Wills Electric Co., Inc. v. Hassan Mirsaidi ( 2001 )


Menu:
  •                  IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    October 9, 2001 Session
    WILLS ELECTRIC COMPANY, INC. v. HASSAN MIRSAIDI,
    INDIVIDUALLY & D/B/A MIRSAIDI CONSTRUCTION COMPANY
    Appeal from the Chancery Court for Davidson County
    No. 99-3001-I   Irvin H. Kilcrease, Jr., Chancellor
    No. M2000-02477-COA-R3-CV - Filed December 13, 2001
    A general contractor withheld the final payment for work completed by his electrical subcontractor,
    and the subcontractor sued for breach of contract. The trial court awarded the subcontractor the
    contracted-for amount, as well as pre-judgment interest and consequential damages. We reverse the
    award of consequential damages. In all other respects, we affirm the trial court.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court
    Affirmed in Part; Reversed in Part; and Remanded
    BEN H. CANTRELL, P.J., M.S., delivered the opinion of the court, in which WILLIAM B. CAIN and
    PATRICIA J. COTTRELL, JJ., joined.
    Richard E. Norman, Jr., Nashville, Tennessee, for the appellant, Hassan Mirsaidi, Individually and
    d/b/a Mirsaidi Construction.
    Joseph Y. Longmire, Jr. and C. Ronald Blanton, Hendersonville, Tennessee, for the appellee, Wills
    Electric Company, Inc.
    OPINION
    I. CONTRACTOR AND SUBCONTRACTOR
    General contractor Hassan Mirsaidi of Mirsaidi Construction signed a contract with the
    Metropolitan Government of Nashville and Davidson County to renovate a branch library. The total
    value of the contract was over $1,000,000. On January 22, 1998, Mirsaidi Construction hired Wills
    Electric as its electrical subcontractor, “to furnish all material, equipment and perform all work
    necessary to complete the electrical system for Pruitt Library . . . .” The initial contract price was
    $97,300, with Mirsaidi required to make monthly progress payments to Wills. The final payment
    was due upon completion of the work. A $4,800 change order, to which the parties agreed on
    December 9, 1998, increased the total payout to $102,100.
    The proof showed that the parties did not enjoy a harmonious relationship while the contract
    was being performed. Russell Wills, who performed and/or supervised all the work done by Wills
    Electric, claimed that Mirsaidi consistently short-changed him on his progress payments, making it
    difficult for him to pay all his labor and his suppliers. Mr. Wills’ wife, Lyndi, the president of the
    company, claimed that Hassan Mirsaidi told her that he would not discuss the alleged shortages with
    her because he didn’t have to talk to a woman. For his part, Mr. Mirsaidi claimed that he always
    paid the correct amount, and that any perceived discrepancy was due to the fact that he had assumed
    the responsibility of making direct payments to a prime supplier of electrical parts which had not
    agreed to extend credit to Wills Electric.
    Despite these difficulties, Russell Wills completed the work on the contract in January of
    1999, and Hassan Mirsaidi admitted the job was satisfactory. But the general contractor held back
    a final payment of $19,013, because Wills had not fully paid all his suppliers or obtained lien
    releases from them. For his part, Wills said he could not pay the suppliers until Mirsaidi made the
    final payment on the contract.
    On February 3, 1999, Mr. Wills submitted a “final request for payment” to Mr. Mirsaidi.
    Payment was not forthcoming, and in a subsequent letter, Wills suggested that joint checks be made
    out to Wills Electric and to three vendors to whom money was still owed. This was still
    unsatisfactory to Mirsaidi, and on October 18, 1999, Wills filed a complaint for the unpaid contract
    amount.
    Mirsaidi answered, admitting that he owed on the contract, but claiming that the exact
    amount could not be ascertained. The contractor also claimed that Wills had refused to accept a
    partial payment check made out jointly to the subcontractor and to two unpaid suppliers, and that
    Wills’ failure to pay his suppliers and to obtain lien releases from them held up Mirsaidi’s final
    payment from Metro. Wills subsequently filed a Motion for Judgment on the Pleadings, which was
    denied by the trial court.
    Wills Electric was a new business, and Mirsaidi’s refusal to make the final payment on the
    completed contract put it in a financial bind. In order to pay his creditors and remain in business,
    Wills borrowed $25,000 from the First Tennessee Bank. On May 11, 2000, Wills amended his
    complaint to add a consequential damages claim for the interest he had to pay on the loan.
