Anchor Pipe Company, Inc. v. Sweeney-Bronze Development, LLC ( 2012 )


Menu:
  •                 IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    May 22, 2012 Session
    ANCHOR PIPE COMPANY, INC. v. SWEENEY-BRONZE
    DEVELOPMENT, LLC ET AL.
    Appeal from the Circuit Court for Sumner County
    No. 2008CV31941       C.L. Rogers, Judge
    No. M2011-02248-COA-R3-CV - Filed August 2, 2012
    This appeal concerns the priority of two liens, a mechanic’s lien and a bank’s deed of trust.
    We have determined that the trial court erred in granting summary judgment in favor of the
    bank. We have further determined that the mechanic’s lien is entitled to priority and that the
    trial court erred in failing to grant summary judgment on that issue.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Reversed and
    Remanded
    A NDY D. B ENNETT, J., delivered the opinion of the Court, in which F RANK G. C LEMENT, J R.
    and R ICHARD H. D INKINS, JJ., joined.
    Todd E. Panther and Stephen Andrew Lund, Nashville, Tennessee, for the appellant, Anchor
    Pipe Company, Inc.
    James Campbell Bradshaw and David Andrew Amonette, Nashville, Tennessee, for the
    appellee, Trust One Bank.
    OPINION
    F ACTUAL AND P ROCEDURAL B ACKGROUND
    The facts underlying this case arose during the development of Enoch Hills
    subdivision in Gallatin, Tennessee. Prior to the construction of residential lots, the property
    was owned by JSC, LLC. Jeffrey Bronze negotiated with James Thigpen, the president of
    Anchor Pipe Company, Inc. (“Anchor”) about doing work on the property. It is undisputed
    that Anchor had a valid contractor’s license with a monetary limit of $750,000.00 throughout
    the relevant time period. Anchor gave a total bid of $3,521,952.00 on the work to be
    performed on this project. Bronze engaged Anchor to do the work, and Anchor began work
    on the property in February 2007.
    In May 2007, JSC, LLC transferred title to the property to Sweeney-Bronze
    Development, LLC (“SBD”). Trust One Bank, which provided a construction loan to SBD,
    recorded a deed of trust on July 24, 2007. Although SBD held title to the property, a
    different entity—Sweeney-Bronze Holdings (“SB Holdings”)—was the grantor of the bank’s
    deed of trust. Anchor continued to perform work on the property. On June 27, 2008, Bronze
    told Anchor that he could no longer pay for the work, and Anchor stopped all work on the
    project. As of that date, SBD had paid Anchor $659,579.06 for work on the project.
    On July 1, 2008, Anchor recorded a notice of lien against the property in the amount
    of $703,192.84; and, on July 25, 2008, Anchor recorded a notice of lien in the additional
    amount of $140,396.55. On November 12, 2008, a deed was recorded transferring title from
    SBD to SB Holdings. The bank recorded an amended and restated deed of trust on the same
    day, again (this time, correctly) listing SB Holdings as the grantor. Anchor recorded an
    amended lien on June 10, 2009 for a total claim of $625,864.
    On June 17, 2009, Anchor filed a verified amended complaint against SBD, SB
    Holdings, Bronze Construction, LLC, Jeffrey Bronze, Jeffrey Sweeney, JSC, and Trust One
    Bank.1 In its complaint, Anchor set forth causes of action for breach of contract, unjust
    enrichment, enforcement of lien, and violation of the Prompt Pay Act; Anchor also sought
    a declaratory judgment that its lien took priority over the bank’s deed of trust. The bank and
    Anchor filed cross-motions for summary judgment.
    The motions for summary judgment were heard in August 2011, and the court reached
    the following pertinent conclusions:
    Contractor is found to be not licensed for the project from its inception.
