. Ry. Co., 
    271 S.W.3d 76
    , 84 (Tenn. 2008) (citations
    omitted).
    In response to Mr. Chapman’s testimony that ICRR complied with the FRSA
    regulation, Mr. Ward proferred the deposition testimonies of his co-workers Gene Bolden,
    Steven Wells, and Brent Hussey for the proposition that ICRR had not fully complied with
    the mandates of 49 C.F.R. § 213.103. Messrs. Bolden, Wells, and Hussey are (or were)
    employed by ICRR as carmen, which is the same position that Mr. Ward held.
    In relevant part, Mr. Bolden testified:
    Q. Did you have any difficulties performing your job as a
    carman in the rail yards from ‘97 to 2006?
    A. Yes.
    Q. Would you describe those for me, sir?
    A. The ballast situation had not changed. The trains, the
    volume of trains that came in and out of the Johnston Yard at
    this time were—were large. We had debris in the yard. We had
    track repairs that were made that were not finished up. We had
    4
    (...continued)
    information regarding Mr. Chapman’s “experience, training, background, expected area of testimony, or
    opinions.” Despite this argument, the trial court relied on the affidavit of Mr. Chapman in granting the
    motion for summary judgment. From our review of Mr. Ward’s brief, he has apparently abandoned the claim
    that Mr. Chapman’s affidavit was inadmissible to shift the burden of production. See Doe A v. Coffee County
    Bd. of Educ., 
    925 S.W.2d 534
    , 536 n.6 (Tenn. Ct. App. 1996) (citing Maryville Housing Authority v.
    Ramsey, 
    484 S.W.2d 73
     (Tenn. Ct. App. 1972)). Accordingly, we will consider Mr. Chapman’s affidavit as
    competent evidence that ICRR complied with the ballast requirements in 49 C.F.R. § 213.103.
    -17-
    standing water. . .
    *                                     *                         *
    Q. Okay. So it’s fair to say as we sit here today you have
    testified that several times between 1997 and 2006 you saw
    debris and had to walk around it in the yard, but you cannot
    testify how many times particularly you had an issue with debris
    in the yard, correct?
    A. Yes.
    *                                     *                         *
    Q. You indicated that there was a problem with standing water.
    Where was that, sir?
    A. In C yard.
    Q. And during which time period was that an issue?
    A. From about mid spring to middle of summer and then
    anytime it came a real bad rain, water would stand in the train
    yards.
    Q. During which years?
    A. All years.
    Mr. Bolden further stated that he had never filed a complaint with ICRR regarding the
    alleged standing water, but did state that one purpose of the ballast was to ensure proper
    drainage. By his testimony, Mr. Bolden admitted that he never observed Mr. Ward while he
    was working and that he and Mr. Ward worked at different locations along the track.
    Testimony of Messrs. Wells and Hussey further established that there was debris on the
    ballast and that the ballast used by ICRR made it difficult to walk.
    Mr. Ward argues that Mr. Bolden’s testimony meets his burden to establish a dispute
    of material fact as to whether the ballast at issue “[p]rovide[d] adequate drainage for the
    track” in compliance with 49 C.F.R. § 213.103. We agree. Taking all reasonable inferences
    in Mr. Ward’s favor, as we must at this stage in the litigation, we conclude that Mr. Bolden’s
    -18-
    testimony creates an issue of material fact as to whether the ballast in place at ICRR provided
    adequate drainage in compliance with federal regulations. See Giggers v. Memphis Hous.
    Auth., 
    277 S.W.3d 359
    , 364 (Tenn. 2009) (holding that in ruling on a motion for summary
    judgment, “[c]ourts must view the evidence and all reasonable inferences therefrom in the
    light most favorable to the non-moving party”). The federal regulation clearly requires that
    the ballast “[p]rovide adequate drainage for the track.” 49 C.F.R. § 213.103. Mr. Chapman,
    in his affidavit, stated that the ballast met this requirement. To undermine this proof, Mr.
    Ward offered the testimony of Mr. Bolden, who testified that the ballast in place in at least
    a portion of the yard allowed water to stand for a significant portion of the year, every year,
    and every time there was significant precipitation. This testimony, taken in the light most
    favorable to Mr. Ward, and drawing all reasonable inferences in his favor, creates a dispute
    of material fact as to whether the ballast in place was, in fact, providing adequate drainage
    for the yard, and therefore, whether ICRR was indeed complying with 49 C.F.R. § 213.103.
    ICRR takes issue, however, with the fact that the evidence submitted by Mr. Ward
    was not expert testimony, but instead came from a lay witness who was not established as
    an expert on the use and maintenance of ballast and track. Rather, as noted above, Mr.
    Bolden, like Mr. Ward, was a carmen, charged with knowledge of mechanical repairs to
    railcars as opposed to the track system. This is a problem that the trial court noted at the
    hearing on the motion for summary judgment:
    THE COURT: So you [i.e., Mr. Ward’s attorney] want me to
    consider your lay witnesses [i.e., Messrs. Bolden, Wells, and
    Hussey] on the appropriateness of the ballast that was on the
    track but you don’t want me to consider [the] assistant chief
    [i.e., Mr. Chapman] when he talks about ballast and it was
    appropriately applied.
    MR. COWEN [attorney for Mr. Ward]: My witnesses aren’t
    talking about ballast. My witnesses are making factual
    observations at various times throughout the same period of time
    that Mr. Ward worked there in the yard. When they worked in
    the yard there’s standing water. Standing water over a period of
    time shows that they [i.e., ICRR] have not complied with the
    portion of the standard that requires [ballast to] to provide
    adequate drainage for the track.
    As discussed in detail above, the crux of Mr. Ward’s case is that he was injured by
    being required to walk on the ballast. In support of its preclusion defense, ICRR offered the
    testimony of its Assistant Chief Engineer, Mr. Chapman, who stated that the ballast used in
    -19-
    the Johnston Yard complied with the mandates of 49 C.F.R. § 213.103, including his opinion
    that the ballast “provides adequate drainage for the track.” In order to avoid preclusion, the
    burden of production then fell to Mr. Ward to create a dispute of fact as to ICRR’s
    compliance with the FRSA regulation. Thus, the question, at this stage in the litigation, is
    simply whether a dispute exists regarding whether ICRR complied with the mandates of 49
    C.F.R. § 213.103. ICRR has cited no law in which the question of whether a railroad has
    complied with 49 C.F.R. § 213.103 must be established by expert proof. From our review of
    the federal ballast regulation, the regulation concerns not the composition or installation of
    the ballast but whether the ballast is adequately serving its purpose, i.e., whether the ballast
    is allowing proper drainage. See 49 C.F.R. § 213.103. To undermine Mr. Chapman’s opinion
    that the ballast properly complied with 49 C.F.R. § 213.103, Mr. Ward offered the testimony
    of Mr. Bolden, who testified based on his observations of the railroad yard that the ballast
    allowed water to stand in the yard. Mr. Bolden’s testimony that there was standing water on
    the yard, based on his own personal knowledge, was, thus, sufficient to controvert Mr.
    Chapman’s affidavit that the ballast was providing proper drainage for the yard in
    compliance with 49 C.F.R. § 213.103. Indeed, in a similar case involving preclusion of a
    widow’s FELA claim based on improper ballast and vegetation, this Court considered
    probative testimony from similarly situated employees of the defendant railroad that
    vegetation was overgrown and could cause problems for employees. See Melton, 322 S.W.3d
    at 189–90 (considering the testimony of a railroad carmen at to what he observed in the
    railway yard). Based on this testimony, the Melton Court concluded that material issues of
    fact existed that prevented summary judgment. Id. Likewise in this case, Mr. Bolden’s
    testimony is competent to undermine Mr. Chapman’s affidavit that ICRR was fully compliant
    with 49 C.F.R. § 213.103 and create a material factual dispute on this issue.
    ICRR further points out that Mr. Bolden’s testimony concerns an area of the yard in
    which Mr. Ward undisputedly did not work. Thus, ICRR contends that Mr. Bolden’s
    testimony is “not probative.” However, this Court has noted that:
    In order to withstand a defendant’s motion for summary
    judgment, the plaintiff does not have to “show” breach and
    causation in the sense of proving those elements, but must
    simply establish by competent means that there is a dispute over
    those material issues of fact raised by the record.
    Bryant v. Bauguss, 
    1996 WL 465539
     (Tenn. Ct. App. 1996) (quoting Gambill v. Middle
    Tenn. Med. Center, Inc., 
    751 S.W.2d 145
    , 146 (Tenn. Ct. App. 1988); Bowman v. Henard,
    