    The trial court conducted a hearing in this case on September 6, 2000. The court observed
    that the parties could have settled this case if Mirsaidi had simply paid the subcontractor what it
    admitted owing, and the subcontractor had used the money to pay off its suppliers and obtained the
    necessary releases. However, the question of pre-judgment interest and consequential damages
    remained at issue.
    At the conclusion of the proof, the court ruled that Mirsaidi was guilty of breach of contract.
    The contractor was ordered to pay $19,013 for the breach, plus pre-judgment interest assessed from
    February 2, 1999 to September 6, 2000 at the rate of 10%, amounting to $3,026.40. The court’s
    -2-
    Final Order also stated that the defendant was liable for “incidental and consequential damages” in
    the amount of $2,853.23, which was the interest associated with the plaintiff’s loan. Plaintiff’s
    counsel was ordered to disburse $11,548 to the remaining creditor of Wills Electric, and to obtain
    a lien release before disbursing any funds to the plaintiff. Mirsaidi appealed.
    II. BREACH OF CONTRACT
    Mr. Mirsaidi admitted at trial that two or three months earlier, Metro had paid him the full
    amount on the master contract, and he concedes on appeal that the plaintiff is accordingly entitled
    to receive the $19,013 owed, so the question of whether or not Mirsaidi breached the contract would
    merely be academic, were it not for his argument that he is not guilty of a breach, and therefore that
    he cannot be held responsible for any damages beyond the contract amount. Mr. Mirsaidi continues
    to insist that Mr. Wills breached the contract by failing to pay off his suppliers and obtain releases
    from them. He also argues that the subcontractor has unclean hands, and that it would be inequitable
    to reward him in any way for the difficulties that he himself created.
    We note that there is nothing in the text of the contract which makes payment of the contract
    amount conditional upon payment to suppliers or upon release of liens. Mr. Mirsaidi alleges that the
    master contract made Metro’s payment to him contingent upon such releases, but the subcontracting
    agreement does not incorporate the terms of the master contract either expressly or by reference. The
    subcontract does contain a payment provision, which reads as follows:
    “. . . [t]he said Contractor agrees that he will pay to the said Sub-Contractor the sum
    of Ninety seven thousand three hundred and 00/100 ($97,300) Dollars. Payment will
    be made as follows: Sub-Contractor will turn in his invoice minus 10% retainage for
    progress payment by 25th day of each month for examination by architect and
    contractor, after approval of the invoice by said architect, the invoice will be sent to
    the owner for payment. Three (3) days after the Contractor received (sic) his
    payment, the Sub-Contractor will receive his check. (The procedure will apply for
    retainage money).”
    It appears to us that the only contingency contained in this provision is the approval of the
    work by the architect and the contractor, and the proof showed that they both gave their approval to
    the completed job. We do not believe the language about payment to the sub-contractor three days
    after the contractor is paid constitutes a condition precedent to the contractor’s obligation to pay. We
    construe it rather as part of a procedure designed to promote an orderly and predictable transfer of
    funds from the client to the ultimate payee.
    It is axiomatic that in contract formation the parties are free to allocate risks and burdens as
    they see fit. Brown Bros., Inc. v. Metropolitan Government of Nashville and Davidson County, 
    877 S.W.2d 745
     (Tenn. Ct. App. 1993); Empress Health and Beauty Spa, Inc., v. Turner, 
    503 S.W.2d 188
     (Tenn. 1973). Thus, the parties could have included a clause making the final payment on their
    -3-
    contract contingent upon receipt of lien releases from all the suppliers the subcontractor dealt with.
    This was not done, so there can be no doubt that Mirsaidi breached the contract at issue.
    III. PRE-JUDGM ENT INTEREST
    It has long been the law in Tennessee that pre-judgment interest is allowable when based
    upon equitable principles. See Fisher v. Klipstatter, 
    689 S.W.2d 870
     (Tenn. Ct. App 1985). The
    common-law rule has been codified at 
    Tenn. Code Ann. § 47-14-123
     (1995), which permits courts
    or juries to award prejudgment interest as damages "in accordance with the principles of equity at
    any rate not in excess of a maximum effective rate of ten percent (10%) per annum."