    Contractor is allowed recover[y] of only documented expenses pursuant to
    T.C.A. § 62-6-103(b). Absence of a valid contractor’s license causes a
    forfeiture of lien rights. Counsel for Contractor relies upon case law which is
    distinguishable from the case at hand. In the case before this Court, the
    Contractor was not properly licensed at the inception of the contract not
    thereafter, contrary to case law relied upon by counsel.
    Reasonable minds could not differ the January 20, 2007 e-mail between
    Contractor and Developer represents an agreement by Contractor to
    1
    The original complaint to enforce lien is not a part of the record on appeal.
    -2-
    subordinate its lien to Bank. The Construction Loan, after such agreement,
    was thereafter made. The material e-mail facts are not disputed. Counsel for
    Contractor puts forth argument [that] such subordination is not enforceable
    because no written subordination or release was sent to or signed by his client.
    The Court finds no legal requirement calling for a written agreement in this
    case.
    It is not necessary to address the dispute between Bank and Contractor as to
    visible commencement of work.
    Based upon this analysis, the trial court determined that the bank was entitled to judgment
    and dismissed Anchor’s claims against the bank. Upon the bank’s subsequent motion, the
    trial court entered an order on September 20, 2011 making the court’s order granting
    summary judgment to the bank a final order.
    Anchor appeals the trial court’s decision granting summary judgment to the bank.
    Anchor asserts that, contrary to the trial court’s conclusions, it has lien rights and those rights
    take priority over the bank’s lien rights.
    S TANDARD OF R EVIEW
    Summary judgment is appropriate when there is no genuine issue of material fact and
    the moving party is entitled to a judgment as a matter of law. Tenn. R. Civ. P. 56.04.
    Summary judgments do not enjoy a presumption of correctness on appeal. BellSouth Adver.
    & Publ’g Co. v. Johnson, 
    100 S.W.3d 202
    , 205 (Tenn. 2003). In reviewing a summary
    judgment, this court must make a fresh determination that the requirements of Tenn. R. Civ.
    P. 56 have been satisfied. Hunter v. Brown, 
    955 S.W.2d 49
    , 50 (Tenn. 1997). We consider
    the evidence in the light most favorable to the non-moving party and resolve all inferences
    in that party’s favor. Godfrey v.. Ruiz, 
    90 S.W.3d 692
    , 695 (Tenn. 2002). When reviewing
    the evidence, we must determine whether factual disputes exist. Byrd v. Hall, 
    847 S.W.2d 208
    , 211 (Tenn. 1993). If a factual dispute exists, we must determine whether the fact is
    material to the claim or defense upon which the summary judgment is predicated and whether
    the disputed fact creates a genuine issue for trial. Id.; Rutherford v. Polar Tank Trailer, Inc.,
    
    978 S.W.2d 102
    , 104 (Tenn. Ct. App. 1998). To shift the burden of production to the
    nonmoving party who bears the burden of proof at trial, the moving party must negate an
    element of the opposing party’s claim or “show that the nonmoving party cannot prove an
    essential element of the claim at trial.” Hannan v. Alltel Publ’g Co., 
    270 S.W.3d 1
    , 8-9
    (Tenn. 2008).
    -3-
    A NALYSIS
    1.
    Anchor’s first argument is that the trial court erred in concluding that it was an
    unlicensed contractor. The pertinent facts on this issue are not in dispute: Anchor had a
    contractor’s license throughout its work on the project, and this license authorized Anchor
    to perform the type of work it performed (underground piping, grading and drainage, and
    base and paving work). The monetary limit on Anchor’s license, however, was $750,000,
    whereas Anchor’s bids exceeded two million dollars. The bank asserts, and the trial court
    agreed, that Anchor was unlicensed because it bid on and performed work in excess of the
    monetary limits of its license.
    We are presented with a question of law: whether a contractor who contracts for work
    above the monetary limit applicable to his license is an unlicensed contractor for purposes
    of the Contractors Licensing Act of 1994, Tenn. Code Ann. § 62-6-101 et seq. This act
    requires persons or entities performing activities defined as “contracting” to have a license,
    and makes it unlawful for a person or entity to engage in contracting without a license. Tenn.