    547 S.W.2d 527
    , 530–31 (Tenn.1977)). Thus, Mr. Ward is not required, at this stage, to
    prove that ICRR’s failure to comply with federal regulations, i.e., its failure to install ballast
    that provided adequate drainage, was the proximate cause of his injuries. Instead, he simply
    -20-
    must submit some competent evidence that creates a dispute over whether the ballast was in
    compliance with federal regulations. Mr. Bolden’s testimony goes directly to this issue. In
    addition, nothing in the record suggests that the ballast in C yard was any different from the
    ballast in Johnston yard where Mr. Ward worked primarily. As previously discussed, in
    ruling on a motion for summary judgment, we must give the non-moving party the benefit
    of all reasonable inferences. See Giggers, 277 S.W.3d at 364. In this case, it may be
    reasonable to assume, without any evidence to the contrary, that the ballast in C yard is the
    same as in Johnston yard. Having submitted evidence that some of the ballast in the railway
    yards was not properly draining in violation of 49 C.F.R. § 213.103, we conclude that Mr.
    Ward has met his burden to establish a material factual dispute regarding whether ICRR’s
    ballast complied with federal regulations regarding drainage. We further note that Mr.
    Ward’s burden is not to conclusively establish that there was a drainage issue with the ballast
    at the railway yard where he worked. Instead, to withstand ICRR’s motion for summary
    judgment, Mr. Ward simply had to submit competent evidence that created uncertainty as to
    whether a factual dispute exists regarding ICRR’s compliance with the federal regulation.
    As stated by our Supreme Court in Evco Corp. v. Ross, 
    528 S.W.2d 20
     (Tenn. 1975):
    The summary judgment procedure was designed to provide a
    quick, inexpensive means of concluding cases, in whole or in
    part, upon issues as to which there is no dispute regarding the
    material facts. Where there does exist a dispute as to facts which
    are deemed material by the trial court, however, or where there
    is uncertainty as to whether there may be such a dispute, the
    duty of the trial court is clear. He [or she] is to overrule any
    motion for summary judgment in such cases, because summary
    judgment proceedings are not in any sense to be viewed as a
    substitute for a trial of disputed factual issues.
    Id. at 24–25. Having met his burden to submit competent evidence calling into question
    whether ICRR was in compliance with 49 C.F.R. § 213.103, the grant of summary judgment
    was in error. See Melton, 322 S.W.3d at 190 (reversing the grant of summary judgment
    because there was a dispute as to whether the railroad complied with federal regulations).
    The judgment of the trial court is, therefore, reversed. All other issues are pretermitted.
    For the foregoing reasons, the order of the trial court granting summary judgment is
    reversed and the case is remanded for all further proceedings as may be necessary and are
    consistent with this Opinion. Costs of this appeal are assessed against the Appellee, Illinois
    Central Railroad Company, for all of which execution may issue if necessary.
    -21-
    _________________________________
    J. STEVEN STAFFORD, JUDGE
    -22-
    