    Such an award is discretionary with the court if the claim involved is for non-liquidated
    damages. Myint v. Allstate Ins. Co., 
    970 S.W.2d 920
     (Tenn. 1998); Howard G. Lewis Construction
    Co., v. Lee, 
    830 S.W.2d 60
     (Tenn. Ct. App. 1991); B.F. Myers & Son v. Evans, 
    612 S.W.2d 912
    (Tenn. Ct. App. 1980). However, when the claim is for failure to make timely payment on a contract
    amount, and there is no dispute as to the amount due, pre-judgment interest is considered a matter
    of right. See Tenn. Code. Ann. § 47-15-109; Jaffe v. Bolton, 
    817 S.W.2d 19
     (Tenn. Ct. App. 1991);
    Performance Systems, Inc. v. First American National Bank, 
    554 S.W.2d 616
     (Tenn. 1977). It is
    presumed in such cases that equity requires that the plaintiff be compensated for the loss of use of
    money he was entitled to collect under the contract.
    Although there may be some cases where it is inequitable to award pre-judgment interest
    when an obligor has failed to make timely payment under a contract, this does not appear to be such
    a case. There was no evidence presented at trial of inequitable conduct on the part of Wills. There
    was, however, some proof that Mirsaidi had told one of Wills’ suppliers that Wills had already been
    paid in full on the library contract when that was not the case, in order to increase the pressure on
    the subcontractor. The award of pre-judgment interest is affirmed.
    IV. CONSEQUENTIAL DAMAG ES
    Although the trial court’s judgment denominated the damages suffered by the plaintiff as
    “incidental and consequential,” these terms are not synonymous. In fact, they refer to two distinct
    forms of damages, for the recovery of which very different standards apply. Incidental damages are
    a type of general damages – that is, those damages “which the law itself implies or presumes [to be]
    the immediate, direct or proximate result, or such as necessarily results from the injury, without
    reference to the special character, condition or circumstances of the plaintiff.” Black’s Law
    Dictionary (6th ed. 1990).
    Consequential or “special” damages are defined in Black’s as “[s]uch damage as does not
    flow directly and immediately from the act of the party, but only from some of the consequences or
    results of such act.” The rule from the venerable and familiar case of Hadley v. Baxendale, 9 Ex.
    341, 156 Eng. Rep. 145 (1854) states that consequential damages will only be awarded if they could
    reasonably be supposed to have been within the contemplation of the parties at the time of
    -4-
    contracting, as a probable consequence of a breach of contract. The Baxendale rule has been
    seconded many times by our Tennessee courts. See, for example, Lane v. Associated Housing
    Developers, 
    767 S.W.2d 640
     (Tenn. Ct. App. 1988); Turner v. Benson, 
    672 S.W.2d 752
     (Tenn.
    1984).
    Several Tennessee cases have stated that our courts may allow recovery of all damages which
    are the normal and foreseeable results of a breach of contract. Moore Construction Co. v. Clarksville
    Dept. of Electricity, 
    707 S.W.2d 1
     (Tenn. Ct. App. 1985); Bush v. Cathey, 
    598 S.W.2d 777
     (Tenn.
    Ct. App. 1979); Wilson v. Dealy, 
    434 S.W.2d 835
     (Tenn. 1968). Such results would include both
    incidental damages and those consequential damages that meet the Baxendale test. For purposes of
    analysis, to say that certain results were foreseeable at the time of contracting, or that they could
    reasonably be supposed to have been within the contemplation of the parties would seem to be
    functionally equivalent.
    In the present case, there is no evidence that at the time of contracting Mr. Mirsaidi knew or
    suspected that failure on his part to make timely and complete payment to Wills would force the
    subcontractor to borrow money to keep his company afloat. It is clear that after contracting Mirsaidi
    became aware that Wills faced some financial difficulties. For example, Braid Electric, which was
    the prime supplier on the subcontract would not extend credit to Wills because the company was too
    new, so Mirsaidi had to purchase the necessary supplies on his own credit. But such after-acquired
    knowledge cannot be used to prove that at the time of contracting Mirsaidi could have foreseen the
    consequences of his failure to make timely payment on the contract.
    Also, as we stated above, the award of pre-judgment interest was meant to compensate Wills
    for the loss of use of the money to which he was entitled. An additional award for interest on money
    borrowed would appear to compensate the plaintiff twice for a single injury. In light of this
    circumstance, and of the rule in Baxendale, we reverse the award of consequential damages.
    IV.
    The judgment of the trial court is affirmed in regard to payment on the contract amount and
    pre-judgment interest, but reversed in regard to consequential damages. Remand this cause to the
    Chancery Court of Davidson County for further proceedings consistent with this opinion. Tax the
    costs on appeal equally between the appellant and the appellee.
    _________________________________________
    BEN H. CANTRELL, PRESIDING JUDGE, M.S.
    -5-