    Code Ann. §§ 62-6-101, 62-6-103(a). In ruling against Anchor, the trial court relied upon
    the following statutory provision:
    Any unlicensed contractor covered by the provisions of this chapter shall be
    permitted in a court of equity to recover actual documented expenses only
    upon a showing of clear and convincing proof.
    Tenn. Code Ann. § 62-6-103(b) (2008) (rewritten by chapter 482 of the Tennessee Public
    Acts of 2009).2 Because it considered Anchor to be “unlicensed,” the trial court held this
    provision applied.
    We disagree with the trial court’s legal conclusion that Anchor should be considered
    unlicensed. We find instructive the Supreme Court’s analysis in Helton v. Angelopolous, 
    629 S.W.2d 15
    , 16 (Tenn. 1982), a case in which the actual construction costs ended up
    exceeding the monetary limitations on the contractor’s license. Id. at 17. The contractor
    sued the property owner for the unpaid balance on a building contract. In examining the
    applicable common law and statutory background, the Court noted the underlying public
    policy of protecting “the consuming public from unqualified builders.” Id. The Court went
    on to distinguish between contractors who are “completely unlicensed” from those “who
    have complied with the licensing laws . . . and may in some manner violate the provisions
    2
    Because this case arose before the new version of the statute took effect, our analysis is under the
    prior version.
    -4-
    or limitations of their respective licenses.” Id. at 18. As to the monetary limitations on
    contractors’ licenses, the Court found their purpose to be “to afford financial security to
    owners, vendors and others dealing with a contractor.” Id.
    There was no evidence that the contractor in Helton was guilty of any negligence in
    submitting his bid. Id. at 19. The Court observed, however, that there were other means
    (apart from precluding the contractor from recovering on the contract) for addressing
    violations by licensed contractors:
    [I]f a licensed general contractor fraudulently, or in bad faith, or through
    collusion with an architect or engineer, submitted a bid upon a project
    obviously beyond the monetary limit on his license, ample sanctions, both civil
    and criminal, are available either through the courts or through the licensing
    agency. A rather complete statutory scheme exists for dealing with violations
    of licensed personnel, as contrasted with individuals or firms which, under
    prior law, undertook to operate in a regulated field without any attempt at
    compliance with the licensing requirements.
    Id. Based on this reasoning, the Court reversed the decision of the lower courts dismissing
    the contractor’s claim. Id.
    While Helton was decided based largely on caselaw, we consider its distinction
    between unlicensed contractors and contractors bidding above the monetary amount of their
    license to be relevant here. The purpose of the monetary limit is to ensure the contractor’s
    financial security and stability. Id. at 18. There is a regulatory scheme set up to address
    violations of the monetary limits by licensed contractors. Id.; see Tenn. Comp. R. & Regs.
    § 0680-01-.13, -.19. Furthermore, the case before us involves a dispute between a contractor
    and the bank that provided financing to the developer. It has generally been held that the rule
    restricting “an unlicensed contractor’s access to court does not apply to disputes between
    contractors and other licensed professionals in the construction business.” Custom Built
    Homes v. G.S. Hinsen Co., Inc., No. 01A01-9511-CV-00513, 
    1998 WL 960287
    , at *3 (Tenn.
    Ct. App. Feb. 6, 1998); see also Gene Taylor & Sons Plumbing Co., Inc. v. Corondolet
    Realty Trust, 
    611 S.W.2d 572
    , 575-76 (Tenn. 1981); Roberts v. Yarbrough, No. 01-A-01-
    9802-CH00096, 
    1999 WL 43252
    , at *2 (Tenn. Ct. App. Feb. 1, 1999). This rationale seems
    equally applicable here where the bank was in the business of approving construction loans
    and reviewing the credentials of contractors. The public policies underlying Tenn. Code
    Ann. § 62-6-103(b)–namely, protecting the safety and property of the public–are not
    -5-
    implicated in a dispute between knowledgeable professionals.3
    We, therefore, conclude that Anchor was not an unlicensed contractor under Tenn.