Document Info

Docket Number: W2012-01839-COA-R3-CV

Judges: Judge J. Steven Stafford

Filed Date: 6/20/2013

Precedential Status: Precedential

Modified Date: 10/30/2014

Authorities (23)

Thirkill v. J.B. Hunt Transport, Inc. , 950 F. Supp. 1105 ( 1996 )

In Re Amtrak \"Sunset Ltd.\" Train Crash in Bayou Canot , 188 F. Supp. 2d 1341 ( 2000 )

Michael v. Norfolk Southern Railway Co. , 74 F.3d 271 ( 1996 )

Lane v. R.A. Sims, Jr., Inc. , 241 F.3d 439 ( 2001 )

Friberg v. Kansas City Southern Railway Co. , 267 F.3d 439 ( 2001 )

Dickerson v. Staten Trucking, Inc. , 428 F. Supp. 2d 909 ( 2006 )

Earwood v. Norfolk Southern Ry. Co. , 845 F. Supp. 880 ( 1993 )

Rice v. Cincinnati, New Orleans & Pacific Ry. Co. , 955 F. Supp. 739 ( 1997 )

Joseph J. Waymire v. Norfolk and Western Railway Company , 218 F.3d 773 ( 2000 )

Central of Georgia Railroad v. Markert , 200 Ga. App. 851 ( 1991 )

Myers v. Illinois Central Railroad , 323 Ill. App. 3d 780 ( 2001 )

Nickels v. Grand Trunk Western RR, Inc. , 560 F.3d 426 ( 2009 )

CSX Transportation, Inc. v. Easterwood , 113 S. Ct. 1732 ( 1993 )

Norfolk Southern Railway Co. v. Shanklin , 120 S. Ct. 1467 ( 2000 )

Leggett v. Duke Energy Corp. , 308 S.W.3d 843 ( 2010 )

Bowman v. Henard , 547 S.W.2d 527 ( 1977 )

Staples v. CBL & Associates, Inc. , 15 S.W.3d 83 ( 2000 )

Green v. Green , 293 S.W.3d 493 ( 2009 )

Amos v. Metropolitan Government of Nashville , 259 S.W.3d 705 ( 2008 )

Byrd v. Hall , 847 S.W.2d 208 ( 1993 )

View All Authorities »