    Code Ann. § 62-6-103(b).
    2.
    Anchor also argues that, even if it were considered an unlicensed contractor, it would
    retain its lien rights. We agree.
    In asserting that an unlicensed contractor forfeits its lien rights, the bank cites Dotson
    v. Gaidos, 
    736 S.W.2d 119
     (Tenn. Ct. App. 1987), a suit brought by an unlicensed contractor
    against the property owner to recover damages and assert a lien. The appellate court agreed
    with the lower court’s conclusion that the fact that the contractor was unlicensed meant that
    he could not assert a lien against the defendants’ property.4 Id. at 120. Our interpretation of
    Dotson, however, must account for the General Assembly’s passage of related legislation in
    1994--what is now Tenn. Code Ann. § 62-6-128.
    Tennessee Code Annotated § 62-6-128 provides that Title 66, chapter 11—the
    provisions governing mechanic’s and materialmen’s liens–“shall not be available on single
    family residential construction to any person, firm or corporation that performs residential
    construction and that is required to be licensed as a contractor pursuant to this part and fails
    to have a valid license when acting as a contractor.” Thus, an unlicensed contractor who
    performs work on single-family residential construction forfeits his lien rights. The provision
    does not include any types of construction other than single-family residential. In
    interpreting statutes, we must presume that the General Assembly had knowledge of prior
    enactments and judicial constructions thereof. State v. L.W., 
    350 S.W.3d 911
    , 918 (Tenn.
    2011). The General Assembly has the authority to change the common law, and the intent
    to do so can be established by a statute covering the specific area addressed by the common
    law. See Kradel v. Piper Indus., Inc., 
    60 S.W.3d 744
    , 751 (Tenn. 2001); Jordan v. Baptist
    3
    The bank cites Kyle v. Williams, 
    98 S.W.3d 661
    , 662 (Tenn. 2003), a case in which the Supreme
    Court concluded that the contractor, who possessed a license when the contract was formed but did not
    maintain the contract throughout the time when services were performed under the contract, was an
    unlicensed contractor for purposes of Tenn. Code Ann. § 62-6-103(b). We find the facts of Kyle
    distinguishable from the present facts in that the contractor in Kyle did not possess a contractor’s license
    during part of the relevant time period. Moreover, it is significant to note that Kyle was an action brought
    by the contractor against the property owner.
    4
    The court went on to conclude that the contractor could recover on a claim for the debt. Dotson,
    736 S.W.2d at 120.
    -6-
    Three Rivers Hosp., 
    984 S.W.2d 593
    , 599 (Tenn. 1999). In construing statutes, we presume
    that the General Assembly did not intend to enact a useless statute. Lee Med., Inc. v.
    Beecher, 
    312 S.W.3d 515
    , 527 (Tenn. 2010).
    In light of the statement in Dotson that an unlicensed contractor had no lien rights, the
    enactment of what is now Tenn. Code Ann. § 62-6-128 appears to be intended to limit the
    rule to single-family residential property. Otherwise, the enactment would have been
    unnecessary. There is no other statutory provision abolishing lien rights for unlicensed
    contractors in other contexts. It is a rule of statutory construction that the mention of one
    subject in a statute means the exclusion of subjects not mentioned. Bryant v. Baptist Health
    Sys. Home Care of E. Tenn., 
    213 S.W.3d 743
    , 749 (Tenn. 2006).
    Given the language of Tenn. Code Ann. § 62-6-128 and the state of the law at the time
    of its enactment, we conclude that, outside the context of single-family residential
    construction, the fact that a contractor is unlicensed does not result in forfeiture of the
    contractor’s lien. Therefore, the trial court erred in finding that Anchor had forfeited its lien
    in this case.
    3.
    The third issue we must address is whether the trial court erred in finding that Anchor
    agreed to subordinate its lien to the bank’s lien rights.
    The trial court based its conclusion on an e-mail sent by Bronze to Thigpen on January
    30, 2007, and Thigpen’s response. The relevant e-mail from Bronze included the following
    statements:
    I am working on the bank loan and its closing. I am checking on the ability to
    start clearing and grading prior to closing construction loan. Will you sign a
    release to the bank if you start prior to the loan closing. That means the banks
    [sic] needs first place in the title position rather than you because you started
    before the loan closed.
    In his e-mail response, Thigpen stated that he would sign a release. The trial court concluded
    that, “Reasonable minds could not differ the January 20, 2007 e-mail between Contractor and
    Developer represents an agreement by Contractor to subordinate its lien to Bank.” We
    cannot agree with this conclusion.
    An agreement by Anchor to subordinate its lien to the bank’s lien rights must satisfy
    the elements of a valid contract: “[A]n enforceable contract must result from a meeting of
    -7-
    the minds in mutual assent to terms, must be based upon sufficient consideration, must be
    free from fraud or undue influence, not against public policy and must be sufficiently definite
    to be enforced.” Jones v. Lemoyne-Owen Coll., 
    308 S.W.3d 894
    , 904 (Tenn. Ct. App. 2009)
    (quoting Klosterman Dev. Corp. v. Outlaw Aircraft Sales, Inc., 
    102 S.W.3d 621
    , 635 (Tenn.
    Ct. App. 2002). An agreement to agree to something in the future is not generally
    enforceable. Four Eights, LLC v. Salem, 
    194 S.W.3d 484
    , 486 (Tenn. Ct. App. 2005). In the
    present case, the e-mails indicate that Thigpen was willing to sign a release in the future.
    The source of the financing for the project had not yet been finalized at the time of this email
    exchange. It is not clear from this exchange whether Anchor would receive financial
    compensation for such a release. While Thigpen’s response reflects a willingness to
    negotiate some future agreement, we do not consider these emails sufficient to establish
    mutual assent to definite terms.5
    Based upon our conclusions regarding the first three issues, the trial court erred in
    granting summary judgment in favor of the bank.
    4.
    The final issue for our consideration is whether the trial court erred in failing to grant
    Anchor’s motion for partial summary judgment that its lien had priority over the bank’s deed
    of trust.
    Bank’s 2007 deed of trust
    As outlined above, the bank recorded two deeds of trust, one on June 24, 2007 and
    another on November 12, 2008. For purposes of determining the priority of the competing
    liens, we must decide whether the bank perfected its lien by the filing of the initial deed of
    trust in June 2007. At that time, the property in question was owned by SBD. Yet, the
    bank’s deed of trust lists SB Holdings as the grantor of the deed of trust. Anchor asserts that,
    as a result of this defect, the 2007 deed of trust was void. We agree.
    A deed of trust is “a conveyance of an interest in real property to secure a debt.”
    Levine v. March, 
    266 S.W.3d 426
    , 438 (Tenn. Ct. App. 2007). It stands to reason that a
    person or entity cannot effectively convey an interest it does not possess. Pursuant to Tenn.
    Code Ann. § 66-4-201, part of the champerty statutes, “[n]o person shall agree to buy, or to
    5
    Given our conclusion that there was no enforceable agreement to subordinate Anchor’s lien, we
    need not determine the effect of Tenn. Code Ann. § 66-11-124(b), which provides that “[a]ny contract
    provision that purports to waive any right of lien under this chapter is void and unenforceable as against the
    public policy of this state.”
    -8-
    bargain or sell any pretended right or title in lands or tenements, or any interest in such
    pretended right or title.” A deed of trust may be champertous when the grantor has no legal
    interest in the property to be conveyed. Levine, 266 S.W.3d at 438.
    The bank cites the case of Wilkins v. Reed, 
    300 S.W. 588
     (Tenn. 1927), to support its
    position that the defect in the deed of trust should not deprive it of its lien priority because
    its 2007 deed of trust was registered and gave notice of the bank’s financial interest in the
    property. We find Wilkins to be distinguishable because it involved a defect in the
    registration of the deed of trust. Id. at 589. In the present case, the deed of trust itself is
    defective in that it fails to convey an interest in property; the registration of such an
    instrument cannot result in a perfected security interest. See In re May, 
    310 B.R. 405
    , 417-19
    (E.D. Ark. 2004); In re Moreno, 
    293 B.R. 777
    , 782-83 (D. Colo. 2003). We likewise reject
    the bank’s assertion that it is entitled to relief based upon equitable principles.6
    The bank argues that the 2007 deed of trust was effective because (a) SB Holdings is
    the parent company of SBD, its wholly owned subsidiary, and was acting as its agent or (b)
    the two companies were engaged in a joint venture. There is a presumption that parent and
    subsidiary corporations are separate and distinct legal entities. Gordon v. Greenview Hosp.,
    Inc., 
    300 S.W.3d 635
    , 651 (Tenn. 2009). The parent’s actions may be attributed to the
    subsidiary only when one company acts as the agent for the other or the two companies are
    alter egos. Id. at 652. The 2007 deed of trust was signed by Jeff Sweeney, President, on
    behalf of SB Holdings, and there is no reference to SBD. If SB Holdings were acting as
    SBD’s agent, Sweeney could have signed the deed of trust for SBD, but there is nothing in
    the record to suggest that SB Holdings acted on behalf of SBD in executing the deed of trust.
    When an agent fails to reveal his status, he is bound as principal. Anderson v. Durbin, 
    740 S.W.2d 417
    , 418 (Tenn. Ct. App. 1987).
    The bank relies on evidence that SB Holdings and SBD were both involved in the
    development and sale of the property. To establish a joint venture requires evidence of
    common interest and purpose and equal right of control. Fain v. O’Connell, 
    909 S.W.2d 790
    ,
    793 (Tenn. 1995). Each party to a joint venture “shall stand in the relation of principal, as
    well as agent, as to each of the other coadventurers, with an equal right of control of the
    means employed to carry out the common purpose of the adventure.” Id. (quoting Spencer
    6
    In declining to provide equitable relief to a bank relying upon a deed of trust from an entity that did
    not own the property, the court in In re May stated: “No entities are better situated to properly perfect interest
    in land than banks, whose purposes are to maximize profit derived from lending money and to ensure the
    repayment of their loans by taking an interest in the borrower’s collateral. Courts can not underwrite
    Defendants’ business risks under the guise of equity when Defendants themselves failed to take minimal
    steps to ensure their interests were properly protected.” In re May, 310 B.R. at 419.
    -9-
    Kellogg & Sons, Inc. v. Lobban, 
    315 S.W.2d 514
    , 520 (Tenn. 1958)). We find no such
    evidence in the record. Moreover, as discussed above, the purported agency relationship
    does not appear on the deed of trust.
    Priority of bank and Anchor liens
    Having determined that the bank’s 2007 deed of trust did not perfect its security
    interest, we must analyze the priority of the bank’s deed of trust recorded on November 12,
    2008 and Anchor’s mechanic’s liens recorded in July 2008.
    With respect to the attachment of mechanics’ and materialmens’ liens, Tenn. Code
    Ann. § 66-11-104(a) provides:
    The lien provided by this chapter shall attach and take effect from the time of
    the visible commencement of operations, excluding however, demolition,
    surveying, excavating, clearing, filling or grading, placement of sewer or
    drainage lines, or other underground utility lines or work preparatory therefor,
    erection of temporary security fencing and the delivery of materials therefor.
    Thus, the issue for determination here is whether the date of visible commencement of
    operations occurred prior to the bank’s recording of its lien in November 2008. Anchor
    points to several categories of construction it performed prior to November 2008 as
    constituting visible commencement of operations sufficient to attach its lien.
    It is undisputed that, prior to the bank’s recording of its lien in November 2008,
    Anchor erected the following: 10 to 12 above-ground concrete retaining walls, an above-
    ground outlet control structure, fire hydrants, and around 30 above-ground catch basins. All
    of these structures are permanent and remain on the property. The retaining walls are
    concrete structures that rise out of the ground about two feet; they provide support for the
    drainage system. The outlet control structure, which is five feet square and approximately
    eight feet tall , regulates the discharge of storm water in the development. The concrete catch
    basins capture stormwater runoff; the vertical leg of these L-shaped structures rises out of
    the ground about one foot from the street grade.
    The parties are in agreement that these structures are related to the property’s drainage
    and utility system. The parties hold conflicting views, however, as to the legal effect of the
    fact that these structures are part of the drainage system.
    This is an issue of statutory construction, a question of law. Seals v. H & F, Inc., 
    301 S.W.3d 237
    , 242 (Tenn. 2010). In statutory interpretation, we “must give effect to every
    -10-
    word, phrase, clause and sentence.” Brown v. Tenn. Title Loans, Inc., 
    328 S.W.3d 850
    , 862
    (Tenn. 2010) (quoting Cohen v. Cohen, 
    937 S.W.2d 823
    , 828 (Tenn. 1996)). Moreover, “an
    exception generally delineates the extent of the general provision.” Ky.-Tenn. Clay Co. v.
    Huddleston, 
    922 S.W.2d 539
    , 543 (Tenn. Ct. App. 1995). Tennessee Code Annotated § 66-
    11-104(a), quoted in its entirety above, excludes “demolition, surveying, excavating,
    clearing, filling or grading, placement of sewer or drainage lines, or other underground
    utility lines or work preparatory therefor, erection of temporary security fencing and the
    delivery of materials therefor.”7 (Emphasis added). The bank argues this provision
    “specifically excludes work related to installation of drainage lines and the delivery of
    materials for that activity.” Anchor asserts that the statutory exception does not broadly
    exclude all structures related to the drainage system.
    The phrase “or other underground utility lines or work preparatory therefor” modifies
    the phrase that precedes it: “placement of sewer or drainage lines.” The use of the words
    “other underground” to describe the excluded utility work suggests that the statutory
    exclusion applies only to underground utility lines, not to structures above ground.
    Moreover, the exclusion applies to “utility lines” and to “sewer or drainage lines,” not to all
    aspects of a sewer or drainage system. Giving meaning to every word and phrase employed
    by the legislature, we must conclude that the utility exclusion does not encompass the above-
    ground structures erected by Anchor as part of the overall drainage system.
    We, therefore, conclude that Anchor’s construction of the above ground concrete
    structures was sufficient to attach its lien. Because these structures were built prior to the
    November 2008 registration of the bank’s deed of trust, we conclude that Anchor’s lien
    should take priority over the bank’s lien. The trial court erred in failing to grant summary
    judgment in favor on Anchor on this issue.
    7
    These exclusions were specifically incorporated into the statutory definition of “visible
    commencement of operations” by a 2007 amendment to Tenn. Code Ann. § 66-11-101(16) that took effect
    in May 2007. Because some of the relevant work may have occurred prior to that date, we rely solely on the
    language in Tenn. Code Ann. § 66-11-104(a).
    -11-
    C ONCLUSION
    The decision of the trial court is reversed and we remand with instructions to grant
    summary judgment in favor of Anchor Pipe on the issue of lien priority. Costs of appeal are
    assessed against the appellee, Trust One Bank.
    _________________________
    ANDY D. BENNETT, JUDGE
    -12-